Professional Documents
Culture Documents
EXECUTIVE SUMMARY
PT.PLN(PERSERO)
(Indonesia
November 2011
China
Executive Summary
Table
of
Contents
1 Introduction ................................................................................................................................ - 1 1.1 Background of the project ............................................................................................... - 4 1.2 Basic conditions of Karama No.1 Hydropower project ................................................ - 5 1.3 Reference Standard .......................................................................................................... - 7 2. Project Survey ........................................................................................................................... - 9 2.1 The mapping data available ............................................................................................ - 9 2.2 Mapping work arrangement ......................................................................................... - 10 2.2.1 Finished work at stage 1 ...................................................................................... - 10 2.2.2 Finished work at stage 2 ...................................................................................... - 10 2.3 Finished surveys ..............................................................................................................- 11 2.3.1 Achievements at stage 1 ....................................................................................... - 11 2.3.2 Achievements at stage 2 ....................................................................................... - 11 2.4 Residual survey work .................................................................................................... - 12 3. Study on hydrology and sediment.......................................................................................... - 13 3.1 Overview of drainage basin........................................................................................... - 13 3.2 Basic data ........................................................................................................................ - 13 3.3 Meteorology .................................................................................................................... - 14 3.4 Runoff.............................................................................................................................. - 15 3.4.1 Runoff of reference stations ................................................................................ - 15 3.4.2 Damsite runoff ...................................................................................................... - 16 3.5 Flood ................................................................................................................................ - 17 3.5.1 Probable maximum flood .................................................................................... - 17 3.5.2 Frequency flood .................................................................................................... - 17 3.6 Sedimentation ................................................................................................................. - 20 3.7 Stage-discharge relation ................................................................................................ - 20 3.8 Specialized hydrologic station planning....................................................................... - 20 4 Engineering geology ................................................................................................................. - 20 4.1 Investigation Brief .......................................................................................................... - 20 4.2 Regional Geology ........................................................................................................... - 21 4.2.1 Topography ........................................................................................................... - 21 4.2.2 Stratigraphic Lithology ....................................................................................... - 21 4.2.3 Geological Structure & Earthquake ................................................................... - 21 4.2.4 Volcanic Activity ................................................................................................... - 22 4.2.5 Hydrogeology ........................................................................................................ - 22 4.3 Geology in Reservoir Area ............................................................................................ - 22 4.3.1 General Geology ................................................................................................... - 22 4.3.2 Engineering Aspects ............................................................................................. - 23 4.4 Geology at Upstream Dam Site ..................................................................................... - 25 4.4.1 Dam Site ................................................................................................................ - 25 4.4.2 Waterway System ................................................................................................. - 26 4.5 Downstream Dam Site ................................................................................................... - 27 4.5.1 Power System........................................................................................................ - 29 4.5.2 Sluice Tunnel......................................................................................................... - 30 4.5.3 Spillway ................................................................................................................. - 30 -
Executive Summary
4.6 Construction Material ................................................................................................... - 30 5 Seismicity .................................................................................................................................. - 31 5.1 Tectonic Features............................................................................................................ - 31 5.2 Seismic Activity .............................................................................................................. - 31 6 Study on power market............................................................................................................ - 32 6.1 Design target year .......................................................................................................... - 32 6.2 Power supply scope ........................................................................................................ - 32 6.3 Existing problems for power grid ................................................................................. - 32 6.4 Load forecasting ............................................................................................................. - 32 6.5 Load curve ...................................................................................................................... - 33 6.6 Development and planning of power supply ............................................................... - 33 6.7 Preliminary power balance of power system ............................................................... - 34 7 Project Layout Selection .......................................................................................................... - 34 8 Project scale .............................................................................................................................. - 35 8.1 Selection of normal pool level ....................................................................................... - 35 8.2 Selection of level of dead water ..................................................................................... - 36 8.3 Selection of installed capacity ....................................................................................... - 36 9 Recommended project arrangement ...................................................................................... - 37 9.1 Project ranking and flood control standards .............................................................. - 37 9.2 Water retaining structure .............................................................................................. - 38 9.3 Water release structures ................................................................................................ - 38 9.4 Diversion power generation system .............................................................................. - 39 9.5 Powerhouse and switching station ................................................................................ - 39 9.6 Treatment of foundation and side slope ....................................................................... - 40 9.6.1 Foundation treatment .......................................................................................... - 40 9.6.2 Side slope treatment and protection ................................................................... - 41 9.7 Safety monitoring design ............................................................................................... - 42 10 Permanent and temporary facilities ..................................................................................... - 43 10.1 Construction design ..................................................................................................... - 43 10.2 Fire fighting design ...................................................................................................... - 43 10.3 Permanent camp .......................................................................................................... - 44 11 Construction organization design ......................................................................................... - 45 11.1Construction conditions ................................................................................................ - 45 11.2 Natural construction materials ................................................................................... - 45 11.3 Construction diversion................................................................................................. - 45 11.4 Main works construction ............................................................................................. - 46 11.5 Construction traffic and general layout of construction .......................................... - 46 11.6 Overall construction schedule ..................................................................................... - 47 12 Hydraulic machinery ............................................................................................................. - 47 13 Metal structures ..................................................................................................................... - 47 14 Electric equipment ................................................................................................................. - 47 15 Transmission Line .................................................................................................................. - 48 16 Environmental impact assessment ....................................................................................... - 49 16.1 Environmental conditions of project area ................................................................. - 49 16.2 Environmental impact forecasting and evaluation ................................................... - 49 16.2.1 Water environment impact forecasting ............................................................ - 49 -
Executive Summary
16.2.2 Impact of engineering inundation land occupancy ......................................... - 50 16.2.3 Ecological environment impact......................................................................... - 51 16.2.4 Adverse impact during construction period .................................................... - 52 16.2.5 Impact on the social economy ........................................................................... - 53 16.2.6 Discharge amount of sewage and domestic garbage during operating period- 54
16.3 Countermeasures and measures for environmental protection ............................... - 54 16.3.1 Environmental protection measures during construction.............................. - 54 16.3.2 Water and soil conservation measures ............................................................. - 55 16.3.3 Ecological conservation measures .................................................................... - 56 16.4 Environment management and monitoring .............................................................. - 57 16.5 Environmental protection investment estimate ........................................................ - 57 16.6 Environmental assessment conclusion ....................................................................... - 57 17 Reservoir Inundation and permanently Land Requisition ................................................ - 57 18 Investment estimate ............................................................................................................... - 60 19 Economic and financial evaluations ..................................................................................... - 60 19.1 Financing scheme ......................................................................................................... - 61 19.2 Calculation conditions ................................................................................................. - 61 19.3 Calculation results ....................................................................................................... - 61 19.4 Economic evaluation .................................................................................................... - 62 20 Legal Environment Analysis and Evaluation ...................................................................... - 62 20.1 Legal Environment ...................................................................................................... - 62 20.1.1 Current Situation of PPP/IPP Development in Indonesia .............................. - 64 20.1.2 Current Situation of the Development of Indonesian Electricity Legislation- 65
20.1.3 Stakeholders in PPP/IPP in Indonesia.............................................................. - 66 20.2 The Basic Legal Issues of the Project ......................................................................... - 66 20.2.1 Business Architecture......................................................................................... - 66 20.2.2 Developing Process ............................................................................................. - 67 20.2.3 Risk Evaluation .................................................................................................. - 71 20.2.4 Cooperation Mode ............................................................................................. - 71 20.2.5 Government Support ......................................................................................... - 71 20.2.6 Contract Structure ............................................................................................. - 73 20.3 Principal Legal Issues .................................................................................................. - 73 20.3.1 Investment Access .............................................................................................. - 73 20.3.2 Project Company................................................................................................ - 73 20.3.3 Land Acquisition ................................................................................................ - 74 20.3.4 Government Guarantees ................................................................................... - 74 20.3.5 Grid Connection ................................................................................................. - 75 20.3.6 Investment Incentives ........................................................................................ - 75 20.3.7 Environmental Protection ................................................................................. - 76 20.3.8 Natural Resources .............................................................................................. - 76 21 Conclusions ............................................................................................................................. - 77 22 Suggestions.............................................................................................................................. - 79 -
Executive Summary
Unit
Quantity or features
km2
5406
Year
30
100 million m3
145.3
m3/s
460.6
m /s
9897
PMF
m3/s
14026
10,000t
510.9
Remark
I Hydrology
1. Catchment area
5.Sediment
Annual average sediment inflow
Annual average sediment content
kg/m
0.29
m.
115.83
m.
115.00
m.
85.00
3
100 million m
14.45
100 million m3
10.52
100 million m3
2.98
Service
20 years
2. Hydropower works
Installed capacity
MW
450
GWh
2412
5360
Plant factor
Design head
for
20 years
Service
0.61
m
71
Annual regulation
-1-
for
Executive Summary
III.
Reservoir
inundation
and
hm2
8118
hm2
5977
Person
8447
10,000m2
21.23
hm2
1077
hm2
232
hm
51
Roller compacted
concrete gravity dam
Foundation characteristics
Degree
Crest elevation
m.
117
m.
119
Length at crest
m.
317
m.
93
No.-m
5-1422
m3/s
9897
m3/s
13895
m3/s
179
m.
66.70
3. Power intake
Design unit discharge
invert elevation
Type
Bell mouth
4. Power Houses
Type
Dimension of powerhouse (Length
127.043.1559.70
m.
30.6
Width Height)
Setting elevation of turbine
-2-
Executive Summary
5.Switchyard
Type
GIS
mmm
79.21323.60
electro-mechanical
equipment
No. of hydraulic turbines
Set
Model
HL247-LJ-430
Rated head
m.
71
Rated output
MW
114.80
No. of generators
Set
Model
SF112.5-40/990
Unit capacity
MW
112.50
Set
Model
SSP10-135000/275,
3032x2.5%/15.75kV
Yn,dll,ONWF,Ud%=14%
V. Construction
1.Quantity of main works
Earth-rock excavation
10,000m3
Earth-rock backfilling
10,000m
5.09
10,000m3
170.71
43076
Curtain grouting
m.
25292
Consolidation grouting
m.
80764
Person
3500
kW
18000
454.60
Diesel
generator
unit
4. Access (highway)
Distance
km
59
Tunnel diversion
6 Period of construction
Preparation
Year
1.7
-3-
Executive Summary
Construction
Year
4.1
Year
4.5
GWh/year
Investment
GWh/year
excluding USD*1000
896
2412
1,335,516
transmission cost
Total transmission cost
USD*1000
63,412
1 Introduction
1.1 Background of the project
Karama No.1 Hydropower project is located on the Karma River in West Sulawesi Province of
Sulawesi Island in the east of Indonesia.
In West Sulawesi Province, the maximum load was 30MW, the electricity consumption was about
120GWh, the installed capacity of power stations (fuel-fired generator units) was only 5MW, and a
capacity of 25MW was in short in 2009. At present, the power grids of West Sulawesi Province and
South Sulawesi Province are connected through the 150kV power transmission wire. In South
Sulawesi Province, the maximum load was 565MW, the electricity consumption was about
3,012GWh, the installed capacity of power stations was only 542MW, and a capacity of 23MW was
in short in 2009. Due to the insufficient installed capacity, power is frequently cut off by pulling the
switch, and also some potential users are unable to purchase the electricity by accessing to the
power grid. According to prediction, the power grids of West Sulawesi Province, South Sulawesi
Province, Southeast Sulawesi Province and Central Sulawesi Province will be connected in 2013;
until 2020, the four provinces power grids will have a maximum load of 2,536MW, the electricity
demand will be 1,2879GWh, the total installed capacity of the power stations both constructed and
under construction will be 1,371.4MW, and a capacity of 1,164.6MW is in shortage. In order to
release the current tension situation of power grids and the demands of potential users, it is
necessary to construct the Karama No.1 Hydropower project.
-4-
Executive Summary
Executive Summary
above-mentioned four provinces and satisfy the demands for electric power and electric quantity
along with the increase of power grid load.
Except for supplying electric power and electric quantity to power grids, Karama No.1 Hydropower
project also can be used for fishing and tourism, providing more employment opportunities during
the construction period so as to promote economic development and flourishing in the project area.
At present, there is no highway passing through the dam site of the Karama No.1 Hydropower
project The road nearest to the dam site is located in Pokarawaan Village, 22km downstream of the
dam site. From Pokarawaan Village to Tarailu Town near the river mouth, there is a road available,
with the corresponding class IV road surface of 4-6m wide, and the bituminous concrete pavement
of about 3.5m wide but seriously damaged. There is a provincial highway from Tarailu Town to
Belang Belang Port (31km) and from Belang Belang Port to capital Mamuju (58km), with good
road conditions.
It is a tropical rainy climate in West Sulawesi Province, and the annual mean temperature is
25~27, with a small temperature difference. Due to the influence of monsoon, there are two
seasons in a year, including the dry season from June to October and the wet season from
November to May. According to the statistics rainfall data from 1983 to 2007 of the weather station,
the annual precipitation is about 2,000~4,200mm and the maximum precipitation is 4,173mm in
1995. In addition, the precipitation change is tiny in wet season and dry season, and the
precipitation in dry season accounts about 40% of the annual precipitation.
-6-
Executive Summary
KARAMA River
KARAMA No.1
KARAMA River
KARAMA No.2
KARAMA No.3
Bone Hau River
Tandokratte
KARAMA No.4
(1)
Code on Compiling Feasibility Study Report of Water Resources and Hydropower Project
(DL/T5020-93);
(2)
Standard for Classification and Flood Control of Water Resources and Hydroelectric
Project SL252-2000
-7-
Executive Summary
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(PEKERJAAN HIDROMEKANIK,
PELENGKAP)
INSTRUMENTASI
DAN
BANGUNAN
-8-
Executive Summary
2. Project Survey
2.1 The mapping data available
For the whole project area, there are 18 sheets of topographic maps with the contour line of 25m
and the scale of 1:50,000 produced in 1991, as provided by West Sulawesi Province, Indonesia.
Four (4) order-2 GPS points provided by Administration of Land and Resources in West Sulawesi
Province have been collected.
Three (3) control points, namely BM0, BM1, and BM2 in Belang Belang wharf have been
collected.
-9-
Executive Summary
Executive Summary
The finished survey achievements on layout of the control points (plane and elevation) at stage
1 are shown as follows:
Control surveying
order-3 GPS
33
order-4 GPS
24
order-3 standard
140km
30km
30km
Executive Summary
Five survey lines of cross sections for construction of lower dam site, with a total section length of
3.34km.
Six survey lines of cross sections for construction of upper dam site, with a total section length of
2.17km.
Scale for section mapping: 1:1000 (transverse); 1:100 (longitudinal)
(2) Topographic survey
S No.
Mapping position
Scale
Mapping area
1:1000
2.67km2
1:1000
2.45 km2
1:1000
2.27 km2
1:1000
1.22 km2
6# gravel yard
1:1000
1.13 km2
8# gravel yard
1:1000
0.45 km2
1:1000
0.78 km2
1:1000
0.54 km2
Executive Summary
(8) The number of survey lines in the large section of river course in reservoir area is about 66.
Executive Summary
Kaluku Hydrologic Station: located on Kaluku River, south of Karama River and about 40km away
from Karama damsite with discontinued hydrologic data from 1999 to 2006.
Maloso Hydrologic Station: located on Maloso River, south of Karama River and about 110km
away form Karama damsite with discontinued hydrologic data from 1977 to 2006.
Mamasa Hydrologic Station: located on Mamasa River, south of Karama River and about 110km
away form Karama damsite with discontinued hydrologic data from 1979 to 2006.
PLN has provided the flow data of Bakaru No.1 HPP and Poso-2 HEPP. Bakaru No.1 HPP is on
constructed on River Mamasa, having a drainage area of 1080km2. It is located downstream from
Mamasa gauge station, where the flow records observed in 1979-1980 and 1982-2010 are available.
Poso-2 HEPP is located in the middle northern part of Sulawesi Island; the drainage area up to the
outlet of Poso Lake is 1754.7km2. The derived inflow data of Poso Lake between 1972 and 2005
are available.
(2) Data analysis of hydrologic station
From the actual measured water stage and discharge relations of plotted for each station, which
show that there is only few actual measured flow rate of low water level and there is no actual
measured flow rate of high water level. The actual measured water levels of Karama Station and
Kaluku Station are affected by tides due to nearer to the seaside, so it is not adequate to use them for
extension of the level-discharge relation and calculation of the river flow.
The stage and discharge relations are quite good for Mamasa Station and Maloso Station. The actual
measured flow rate is about 350m3/s and high water level of the stage and discharge relations are
extend according to actual measured stage and area relation, actual measured stage and velocity
relation, and actual measured stage and discharge relation. The observed data from Mamasa and
Maloso stations are much better with certain accuracy, so it is basically reliable.
3.3 Meteorology
Indonesia belongs to tropical rainy climate. Affected by eastern and western monsoon, it is
generally divided into the dry season and the wet season. From June to October, it is affected by the
eastern monsoon with small moisture content and forms the dry season. From November to next
May, it is affected by the western monsoon with large moisture content and forms the wet season.
- 14 -
Executive Summary
According to the statistics of meteorological data of Majene Meteorological Station from 1983 to
2009, the annual precipitation has been 1530mm for many years. The mean annual precipitation of
dry season (June to October) is 359.4mm, accounting for 23.6% of the total year. The average
annual precipitation of wet season (November to next May) is 1170.6mm, accounting for 76.4% of
the total year. The largest annual precipitation is 2446mm occurring in 1988 and the smallest annual
precipitation is 905mm occurring in 1991. The average evaporation capacity has been 1748mm for
many years. The average annual temperature has been 27.6 for many years with the highest of
39.2 and lowest of 18.2. The average relative humidity has been 79% for many years. The
average wind speed has been 2.7m/s for many years with the maximum of 12.3m/s.
3.4 Runoff
3.4.1 Runoff of reference stations
(1) Runoff characteristics of reference stations
The two reference stations only have daily average water levels; therefore, daily average discharge
should be inferred on the basis of daily average water level and stage-discharge relation.
Daily average discharge of the two reference stations can be obtained on the basis of actual
measured daily average water level and extended stage-discharge relation of the two reference
stations. Data of 27 years (1979~2006, except 2001) of Mamasa Station are available and data of 16
years (1977~1979, 1983~1985, 1991~1996 and 2003~2006) of Maloso Station are available.
The average discharge of 27 years of Mamasa Station is 58.2m3/s and the annual runoff is 1,830
Mm3. The largest annual runoff is 3,230 Mm3 (in the year of 2002) and the smallest annual runoff
is 1,120 Mm3 (in the year of 1982) with the extreme value ratio of 2.89. The average discharge of
16 years of Maloso Station is 85.6m3/s and the annual runoff is 2,700 Mm3. The largest annual
runoff is 4,180 Mm3 (in the year of 2005) and the smallest annual runoff is 1,480 Mm3 (in the year
of 1991) with the extreme value ratio of 2.82.
(2) Runoff interpolation and extension of reference stations
Theres only 14 years actual measured runoff series of Mamasa Station and Maloso Station. So
theres no way to interpolate the missing annual runoffs and no other data available. Therefore, the
correlativity of annual runoffs in the same period of Mamasa Station and Maloso Station is
formulated to interpolate the annual runoff series of the two stations. The correlativity is quite good
- 15 -
Executive Summary
with the coefficient of 0.84. The measured annual mean flow is applied for those missing runoff in
2001, and interpolation and extension will be made with each other for other missing data. After
interpolation, the 30-year (1977~2006) average discharge of Mamasa Station is 57.7m3/s with
runoff depth of 2004mm (2021mm for actual measured runoff depth in many years); the 30- year
(1977~2006) average discharge of Maloso Station is 86.3m3/s with runoff depth of 3368mm
(3341mm for actual measured runoff depth in many years).
(3) Flow at Bakaru No.1 HPP and Poso-2 HEPP
It is calculated the annual mean flow at Bakaru No.1 HPP is 63.0m3/s. After interpolation, a
complete flow series in 1977-2006 is available at Mamasa gauge station, with the mean annual flow
calculated at 57.7m3/s. Considering that the drainage area of Mamasa gauge station is 908km2, and
that the mean annual flow at Bakaru No.1 HPP is 63.0m3/s, this flow result calculated at Mamasa
gauge station is satisfactory. Poso-2 HEPP is located in the middle northern part of Sulawesi Island,
downstream from the outlet of Poso Lake. The drainage area of Poso Lake extends from south to
north, and the drainage area up to the outlet of Poso Lake is 1754.7km2. The mean annual inflow of
Poso Lake is calculated to be 140m3/s. Judging from the location and the distance from Karama
drainage area, the Mamasa and Maloso gauge stations are better suited as the reference gauge
stations in calculating the flow in Karama drainage area. Since the drainage area of Poso Lake is
located in the middle northern part of Sulawesi, not close to Karama drainage area, its flow series
will not be directly referenced in calculating the flow series of Karama drainage area.
3.4.2 Damsite runoff
The landform of Karama drainage area is high in the east and low in the west and its upstream
belongs to mountainous landscape, and its location is similar to Mamasa drainage area. Its
downstream belongs to the transition area from plains to mountain areas and it is similar to Maloso
Station drainage area. Therefore, the average value 2,686mm of average runoff depths of the two
stations is adopted as the value of Karama drainage area.
Taking the monthly runoff process of Mamasa Station as the model, the damsite is established
according to the area and runoff depth. Then the 30-year (1977~2006) runoff series of Karama
Hydropower Station can be inferred. The average annual discharge is 460.6m3/s and the average
runoff is 14,530 Mm3 for many years. In the 30-year (1977~2006) series, the largest annual
discharge is 817.8 m3/s of 2002 and the smallest is 282.5 m3/s in 1982 with the extreme value ratio
of 2.9. Runoff mostly occurs from December to next June which accounts for 70% of the annual
- 16 -
Executive Summary
Statistical parameter
Average
Cv
Cs/Cv
10%
25%
50%
75%
95%
145.3
0.33
4.0
209.4
169.5
135.0
110.0
87.8
3.5 Flood
3.5.1 Probable maximum flood
The Probable Maximum Precipitation (PMP) is the greatest depth (amount) of precipitation, for a
given storm duration, that is theoretically possible for a particular area and geographic location. The
Probable Maximum Flood (PMF) is the flood that may be expected from the most severe
combination of critical meteorological and hydrologic conditions that are reasonably possible in a
particular drainage area.
PMP is estimated by the simple statistical Hershfield method using a series of the annual maximum
daily rainfall records. This method is widely applied in the basin where rainfall records are available
but other basic climatological records are hardly obtainable.
The preliminary computation process of the point PMP at the Kalumpang station is estimated to be
703 mm. The probable maximum flood (PMF) of 14.026 m3/sec.
3.5.2 Frequency flood
(1) Design flood at reference stations
Data series of Mamasa Station are adopted in analyzing damsite design flood because the Maloso
reference station only has short-time data series and is lack of statistic analysis of peak discharge
and period flood volume.
- 17 -
Executive Summary
Years with instantaneous highest water levels of Mamasa Station are 1991, 1992, from 1995
through 2000, 2004 and 2006. The flood peak of these years can be obtained by instantaneous
highest water levels and stage-discharge relations. The flood peak of those years without
instantaneous highest water levels can be obtained by establishing the correlation of the concurrent
instantaneous flow and the corresponding daily mean flow.
It is analyzed that the flood hydrograph at the reference station is in general not more than 15 days.
Thus, the flood volume at certain period will adopt the annual maximum 24h, 3d, 7d and 15d
periods. The annual maximum 24h flood volume will be obtained based on maximum 1d flow
records to be magnified via the factor of 1.1. The factor of 1.1 will need to be verified later via the
measured data. According to the statistics, the 27-year flood volume series of 1979-2006 obtained
from Mamasa station is not continuous.
After analysis, the correlativity of peak discharge and period flood volume of Maloso Station and
Mamasa Station is quite weak. The data series of Mamasa Station cannot be extended. Therefore,
calculate the empirical frequency according to even sequence series on the basis of 27-year flood
peak and flood volume series of Mamasa Station. Draw the Figure with theoretical frequency curve
of P-III type.
See Table 3.5-1 for design flood results of Mamasa Station.
Table 3.5-1 Design flood results of Mamasa Station
Flood peak in m3/s and flood volume in 104m3
P (%)
Item
Average value
Cv
Cs/Cv
0.1
0.2
10
Qm
652
0.63
3352
3013
2235
1906
1479
1164
W24h
2750
0.64
14405
12935
9564
8139
6292
4937
W3d
6300
0.72
38099
33941
24466
20496
15406
11735
W7d
12000
0.75
76371
67845
48462
40367
30030
22620
W15d
18800
0.66
102191
91570
67268
57014
43772
34091
Executive Summary
China GeZhouBa Group Company Limited (CGGC in short) has sent a group of professionals to
Indonesia from June 11 to June 28, 2011 for survey of the historical flood for Karama River, with
the investigation emphasized on the Karama stretch from Pedasi village to the upper dam site.
Pedasi village is located on the left bank of Karama River downstream of the dam site. According to
memory of a 48-year-old villager, the a severe flood in Karama river happened in 2004 when the
village was flooded with the flood depth of more than 1.0m, and he remembered the flooding traces
on a huge tree. The 2004 flood is the flood event all villagers experienced in recent years, so the
villagers verification of this historical flood event is reliable. According to his memory, this is the
maximum flood he ever experienced and no larger flood event than the 2004 flood was happened
from the elders in the village. It is then estimated that the 2004 historical flood is at the occurrence
frequency of one in 40-50 years. It is calculated with Manning formula that the flood peak in 2004
event reaches 6,110m3/s.
(3) Design flood at dam site
The design flood of Karama dam site is obtained by magnifying the design flood of Mamasa Station.
The area ratio index is 0.6667 for peak discharge and 1.0 for flood volume area. These area indexes
need to be verified via the actually measured data. Results of design flood are shown in Table 3.5-2.
Table 3.5-2 Design flood results of Karama Project
(flood peak in m3/s and flood volume in 108m3)
P (%)
Average
Item
Cv
Cs/Cv
value
0.1
0.2
10
20
Qm
2142
0.63
11011
9897
7342
6261
4857
3825
2836
W24h
1.64
0.64
8.58
7.70
5.69
4.85
3.75
2.94
2.17
W3d
3.75
0.72
22.68
20.21
14.57
12.20
9.17
6.99
4.95
W7d
7.14
0.75
45.47
40.39
28.85
24.03
17.88
13.47
9.40
W15d
11.19
0.66
60.84
54.52
40.05
33.94
26.06
20.30
14.82
- 19 -
Executive Summary
3.6 Sedimentation
Currently there is no sediment measurement data. Catchment area of Bakaru reservoir near Karama
is 1080 km2, and mean annual sediment yield is 7.53 Mm3/year. According to the dam site
catchment area of 5406.09 km2, and reference on the sediment data of Bakaru reservoir, by means
of amplifying the area ratio, then the annual sediment yield of No.1 Hydropower Station at Kalama
can be calculated as 3.784 Mm3.
4 Engineering geology
4.1 Investigation Brief
Primary Study Report of Hydropower Potential along Karama River (kegiatan kajian
pengembangan enrgi sungai Karama provinsi sulawesi barat) was prepared by two professors of
`rogram has been proposed and implemented during this investigation. Investigation methods
include recheck of regional linements, geological mapping, drilling, geophysical survey, exploratory
shaft/pit/trench, field and Laboratory Testing, and so on.
- 20 -
Executive Summary
- 21 -
Executive Summary
Executive Summary
The rock formations are less affected by tectonic activities and featured by sparsely spaced joints.
Sedimentary rocks generally show a monoclinal structure with localized anticlines and synclines.
The rainfall is rich in the project area. Groundwater at reservoir area includes fracture water in
bedrock and phreatic pore water in loose Quaternary deposition.
According to Location Map of Mineral Deposits in West Sulawesi Province, Indonesia, several
minerals have been reported in reservoir area of No.1 HEPP, such as coal, gold, iron and copper.
Rock mass at the reservoir area is dominantly acted by physical weathering. Stress-relief action is
prevalent on steep slopes flanking the tributary stream due to deeply and quickly cut of valleys.
Loose debris or landslide deposits are accumulated at the foot of slopes at where are occupied
mainly by claystone and argillaceous siltstone with less vegetable located at upstream of Village
Kalumpang.
4.3.2 Engineering Aspects
(1) Reservoir Seepage
Since the reservoir is surrounded by massive hills and mountains, as well as major tributaries on
reservoir rim have perennial flow and drain into Karama River, the reservoir is topographically
water tightness.Therefore, it is preliminarily concluded that the reservoir rim should be water tight.
Upstream of where the Bone Hau River enters, the reservoir is confined within slightly open valley
with generally gentle slopes, widely occupied by claystone, argillaceous siltstone and sandstone.
Though the natural slopes are generally stable, slumping and slipping may occur on where slope
mainly comprising claystone and argillaceous siltstone under actions of reservoir water and its
waves due to their weak strength and low weathering resistance. The slide area and stability of
slopes occupied by claystone and argillaceous siltstone may be affected adversely by the reservoir
impoundment and operation, and slopes of reservoir may become gentle under such geological
process.
Downstream of the confluence of stream Bone Hau with river , the valley is V shaped with
generally steep slopes, dominantly occupied by massive volcanic rocks and sed pyroclastic rocks
with rare discontinuities. Thus, the slopes are stable except local rock toppling/falling at places.
The other flanks of the reservoir to be submerged is composed of thinly to moderately bedded
sandstone, siltstone and silty claystone with poorly developed discontinuities, which steeply dips
- 23 -
Executive Summary
and runs obique to the nullah in general, the bedding joint on left flank dipps towards the slope at an
angle steeper than the slope, while on right flank dipps inwards the slope, so the slopes are
generally stable.
(2) Inundation and Immersion
At the end of reservoir, the majority of land, forest and housing are on the terraces above the Full
Reservoir Level, however, they may be impacted by impoundment of reservoir due to uplift of
groundwater level.
(3) Solid Sedimentation
The Karama River, Bone Hau River and tributary gullies on both banks produce a considerable
amount of sediments, most of which originated from gravels and cobbles carried during flood
season as they are lying on their course, decomposed sandstone, claystone, volcanic rocks and
minor amount of rebuilt debris. However, since the reservoir rims are covered by dense vegetation,
the sedimentation volumes involved are insignificant compared with the total reservoir volume.
(4) Reservoir Induced Earthquake
As the pool water level will be raised about 80 m in front of the dam after the completion of the
project, state of ground stress would be considerable changed in reservoir and adjacent area.
Furthermore, a main fault extends across the reservoir area about 2.6km upstream of the upstream
dam site, which is compressive fault with weakly permeable. Therefore, it is preliminarily
concluded that there is low possibility to occur earthquake induced by reservoir, additional studies
would be necessary to conclusively address this issue based on analysis of regional faults activity.
(5) Impacts on Mining
Since mineral deposits in reservoir area are still in prospecting without yield so far, it is difficult to
evaluate the impacts of pool impoundment on minable mineral. It is recommended to refer
professional agency to conclusively address this issue.
- 24 -
Executive Summary
Executive Summary
Executive Summary
groundwater level. Given the influenced factors, stability of surrounding rocks along the tunnel
section is fair mostly falls into Class III, while at inlet and outlet portal is poor to very poor into
Class IV~V.
The natural slopes at the proposed powerhouse area is relatively steep, thus, slopes at the back and
left flank of powerhouse will be high after excavation. Since the project area has rich rainfall, it
would have significant effect on stability of slope and should be taken into consideration in design.
Executive Summary
deposition and fracture water in bedrock. Groundwater level is higher than the river level.
The permeability of slightly weathered to fresh rock mass varies mildly, belongs to weakly
permeable in general and slightly permeable locally. The permeability of rock mass at shallow depth
is controlled by weathering and stress-relief action.
Both river water and groundwater falls into HCO3 - CaMg type, the groundwater on right flank has
no erodibility to conventional concrete and weak erodibility to steel structure; while river water has
weak bicarbonate erodibility to conventional concrete and weak erodibility to steel structure.
(2) Engineering Aspects
The rock mass presents blocky to very blocky in two Grades five sub kinds structures, i.e. blocky,
very blocky, thickly bedded, intermediately bedded and thinly bedded structure in point view of
Code for engineering geological investigation of water resources and hydropower (GB50487-2008).
The rock mass are preliminarily classified as Class CIII, and CIV considering compressive strength,
structure, weathering degree, integrity and characteristics of rock mass, wave velocities of seismic
survey and so on.
Rolled Concrete Gravity Dam
The loose overburden layer is incompetent for dam foundation and should be stripped wholly. The
underlying slightly weathered to fresh rocks are sound but weak, significant settlement and
deformation should be expected under the applied load due to their low strength.
Concrete Faced Rockfill Dam:
The thick loose overburden layer can be used as dam foundation if suitable treatment is taken to
enhance its bearing capacity. Since the river deposits of sandy gravel is very highly to highly
permeable, seepage cut measures should be taken duly. Since sand layer and/or lenses may present
in river deposits, adverse effects should be expected on dam foundation stability against sliding in
case that the rockfill dam is based on river deposits. Since the rocks on both flanks is highly
weathered and stress-relieved within limited depth, it is suggested to rest the concrete plinth on
lower portion of moderately weathered rocks and the rock embankment on highly weathered rocks
- 28 -
Executive Summary
and /or river deposits of sandy gravel after stripping the top fine material. Though the persistence of
fine sand layer is unkown, liquefaction potential under larger earthquake should be considered in
the case that the rockfill dam is based on river deposits.
Given the distribution of the valley and exposed rock strata, deep depression zone can not be
excluded so far and should be further investigated in next stage.
The both abutments are of high slope. Though the natural slopes are generally stable, the slopes are
composed of soft rock mass, attention should be paid duly to the adverse factors, such as
construction disturbance, destruction of vegetation, actions of reservoir water and its waves and
rainfall, especially prolonged dense rainfall.
4.5.1 Power System
The area is mainly covered with talus debris soil and thick vegetation, scattered with tuff and
volcanic breccias outcrops. The underlying rocks are mainly composed of sandstone, siltstone and
argillaceous siltstone at intake portal area, of tuff and volcanic breccias along twin tunnels, and of
volcanic breccias at powerhouse area. Though the integrity of rock mass is good to fair with
sparsely to moderately spaced joints, it is weak with less strength.
Since rock mass at the intake portal area is composed of strong sandstone and weak siltstone and
argillaceous siltstone, differential settlement problem will be raised under the applied loading.
The headrace tunnel will intersect volcanic rock beds mainly of tuff and breccia. The rock mass is
commonly weak with fair to good integrity, jointed at places. The groundwater level is rather high
and the majority of the tunnels would be excavated below the groundwater level. Fortunately the
rock mass should be weakly permeable in general.
Since the rock formation at the powerhouse area generally strikes northeasterly and dips
northwesterly, it runs outwards and will be adverse for slope stability of the back slope of
powerhouse.
- 29 -
Executive Summary
( numbered Q1 and Q2) on bank slopes were identified, amongst which borrow area 6and 8,
quarry area Q1 and Q2 were selected for preliminary investigation.
Main borrow areas are located on Grade I terraces about 5~6km downstream of the lower site, at
where the upper unit of silty clay, clayey silt and fine sand is several meters thick, and the lower
unit of gravels, pebbles, course sand with cobbles is mostly under the groundwater level. Quarry
area of limestone is located about 1.5~2.5km downstream of the lower site. As limestone presents as
sandwiched layers at steep dipping angle, each of thin thickness, covered by conglomerate with
- 30 -
Executive Summary
variable thickness, it would be difficult for excavation. Quarry area of andesite is located about
2.5km downstream of the upper site, at where the unusable cover is estimated to be rather thick that
should be further verified in next stage so as to determine the economic effect of exploitation. The
materials in selected areas can basically meet the demand both in quantity and quality.
5 Seismicity
5.1 Tectonic Features
The project area is tectonically located at a meeting region of two continental clusters, namely; the
continent of Asia and Australia. The main structural features are faults which trend NE to SW or
NW to SE. In addition there are also bedding fault with highly variable dip direction. Number of
faults and varying dip directions indicate a multi-staged strong tectonic activity.
There is a north-south trending active fault, i.e. Palu-Koro fault, runs across northern Sulawesi. It is
a strike-slip fault, dips NE50, with a length trace of 459km and annual slip rate of 30~44mm. The
shortest distances from the Fault trace to the upstream dam site is about 100 km.
There are three major faults that control the flow and child-Karama River tributaries. A section of
Karama River runs along a fault at upstream of Kalumpang. Two faults control the flow of the
biggest tributary stream Bone Hau River on upstream and downstream reaches respectively.
Executive Summary
Executive Summary
is 12879GWh and the amount of hours using the maximum load are 5078 hours; in 2025, the
maximum load is 4043MW (simultaneity is 1), and electric energy production is 20680GWh and
the amount of hours using the maximum load are 5115 hours.
Executive Summary
Executive Summary
The crest of spillway weir (overflow monoliths) is at El.93.0m, with the net bay width of 14m. The
weir surface uses WES curve, followed by a straight line section with slope ratio of 1:0.85, and the
downstream of the straight line section is connected with a 30m-radius ogee section. Energy
dissipation by trajectory jet is applied. The weir crest working gate is adopted as steel radial gate,
and the maintenance gate is adopted as stop-log gate.
The headrace system is provided at the left bank with a power intake integrated in the dam. The
invert and the crest of the power intake are at El.66.70m and El.117.00m respectively. There are two
headrace tunnels, each of which would be bifurcated to feed two units. In each headrace tunnel, the
trunk is the trunk is 579.02m long and the branches are 60.72m and 50.95m long respectively. The
trunks have a diameter of 10.8m, and their centerlines are spaced at an interval of 40.60m.
The river bank powerhouse is about 550m from the dam axis, and the dimensions of the main
powerhouse are 127.0043.15m (lengthwidth). There are four 112.5MW Francis turbine generator
units installed, with a total installed capacity of 450MW. The powerhouse complex consists of the
main powerhouse, auxiliary powerhouse, switch station and downstream tailrace channel.
8 Project scale
8.1 Selection of normal pool level
It is required to mainly consider technological and economic indicators such as kinetic energy
indicator, reservoirs flooding, hub investment and economic indicator when selecting normal pool
level of Karama No.1 hydropower station. For normal pool level of reservoirs, five schemes are
compared, i.e. 100m, 105m, 110m, 115m, and 120m; the level of dead water of reservoirs is
calculated according to the ratio of drawdown depth and maximum waterhead, i.e. 40%; and
corresponding levels of dead water of reservoirs are 76m, 79m, 85m, and 88m.
(1) In terms of kinetic energy indicator, the higher the normal pool level of reservoirs is, and the
larger the adjusting capacity of reservoir is; and guaranteed output and electric energy production of
power plant are more and the kinetic energy indicator is better.
(2) In terms of reservoir flooding investment and project investment, with increasing normal pool
- 35 -
Executive Summary
level, population needing migration, flooded cultivated land, forest land, land acquisition and
migration resettlement subsidies and project investment are more.
(3) Seen from the perspective of economic internal rate of return (EIRR), when the normal pool
level increases from 100m to 115m, EIRR increases from 11.84% to 13.74%, when the normal pool
level increases from 115m to 120m, EIRR decreases from 13.74% to 13.71%.
To sum up, though the higher the normal pool level is, the better the kinetic energy index will be
but because when the normal pool level lifts from 115m to 120m, the population, land requisition
and residents-relocation grants as well as project investment influenced by the reservoir will be
greatly increased and the economic index of normal pool level scheme of 115m will be the best,
therefore, the recommended reservoir normal pool level will be 115m.
Executive Summary
compared, i.e. 300MW, 350MW, 400MW, 450MW, and 500MW. It is required to select installed
capacity mainly in terms of kinetic energy indicator, project investment and economical efficiency
of supplementing installed capacity.
(1) In terms of kinetic energy indicator, the larger the installed capacity of power plants, the larger
electric energy production is, but the rate of increase in electric energy production, operation hours
of installed capacity and operation hours of supplemented kilowatts gradually decrease.
(2) In terms of project investment, the larger the installed capacity of power plants, the more project
investment is.
(3) Seen from the perspective of economic internal rate of rate (EIRR), when the installed capacity
increases from 300MW to 450MW,
The above economic index shows that, the installed capacity scheme of 450MW is the best,
therefore the recommended station installed capacity is 450MW, annual average generation is
2,412GWh, and the annual utilization hours is 5,360 hours, the utilization rate of the equipment is
0.61.See Table 8.3-2 for the annual power output process of the station representative of good,
normal and poor years.
Executive Summary
important structures such as retaining wall are categorized as Grade III, the temporary hydraulic
structures are categorized as Grade IV. In line with the seismic zoning map of Indonesia (2010
version), the seismic dynamic peak acceleration with probability of more than 10% in the project
zone in fifty-year reference period is between 0.20g and 0.25g (Figure 2.5-3), equivalent to VIII
degree of basic earthquake intensity. Design peak value of seismic ground motion for main
constructions is 0.3g.
Executive Summary
Executive Summary
The three-storey auxiliary powerhouse is located at the left side of the main powerhouse with a
length of 51.7m and awidth of 24.6m.
Executive Summary
quincunx; the hole depth of main impervious curtain adopts 80m according to 0.7 of the dam height
and that of the auxiliary impervious curtain adopts 55m.
(3) Foundation drainage
Set a line of drainage holes linking downstream on downstream side of grouting gallery to reduce
the seepage pressure of dam foundation. The main drainage holes are 2.5m in hole spacing and 25m
in hole depth. Set foundation drainage holes with hole spacing of 2.5m and hole depth of 7m at each
downstream drainage hole and gap of the dam foundation.
(4) Foundation consolidation grouting
In order to strengthen the integrity, increase the elastic modulus and improve the impermeability of
bed rock, grouting treatment shall be carried out for the whole dam foundation plane. The hole
spacing and row spacing are 3m and hole depth is 7m for consolidation grouting.
9.6.2 Side slope treatment and protection
In combination with the geological condition of excavation site, the permanent side slope formed by
excavation shall be treated according to the following principles:
(1) The cover layer of bank slope shall be excavated according to the slope of 1:1.25; set a riding
way of 2-4m every 10m, set a barricade locally and pave a three-dimensional vegetation net on
the surface layer. The excavation slope of alluvial river bed sand gravel stratum shall be 1:1.5
and set a riding way with width of 2-4m every 10m.
(2) Excavation slope of rock: the excavation slope shall be designed according to the geological
condition of side slopes of different rock stratums and construction experience and for
construction convenience, generally a riding way with width of 3m is set every 15m. the
strongly weathered rocks shall be excavated according to 1:1.5, weakly weathered rocks
excavated according to 1:0.7 and slightly weathered rocks excavated according to 1:0.5.
The weakly weathered rocks shall be sprayed with plain concrete with thickness of 10m on the
surface for protection and the strongly weathered rocks shall be sprayed with concrete of 15cm
- 41 -
Executive Summary
thick on the surface with a net hung; for local breaking areas, adopt anchor rods for reinforcement
treatment and PVC drainage pipes with spacing of 3m3m are provided where the concrete is
sprayed.
Executive Summary
Executive Summary
provided with crest access road and its ends are provided with turnaround of fire truck of 15x15m.
The dam area is provided with high and low-voltage power distribution rooms of 100m2, diesel
generator room of 80m2 and water treatment room of 200m2 . The dam crest is provided with hoist
room and oil pump room according to the needs.
The permanent camp is located about 5km from the downstream side of the axis of dam with an
area of 50000m2, field elevation of about 55m and total construction area of 5610m2; it is provided
with 9 units in total, including built-in office building, guard room, dinning hall, duty dormitories,
flood prevention warehouse, machine repair room and water treatment room. The camp is provided
with ring fire fighting lane that can lead to each unit, with width not less than 4m. The spacing
between each building shall not be less than 10m.
The water source for fire fighting is taken from the dam area. The raw water enters water treatment
equipment through the submersible pump and the effluent water enters the gravity and technology
common pool of 400m3 through the fire pump; the fire water supply system is mainly responsible
for the fire water supply of buildings like powerhouse and electromechanical equipment like
generator unit and it is set as permanent high-pressure fire water supply system.
In order to guarantee that the accident will not expand through the ventilation system when a fire
occurs to the powerhouse as well as to create a good working condition for fire fighting, different
fire fighting measures are taken to each ventilation system according to relevant specifications.
Executive Summary
built-in office building, guard room, dinning hall, duty dormitories, flood prevention warehouse,
machine repair room and water treatment room etc. The office building and duty dormitories adopt
3-floor frame structure and other monoblocks adopt single-floor frame structure.
- 45 -
Executive Summary
Executive Summary
at the mouth of Salu Kamassi Trench at the left bank and Trench at the right bank, with weighted
average transportation distance of about 10km.
12 Hydraulic machinery
Karama No. 1 Hydropower project is located at the downstream of Karama River, Sulawesi,
Indonesia. The normal pool water level of reservoir is 115m, the installed capacity is 450MW and
the number of units is 4.
According to the operating water head scope of the station, vertical shaft Francis turbine is used.
The turbine type is HL247-LJ-430 and the rated water head Hr is 71m. The generator Type is
SF112.5-40/990 and its rated capacity is 112.5MW.
13 Metal structures
The metal structures of Karama No. 1 Hydropower project are distributed at the flood-discharge
surface hole, entrance of power tunnel, powerhouse tail water and entrance of diversion tunnel.
There are 28 sluice gates and trashracks, 36 sets of embedded parts and 12 sets of hoists (including
trashrake). Quantities of metal structures are about 4,577t.
14 Electric equipment
Karama No. 1 Hydropower project will connected to Mamuju substation to supply power for four
provinces grid via two circuits of 275kV overhead line. In the Karama power station, Combination
- 47 -
Executive Summary
mode of one generator-one transformer is adopted; 275kV voltage grade is adopted at the step-up
side, and four-circuit main transformer incoming line, two-circuit overhead outgoing line and
double-bus connection wiring are adopted.
The power station will use the full computer monitoring mode, no conventional monitoring is set,
and is designed according to the on-duty way with few people. The concentrated control and
monitoring of main electromechanical equipments in the whole station can be realized through host
machine and operator workstation in the central control room. The system uses the remote control
way to dispatch the power station. Meanwhile, it can make use of the interface supplied by
computer monitoring system to carry out the dispatching. The relay protection uses the
microcomputer type relay protection device. The excitation system of generator uses automatic
shunt excitation and static silicon-controlled excitation way. The excitation regulator uses the
microcomputer type.
According to the status of hydropower station and requirements of incoming system, as for the
dispatching management mode and detailed conditions of hydropower station such as installed
capacity, project arrangement and construction organization after the completion of works,
determining the general communication scheme includes construction communication and
permanent communication. The permanent communication includes the system communication,
in-plant voice communication, external communication and comprehensive communication
network, etc.
15 Transmission Line
According to the local power grid data we collected, analysis of connection to the grid for the
Karama No. 1 Hydropower project was proceded; after calculation of load forecasting, load flow
and short circuit.etc, the energy of the new power station will be transmitted to Mamuju substation
to provide power for four provinces grid. Two circuits of 275kV overhead line will be constructed,
and the Mamuju substation will be updated to ensure the connection.
- 48 -
Executive Summary
Executive Summary
into the water body, it is also capable to cause worse water quality at the initial stage of water
storage upon completion of reservoir.
Since the area of the project location is tropical area at the equator, with an average air temperature
for years of 27.6 and a minimum air temperature over the years of 18.2, the temperatures all
the year round do not change much and the reservoir will build up stable temperature stratification,
without inter-annual change impact. The reservoir will discharge through surface hole after normal
operation, thus the water temperature stratification of the reservoir will not cause obviously adverse
impacts to downstream aquatic organism and fish.
(2) Impact on the hydrologic situation of downstream
The reservoir construction will not cause greater impact on the change in water level at the
downstream of dam site. The discharge of tail water in the reservoir will lead to the increase in
downstream flow within a smaller scope. The fluctuation of hydrologic situation is not obvious on
the whole.
16.2.2 Impact of engineering inundation land occupancy
(1) Impact of engineering excavation and land occupancy on integrity of regional ecosystem and
measures
The construction works will cause the disturbance and damage to the ground surface during
construction. However, except for the permanent land occupancy of works, the construction
production, living area and construction road and so on are just occupied temporarily and the impact
scope is less. In addition, there are no ecological sensitive points near the project. The impact on the
natural ecosystem will be controlled within certain scope by implementing the environmental
protection and water protection measures.
(2) Impact of reservoir inundation
The reservoir construction will inundate all the area within the reservoir range below El 115m.
According to the initial investigation, the biological resources in the inundated area are very
abundant and may involve the endangered animal and plant types. It is necessary to carry out the
investigation and research of special topic in the next stage. Most of land types which are directly
inundated are cultivated land and forest land. The complete change in the way to use the land will
- 50 -
Executive Summary
Executive Summary
of land use within the occupied land range. The land within the scope of permanent occupation will
change the original nature and the new performance will maintain unchanged for a long time; the
land within the scope of temporary occupation will restore its original function or be developed
reasonably according to actual conditions upon completion of the project.
16.2.4 Adverse impact during construction period
(1) Impact of sewage during construction period
The sewage generated by construction is composed of production sewage and domestic sewage. If
the sewage generated by construction is discharged at will, it will cause adverse impact on the
environment of surrounding surface water and it is required to take the sewage treatment measures.
(2) Impact on the air environment quality
The air pollution during construction period is mainly the harmful gas generated by burning diesel
oil by construction machinery and transport vehicle and living fuel of construction personnel and
the dust generated by rock excavation, blasting and mechanical pulverization. The above air
pollution will lead to adverse impact on the on-site construction personnel and ambient
environment.
(3) Impact on the sound environment
The noise source in the construction area is mainly from the noise generated by automatic concrete
mixing system, large excavator, bulldozer, dumper, motor vehicle and blasting. It will affect the
daily life of residential areas which are closer to the construction area and harm the health of
construction personnel and it is required to take the labor protection.
(4) Impact of solid waste
The spoil and abandoned dreg are the main source of water loss and soil erosion and mainly include
the abandoned dreg, building garbage and domestic garbage generated during construction. There
are 3,500 personnel during construction peak period, each person generates almost 1.0kg of
domestic garbage each day and the construction period is 4.5 years, so the garbage will almost
increase by 5,700 tons. If the garbage that is generated during construction is not managed and
treated reasonably, it will cause stink, pollute the water body and harm the population health.
Dumping the solid waste at random will damage the original landform and surface vegetation
- 52 -
Executive Summary
within the land occupied by construction to different degrees. In order to protect the water and soil
resources, it is required to pay attention to the concentrated stacking of spoil and abandoned dreg
during construction and take engineering and plant measures to carry out the protection. It is also
required to carry out the ecological restoration in the construction area where the original landform
is damaged and lessen the impact on the regional ecology due to construction activities as far as
possible.
(5) Impact on the population health
There are a number of outside personnel to station on the site during construction peak time. During
construction, due to incomplete living conditions and worse sanitary conditions, the incidence rate
of pandemic diseases such as dysentery and pneumonia may increase. Due to crowded population
and high construction strength, it may cause the decrease in the disease resistance of construction
personnel and it is easy for them to catch a disease. In addition, if because the accident causes that
the personnel are injured accidentally during construction, they shall go to see a doctor in time in
order to avoid the infection.
16.2.5 Impact on the social economy
The construction of Karama No. 1 Hydropower project of Indonesia does not only improve local
transportation conditions but also creates favorable conditions to promote the development of local
economy along with a plenty of capital investment; at the same time, as for the demand of human
resource, the engineering construction also provides a number of employment opportunities for
local people; the stationing of engineering construction team and demand of daily necessities also
will promote the development of local service industry; it also plays an important role in promoting
the economical development by enhancing the external communication, expanding the information
amount and changing the ideas, etc.
After the reservoirs are built, it is favorable to for a microclimate in the reservoir area, increase the
air humidity and decrease the temperature and it is fit for travel as summer resort. Both the
development of tourism in the reservoir area and perfection of power and water supply facilities in
the towns will have positive impact on the local development.
There are abundant natural resources and better ecological environment in the area at which the
power plant is located. The ethnic customs and beautiful natural landscape make this region have
- 53 -
Executive Summary
great tourism development potential. Along with the development, construction and perfection of
transportation and communication conditions plus rich human environment of this region, it will
certainly substantially promote the tourism development of this region.
Electricity instead of firewood is used for the development and construction of hydropower station,
so less forest trees will be cut and effects of protecting the forest and preserving soil and water will
be achieved, which have active function for keeping ecological balance of regions.
16.2.6 Discharge amount of sewage and domestic garbage during operating period
During operating period of power plant, there will be 150 personnel in the management department
and almost 14.4m3/d domestic sewage each day. The domestic sewage includes the sewage in the
kitchen and that for washing, etc. The main pollutants are organic pollutant, ammonia nitrogen and
fecal coliform, etc. If the production garbage during operating period is calculated by 1kg of
average generated amount per person per day, there will be 150kg of domestic garbage every day. It
is necessary to take measures to treat the domestic sewage and garbage in the engineering
management area during operating period.
Executive Summary
domestic sewage in the living area and discharge or recycling it to the required standard. In addition,
it is required to build temporary dry closet and mobile toilet in the construction area and to clean
them regularly.
(2) Air pollution prevention measures
In the process of loading and unloading the cement, it is necessary to keep excellent sealing state;
the side slope angle to stack the aggregate shall not be too big and it is required to appropriately add
the humidity in order to avoid the fine aggregate from being blew away by wind; add the water
firstly and then add the materials in order to avoid the cement from running away when mixing the
concreter; it is required to water frequently in the process of soil excavation; when loading the dusty
materials, it is necessary to cover the materials with canvas or properly add their humidity and often
clean the transport vehicle; regularly maintain the mechanical equipment.
(3) Noise pollution prevention measures
Adopt the production equipment with lower noise and advanced protection technology as far as
possible; enhance the maintenance of equipment; the on-site construction personnel wear the
individual noise-proof tool to prevent the noise.
(4) Treatment of domestic garbage during the construction
Set up 1 garbage can every 50 persons in the living area, so as to centrally collect garbage, and
arrange 1~2 sanitation worker(s) to collect, clear and dispose garbage. Garbage that can not be
recycled shall be transported to nearby slag yard to carry out sanitary landfill.
(5) Population health prevention measures in the construction area
Build the construction health center, provide necessary medical instruments and prevention and
treatment medicines of various infectious diseases, perfect the disinfection measures and avoid the
propagation of epidemic disease source in the engineering construction area; when the engineering
personnel enter the construction area, it is required to carry out the physical examination for them
and enhance the individual health protection; centralized water supplying shall be used in the
construction area to ensure safe drinking water.
16.3.2 Water and soil conservation measures
Green and beauty measures are taken in the project management area; provisional earth drainage
- 55 -
Executive Summary
ditch is built on both sides of construction road and in the construction camps. The design section is
trapezoid with a bottom width of 0.4m, a height of 0.4m and a slope ratio of 1:1.
The dreg yard of the project is coated by galvanized cage stone with a thickness of 0.5m and
masonry wall is designed at the bottom of the dreg yard. Provisional earth water retaining banks are
set all around at the top, so as to prevent loss of dregs during the stacking of abandoned dreg and
after the stacking.
Topsoil stripping and grass planting measures are used for stock yard.
16.3.3 Ecological conservation measures
As for the disturbance and damage to ecological environment which may occur during construction
period, it is required to take corresponding environmental protection and water and soil
conservation measures to recover the original ecosystem. Take following main measures:
(1) Strengthen the environmental management and monitoring and restrain the behavior to damage
wild animal and forest and grass;
(2) Strictly control the scope of temporarily occupied land by construction and selection of
temporarily occupied land of area beyond the inundated area of reservoir. It is required to
reasonably arrange the temporary building construction and decrease the damage to tropical
vegetation as far as possible;
(3) Enhance the water and soil conservation construction of works, decrease the water loss and soil
erosion caused by abandoning the dreg and borrowing earth, reduce the disturbance to
protogenic surface as far as possible and complete the landscape recovery;
(4) It is strictly prohibited to expand the scope of construction impact at will. The construction
personnel are restrained and not allowed to enter the forest beyond the affected area and it is
prohibited to damage the environment of area beyond the affected area. It is required to
strengthen the propaganda of ecological environment protection and prohibit felling trees
illegally.
(5) Strengthen the investigation and research on local aboriginal fish species. It is recommended to
consider the whole aboriginal fish area as protected object and set up the fish resource
monitoring station.
- 56 -
Executive Summary
Adverse effect to
be caused to environment can be mitigated by taking adequate ecological protection and soil and
water conservation measures. Based on the analysis on environment, we preliminarily hold that
there is no severe environmental restraint for construction of this project and the project plan is
basically feasible.
Executive Summary
technicians to go to the site and carried out additional investigation and data collection from 11th to
29th June.
According to relevant specifications, the design flood standard for inundation treatment is as below:
(1) 5-year flood for cultivated land and garden landP=20%;
(2) 20-year flood for rural residential areaP=5%;
(3) Normal pool level for forest land and meadow;
(4) Flood standard for industrial and mining enterprise and special facility is the same as that of
residential area.
Investigation and treatment zone of reservoir inundation of Kalama No.1 Hydropower project is
primarily determined by taking the influence of reservoir flood backwater, freeboard and sloughing
bank, landslide and submersion of the reservoir into consideration.
According to investigation, in lower dam site scheme, the places below 110m backwater water level
of reservoir involve 48 natural villages of 10 administrative villages in two County Benehua and
Kalumpang. In upper dam site scheme, the places below 120m backwater water level of reservoir
involve 59 natural villages of 12 administrative villages in two counties, County Benehua and
Kalumpang.
In reservoir area of lower dam site scheme, the submerged places below 110m backwater water
level and affected places above backwater water level have totally 7479 people from 1701 families;
and 174092m2 of 2406 blocks of houses; total land area about 8093hm2, including paddy field about
621hm2, dry farmland about 327hm2, garden land about 4444hm2, forest land about 1617hm2, land
requisition of village about 289hm2, land requisition of road about 19hm2, water surface of river
about 776hm2.
In reservoir area of upper dam site scheme, the submerged places below 120m backwater water
level and affected places above backwater water level have totally 9752 people from 2187 families;
and 213958m2 of 2976 blocks of houses; total land area about 9925hm2, including paddy field about
- 58 -
Executive Summary
2
1033hm , dry farmland about 485hm , garden land about 5776hm2, forest land about 1527hm2, land
requisition of village about 356hm2, land requisition of road about 19hm2, water surface of river
about 729hm2.
Furthermore, it will submerge and affect 47km class four roads, 10 bridges, 18km 10kV power line,
one abandoned solar power station, three small hydropower stations and eight industrial enterprises.
Reservoir inundation area and junction construction area need to move some local inhabitants,
expropriate cultivated land and garden land, and need to make resettlement planning. Resettlement
planning and moving planning shall be uniformly arranged and solved by Sulawesi Barat Province
government where Karama No.1 hydropower project is located.
Residents can be resettled on the right bank of Bonehau River according to the understanding of
material index of inundation investigation carried out by CGGC engineers and technicians and the
road construction of traffic restoration around the reservoir of this project. There are three places
with good topographic conditions with the total area about 2800 hm2 on the right bank of Bonehau
River for resettlement according to preliminary site survey.
The minerals within the boundaries of Bonehua county and Kalumpang county mainly include gold,
coal, manganese, iron and limestone, etc. There are 8 minerals below 120m elevation along the
banks of Bonehua River and Karama River, including one iron mine, one manganese mine and six
coal mines. Early-stage exploitation has been made to the manganese minerals. In the next phase,
minerals in reservoir area shall be investigated and reasonably determine compensation investment
on mineral resources.
According to investigation, the project involves special facilities within the scope of 120m elevation
along banks of river of the two counties, they are mainly traffic facilities, electric power facilities,
and water conservancy facilities; there is no other special facilities, such as radio and television,
communications and telecommunications, etc.
Because Saltiwo solar power station and Kalumpang small hydropower station have been
abandoned now, and Hinua small hydropower station hasn't finished construction, therefore, no
reconstruction is needed.
- 59 -
Executive Summary
The installed capacity of Mappu hydropower station is only 0.7MW, the scope of power supply is
two villages: Mapppu and Lumika. The power station is in service. Its reconstruction should be
taken into comprehensive consideration with the resettlement.
The special facilities that need to be explicitly reconstructed in reservoir area mainly are road from
Mamuju to Kalumpang along the Bonehua river. It plans that this road shall span Bonehua River on
the upper reaches of Pelosian; it shall be built to the lower reaches of Bonehua River along the
river's right bank above the river line; the end of the road will be near Village Mappu. A wharf shall
be constructed to settle travel problems of residents on upper reaches of Kalumpang of the Karama
River.
According to relevant regulations and field investigation data calculation, direct investment on
reservoir inundation of 115m in upper dam site scheme is $ 117247000, total static investment is
$ 128970769.
18 Investment estimate
The total cost of the Project is estimated to be 1,335.516 million USD, The cost of transmission line
is estimated to be 63.412 million USD.
Executive Summary
the benefit will reaches 37.2% and 100% of the design value in the 5th, and 6th years respectively
after project commencement.
Executive Summary
Regulation of Ministry of Finance No. 38/2006 concerning the guide on risk control and
management of infrastructure project construction;
Regulation of CMEA No. 4 /2006 concerning the evaluation of the infrastructure PPP projects
required Government Support;
MEMR Regulation No.5/2009 and No. 31 concerning Guidelines for electricity purchasing
price by PLN from cooperation and other business entities;
Executive Summary
Presidential Regulation No. 36/2005 concerning procurement of land for development of the
public interest;
Presidential Regulation No. 25/2006 concerning the provisions of Presidential Regulation No.
36/2005 regarding the procurement of land for the implementation of development for the
public interest;
Regulation of the Head of the National Land Agency No. 3/2007 concerning the provisions of
Presidential Regulation No. 36/2005 regarding the procurement of land for the implementation
of development for the public interest;
Executive Summary
Government Regulation No. 10/2010 concerning guidelines for the division and function
change of forestry land;
Company Law, labor Law, tax law, anti corruption law, bilateral/multilateral investment
agreement, and dispute resolution.
- 64 -
Executive Summary
In the second generation since post Asian Financial Crisis to 2008, only 18 PPP/IPP projects were
awarded. These projects mostly operated under Build-Own-Operate (BOO) scheme and IPP
appointments were granted from competitive tendering. In this generation, Indonesian government
has done a series of meaningful work to promote the development of PPP, including inter alia, PPP
legal framework was established through Presidential Regulation NO. 67/2005; new legislation
suitable for PPP scheme was enacted in various fields of railways, ports, airports, ground
transportation, electricity, sewage management and power; establishment of professional
institutions including the Committee for the Acceleration Program (KKPPI), the PPP Central Unit
(P3CU) and Risk Management Unit (RMU) etc.
In the third generation from 2010 onwards, in line with Presidential Regulation No.13/2010, the
Indonesian government has provided PPP projects with more governmental support and guarantees
such as in relation to land acquisition. In this period, the most outstanding project is the 21000MW
coal-fired power station in Center Java. The Project has stood to provide practical guidance to other
PPP/IPP projects operated according to Presidential Regulation No.67/2005, Presidential Regulation
No.13/2010 and Presidential Regulation No.56/2011. These are the basic regulations on
infrastructure PPP projects which include airports, port, railway, highroads, raw water supplement,
irrigation system, drinking water, wastewater treatment, solid waste treatment, information
communication technology, electricity and oil and gas.
20.1.2 Current Situation of the Development of Indonesian Electricity Legislation
The legislation for the electricity sector in Indonesia has gone through three phases namely the 1985
Electricity Law, the 2002 Electricity Law, and the 2009 Electricity Law. And it is the 2009
Electricity Law that is in force at present. According to 2009 Electricity Law, PLN is not monopoly
in electricity infrastructure whereas it is still the offtaker of power plants.
In the fields of PPP, fundamental laws for PPP projects in infrastructure projects are Presidential
Regulation No.67/2005, Presidential Regulation No.13/2010 and Presidential Regulation
No.56/2011. According to these regulations, business entities participate in electricity infrastructure
(including generating, transmitting and distributing electricity) through the public tender.
- 65 -
Executive Summary
Other laws related to the Project include without limitation laws concerning foreign investment,
government guarantees, environmental conservation, space utilization, water resources, labor,
company, tax matters and dispute settlement etc.
20.1.3 Stakeholders in PPP/IPP in Indonesia
Various governmental offices and institutions are involved in Indonesian PPP/IPPs. And key
stakeholders and their relations are shown in the chart below:
- 66 -
Executive Summary
China Gezhouba Group Company Limited International (the Company) is responsible for invest and
develop Indonesian KARAMA No.1 HEPP of West Sulawesi Province (the Project). After the
accomplishment of the hydropower plant, the Company should operate and maintain the
hydropower plant and sell the generated electricity to PLN. Then, PLN sells the electricity to
ultimate consumers by its own electricity transmission and distribution network. The Company acts
as IPP.
20.2.2 Developing Process
The developing process of PPP projects in Indonesian electricity industry is composed of 7 stages
which are identification and priority, feasibility study, evaluation and approval, public tender,
financing, building, operation and maintenance. These are regulated in Presidential Regulation No.
56(2011).
In the stages of identification and priority, feasibility study, the tasks in these two stages should be
- 67 -
Executive Summary
Executive Summary
Executive Summary
determination date of the best offer from the Cooperation Project public tender. The added value
could be given to the initiator in the terms of participating in the public tender. The feasibility study
report and other supportive documents are transferred to GCA without any payment or
compensation. If the initiator rejects to participate in the public tender, the initiator could get
compensation on the expense of initiation (including intellectual property) from GCA or tender
winner. The standard of compensation is determined by GCA based on the evaluation of chosen
independent auditor. The compensation covers the expenses of feasibility study preparation and
Cooperation Project transaction until Financial Closing. The compensation in any form should be
approved by GCA.
The process of public tender could be shown as follows:
5) Financing
Financing Closing should be obtained in 12 months after the signature of PPA by Project Company
and GCA. Financing Closing is accomplished after the signature of loan agreement and payment of
partial loan for the construction of the Project. If the financing failure does not result from the
negligence of Project Company, GCA may extend another 12 months for financing. The Financing
Closing does not accomplished in the first 12 months or in the extension months, the PPA should be
terminated and GCA has the right to confiscate the performance guarantee.
After the Financing Close, Project Company should finish the construction based on the
Cooperative Agreement as well as operate and maintain the project in the business operation period.
- 70 -
Executive Summary
Executive Summary
hereinbefore issue.
Presidential Regulation No. 36/2005 and Presidential Regulation No. 25/2006 regulate the process
of land acquisition conducted by the government. The government should establish land acquisition
committee responsible land acquisition. Land acquisition committee should delegate independent
land evaluation agency to fix the land price. In the condition that land acquisition committee could
not make an agreement on land compensation with the land owner, its land acquisition committees
right to fix the compensation standard and require related agencies to draw the compensation in
regional courts in order to expropriate the land. Additionally, once the government fixes certain land
for infrastructure project, anyone should get a primary governmental approval for purchasing the
land.
Tax incentives are decided by MoF.
Regulation of Ministry of Finance No. 38/2006 concerning the guide on risk control and
management of infrastructure project construction rules the conditions and procedures of providing
government guarantees. Government guarantee should be applied by GCA followed by evaluation
of P3CU and acceptance of KKPPI. Then the application of government guarantee is submitted to
RMU under MoF for evaluation which should be submitted to MoF who has the final power to
approve the government guarantee. Once MoF approves, the government guarantee should be
executed by Indonesian Infrastructure Guarantee Fund (PT PII, IIGF). Pursuant to Governmental
Regulation No. 35/2009 concerning governments involvement on establishment of limited
company (PT) on infrastructure guarantee, Indonesian government establishes PT PII to manage the
government guarantee in order to decrease the financing expense of infrastructure PPP projects,
improve the quality and credibility of the project, as well as assist the government for better risk
management.
In addition, the Company signed a meeting memorandum with the government of West Sulawesi
Province on June 23, 2011. In the meeting memorandum, it is clear that government of West
Sulawesi Province should provide Government support in land acquisition, resettlement,
environment effect evaluation, tax incentives and government approvals.
- 72 -
Executive Summary
Indonesia
Infrastructure
Guarantee Fund
PT PII
Multilateral Development
Bank
Debt Financing
Project Initiator
Debt Financing
Debt Financing
Operation and
Maintenance
General Contracts
O&M Contract
Shareholders Agreement
Capital Stock
Project Company
Other
Shareholders
Indonesia
Infrastructure
Financing Fund
(PT IIF)
EPC Contract
Construction
General Contract
Capital Stock
/shareholder Debt
Shareholders Agreement
Water Supply
Agreement
National Water
Resources
Administration
Other Shareholders
Shareholders
Agreement
State-owned Electricity
CompanyPLN
Support
Agreements
Executive Summary
companies in Indonesian laws. It would ultimately be subject to the guides and policies made and
adjusted from time to time by the Capital Investment Coordination Board (BKPM). BKPM expects
that capital of foreign investment for a hydro power station should be no less than US1 million to
US1.5 million per MW of installed capacity, of which equity capital shall amount a quarter. In the
Project, installed capacity of the hydro power station is 450 MW, so the investment capital should
be at least US450 million to US675 million, with equity capital of US112.5 million to US
168.8 million.
20.3.3 Land Acquisition
The issue of land acquisition has become one that the Company should better pay the most attention
to. According to Indonesian laws, the company should submit a Land Acquisition and Resettlement
Action Plan (LARAP) for the Project.
Resettlement compensation can be cash compensation, actual resettlement compensation or others.
The principle is not to lower the land owners living standard. Pursuant to Presidential Regulation
No. 36/2005 and Presidential Regulation No. 25/2006, the amount of resettlement shall be decided
through a process as follows: a draft of resettlement compensation would be negotiated by an
independent appraisal consultant together with land owners and initiators of projects. And then the
draft would be submitted to the Land Acquisition Committee for discussion. It will be finally
decided after the negotiations among the Land Acquisition Committee, the land owners and PLN.
20.3.4 Government Guarantees
The Project can apply to IIGF, PT PII for Indonesian national financial guarantee. The following
conditions shall be met: it should be a PPP project in line with Presidential Regulation No.67/2005,
Presidential Regulation No.13/2010 and Presidential Regulation No.56/2011; it should be in
accordance with relevant trade standards and was appointed through fair, transparent and
competitive tendering process; it should be in line with public interests and is feasible technically,
economically, financially and environmentally; suitable arbitration clause should be included in
cooperation agreement.
Pursuant to Presidential Regulation No. 9/2009 concerning the financing agencies, IIGF, PT PII can
- 74 -
Executive Summary
guarantee risks including government approval, financing failure, legal changes, government breach,
local grid connection, competitive risks, government payment, government demand, price changes,
collection, remittance, force majeure suffered by the government etc.
20.3.5 Grid Connection
Electricity generated in the Project will be sold to PLN directly so the Company might not be
concerned about the issue of grid connection. It is located, however, in remote areas far away from
PLN grid, so it becomes necessary to build transmission cables and transformer stations between
the site and PLN grid. It is necessary to estimate cost for transmission cables and to provide bill of
quantities for building the same.
20.3.6 Investment Incentives
In the Project, the Company can apply to Indonesian government for investment incentives as
follows:
Incentives for encouraged new industries: (1) Import duty exemptions for principal operating
equipment; (2) Import duty reduced to 50% for auxiliary operating equipment; (3) Import duty
exemptions for components to manufacturing principal operating equipment, with a ceiling value of
5% of the equipment value (if exceeded, you will still have to pay duties); (4) Within two years of
commercial operation, import duty exempted for those materials imported at a rate of lower than
5% and reduced to 50% for those imported at a rate higher than 5%; (5) Duty exemptions for
principal operating equipment related consumable articles in the first year; (6) VAT and luxury tax
collection can be delayed for fixed assets imported from abroad or purchase from Indonesian local
market; as long as the abovementioned assets are not sold or changed for other purposes, VAT and
luxury tax can be exempted until the end of depreciation of such assets; or VAT and luxury tax
would have to be collected.
Incentives for investment in certain areas: in the Project, the Karama River, abundant in hydro
resources, is located in remote area where tax incentives can be granted including, inter alia, as
follows: (1) for a finite period net income tax would not be imposed until investment has reached
certain amount; (2) for a finite period import duties for capital goods, machines or equipment that
- 75 -
Executive Summary
cannot be produced in Indonesia can be exempted; (3) for a finite period when certain conditions
are met, import duties on raw materials or auxiliary materials can be exempted; (4) for a finite
period, VAT on capital goods, , machines or equipment that cannot be produced in Indonesia can be
exempted or delayed; (5) accelerated depreciation or amortization; (6) land and construction tax in
certain areas for certain purpose can be reduced or exempted; (7) import duties for existing
investment enterprises to renew machines or other capital goods can be reduced or exempted.
Incentives for foreign investors: (1) Enterprise income tax, at a rate of 25%, can be paid up in six
years, that is paying 5% per year; (2) accelerated depreciation and repayment; (3) during dividend
allocation, income tax rate for foreign invested enterprises is 10%, or according to double taxation
agreement in force at present, lower rate will be applied; (4) deficit offsetting period of more than 5
years can be granted, yet no longer than 10 years; (5) a exemption period from 5 years to 10 years
can be granted to foreign investment project in the field of fundamental metal, oil refining, gas
organism chemistry, renewable resources and telecommunication equipment with an investment
amount of more than US117 million.
20.3.7 Environmental Protection
The installed capacity of the Project is 450 MW for which environmental impact assessment
(AMDAL) and environment permit (EP) would be required for the project company to be granted
IUPTL, according to Law No. 32 /2009 concerning environment conservation and management
20.3.8 Natural Resources
Pursuant to Government Regulation No. 24 /2010 concerning forest utilization, forest resources
protection should be like this: if the Project is located in forest protect zone, an IPHK shall be
acquired from Ministry of Forestry, but compensation is unnecessary for collection of forest land.
Space resources protection: based on Law No. 26/2007 concerning spatial arrangement and other
regulations concerning spatial arrangement, space utilization in the Project shall be in line with
space division plan and approved by the West Sulawesi government.
- 76 -
Executive Summary
Hydro resources: Law No. 7 /2004 concerning water resources regulates that water utilization
approval shall be acquired from National Hydro Resources General Office.
21 Conclusions
(1) Karama No.1 Hydropower project is located at the KARAMA River in the West Sulawesi of
Indonesia, with the catchment area upstream of the dam site of 5,406km2, mean annual runoff
of 14.53 billion m3 and mean annual flow of 460.6m3/s.
(2) As for the normal pool level, 5 schemes of El 100m, El 105m, El 110m, El 115m and El 120m
are compared and analyzed, and finally the El 115m scheme with the highest economic internal
rate of return is recommended. And as for the installed capacity, 5 schemes of 300MW, 350MW,
400MW, 450MW and 500MW are compared, and the scheme of 450MW with the highest
economic internal rate of return is recommended, and the mean annual output of the
hydropower station is 2,412GWh.
(3) According to the seismic zoning map of Indonesia (2010 version), the seismic peak ground
acceleration in the project area is 0.20~0.25g, 0.25g is equal to the basic seismic intensity of
VIII degrees and suggested to be adopted in this phase. The formation lithology of the reservoir
area is dominantly in sandstone, silty mudstone and mudstone of the lamina-medium bed of the
neogene system and the homochronous volcanics and volcanic breccia, the reservoir has a weak
permeability and closure property of the reservoir basin, and no possibility of reservoir
permanent leakage would occur.
(4) According to the survey and design of two dam sites in the planning phase, the formation
lithology of the lower dam site is dominant in the deposited volcanic breccia and tuffites of the
upper Tertiary (N). The rocks are mainly soft rocks, and the rock mass is relatively complete
but the local integrity is poor. The formation lithology of the upper dam site is dominantly in
tuff, volcanic breccia and andesite of the upper Tertiary (N), the rocks are mainly hard rocks
and the rock mass is relatively complete but the local integrity is poor. Considering the
topographic and geological conditions, the lower dam site is suitable for building the local
material dam, and the upper dam site is suitable for building the concrete gravity dam or local
- 77 -
Executive Summary
material dam. Considering the available natural construction materials, downstream of the
lower dam site is relatively rich in natural construction materials and the upper dam site is
relatively lack of natural construction materials nearby and with the farther distance. Through
the technical and economic comparison and analysis, the upper dam site is recommended and
the dam type of roller compacted concrete dam is proposed.
(5) The multi-purpose project is categorized as Class I and the project ranking is as large (I) type.
This project is composed of water retaining structure, water release structure and water
diversion and power generation system. The water retaining structure is the roller compacted
concrete gravity dam, with the crest elevation of El 117.00m. The minimum elevation of dam
foundation is El -2.00m, the maximum dam height is 119m and the dam crest length is 317m.
There are 14 monoliths in total. The water release structure adopts the flood discharging way of
surface hole overflowing, surface hole overflowing monoliths No.711 (5 in total) are
arranged in the middle of riverbed with each of 22m long. Five 14m22m (width height)
surface holes are arranged with total net width of 70m and the total length of overflowing
section is 110m. The diversion system is composed of water intake and diversion tunnel. One
tunnel for two units is adopted as the way of water supply. There are 2 diversion tunnels in total
with the length of the main tunnel of 579.02m. The total construction period of the project is 54
months (from January of the first month to June of the fifth year), and the construction
preparation period is 20 months, the power generation period of the first unit is 49 months (by
the end of the fifth year) and the power generation period of the last unit is 51 months (by the
end of March of the fifth year).
(6) Karama No. 1 Hydropower project will be constructed and operated to produce clean energy,
and its main adverse effect on environment is the reservoir inundation and project land use
within part of ecological environment reserve, but this can be relieved by adopting the
ecological protection and soil and water conservation measures. This hydropower station will
inevitably cause certain adverse effect on the environmental quality in certain range of the
project area during construction period, but the influenced area is relatively small. As long as
the Employer and Contractor are cooperated to implement each environmental protection
measure as mentioned in this report during the construction and operation processes, the
adverse effect to be incurred from this project is local and controllable and is feasible to certain
degree, and no restraint factors exist. The project construction is dominant in favorable effect
- 78 -
Executive Summary
on environments.
22 Suggestions
(1) Currently, there is no practically measured datum about the KARAMA River, and the runoff of
the dam site is obtained only by comparing the runoff information of the nearby river basin. It
is suggested to install a special hydrologic station nearer to KARAMA power station dam site
for water level, flow and rainfall observations.
(2) Considering that the regional faults exist in the reservoir area and the historical seismic activities
exist in the neighboring areas, the seismic risk evaluation will be conducted in the next stage.
(3) It is suggested to replenish and perfect the status survey in the next stage and perfect the
environmental impact assessment analysis and forecast according to the site survey results. It is
necessary to carry out the fish survey and aquatic ecosystem special study so as to provide
evidences for the environmental impact assessment for drawing out a reasonable and
comprehensive evaluation conclusion. It is also required to coordinate with relevant
departments, for carrying out the public participation survey, learning the publics opinions and
suggestions for this project comprehensively and recording the survey results into special report
of environmental impact assessment.
- 79 -