Professional Documents
Culture Documents
1.
SCOPE
This procedure applies to the installation of formwork
and the controls required during assembly, erection
and final positioning of formwork used in Structural
concrete operations.
Project
Engineer
Contract
Specs.
Project
Shop
Drawings
Project
Director/
Manager/
Resources
Manager
General
Foreman
Formwork
Shop
drawings
2.
PROCEDURE
.1
.2
.3
.4
.5
.6
.7
Foreman
Gen.
Foreman/
Designer
Gen.
Foreman
WORK PROCEDURE
PROJECT: PROJECT NAME
SECTION:
CONCRETING
SUBJECT:
CONTROL OF FORMWORK
.8
.9
.10
.12
.13
.14
.15
.16
.17
.18
.19
VERIFY
CONC/04/
A
CONC/04/
A
CONC/04/
A
WORK PROCEDURE
PROJECT: PROJECT NAME
SECTION:
CONCRETING
SUBJECT:
CONTROL OF FORMWORK
.21
When unsleeved tie bars are being used, ease them Gen.
slightly before the concrete sets, and remove them as Forema
soon as it is safe.
n
.22
Check
sheet
ii)
.23
ii)
iii)
iv)
Project
Safety
Plan