Professional Documents
Culture Documents
Ultra Mega Power Projects (UMPP) was a program introduced in 2005 by the Ministry of
Power in association with the Central Electricity Authority and the Power Finance Corporation
to address the countrys lingering power deficits and to provide for the growing energy demands
(see Section on Power Scenario on India) of the ever-increasing Indian population and the new
culture of mass consumerism prevalent in the country. With the help of this scheme the
government intended to overcome bureaucratic obstacles hindering the development of large
thermal plants working in the country in order to achieve its objective of Electricity or all by
2012.[1] The UMPPs can actually be seen as a successor or an expansion of the Mega Power
Projects (MPP) that the Government undertook in the 1990s with limited success. In the first of
the two stages that are involved in the UMPP program, the Power Finance Corporation (PFC)
creates a shell company called a Special Purpose Vehicle (SPV) [refer to terminologies for
details]. The purpose of SPV includes securing environmental clearances, acquisition of land and
water, and obtaining commitments for coal, either domestic or from abroad. After the completion
of these steps, private companies are given a chance to acquire the shell company under a
process of competitive bidding, in the second stage. The bidder guaranteeing to sell power at the
lowest levelised tariff (refer to terminology section for details) to the consumers is awarded the
project.[2]
The characteristic features of UMPPs includes:[1]
Use of supercritical technology (refer to terminologies for details) for increased fuel
efficiency and to ensure reduction in greenhouse gas emissions;
Allocation and sharing of power among multiple states typically with the help of stateowned electric utilities;
Dedicated captive coal blocks (rather than coal linkages as seen in earlier programs) for
projects located in the interior;
Imported coal for coastal projects (For example Tata Mundra UMPP imports coal from
Indonesia);
Estimated investment in each UMPP: approximately Rs. 16,000 to Rs. 20,000 crores
Private entitys responsibility: arrange funding, technological tie-ups, place orders for key
equipment, execute and operate the project
Originally in 2005, only nine projects were proposed, of which four were planned to be pit-head
projects and the other five were coastal projects that would use imported coal. Later in 2007 few
projects had to be abandoned due to various reasons and later additional projects were proposed.
So far, 16 UMPPs have been planned in various states including Andhra Pradesh, Chhattisgarh,
Gujarat, Jharkhand, Karnataka, Madhya Pradesh, Maharashtra, Orissa and Tamil Nadu.
The present status of the UMPP scheme with proposed project and location has been shown
below: [3]
State
Plant
Owner
MW
Type
Status
Andhra
Pradesh
Krishnapatnam Coastal
UMPP
Andhra
Power Ltd.
Reliance
Power
3960
Coastal
Deferred
Andhra
Pradesh
Nayunipalli
Tatiya
Not yet
Andhra
awarded
Mega Power
Ltd.
4000
Coastal
Proposed
4000
Interior
Cancelled
2013
Gujarat
Tata Mundra
UMPP
Coastal
Gujarat
Power Ltd.
Tata
Power
4000
Coastal
Unit 1
Commissioned
2012; Units 23 in
construction
Jharkhand
Tilaiya UMPP
Jharkhand
Reliance
3960
Interior
Early
UMPP
Special
Purpose
Vehicle
Integrated
Power Ltd.
Power
Development
Karnataka
Tadri UMPP
Coastal
Karnataka
Power Ltd.
Not yet
awarded
4000
Coastal
Deferred
Madhya
Pradesh
Sasan UMPP
Sasan
Power Ltd.
Reliance
Power
3960
Interior
Unit 1
commissioned
2013; Units 25 in
construction
Maharashtra
Girye UMPP
Coastal
Karnataka
Power Ltd.
Not yet
awarded
4000
Interior
Deferred
Odisha
Sundargarh
UMPP
Orissa
Integrated
Power Co.
Ltd.
Not yet
awarded
4000
Interior
Proposed
Odisha
Sakhigopal
UMPP
Sakhigopal
Integrated
Power Co.
Ltd.
Not yet
awarded
4000
Interior
Proposed
Odisha
Ghogarpalli
UMPP
Ghogarpalli
Integrated
Power Co.
Ltd.
Not yet
awarded
4000
Interior
Proposed
Tamil Nadu
Cheyyur
UMPP
Coastal
Tamil Nadu
Power Ltd.
Not yet
awarded
4000
Coastal
Coastal
Proposed
As explained earlier 4 UMPPs (Figure 2) have been successfully awarded but they continue to
grapple with a gamut of challenges ranging from land acquisition (The landmark Land
Acquisition, Rehabilitation and Resettlement Act, 2013 is expected to address this problem
Terminology used:
Special Purpose Vehicle (SPV) - A special purpose vehicle (SPV), also known as a shell
company, is used to provide a temporary sponsor for a project while it goes through the
initial stages of acquiring land, water, coal, and clearances. SPVs are wholly owned
subsidiaries of the Power Finance Corporation (PFC). Once an SPV completed the initial
stage of project development, the project is awarded through a competitive bidding process
to a private owner which proceeds to build, own, and operate ("BOO" in economic parlance)
the coal plant. [4]A shell
Ultra Mega Power Project (UMPP) - Large projects, usually 4000 MW in size, developed
using SPVs.
BOO
Levelised tariff- Levelised tariff is the tariff arrived by discounting the tariff of 25 years as
calculated by
bidders using assumptions of their choice, as well as, the same given by the Government in the
bidding documents. This is only a tariff to evaluate the various bids and decide a winner. Actual
tariff will differ based on actual escalation of various tariff components at any point of time.
Competitive Bidding Procedure- (from UMPP page)
for feeding cattle, health problems, migration of skilled manpower, lack of opportunity for
women to be part of income generation activities.
So the following income generating programs were launched by CGPL on yhe lines of Gandhian
principles of self-reliance and self-sustainability of communities:
a) Gaushala- to check the decline in area of pasture land available for feeding cattle. The project
successfully built various centers that supplied fodder and erected two massive gaushala
containing many sheds for storing fodder and many sheds for keeping cattle. This has led to
increase in cattle population and subsequently the milk production and availability in the area.
b) Project Utkarsh- successfully made groups of cattle-rearers in order to increase their
bargaining power, to educate them on livestock rearing, to share the risk and investment needed.
c) Various nutrition kits were provided to children, many ROs were set up to ensure safe
drinking water, check dams established for effective water management.
d) Project Sagarbandhu was rolled out for the welfare of the fishing community through
development of ponds for them and by educating them on fish breeding.
e) Kalaraksha program- Kalaraksha Trust was set up with the sole objective of promotion of
handicrafts by the local artisans. Various fairs and exhibitions are organized to make people
aware and hence preserve the art of these artisans.
f) Vivekananda Research and Training Institute(VRTI) was set up to form groups of women and
train them in activities like sewing, embroidery, tie and dry work etc. and to connect them to
local markets.
2.