Professional Documents
Culture Documents
Introduction
Page 1
increase, the propulsion shafting alignments are increasingly more sensitive to disturbances
affecting vertical offset of the bearings. These disturbances primarily result from hull
deflections and temperature change. However, another very significant influence on the
quality of the alignment is the accuracy of the shaft alignment analyses and the alignment
procedure itself.
The shaft alignment problem can be summarized as follows:
High sensitivity of the shaft alignment to small disturbances in the bearing vertical position
Disparity between highly flexible hull girder structure and the rigid propulsion shafting
Difficulties in hull girder deflection evaluation
Problems in maintaining the desired accuracy of the shaft alignment analysis
Inconsistency and inaccuracies in conducting the alignment procedure.
2.1
The preferable condition for performing the propulsion shafting alignment procedure
would be in the dry dock, just before the vessel is launched. At that stage, the vessels
structural work is nearly complete. Thus, a minimum disturbance on the alignment resulting
from the construction work after the launching may be expected.
However, to comfortably rely on dry dock alignment, the hull deflections need to be
predicted with relatively high confidence. Prediction of hull deflections would enable the
design of a dry dock alignment robust enough to prevent other than hull deflection
disturbances from adversely affecting the alignment.
NMAMIT, NITTE
Page 2
NMAMIT, NITTE
Page 3
SECTION
General
As already mentioned, the propulsion shafting alignment process consists of the design,
analysis, and the alignment procedure and measurements. The alignment procedure is the
executable part of the alignment process where the alignment is performed in accordance
with the requirements defined by the alignment designer. The alignment procedure is not
uniformly defined and applied in the industry. The procedure often depends on shipbuilders
practices, experiences, and even more so on the production schedule of the particular builder.
The shaft alignment procedure is not expected to start before the vessel stern blocks are
fully welded and all of the heavy stern structure is in place. Only then should the reference
line for positioning the shafts, bearings, main engine and gear box be established. This is not
always the case, however. Some yards do start the procedure much earlier, even during block
stage, or without a fully welded stern area of the vessel, or/and with no superstructure in
place. These different practices will be addressed later in the text and discuss possible
consequences which such approaches in alignment procedure may yield, along with solutions
to the possible problems.
The propulsion shafting alignment procedure can be summarized in the following
activities:
Sighting through (bore sighting)
Bearing slope boring or bearing inclination
Engine bedplate pre sagging
NMAMIT, NITTE
Page 4
The process of establishing the reference line is often called sighting through or bore
sighting. The procedure is conducted by optical instruments, laser or a piano wire.
FIGURE 1
NMAMIT, NITTE
Page 5