2.
For a P11 material piping under repair, what sort of heat treatment is
required?
1.
2.
3.
4.
3.
5.
For a 16mm thick 30 pipe repair work what is the correct heat treatment
1.
2.
3.
4.
4.
The inspector
The piping engineer
The owner/user
The Fabricator
The weld should be parallel to the longitudinal axis of the bend and
the root should be in the convex
The weld should be perpendicular to the longitudinal axis of the
bend and the root should be in the convex
The weld should be parallel to the longitudinal axis of the bend and
the root should be in the concave
The weld should be perpendicular to the longitudinal axis of the
bend and the root should be in the concave
(API-570-Mockup-CB) 2/18
6.
7.
8.
< NPS 2
< NPS 3
< NPS 2 1/2
> NPS 2
11.
10.
A pipe support moved outs of its base and is hanging what is your
assessment as an inspector
1.
2.
3.
4.
9.
It is to be rejected
It acceptable provided it meets the density and sensitivity
limitations of ASME Sec.V Article.II
It is depends on the project spec
A Level-III shall be consulted
(API-570-Mockup-CB) 3/18
12.
13.
14.
51.4 mm
53.98 mm
53.00 mm
54.98 mm
17.
16.
15.
A black image
A white image
A dark image
A gray image
600 #
900#
300 #
400 #
590 psi
570 psi
516 psi
885 psi
(API-570-Mockup-CB) 4/18
18.
19.
Out of long and short-term corrosion rate which one will be used for
MAWP calculation
1.
2.
3.
4.
20.
12 or 3 OD whichever is greater
10 OD of the pipe
6 OD of the pipe
3 OD of the pipe
What are the minimum marking shall be made of a buried piping leak
temporarily clamped area
1.
2.
3.
4.
23.
API publ.2201
API RP 574
API RP 578
ASME Sec. VIII Division-1
22.
21.
The soil closed potential survey is being carried out for a non-cathodically
protected system is
1.
2.
3.
4.
Once in 5 years
Once in 3 years
Half of the remaining life
Once in 6 months
(API-570-Mockup-CB) 5/18
24.
25.
26.
27.
Gate valve
Ball valve
Globe valve
Slide valve
30.
2000F
2000C
930F
3000F
Valve
elbows
flanges
Blind flanges
(API-570-Mockup-CB) 6/18
31.
32.
33.
36.
30 dia pipe
bolts
2 dia cooling water line
Small bore fitting
A 20 dia pipe has internal leakage near the flange to pipe weld. During
shut down what sort of inspection will be planned for this
1.
2.
3.
4.
35..
visual
radiographic
internal visual
ultrasonic
34.
atmospheric corrosion
microbiologically induced corrosion
erosion - corrosion
sulphidation
Approved inspector
Industry qualified UT inspector
API qualified inspector
Any examiner qualified to carry out NDT
(API-570-Mockup-CB) 7/18
37.
38.
Out of the repair carried out in the piping system which one is considered
to be a permanent one
1.
2.
3.
4.
39.
42.
41.
40.
(API-570-Mockup-CB) 8/18
43.
44.
45.
2 to 2.5
2
1.5 to 4.0
1.5 to 3.0
48.
It is not acceptable
Check for leak along the pipe work
The test is acceptable
To be consulted with a inspector
47.
10 minutes
3 minutes
30 minutes
1 hour
When a buried piping with a design pressure of 100 psi is under leak test
at 125 psi. The initial 4 hrs. of testing shows a slight pressure drop and
has been adjusted. The second 4 hrs recorded a drop in pressure
of 5 psi, the test
1.
2.
3.
4.
46.
1.
2.
3.
4.
(API-570-Mockup-CB) 9/18
49.
A radiographic testing for the welder qualification is not allowed for which
process
1.
2.
3.
4.
50.
51.
2.
3.
d.
52.
Piping Engineer
Inspector
Repair Organisation
Operating Personnel
(API-570-Mockup-CB) 10/18
53.
Which of the following are some of the mandatory requirements for rerating a piping system?
1.
2.
3.
4.
54.
55.
Elbows
Expansion loops
Tees
Valves
57.
Normally required
Not required at all
Depend on opinion of piping inspector
Only 1 and 3 above
56.
Which of the following are areas on piping systems which are susceptible
to CUI during the range of 25F to 250F:
1.
2.
3.
4.
(API-570-Mockup-CB) 11/18
58.
59.
API 2201
API 574
ASME B 31 G
None of the above
60.
61.
For which of the following, the approval from piping engineer is not
mandatory:
1.
2.
3.
4.
62.
(API-570-Mockup-CB) 12/18
63.
64.
65.
67.
Ductility of weld
Strength of weld
Soundness of weld
Both soundness and ductility of weld
66.
(API-570-Mockup-CB)13/18
68.
69.
70.
1 times
2 times
3 times
4 times
72.
71.
True
False
Depends on company policy
Depends on client of the company
3-1/2
2
4
Any diameter possible
5.0 years
4.5 years
6.0 years
None of above
(API-570-Mockup-CB) 14/18
73. Common locations which are susceptible to CUI on the insulated piping
are:
1.
2.
3.
4.
74.
75.
4.
78.
77.
Each year
Each two years
When possible
Every 6 months
76.
(API-570-Mockup-CB) 15/18
79.
80.
81.
84.
Annually
Six monthly
Once in 3 years
None of the above
The pressure gauges for leak testing shall be calibrated as an ASME Sec.
V requirement, at least:
1.
2.
3.
4.
83.
1/16
1/8
1/32
None of the above
82.
Radiography
Ultrasonic
Hardness survey
None of above
(API-570-Mockup-CB) 16/18
85.
86.
87.
2G
5G
3G
1G
90.
Sub-surface cracks
Surface cracks
Both 1 and 2
For none of 1 and 2
The pipe welding test position in which the pipe is horizontal and rotated
so that welding takes place at or near the top is designated as?
1.
2.
3.
4.
89.
PMI Testing
Non-destructive examination
Vacuum visual examination
Hammer Testing
88.
Ultrasonic technique
Radiographic profile technique
Anyone is okay.
None are okay.
(API-570-Mockup-CB) 17/18
91.
92.
one
two
minimum 10%
all
93.
94.
For calculating MAWP of Piping Circuit which is put in service the wall
thickness used in computations is:
1.
2.
3.
4.
95.
96.
As per API 570 for bolted flanged joints, bolts and nuts are considered as
acceptably engaged if the lack of complete engagement is:
1.
2.
3.
4.
(API-570-Mockup-CB) 18/18
97.
98.
For a typical injection point pipe circuit starts upstream of injection point
from a distance of
1.
2.
3.
4.
99.
100.
4 inches to 12 inches
4 inches to 10 inches
3 inches to 10 inches
3 inches to 8 inches
MASTER
Q
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
A
3
3check
2check
3
1
2
3
1
4
2
3
2
Check
1
2
1
4check
1
3
1
1
3
1
2
1check
Q
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
A
3
1
Check
New
4
3
1
3
1
1
Check
New
2
1
1
3
2
1
2
2
1
3
3
1
1
2
4
-0-0-0-0-0-
Q
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
Q
A
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.
98.
99.
100.