JARVIS INVESTMENTS LIMITED
To,
Dubai Electricity & Water Authority
PO. Box # 564
Dubai, U AE
Date: 06.04.2016
Attn: SENIOR MANAGER
CONNECTION SERVCES DEPT.
Application : E-971253.
Project, HOTEL STAFF ACCOMMODATION
Owner:. JARVIS INVESTEMENT LIMITED.
Plot, Area OAS.003, DUBAI- IMPZ.
Subject :CONFIRMATION LETTER/FLOW CHART
Dear Sir,
With reference to the above project this is to confirm that the Electrical DB's , All the Light
fittings and equipments (if any) will be installed later by the Tenant in future as per DEWA rules
and regulations, according to the attached chart.
| request you to arrange for release of power supply for my project.
This is for your information and records,
(Ws
Yours Fafthfully, |
‘Offshore Company with limited (GEA aJARVIS INVESTMENTS LIMITED
‘Approval and inspection of L.V. wiring installation in tenant areas for proposed
On Plot No. OAS.003 International media production zone for JARVIS INVESTEMENT LIMITED.
1 ‘We have already obtained provisional approval on the LV installation drawings which
show proposed loads and location of point of supply (DB) within each tenant’s premises.
Distribution Boards are located near tothe entrance of the tenant premises.
2. ‘The Tenant's area clectrical works shall be caried out by DEWA registered electrical
contractor(s).
3. ‘The shop drawings shall be submitted to DEWA prior to commencement of works.
44. The shop drawings shall be prepared by the electrical contractor and submitted to the
Cheat ond Client Shall review the drawings in line with provisional approval and forward
to DEWA along with the following
8) No Objection letter as per the attached specimen.
b) Updated status on summary of MDB and SMDB indicating status of power
supply to tenant areas (to identify the power released and pending areas)
5. Electrical MDB’s and Metering Arrangements are provided to connect tenant areas in the
Lv room.
6. Application for inspection shall be submitted by the Electrical Contractor as per attached
format at least 1 week in advance, routed through dewa approved contractor.
7. Co-ordination shall be done by electrical contractor for Inspection at site by DEWA.
8. ‘The electrical contractor shall produce original approved drawings at site.
9, Submission of test certificate, payment of security deposit and release of supply shall be
coordinated by electrical contractor.
10. Any non-compliance of DEWA approved drawings at site shall be resolved by electrical
‘contractor (Tenants shall not be permitted to approach DEWA to resolve the issue).
11. The Landlord will identify the authorized Electrical Engineer (well qualified and
experienced) to coordinate with DEWA for technical discussion, inspections eto
[GES
in nt’
‘Shops — Fit outs:
“Ofthore Company with rtd Unblty under Reqisu won F1SST22
Correspondence Address -.0, Box 50127, Dube UAE. * Tel #O4~333 1658 * FexO4~3331027JARVIS INVESTMENTS LIMITED
Tenant Contactors
Prequalification
Landlord Approval
Decision Not Approved
a
Selected Tenant Contractor
‘Shop Drawings by Tenant
Contractor
Landlord - Approval /
Decision
DEWA Submission
Application for DEWA’s
inspection along with
contractor's test certificate
{Tenant's Elect. Contractor]
DEWA Inspection
——
Security Deposit Payment at
DEWA
‘ ‘Supply release to the premise - Shop
3932027