You are on page 1of 2

OIL & GAS PRODUCTION

ENTERPRISE (OGPE)

FINAL DOCUMENTATION
20 BI-DIRECTIONAL PIPE PROVER
PROJECT

PART 1
PART 1

ENGINEERING & DESIGN DOCUMENTS

1.2

Data Sheets
c)

Detector Switch

PROJECT : VSP 20" BI-DIRECTIONAL PIPE PROVER PROJECT


DOCUMENT NO: OVL076-DSH-03

REVISION : 1

DATA SHEET FOR DETECTOR SWITCH

PROCESS DATA

1
2
3
4
5
6
7
8
9
10
11

MAIN LINE SIZE / SERVICE


PIPING CLASS
FLUID
FLOWRATE (m3/Hr)
OPERATING PRESSURE (kg/cm2)
OPERATING TEMPERATURE (Deg C)
DESIGN PRESSURE (kg/cm2)
DESIGN TEMPERATURE (Deg c)
DENSITY (kg/m3)
VISCOSITY (cst)
TAG NO.

12 FEATURE
DETECTOR
SWITCH

MANUFACTURER/
MODEL

1
0
REV

13
14
15
16
17
18
19
20
21

MOUNTING
MATERIAL - SENSOR
MATERIAL - MOUNTING BASE
CONNECTION
CONDUIT CONNECTION
PROTECTION
MANUFACTURER
MODEL
QTY

16.07.2012
02.02.2012
DATE

AS-BUILT
ISSUED FOR APPROVAL
DOCUMENT ISSUED PURPOSE

10" DIESEL OIL METERING


150# CARBON STEEL
DIESEL OIL
40~1200
10
50
15
75
780
7 @30 Deg C
ZS-01 & ZS-02
HERMETICALLY SEALED PROXIMITY SWITCH
PERMANENTLY BALANCED MAGNETIC FIELD
HEMI-SPHERICALLY SHAPED PROBE
ON 20" PIPE
SS316
CARBON STEEL (A105)
WELDED
M20
EXPLOSION PROOF
KIDD
100-S
2PCS

TYNG
TYNG
PREPARED BY OVAL

VL
VL
APPROVAL BY