Professional Documents
Culture Documents
Improvement
Project(APWSIP)-Nagarjunasagar Project
with the assistance of World Bank
Er.V.R.S.Sarma
B.Tech., M.E., PGDCS, MIE.,(MHRM)
Executive Engineer and Senior Faculty
member(Retd.), WALAMTARI
Various items of works were divided into 4
components, each of which would be
addressing group specific and allied works as
envisaged in the project document
Component A:Improving Irrigation Service Delivery in
Nagarjuna Sagar Scheme (Base Cost US$ 752.15
million)
This component focuses on improving the irrigation service delivery in the NSS
through
•The rehabilitation and modernization of the scheme’s infrastructure,
•Effective participation of WUOs,
•Increased cost recovery,
•Ensuring full provision of O&M costs,
•Improved delivery of irrigation water to WUOs at all levels as per their share
determined by the APWRRC, and implementation of improved water management
practices and instruments.
This component would support five sub-components:
➢ A1: participatory rehabilitation and modernization of irrigation system;
➢ A2: dam safety works;
➢ A3: fostering and capacity building of water user organizations;
➢ A4: improved water management practices; and
➢ A5: social & environmental management plan.
Component B: Irrigated Agriculture
Intensification and Diversification (Base Cost
US$21.27 million)
• This component aims at increasing farmer incomes in the NSS by
improving productivity, diversification, and profitability of field and
horticultural crops, livestock, fisheries, and other production activities.
With project
Net farm income(a) Rs./ha 20885
Per capita income(b) Rs./ha 4177
Minimum holding size to meet poverty line income levels ha 0.99
Poverty Alleviation Impact
Total number of farm holdings No 716850
Number of farm holdings between 1 to 1.5 ha No 64517
Poverty Alleviation Impact % 9
(a) Estimated based on crop and farm budgets for small farms (< 2 ha); only crop
(b) Average farm family size is five
(c ) GOI Official poverty estimates for rural Andhra Pradesh (2004-05), converted to
2006/07 prices
The development objectives of the
proposed APWSIP are