SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)
Rev 3
SAIC NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Fireclay Bricks & Mortar
SAIC-N-2037
PROJECT TITLE
WBS / BI / JO NUMBER
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
LAYOUT DRAWING NUMBER
REV. NO.
SCHEDULED INSPECTION DATE & TIME
ACTUAL INSPECTION DATE & TIME
CONTRACTOR INSPECTION LEVEL
A2
PLANT NO.
EC / PMCC / MCC NO.
MH's SPENT
TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO INSPECTION LEVEL
A1
SYSTEM ID.
QUANTITY INSP.
SAUDI ARAMCO ACTIVITY NUMBER
A.
MECH-
CONTRACTOR / SUBCONTRACTOR
PURCHASE ORDER NUMBER
ACCEPTANCE CRITERIA
QR NUMBER
150-Dec-09
EQPT CODE
SAUDI ARAMCO TIP NUMBER
ITEM
No.
30-Jun-08
DATE APPROVED
WORK PERMIT REQUIRED?
REFERENCE
PASS
FAIL
N/A
RE-INSP DATE
General Requirements
Firebricks (Class & Type) are correct per Table 3 of SAES-N-100
(Equipment Specific Requirement).
See Note 1 & Attachment 1.
Received firebricks have certificates showing acceptable ASTM Test
results as listed on SA Inspection Requirement Form 175-328110.
SAES-N-100,
Para. 9.1
SAES-N-130,
Para. 8.1
See Note 2 & Attachments 1, 2.
A3
Mortar data sheets (from manufacturer) are available & materials are in
proper proportion as per mixing instructions of the manufacturer.
SAES-N-130,
Para. 8.3
A4
Material Safety Data Sheets (MSDS) are available from manufacturer.
SAES-N-130,
Para. 7.2
A5
Asbestos is not used in the manufacture of firebrick & materials.
SAES-N-100
Para 7.1.1
A6
Refractory installer has a proper storage area to protected the received
fireclay bricks from any mechanical damage.
See Note 3.
SAES-N-130,
Para. 7.1
A7
Materials stored (mortar, etc) are within their manufacturer expiry date.
SAES-N-130,
Para. 8.1
REMARKS:
REFERENCE DOCUMENTS:
1. Schedule Q -- Quality Requirements (Project Specific)
2. SAES-N-100 -- Refractory Systems (30 Jan 2007)
3. SAES-N-130 -- Installation Requirements-Fireclay Bricks (30 jan 2007)
ATTACHMENTS:
1. Attachment 1 -- ASTM C27 Table 1 (Firebrick Classification Table)
2. Attachment 2 -- ASTM Table C133 (Cold Crushing Strength) & ASTM Table C134 (Firebrick Precision Statistics)
3. Attachment 3 -- SA Inspection Requirement Form 175-328110 (Refractories)
NOTES: 1. SAES-N-100, Table 3 (requires specific firebrick for specific equipment) is not attached. A field copy is needed.
2. Firebricks already manufactured are accompanied with full certification & have been accepted by Vendor Inspection prior to shipment.
Check detail drawings against materials received. Firebricks are per drawings, are visually acceptable with consistent dimensions per ASTM C134.
3. Firebricks are received on proper pallets with protective (padded) banding securement. They are kept off the ground and covered to prevent any
chemical fouling or contamination. Check exterior layers of bricks under securement straps closely for cracking and damage.
Contractor / Third-Party
Saudi Aramco
Construction Representative*
PMT Representative
Work is Complete and Ready for Inspection:
Name, Initials and Date:
QC Inspector
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
PID Representative
Performed Inspection
Work / Rework May Proceed
Name, Initials and Date:
Name, Initials and Date:
QC Supervisor
Proponent and Others
Quality Record Approved:
Name, Sign and Date:
T&I Witnessed
Name, Initials and Date:
Name, Organization,
Initials and Date:
Page 1 of 5
*Person Responsible for Completion of Quality Work / Test
Y = YES
Page 2 of 5
N = NO F = FAILED
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)
Rev 3
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Fireclay Bricks & Mortar
SAIC NUMBER
SAIC-N-2037
30-Jun-08
DATE APPROVED
15-Dec-09
QR NUMBER
MECH-
Attachment 1 -- ASTM C27 Table 1 (Firebrick Classification)
Page 3 of 5
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)
Rev 3
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Fireclay Bricks & Mortar
SAIC NUMBER
SAIC-N-2037
30-Jun-08
DATE APPROVED
QR NUMBER
15-Dec-09
Attachment 2 -- ASTM C133 & ASTM C134 Tables
Page 4 of 5
MECH-
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)
Rev 3
SAUDI ARAMCO INSPECTION CHECKLIST
Receiving Inspection of Fireclay Bricks & Mortar
Page 5 of 5
SAIC NUMBER
SAIC-N-2037
30-Jun-08
DATE APPROVED
15-Dec-09
QR NUMBER