Professional Documents
Culture Documents
DIXIT
Management Consultant, Baroda, India
Advantages of installing trays in • Tray design is more rigid as a single non-metal section). These beams should
column horizontal position: The ad- assembly so as not to deform and be bolted at both ends to keep all assem-
vantages of installation trays in the col- dislodge from position during bled tray deck plates pressed downward,
umn horizontal position include: transportation and lifting. which will prevent vibration and deflec-
tion of tray parts during lifting
and transportation. The bracing
Tray operation is sensitive to levelness and requires beams also act as secondary sup-
precision installation. Tray levelness should be ports from the top of the tray.
Transportation and erec-
checked in the tray horizontal position. The majority tion specifics. The verticality
of trays used in industry are valve or sieve trays. of all tray support rings and the
alignment of the bolting bars
should be checked at the time of
• The tray installation team does not Procedure followed. The planning work construction. Thorough measurements
need to wait for column erection or of tray design and detailing starts at the should be taken of all important dimen-
consider the related safety issues design stage itself. The size and location sions before starting work. Lifting and
• Considerable time and effort are of the column access holes are important. rigging procedures should be established
saved in lifting each component Design stage specifics. All downcom- and reviewed with an erection contrac-
from floor level to working level er bolts must be full-length and bolted tor. Crane capacity and load charts should
• Plant floor space is not engaged in completely through the plate. No friction be checked. A transport vehicle and road
tray mockup trials and storage clamps should be used. The bottom down- survey should be conducted to ensure a
• Safety and efficiency are enhanced comer plate is the weakest plate, so it must smooth ride that is free of bumps.
for the tray installation team be stiffened and provided with downcom- Balance work at site after erection.
• Tray installation and column er brackets to maintain the flow area below After the column is erected at the site,
dressing work can be done the downcomer and avoid vibration. Edge column access holes and tray access ways
together, which saves time. clamps and beam clamps should be placed should be opened again to inspect all
at close pitch for the friction clip. trays. Bracing beams should be removed.
Challenges of installing trays in col- All bolting and clamps must be Additionally, if required, leakage tests of
umn horizontal position: The chal- checked for tightness, using torque liquid holding parts (e.g., seal pans/draw-
lenges of installation trays in the column wrenches. Care should be taken not to off pans) should be conducted, as per
horizontal position include: damage the clamp by overtightening. For design requirements. After these steps
• Additional weight of trays must be larger-diameter plates, the use of thicker are finished, clearance to box up the trays
considered for the column erection clamps is recommended. can be issued.
• Closer manufacturing tolerance It is difficult to hold the tray plates in a
for tray support ring and bolting vertical position when the column is hori- Takeaway. The methodology reviewed
bars, which helps maintain the zontal. Additional cleats can be welded to in this article can be easily used for col-
tray levelness and the fitting of the column wall (FIG. 4). Cleats should umn diameters of 1,200 mm–3,000 mm.
additional parts have a narrow gap of tray thickness plus In smaller-diameter columns, it is difficult
• Closer inspection and measurement 3 mm between the support rings. The tray for a technician to work inside in a sitting
of tray parts and downcomers, plate should be inserted within this gap position. For larger-diameter columns, the
per the tolerances specified by and then clamped to support the ring. weight of trays and supporting structures
the design Additional bracing beams across the may be significant, which may require an
• Placement of column on temporary diameter (FIG. 4) must be provided. The additional working platform and scaffold-
saddle in desired orientation for ease bracing beams can be made of any in- ing with weight-handling hoists inside.
of entering and handling tray parts expensive material (wooden batten or With the outlined suggested methods,
field tray installation work—which nor-
mally runs for weeks at a site—can be re-
duced to days.
PRAMOD DIXIT works as a
freelance Consultant in Baroda,
India. He spent 20 yr at Engineers
India Ltd., working as a tray and
tower internals specialist. He has
another 20 yr of senior-level
experience at Larsen & Toubro
and Essar Offshore. He provides training, consulting
services and troubleshooting to operating and
engineering companies for static equipment, trays
and tower internals. He holds a BTech degree in
mechanical engineering from the Indian Institute
FIG. 4. Tray assembly items held by bracing beam. of Technology at Roorkee, India.
20 SEPTEMBER 2020 | HydrocarbonProcessing.com