You are on page 1of 2

Project P.

DIXIT
Management Consultant, Baroda, India

Reduce installation schedule for column trays


The implementation of a project Tray construction features. Trays are bearing part of the tray. Some
schedule must avoid slippage, which can made of thin carbon-steel or stainless- tray manufacturers use friction
lead to budget overruns and delays in com- steel sheets 2 mm or 3 mm thick. The seg- clamps in the bottom section of
missioning and production. Conversely, a ments are designed to pass through the the downcomer to save time,
reduction in project schedule results in an column access hole. The larger the access which is not recommended here.
early startup of the plant, creating advan- hole, the easier it is to handle larger tray 5. Major beams or trusses (FIG. 2
tage for stakeholders. Customers often parts. The tray assembly consists of the and FIG. 3) are firmly bolted to
demand reductions in schedule timelines, following major parts: their respective stools and bracket
which can be difficult for engineering, 1. The tray deck plate has perforated welded to the column. These
procurement and construction (EPC) plates, as well as un-perforated beams/trusses are major load-
contractors to implement. New innova- plates under the downcomer. bearing parts. Normally, trays up
tions like concurrent engineering, modu- Tray segments are held in position to 2 m in diameter do not have
lar construction, prefabricated pipe racks with friction clamps, beam clamps any loose major beams or trusses,
and structures, etc., are already in practice. and edge clamps (FIG. 1). The trays but for a tray diameter of more
Erection of columns and vessels in are further reinforced by bending than 3 m, trusses are used.
dressed condition is also a regular prac- the tray plate itself, making it
tice. Future work centers on how to install an integral beam.
trays inside the column at the manufactur- 2. Trays are fixed on support rings
ing shop. This could save considerable site with tray edge clamps. The
time, site space and labor. However, fixing clamps hold the tray from the
trays in the column vertical condition is bottom, while the bolt passes
still a recommended practice from most through slots provided in the tray.
tray manufacturers and plant owners. The Support rings do not have any
reason is likely due to the clamped con- holes. This provides flexibility of
struction of trays and the fear of possible tray installation without much
tray damage during column transportation adjustment. Tray beam clamps FIG. 1. Tray beam clamp with integral beam.
and erection. Tray operation is sensitive to are simply oblong or rectangular
levelness and requires precision installa- plates that are provided on
tion. Tray levelness should be checked in integral beams. A number of
the tray horizontal position. tray suppliers use finger-type
The author worked on several projects interlocking arrangements in
where the customer required columns place of tray beam clamps, which
supplied with trays fixed in position for a further reduces installation time.
brownfield project. This requirement was 3. Friction clamps work as an
due to a tight project schedule, a lack of additional safety device to prevent
site working space and a lack of site labor. damage to the column. In case
The column diameters were in the range of pressure surge, clamps slip out FIG. 2. Tray with loose major beam and
downcomer.
of 2,000 mm–2,400 mm. This article de- of the support ring and allow
tails the thought process and additional tray parts to dislodge, thereby
work carried out jointly with designers, saving the column.
fabricators and erection engineers. The 4. Downcomer vertical plates
tray installation was carried out in column are bolted to the bolting bars.
horizontal condition. Projects were com- Downcomer plates are bolted
pleted successfully, without any damage together in multiple segments.
or rework at the site. The bolting bars are provided
At present, the majority of trays used with oblong holes for fixing
in industry are valve or sieve trays. Other the downcomer plates in place
types of trays, such as bubble cap or pro- and ensuring column ovality.
prietary trays, are not part of this study. FIG. 3. Critical dimensions must be checked.
Downcomer plates are a load-
Hydrocarbon Processing | SEPTEMBER 2020 19
Project Management

Advantages of installing trays in • Tray design is more rigid as a single non-metal section). These beams should
column horizontal position: The ad- assembly so as not to deform and be bolted at both ends to keep all assem-
vantages of installation trays in the col- dislodge from position during bled tray deck plates pressed downward,
umn horizontal position include: transportation and lifting. which will prevent vibration and deflec-
tion of tray parts during lifting
and transportation. The bracing
Tray operation is sensitive to levelness and requires beams also act as secondary sup-
precision installation. Tray levelness should be ports from the top of the tray.
Transportation and erec-
checked in the tray horizontal position. The majority tion specifics. The verticality
of trays used in industry are valve or sieve trays. of all tray support rings and the
alignment of the bolting bars
should be checked at the time of
• The tray installation team does not Procedure followed. The planning work construction. Thorough measurements
need to wait for column erection or of tray design and detailing starts at the should be taken of all important dimen-
consider the related safety issues design stage itself. The size and location sions before starting work. Lifting and
• Considerable time and effort are of the column access holes are important. rigging procedures should be established
saved in lifting each component Design stage specifics. All downcom- and reviewed with an erection contrac-
from floor level to working level er bolts must be full-length and bolted tor. Crane capacity and load charts should
• Plant floor space is not engaged in completely through the plate. No friction be checked. A transport vehicle and road
tray mockup trials and storage clamps should be used. The bottom down- survey should be conducted to ensure a
• Safety and efficiency are enhanced comer plate is the weakest plate, so it must smooth ride that is free of bumps.
for the tray installation team be stiffened and provided with downcom- Balance work at site after erection.
• Tray installation and column er brackets to maintain the flow area below After the column is erected at the site,
dressing work can be done the downcomer and avoid vibration. Edge column access holes and tray access ways
together, which saves time. clamps and beam clamps should be placed should be opened again to inspect all
at close pitch for the friction clip. trays. Bracing beams should be removed.
Challenges of installing trays in col- All bolting and clamps must be Additionally, if required, leakage tests of
umn horizontal position: The chal- checked for tightness, using torque liquid holding parts (e.g., seal pans/draw-
lenges of installation trays in the column wrenches. Care should be taken not to off pans) should be conducted, as per
horizontal position include: damage the clamp by overtightening. For design requirements. After these steps
• Additional weight of trays must be larger-diameter plates, the use of thicker are finished, clearance to box up the trays
considered for the column erection clamps is recommended. can be issued.
• Closer manufacturing tolerance It is difficult to hold the tray plates in a
for tray support ring and bolting vertical position when the column is hori- Takeaway. The methodology reviewed
bars, which helps maintain the zontal. Additional cleats can be welded to in this article can be easily used for col-
tray levelness and the fitting of the column wall (FIG. 4). Cleats should umn diameters of 1,200 mm–3,000 mm.
additional parts have a narrow gap of tray thickness plus In smaller-diameter columns, it is difficult
• Closer inspection and measurement 3 mm between the support rings. The tray for a technician to work inside in a sitting
of tray parts and downcomers, plate should be inserted within this gap position. For larger-diameter columns, the
per the tolerances specified by and then clamped to support the ring. weight of trays and supporting structures
the design Additional bracing beams across the may be significant, which may require an
• Placement of column on temporary diameter (FIG. 4) must be provided. The additional working platform and scaffold-
saddle in desired orientation for ease bracing beams can be made of any in- ing with weight-handling hoists inside.
of entering and handling tray parts expensive material (wooden batten or With the outlined suggested methods,
field tray installation work—which nor-
mally runs for weeks at a site—can be re-
duced to days.
PRAMOD DIXIT works as a
freelance Consultant in Baroda,
India. He spent 20 yr at Engineers
India Ltd., working as a tray and
tower internals specialist. He has
another 20 yr of senior-level
experience at Larsen & Toubro
and Essar Offshore. He provides training, consulting
services and troubleshooting to operating and
engineering companies for static equipment, trays
and tower internals. He holds a BTech degree in
mechanical engineering from the Indian Institute
FIG. 4. Tray assembly items held by bracing beam. of Technology at Roorkee, India.

20 SEPTEMBER 2020 | HydrocarbonProcessing.com

You might also like