Flat and level concrete floors are vital for warehouses.


By
David Fudala

Credit: Allflat
A crew inspects the floor after a completed grind at a very narrow aisle facility.
Credit: Allflat
A crew inspects the floor after a completed grind at a very narrow aisle facility.
The forklifts and material handling equipment traversing many warehouses and distribution centers at times may rival
a big citys rush hour traffic. These vehicles are most effective when the facilitys concrete floor is perfectly flat and
level.
The best way for a building owner who needs a concrete floor to meet flatness and levelness requirements for this
equipment is to specify the floor tolerance requirements at the very beginning, at the conception phase of the project.
In fast-track construction of new big box facilities, floors sometimes are placed and finished in pours of 50,000 to
80,000 square feet or more with laser screeds and large riding trowels with pans. Then, the surface is remediated to
a specific tolerance by grinding the material handling equipment wheel paths only or simply the width of the aisles
between the racks to increase throughput or material handling efficiency. Both depend on the owners necessary Fmin tolerance.
For example, a FF 50/FF 35 floor is specified in a building which sits empty for six months or more before it is
occupied. Depending on how the facility is proposed to be laid out by the new tenant/owner and depending on the
amount of slab curling and settling that occurred while it was vacant, it will likely require remediation to meet F-min
tolerances of at least F-min 50 to F-min 100 or higher if required by forklift manufacturers recommendations or the
architect/engineers tolerances. (See ACI 360-10, Guide to Design of Slabs-on-Ground.)
In lieu of Type II concrete, Type K shrinkage compensating concrete is placed and finished in large square pours by
experienced contractors. Construction joints or form boundaries are set about 100 feet apart. These methods may
allow for quicker installation of the floor and could reduce the amount of grinding at joints due to the lack of curling
because of the expansive properties of Type K cement.

Strip pour
Some owners and contractors prefer to get high-tolerance F-min floors using the strip pour method. This placing
and finishing method uses forms set to rigid tolerances of plus or minus 1/16-inch, milled wood form tops or thin steel
edge forms, and vibrating truss screeds with hand tools (check rods and bump cutters) used for strike-off. Some
contractors prefer laser screeds instead of truss screeds. Floors installed this way usually require little or no
remediation, as tolerances are more stringently controlled with the narrow strips.
What if owners want to expand or move, and must buy or lease an existing facility? What if they have an existing
facility and want to upgrade, move, or reconfigure the current material handling equipment, racking layout and
conveyors, but the floor isnt up to par?

There are usually three options. But first, they should hire a qualified firm to measure the existing slab with the proper
floor flatness and levelness equipment to assess its current condition. This could save time and money if deciding to
lease a nearby facility that could be better than the one the owner is seeking to rent.

Credit: Allflat
The strip pour method uses forms to set rigid tolerances, milled wood form tops or thin steel edge forms,
and vibrating truss-screeds with hand tools used for strike-off.
Credit: Allflat
The strip pour method uses forms to set rigid tolerances, milled wood form tops or thin steel edge forms, and
vibrating truss-screeds with hand tools used for strike-off.
There are three common methods for upgrading:
1. Remove and replace, which is expensive, invasive, and time consuming in an operational facility or one that must
be operational soon.
2. Apply a self-leveling or epoxy topping, which often requires scabbling or scarifying the existing surface for an
underlying mastic layer. If not applied by an experienced contractor, this can be challenging, time consuming, and
have a high probability of failure (blister or delaminate) due to moisture content of the subgrade and high alkalinity at
the surface.
3. Usually the most cost-effective fix entails grinding, but dont be afraid, read on.
Grinding might have its pitfalls. People immediately think of loud noises (engines and blades), dust (silicosis), and
downtime. However, relatively quiet and dust-free concrete floor resurfacing equipment capable of creating superflat
F-min tolerances for very narrow aisle (VNA) applications does exist and is used every day with great success.
Some grinding equipment was designed to work in operational VNA buildings, order picker paths, crane rows, or even
wide open areas while the facility continues to operate with little or no interruption. Hundreds of building owners that
had their floors ground as long as 25 years ago are currently operating today with great success.

Planing, skimming
What is the F-min System?
The most effective vehicle material handling system for warehouse and distribution centers is based on floors that
have superior flatness and levelness.
F-min is a floor industry standard measuring system for very narrow aisle (VNA) traffic floors. It is expressed as a
unitless number for both the longitudinal and transverse axis for the exact wheelbase configuration of a VNA forklift or
truck or order picker crane in high-stack warehouses. The higher the number, the more flat and level the floor. As an
example, it may be expressed at F-min L 85/F-min T 100 (L = longitudinal; T = transverse).
The primary reason for developing the F-min system was to quantify the threshold of mast sway for preventing lift
truck payload racking strikes and analyze the bumpiness of VNA floors. The system allowed contractors to expedite
floor repairs and ultimately paved the way for development of construction techniques to manufacture this type of
floor.

Because a VNA lift trucks wheel path does not vary in its movement down an aisle from side to side, it is important to
measure the exact path that the truck will travel. F-min measurements are taken by a vehicle lift truck simulator that
tracks the exact wheel paths the actual lift truck follows in the aisle.
ALLFLATs proprietary measuring device, the F-min Profiler, is a digital, semi-continuous recording dual-axis
differential profileograph. The data from the profileograph is used in the F-min calculations to provide a certification of
compliance or to report any noncompliance, which then indicates the location of any required remedial activity or
grinding.
For more, visit www.allflat.com.
Instead of grinding, it should be called planing or skimming, which does not sound so harsh. Think of it this way: If the
American Concrete Institute says an F-min 100 floor is approximately plus or minus 1/16-inch in any one location and
a floor is currently plus or minus 1/8-inch, then only 1/16-inch needs to be removed.
It does not take much to throw off the performance or longevity of material handling equipment in warehouses. That is
true for the amount of concrete that must be removed to make an ordinary Random-Traffic FF/FL floor a DefinedTraffic Superflat Floor. (See ASTM E 1155, Standard Test Method for Determining FF Floor Flatness and FL Floor
Levelness Numbers.)
However, the key to this is doing it planar or kept to a high degree of levelness. Thats the tricky part, but there is
equipment that can do the job. Many concrete grinders are on the market, but they are usually manually operated
(although there are a few laser-guided models.)
The problem is one will almost always encounter an area that needs 1/2 to 3/4 inches removed. That is a lot of
concrete to remove, but some equipment can move right through it with a single pass with results well above F-min
100.
In conclusion, there are different ways to design a high-tolerance concrete floor with a specific use, and there are
several qualified architects, engineers, and consultants who can assist owners and developers with their projects.
There are many experienced contractors who can install these types of floors every day.
David Fudala is the founder and CEO of ALLFLAT Consulting, San Diego, which provides professional services for
concrete slabs from design phase and construction to testing and inspection. Visit www.allflat.com.