Professional Documents
Culture Documents
API-510
PRESSURE VESSEL INSPECTOR
PREPARATORY TRAINING PROGRAM
Final Exam (Close Book)
1. 0.5
2. 1.5
3. 1.0
4. 2.0
3. What positions are used to qualify a welder for all position pipe welding?
1. Must use the fixed horizontal (2G) and the fixed vertical (5G).
2. Fixed vertical (5G) and the multiple position (6G).
3. Fixed horizontal (2G) and the multiple position (6G).
4. Fixed horizontal (2G) and the fixed vertical (5G) or the multiple position
(6G).
1. API-510 Inspector
2. Welder
3. Quality Control Manager
4. Fabricator
1. Corrosion
2. Operating conditions
3. Improper installation
4. Water damage
(API-Final-CL)- 2/20
1. ASNT-TC-1A
2. Sect V
3. Sect VIII
4. APl-510
1. three measurements
2. at least two measurements
3. two or three measurements
4. two measurements where the thickness covers the range to be
measured
1. 6" '
2. 12"
3. 3"
4. 3’
12. Longitudinal joints that are not staggered at a distance of at least 5 times the
thickness of the shell:
1. The Manufacturer
2. Authorized Pressure Vessel Inspector
3. An Engineer
4. ASME code committee
15. Who is required to verify the application of the Code Symbol Stamp to a Code
vessel?
1. The Manufacturer
2. Authorized Inspector
3. An Engineer
4. ASME code committee
(API-Final-CL)- 4/20
16. Which item below is not an organization permitted by the code to make
repairs to pressure vessels?
17. Which item below is not a requirement that must be met before a pressure
vessel can be re-rated by changing the temperature or the maximum allowable
working pressure.
1. Safety valve
2. Relief valve
3. Control valve
4. Pilot-Operated valve
21. Under what conditions may surface defects in material be repaired by the
manufacturer?
22. What is the permitted under tolerance for plate material in Section VIII
provided the material specification permits plate to be furnished to an
under tolerance?
23. What part of Section VIII applies specifically to low alloy and carbon
steel fabrication of vessels?
1. Part UCL
2. Part ULC
3. Part UCS
4. Part UHA
24. What is the maximum carbon content of carbon and low alloy steels to be
used in welded construction or to be shaped by thermal cutting process?
1. 3.5%
2. 0.15%
3. 0.30%
4. 0.35%
25. Which material product form always requires a Material Test Repc-. 7
1. Bar
2. Pipe
3. Plate
4. Structural shapes
26. Which welding process may not be used for qualifying a welder by
radiography?
1. smooth
2. bright
3. confined to a local area .
4. all of the above:
28. An SMAW WPS specifies an amperage range of 50-300 amps for E7018
electrodes. The welder wants to use 400 amps to weld a groove weld.
What must be done as a minimum?
29. A welder was qualified with a P-l test coupon using SMAW E7018
electrodes. What below would not be permitted for this welder for this
qualification?
1. P5 or P-8
2. P1 to P1
3. P25 to P8
4. P8 to P8
30. For Typical process services, the maximum interval between pressure relieving
device inspections is;
1. 5 years
2. 10 years
3. As per vendor recommendations
4. dependent of service
31 Which welding below would not be permitted for a welder who is qualified
using a double-groove weld?
1. A lap weld
2. A fillet weld
3. A single V-groove weld with backing
4. A single V-groove weld without backing
(API-Final-CL)- 7/20
32. Who is responsible for the quality of welding and welding qualifications in a
repair of pressure vessels?
33. What other welding technique may be used in lieu of Post Weld Heat
Treatment for P-1 and P-3 materials?
1. None
2. SAW never needs PWHT
3. Twin arc welding
4. Temper bead welding.
1. The original data report is available and it satisfies the intended use of
the vessel. internal inspection is not required.
2. The nameplate is verified and as the necessary information
required.
3. The original data report has seen reviewed and is satisfactory to the
Inspector,
4. The vessel will be inspected at a frequency established by owner.
(API-Final-CL)- 8/20
37. When rerating a pressure vessel, one of the steps of the rerating is the
documentation of the;
1. Calculations from the manufacturer or the owner-user’s engineer.
2. Approval of the operation’s engineering department.
3. Report from a professional engineer.
4. Approval of the ASME.
38. What item below is not part of a pressure relieving device inspection?
40. Under ASME Code Section V. what are the upper and lower densities
acceptable for viewing if the density through the body of the IQI is 2.7?
Assume single film viewing.
1. 2.295 to 3.510
2. 1.890 to 3.105
3. 1.8 to 4.0
4. 1.3 to 4.0
1. 1.1
2. 1.25
3. 2.0
4. 1.3
44. When conducting a pressure test as part of a periodic inspection. What shall
be temperature as during the test for a 1" thick vessel ?
46. Which item below would not permit exempting a vessel with a known
corrosion rate less than 0.005 inch per year from an internal inspection.
47.0 For alterations or repairs initially post weld heat treated as a code requirement,
what postweld treatment alternative may not be used?
1 Preheat to not less than 3000 F
2 Temper bead technique
3 Duplication of the original heat treatment
4 Preheat to not less than 8850F
48 Rerating of a pressure vessel is considered complete when ;
49The owner of a pressure vessel requires a head of the vessel to be changed with
same head design due to corrosion. This will be classified as:
64. When looking for surface cracks in a vessel made of ferrous material which of
the following is the most capable of detection?
1. Fluorescent Penetrant Method.
2. Radiography.
3. Fluorescent Magnetic Particle Method.
4. Close visual Inspection with good lighting.
65. One major area of concern when inspecting guy wires for a vessel is crevice
corrosion, where does this occur?
1. On the free end of the turn buckle.
2. In the threaded areas
3. On the guy wires.
4. Where the wires contact the ground.
66. You are inspecting a failure in a vessel wall, what conditions would you look for
if it was believed that the fracture was brittle?
1. There is almost a no lack of ductility.
2. The fractured surfaces has a smooth surface
3. The surface of the crack would have jagged edges.
4. There is an almost complete lack of ductility and the failure site will have a
faceted surface.
(API-Final-CL)- 14/20
67. If steel plate of a vessel has exceeded its yield point, upon the removal of
pressure and heat it will;
1. return to its original shape
2. contain a permanent deformation
3. split or rupture
4. be oblong
68. Of the types of stresses placed on a thin walled cylinder the most severe is;
1. Circumferential
2. Longitudinal
3. Compressive
4. Radial
69. The report for qualifying a welder is:
1. WPS
2. PQR
3. WPQ
4. WQR
70. Which of the following inspection techniques requires direct visual examination
of the test specimen?
1. Radiography testing
2. Ultrasonic testing
3. Magnetic particle
4. Eddy current
71. A welding procedure is a detailed plan developed by whom to ensure sound
welds.
1. API-510 Inspector
2. Welder
3. Quality Control Manager
4. Fabricator
72. The primary cause of deterioration in pressure vessels is:
1. Corrosion
2. Operating conditions
3. Improper installation
4. Water damage
(API-Final-CL)- 15/20
74. Which of the following techniques is considered the primary means to determine
the minimum thickness of a vessel’s components?
1. A boat sample remove from a thin area
2. Measuring from a corroded area
3. Any suitable destructive method of examination
4. Ultrasonic thickness measurements.
75. The rules for impact testing of carbon steel in Section VIII vessel materials
require what kind(s) of impact test.
1. Brinell & Rockwell
2. Izod & Charpy V-notch
3. Charpy V-notch only is acceptable.
4. Brinell only is acceptable
76.. When a crack is discovered in a vessel that is in a highly stressed area. What
action should you recommend be considered as a first step in any effort to correct
the flaw?
1. use as is
2. Call in a pressure vessel engineer.
3. Using an insert patch.
4. Removing the crack using by grinding and inspect using an NDE procedure
before repair by welding.
77. What is the minimum length of weld metal to be radiographed for a Welder’s
Performance Qualification using an NPS 6 inch pipe coupon made of P No 5
materials utilizing the SMAW process?
1. Six inches of weld metal
2. The entire circumference of the pipe coupon
3. Stops and starts only
4. None, not allowed by Section IX
78. The API authorized pressure vessel inspector may give prior authorization for
repairs that do not involve;
1. Pressure tests
2. Radiography
3. Pneumatic testing
4. Final visual inspections
(API-Final-CL)- 16/20
79. The two types of impact tests required by Section VIII Div. 1 are;
1. Izod and Drop Weight
2. Brinell and Rockwell
3. Charpy and Drop Weight
4. Weld metal and Base metal
80. In Section VIII Div. 1 acceptance of a radiograph is based on;
1. the speed of the film used.
2. the geometric unsharpness of the image.
3. the absence of backscatter.
4. the ability to see the essential hole or wire, if a wire type IQI is used.
81. A spot radiograph of a butt weld in a 1 inch thick shell of a vessel marked RT-3
was found to have a rounded indication, the dimension of such an
indication according to Section VIII Div. 1 is;
1. 1/32 of an inch.
2. 1/3 of an inch.
3. 2/3 of an inch
4. None, rounded indications are not a consideration with spot radiography.
82. Section VIII Div. 1, is very specific about the number of spot radiographs
required when applying it for quality control, the basic premise is to;
1. insure that all welds are made perfectly.
2. make sure someone is held responsible for any poor welding.
3. apply the radiographs immediately after welding in order to take corrective
steps if needed.
4. fire as many welders as possible.
83. A P No. 1 material that is plate has been rolled into a cylinder and butt welded.
The cylinder is exactly 1-1/4” thick, and it is used in the repair of a pressure
boundary on a U stamped vessel, the following is a true statement.
1. It must receive full radiography.
2. It may be not spot radiographed.
3. It may not be fully radiography.
4. It may receive either spot, full, or no radiography depending on
original U1 form.
(API-Final-CL)- 17/20
84. Charpy impact tests are intended to prove that a material is;
1. tough at the desired MDMT of the vessel to be constructed using that
material.
2. some what prone to brittle fracture.
3. acceptable for use in high temperature service.
4. not required to be heat treated.
85. According to Section IX, all welders must be re-tested for a process;
1. if they have not been tested before.
2. if they have not used a process in the past 9 months or longer.
3. if they have not used a process for the past 12 months or longer and have not
been welding with other processes.
4. if the welder’s ability to make sounds welds with process is in doubt.
86. The testing apparatus used, and the techniques for performing Charpy impact
tests are found in;
1. Section VIII Div. 1 Paragraph UG-84
2. SA-270
3. SA-370
4. Section IX paragraph 401.32
87. An above the ground vessel is required to receive an external inspection;
1. Every 4 years.
2. At the half corrosion-rate life.
3. Every 10 years.
4. Every five years or at the same interval as the internal inspection whichever is
less.
88. Before starting the inspection of a pressure vessel, especially one in severe
service, the inspector should determine;
1. The pressure and temperature conditions under which the vessel has been
operated since the first inspection.
2. The pressure and temperature conditions under which the vessel has been
operated during the period since the last two inspections.
3. The pressure and temperature conditions under which the vessel has been
operated since the current inspection.
4. The pressure and temperature conditions under which the vessel has been
operated since the last inspection.
(API-Final-CL)- 18/20
89. The inability to draw the products of fractionation or distillation from certain trays
may
1. indicate fouling or loss of tray parts in a process tower.
2. indicate that instrumentation is giving false readings.
3. prove that the piping diameter is too small.
4. indicate that the trays have lost all bubble caps or tray valves, or possibly
the tray has collapsed.
90. Prior to witnessing a pneumatic test of a pressure vessel, which has been
repaired by welding, the inspector should;
1. Determine if the vessel has had all relief devices removed.
2. Observe that the digital pressure gage to be used for the test is of the proper
range.
3. Check that the personnel conducting the test have been properly trained to
perform hazardous tests.
4. Make sure that the analog pressure gage is of the proper range for the test
pressure.
91. Widely scattered pits may be ignored as long as the following are true:
a. No pit depth is greater than one half the vessel’s wall thickness exclusive of the
corrosion allowance.
b. The total area of the pits does not exceed 7 square inches (45 square
centimeters) within any 8-inch (20-centimeter) diameter circle.
c. The sum of their dimensions along any straight line within the circle does not
exceed 2 inches (5 centimeters).
d.?
What is the missing item in d above is?
1. The pit depths must be measured from the side the pit is located on.
2. The 8 inch diameter is to be measured from the center of the deepest pit.
3. There are no missing item there are only 3 items listed for this rule.
4. The total area of the pits cannot exceed 3.5 square inches in a 4-inch
diameter circle.
(API-Final-CL)- 19/20
92. The surface remote from a welded joint is determined as follows;
1. 1 inch on either side of the toe of weld or twice the minimum thickness which
ever is greater.
2. 1 inch on either side of the weld or twice the minimum thickness which ever is
less.
3. For vessels with inside diameters less than 60 inches 20 inches or ½ the
vessel diameter.
4. 2 inches on either side of the weld.
93. Before any repair to a pressure vessel in accordance with its code of
construction, what if any additional requirements for inspection may need to be
considered?
1. Jurisdictional requirements that might override the API 510 Code.
2. Who is doing the repair?
3. The quality of the repair materials.
4. The need for qualified welding procedures.
94. Some jurisdictions require that welded repairs to a pressure vessel be
documented by the completion and filing of;
1. A detailed report of the location and extent of repairs.
2. A qualifications record of all repair personnel.
3. A permit issued by the jurisdiction.
4. The National Board of Boiler and Pressure Vessel Inspectors Form “R-1”.
95. While inspecting an operating vessel you observe that cracks are present in the
connecting welds for a gauge glass, you also notice vibrations are occurring in the
assembly. Before you recommend corrective actions you should;
1. Re-evaluate the materials used in the fabrication of the gauge glass.
2. Write a report of the location with a recommendation for the type of repairs
needed.
3. Research the inspection records for previous failures of this type.
4. Check with a pressure vessel engineer to see if the cracks are caused by
fatigue failure.
96. Carbon dioxide considered corrosive when?
98. The main reason(s) for inspecting heat exchanger bundles after removal and
prior to cleaning is/are;
1. Location of scale on tubes can reveal non-operational problems.
2. Deposits on the tubes can reveal acid contamination problems.
3. Color of the tube ends can reveal de-zincification.
4. Color of deposits and scale can reveal corrosion problems.