An Oracle White Paper
December 2005

eAM Preventive Maintenance

EXECUTIVE SUMMARY ................................................................................................ 1


INTRODUCTION.............................................................................................................. 1
DESCRIPTION OF THE INITIAL SETUP ................................................................ 2
SET NAME ........................................................................................................................... 2
METER .................................................................................................................................. 3
LAST SERVICE INFORMATION ................................................................................. 4
PREVENTIVE MAINTENACE SCHEDULE............................................................ 5
Day Interval Rules............................................................................................................ 6
Scheduling Options.......................................................................................................... 6
Start to Start.................................................................................................................. 6
Forecast Work Order ............................................................................................. 6
Start to End................................................................................................................... 8
End to Start................................................................................................................... 8
Lead Time In Days ................................................................................................. 9
End to End ................................................................................................................. 10
Reschedule Manual Work Orders ...................................................................... 10
Runtime Rules................................................................................................................. 12
No Meter Readings.................................................................................................... 14
Usage Rate Not Recalculated................................................................................... 14
Usage Rate Recalculated ........................................................................................... 15
Work Order Completion Change in Last service Information ...................... 17
Meter Reading Reset.................................................................................................. 18
Schedule Based On................................................................................................ 19
List Dates......................................................................................................................... 21
Generate Preventive Maintenance Work Orders program................................. 21
SUPPRESSION .................................................................................................................. 22
Tolerance In Days .......................................................................................................... 25
PREVENTIVE MAINTENANCE TEMPLATE....................................................... 26
CONCLUSION.................................................................................................................. 26
APPENDIX A: LOG FILE CREATED BY THE GENERATE PREVENTIVE
MAINTENACE WORK ORDER CONCURRENT REQUEST ........................ 27

ii

eAM Preventive Maintenance

EXECUTIVE SUMMARY

Maintenance activities are carried out on the assets in an organization, the details of
which are captured through work orders. The work orders can be generated either
manually or automatically. Maintenance activities can be scheduled periodically
based on time interval or based on the readings of meters associated to the asset or
based on predefined calendar dates. Enterprise Asset Management makes periodic
scheduling possible through Preventive Maintenance.
INTRODUCTION

Enterprise Asset Management (eAM) enables users to optimally plan and schedule
maintenance activities with minimal disruption to an organizations operations or
production. By effectively monitoring an assets operating condition, effective
preventive maintenance strategies can be implemented. Preventive maintenance
activities reduce the probability of failure or degradation of the assets physical
conditions. Preventive maintenance helps to establish a maintenance strategy that
ensures minimal downtime.
It is possible to forecast the frequency at which preventive maintenance should be
performed. The frequency is decided based on meter readings, runtime intervals or
calendar dates. Meters are entered to measure any maintained number that needs to
be measured and periodically serviced, based on the measurement.
Preventive Maintenance Schedules(PM schedules) are defined for asset -activity
combinations. Multiple schedules can be defined for experimenting with different
maintenance strategies (simulation and what-if scenarios) but it is the default
schedule which is used for generating work orders. The work orders are generated
from the PM schedules either by running the Generate Preventive Maintenance
Work Orders concurrent program or from the Forecast Work Orders form.
This paper covers the basic setup and functionality of preventive maintenance.
Runtime Rules, Day Interval rules and List dates are covered in this paper .
Readers with an understanding of basic concepts of enterprise Asset management
would be in a position to appreciate the entire gamut of this paper.
Note: The paper has been written with Oracle Application Release 11.5.9 in mind
The screen shots indicated pertain to 11.5.9 only.

1 eAM Preventive Maintenance

DESCRIPTION OF THE INITIAL SETUP

The maintenance organization used in this paper is EM1. Cabs is the Asset group
defined. The Asset numbers under this asset group are CAB001 to CAB006. There
are two maintenance activities carried out on each of the above mentioned assets :

Cab Maintenance this activity involves all the maintenance activities


carried out on the cab

Cab Engine Overhaul this activity is carried out only on the cabs engine.

The routing for both the activities are the same. The first operation involves
department Contract. This department has one resource OSP Res and the
usage defined for this resource is 12 hours . The second operation is done in FMaint department and uses resource Cab-Mech for 12 hours. The total
duration for completing the activity is 24 hours.
SEQ

Department

Resource

Assigned units

Usage

UOM

10

Contract

OSP Res

12

HR

20

F-Maint

Cab-Mech

12

HR

The resources OSP Res and Cab-Mech are available 24 hours. The calendar for
the organization is defined as all seven days in the week as working days and does
not include any exceptions.

SET NAME

"Preventive Maintenance Set Name" gives users the option of creating multiple PM
schedules for one asset-activity association and provides ways of experimenting
with different maintenance strategies. A PM schedule for an Activity and a
Maintained Number or Maintained Group must uniquely belong to a Set Name.
Set names are defined in the "Set Name" window (Navigation : Preventive
Maintenance  Set Name Definition). The set names used in this paper are
Cab_Main and Cab_Simulation.
Some important points to note :

Main is a seeded set

PM schedule for the same Maintenance Number and activity combination


can be created across sets

Each PM schedule will have a set name field. It is a mandatory field

Every PM set has an end date. Every PM schedule that belongs to the set
must have its effective-to date before the end date of the PM set.

There can only be one default PM schedule per asset-activity association.

2 eAM Preventive Maintenance

Users will be able to set and unset a default PM schedule.

Default PM schedules will be automatically picked up by the PM engine to


generate work orders.

Non-default PM schedules will be mainly used for simulation and What-If


scenarios and they will never generate work orders

In the Set Name window, choose Templates to view or modify the PM


schedule templates or choose Schedules to view or modify the PM schedules
associated with the set name.
METER

Meters are associated with maintained numbers to measure a variable of the asset
or rebuildable item. Meters are entered to measure any Maintained Number that
needs to be measured and periodically serviced, based on the measurement.
Meters are defined using the meter definition screen.

Enter a meter name ,description and a unit of measure (UOM) for the
meter. The meter defined here is OMCAB004_01 with a UOM of Hours.

Choose whether the meter readings are ascending, descending or fluctuating.

If the meter has to be used in scheduling, then mark the Used In


Scheduling check box. As soon as this is check marked, the Rate (per
day) and the Number of Past Readings fields are enabled.

Enter the usage rate and the number of past readings (if Used in
Scheduling is marked) . The number of past readings designates how many

3 eAM Preventive Maintenance

readings prior the scheduler should go to for calculating the usage rate. If
there are an insufficient number of readings, then the usage rate defined
here is used. A usage rate of 20 and a number of past readings of 5 is
entered for the meter OMCAB004-01

The initial meter reading and the effective dates are optional. For meter
OMCAB004-01 , an initial reading of 0 was entered on 15th Nov, 2004

The Meter defined can be associated with the asset number (Navigation : Meter 
Meter Association) . Meter OMCAB004-01 is associated with Asset number
CAB004.
Another way to define meters is through the Meter Template . In the Meter
Template definition, meter templates are associated with maintained groups .After
the association, whenever a new asset number is created under the maintained
group, a meter is created and attached to the new asset number automatically.
LAST SERVICE INFORMATION

The last service information captures details of the date and the reading when the
last maintenance activity is done on an asset.
Last service reading captures the meter reading when the activity was performed
most recently on the asset. The last service reading cannot be greater than the last
meter reading (in case of ascending meter) or less than the last meter reading (for
descending meters)
Similarly, last service date captures the date when the activity was performed most
recently on the asset . Last service start date captures the date when the activity
started and last service end date captures the date when the activity ended. Last
service start/end date serves as a starting point for rule based scheduling.
The last service information is usually updated from the work order completion.
When a work order is completed, the last service start & end date will be updated
with the work orders actual start & end date and the last service meter readings will
be entered. The last service information can be modified from the Last Service
Information screen (Navigation : Preventive maintenance  Last Service Info)

4 eAM Preventive Maintenance

There is no meter associated with the asset number CAB001 so no meter details are
seen in the screenshot provided above
PREVENTIVE MAINTENACE SCHEDULE

Preventive maintenance schedules are defined to create or forecast work orders


based on rules or based on a list of specific date. A preventive maintenance
schedule can be created on asset number activity or asset route-activity
combination.
The PM schedule is defined in the Preventive Maintenance (Schedule Definition)
window ( Navigation : Preventive Maintenance  Schedule definition).
In the PM schedule definition window, enter the following details :

Enter a unique Schedule name

Choose the Item type. You could choose between Asset and rebuildable.

Enter a valid set name. The set name must be defined in the Set name
definition window. Every Set Name has an end date. Every PM schedule
that belongs to the Set Name must have its effective-to date before the
end date of the PM Set Name.

Select a Maintained Number . If the Item Type chosen is Asset, then


this field refers to the Asset number else it refers to the rebuildable number.
In the case of Non serialized rebuildable item, then this field is not
required

The maintained group is populated automatically as soon as a value is


entered for the maintained number field.

Select the Activity. Only the activities associated with the asset number /
rebuildable is available in the list of values.

Choose the Schedule type. The options available are Rule Based and List
Dates. The Day Interval Rules tab and the Runtime Rules tab are
enabled if you choose Rule Based schedule type . The List dates tab
becomes enabled when the schedule type chosen is List dates

The Effective date defaults from the activity chosen. The Effective from
and Effective To dates can be updated

Run to failure items are those whose items costs are cheaper than the
maintenance cost of the item. If the Run To Failure check box is selected,
the PM Scheduler will not automatically schedule the maintained number
and Activity association, however manual Work Orders can still be created.

The Default check box, if marked, indicates that the PM schedule is the
default schedule for the maintained numberactivity combination. Work
orders will be generated only based on the default PM schedules

5 eAM Preventive Maintenance

Day Interval Rules

The day interval rule specifies the time span in days, between the creation of each
work order . This is based on the last service information.
For information on the last service start date & end date, pls refer to the Last
Service Information described above

The above PM schedule will be used to explain the Scheduling options


Scheduling Options

The Scheduling Options controls the way the work order dates are calculated by
the PM scheduler. This decided whether forward scheduling or backward
scheduling must be used by the PM Process.
Start to Start

This is a Forward Scheduling Method. The PM scheduler uses the base point as the
Last Service START date and calculates the START dates for the scheduled work
orders.
Forecast Work Order

In the Maintenance Workbench (Navigation : Work Order planning 


Maintenance Workbench), choose the Asset number CAB001. In the work order
form, Press on the Forecast Work button to get the Forecast Work Order
form. In the Forecast Work Order form :

The Start date would default to current date

Enter the cutoff date. The Cutoff Date decides the date till which you would
like the Work Orders to be created from the suggested dates.

6 eAM Preventive Maintenance

The horizon is the difference between the start and cutoff date. If the
horizon is changed, then the cut off date gets recalculated

Optionally enter a Set name. If a set name is entered then the Simulate
button gets enabled and the Run and Implement button grays out. On
the other hand if no set name is chosen, then the Simulate button is
grayed out and the Run and Implement buttons are enabled. . No PM
schedule will be picked up for the asset/activity association if there is no
simulation PM schedule with the set name existing.

When Combine with Default is checked, the default PM schedules gets


picked up in the cases where no PM schedules with the specified set name
exist. When Combine with Default is not checked, only PM schedules with
the set name specified will be picked up by the PM engine.

For the asset CAB001 (schedule attached to this asset number is CAB001_CM),
when the Forecast Work Order is run from the Maintenance Workbench, the
following work orders are suggested .

The last service start date was 24th Nov, 2004. With a day interval of 30, the first
work orders START date is suggested on 24th Dec, 2004 and the consecutive work
orders are created with a difference of 30 days.
The Implement button could be chosen to convert the forecasted schedules into
work orders. Implementing the third line in the above schedule, would create work
order with the start date as 22-Feb-2005 and completion date as 23-Feb-2005.

7 eAM Preventive Maintenance

Start to End

This is a Backward Scheduling Method. The base point here is the Last Service
START date and using the base point, the PM process calculates the END dates
for the scheduled work orders.
For the PM schedule, CAB001_CM, change the Scheduling option to Start to
End.. The screenshot below shows the forecasted schedule for the asset number
CAB001 for the Start to End option

The last service START date was 24th Nov, 2004. With a day interval of 30, the first
work orders END date is suggested on 24th Dec, 2004 and the consecutive work
orders are created with a difference of 30 days.
Implementing the third line in the above schedule, would create work order with
the start date as 21-Feb-2005 and completion date as 22-Feb-2005.

End to Start

This is a forward scheduling method . Here the PM scheduler uses the last service
END date to calculate the START dates for the scheduled work orders.
Changed the Scheduling option to End to Start for the schedule CAB001_CM and
forecasted the work orders. The last service end date was 26th Nov, 2004. With a
day interval of 30, the first work orders START date is suggested on 26-Dec-2004
and the consecutive work orders are created with a difference of 30 days. The
suggested work orders are shown in the next screen shot.

8 eAM Preventive Maintenance

Lead Time In Days

The Preventive Maintenance process suggests work orders to be created or


scheduled in the horizon between the forecast start date to the cut-off date
specified while running the process. Lead Time In Days specifies the work orders
for those extra days beyond the cut-off date mentioned. To illustrate this example,
for the schedule CAB001_CM, a value of 25 is entered against the Lead Time In
Days field.

The PM process was run with a cutoff date as 01st May, 2005. The lead time of 25
days was taken into the picture while running the PM process so a work order was
also forecasted for 25th May 2005.

9 eAM Preventive Maintenance

End to End

The PM scheduler uses the base point as the Last Service END date and
calculates the END dates for the scheduled work orders. This is a Backward
Scheduling Method.

Note : The Lead Time In Days is set to zero for the following simulations
Reschedule Manual Work Orders

In the PM schedule, mark the Reschedule Manual Work Orders check box. If the
box is checked, the unreleased manual work orders will be taken into account
during PM rescheduling, else not. PM engine will not reschedule firmed or released
work orders.
Another change introduced in the PM schedule, CAM001_CM, is the Multiple
Rules defined for the day interval rule. The interval between the scheduled work
orders is 30 days between 24-Nov- 2004 and 28-Feb-2005 . From 01-Mar-2005 to
15-Aug-2005 , the day interval specified is 45 days.

The details of the 3 work orders already existing for the asset CAB001 is shown
below
Sl

Work Order
Number

Scheduled Start date

Scheduled
Completion date

Status

EM182073

14-Jan-2005 05:31:00

15-Jan-2005 05:31:00

Unreleased

EM182074

10-Feb-2005 13:17:00

11-Feb-2005 13:17:00

Unreleased

EM181973

23-Jun-2005 00:00:00

24-jun-2005 00:00:00

Released

10 eAM Preventive Maintenance

When the PM engine is run, the schedule shown below is proposed

Line 1, 2 ,4 and 5 in the above forecast corresponds to the interval rule of 30 days.
After 26th Mar, 2005, the interval rule of 45 days is added to get the next effective
date of 10th May ,2005. The next expected schedule must be with the schedule end
date of 24th Jun, 2005 but as there is already a work order on the 24th June, no work
order is suggested by the PM engine.
Also note that for the released work order EM181973, the action column contains
a value of No Action. For work order EM182073, the check box is marked
meaning that the work order will be rescheduled to the expected end date. For

11 eAM Preventive Maintenance

work order EM182074, the check box is not marked so the work order will not be
rescheduled.
Implementing the forecasted work orders would provide the following work orders

The work orders forecasted for this schedule is shown below


Runtime Rules

Runtime rules are based on meters. The interval between the work orders is
calculated based on the interval divided by the usage rate.
Ensure that the following setup is complete before defining a runtime PM schedule

Activity Definition

Maintained Number or maintained Group - Activity Association

Meter Definition

Meter/Asset Association

Maintained Group (Non-Serialized Rebuildable) or Asset or Maintained

Number/Activity Association

The Runtime rule will be explained using asset number CAB004. Meter
OMCAB004-01 is defined and attached to the asset CAB004 (refer Meter
definition explained before). Schedule CAB004_CM is defined for the asset
CAB004 as shown in the next screen shot:

12 eAM Preventive Maintenance

The interval defined for the meter OMCAB004-01 in schedule CAB004_CM is 300
KM. Usage rate defined for the meter is 20 KM
The last service information can be entered from the PM Schedule screen by
pressing on the Last Service Info button. The service start and end date is on
15th November , 2004 and the last service reading is 0 KM

13 eAM Preventive Maintenance

No Meter Readings

No meter readings are entered. When running the PM engine from the Forecast
Work Order screen, the following work orders are forecasted :

The usage rate is 20 KM and the interval is 300 Km so the work orders are
scheduled at a gap of 15 days. The current meter reading date is 15th Nov,2004 so
the first work order is created on 30th Nov, 2004 and thereafter a work order is
created every 15th day.
Usage Rate Not Recalculated

Meter readings are now entered in the meter reading screen(Meters  Meter
Reading). The reading history shows the following :

The number of past readings is 5 whereas only two entries have been made so the
usage rate is 20 (defined in the meter definition form). The system uses the Life To
Date meter reading to calculate the Usage Rate.

14 eAM Preventive Maintenance

The PM schedule forecasts the following schedules

The first Scheduled date is not 30th Nov, 2004 00:00:00 but it is 28th Nov, 2004
15:36:00. This is calculated using the following logic :
Current Meter reading = 67

Current Meter reading Date = 17-Nov-2004

For the PM Schedule,


Last Service Date = 15-Nov-2004

Target Meter Reading = 300

Due date for next service = Current Meter reading date + (target meter reading Current reading)/rate
= 17-Nov-2004 + (300 - 67)/20
= 17-Nov-2004 + 11.65  28-Nov-2004 15:36:00
The work orders after 28-Nov-2004 15:36:00 are spaced at an interval of 15 days
Usage Rate Recalculated

A few more meter readings are entered as shown below

15 eAM Preventive Maintenance

The number of past readings defined for the meter is 5. The number of readings
available for the meter OMCAB004-01 is more than the required number so the
usage rate is recalculated using the last 4 meter readings. The readings seen in the
above screen shot is Life to date reading. The actual readings entered is given below
DATE
Actual Value
Life to date
Nov, 2004
0
0
16th Nov, 2004
35
35
17th Nov, 2004
32
67
th
18 Nov, 2004
33
100
19th Nov, 2004
30
130
20th Nov, 2004
25
155
The usage rate is calculated as the total of the meter readings value changes,
divided by the total of the meter reading date intervals
15th

= (Total of meter Reading value changes)/ (Total of reading date intervals)


= (155-35)/(20th Nov- 16th Nov) = 120/ 4  30
The first date is calculated using the logic :
Current Meter reading = 155

Current Meter reading Date = 20-Nov-2004

For the PM Schedule, Usage Rate = 30


Last Service Date = 15-Nov-2004

Target Meter Reading = 300

Due date for next service = Current Meter reading date + (target meter reading Current reading)/rate
= 20-Nov-2004 + (300 - 155)/30
= 20-Nov-2004 + 4.833  24-Nov-2004 20:00:00
The work orders after 20-Nov-2004 20:00:00 are spaced at an interval of 10 days
(interval/usage rate  300/30). Now when the PM engine is run, the following
work orders are forecasted

16 eAM Preventive Maintenance

Work Order Completion Change in Last service Information

A work order is created for asset CAB004 for activity cab maintenance. The
scheduled start date is 20-Nov-2004 00:00:00 and completion date is 21-Nov-2004
00:00:00. The work order was completed and the actual start and end dates of the
work orders are the same as the scheduled dates. While completing the work order ,
a meter reading of 179 was entered. The last service information of the CAB004cab maintenance is shown below :

One more reading is entered on the 22nd November ,2004. the meter readings
history is shown in the table below :

DATE

Actual Value

Life to date

15th Nov, 2004

16th Nov, 2004

35

35

17th Nov, 2004

32

67

18th

Nov, 2004

33

100

19th

Nov, 2004

30

130

20th

Nov, 2004

25

155

21st Nov, 2004

24

179

22nd Nov, 2004

21

200

The usage rate now recalculates to 25 ( (200-100)/4 25). When the work orders
are forecasted, the following schedule is proposed

17 eAM Preventive Maintenance

The logic behind this :


Current Meter reading = 200

Current Meter reading Date = 22-Nov-2004

Usage Rate = 25
For the PM Schedule,

Last Service Date = 20-Nov-2004

Target Meter Reading = 479 (last service reading of 179 +interval of 300)
Due date for next service = Current Meter reading date + (target meter reading Current reading)/rate
= 22-Nov-2004 + (479 - 200)/25
= 22-Nov-2004 + 11.16  03-Dec-2004 03:50:24
The work orders after 03-Dec-2004 03:50:24 are spaced at an interval of 12 days
(interval/usage rate  300/25)
Meter Reading Reset

The meter OMCAB001-04 is reset to zero on 24th Nov, 2004 00:00:00. The value
before Reset was 200. The forecasted orders are shown below :

18 eAM Preventive Maintenance

The usage rate remains at 25 and the logic of calculation remains the same as
shown under work order completion except that now the last meter reading is on
24th Nov, 2004 (for the work order completion calculation it was 22nd Nov, 2004)
so the first work order is suggested on 05th Dec, 2004 03:50:24.
Disabled meter readings are not considered by the PM schedule.

Schedule Based On

PM Schedule CAB005_CM will be used to understand the functionality of the


schedule based on option. The screenshot of the schedule definition is posted
below:

The schedule, CAB005_CM, is based on Runtime Rules and has two meters
OMCAB005-01 and OMCAB005-02 attached to it. The usage rate for meter
OMCAB005-01 is 25 KM /day and the interval defined for this meter is 100 KM.
The second meter OMCAB005-02 has a usage rate of 50 KMs and an interval of
250 KM.
Common information about meter OMCAB005-01 and OMCAB005-02 :

Number of past reading is 3. Last service start and end date is 30-Nov-2004 and the
last service reading is Zero.

19 eAM Preventive Maintenance

With a start date of 30-Nov-2004 and a cutoff date of 01st Jan, 2005, the work
orders created for meters independently are shown below.

1
2
3
4
5
6
7

OMCAB005-01
04th Dec, 2004
08th Dec, 2004
12th Dec, 2004
16th Dec, 2004
20th Dec, 2004
24th Dec, 2004
28h Dec, 2004

1
2
3
4
5
6

OMCAB005-02
05h Dec, 2004
10th Dec, 2004
15th Dec, 2004
20th Dec, 2004
25th Dec, 2004
30th Dec, 2004

For OMCAB005-01, the work order will be scheduled every fourth day (interval =
100, usage rate =25) and for meter OMCAB005-02, work orders will be scheduled
on every fifth day (interval =250, usage rate =50).
When the Schedule Based on is set to First Due Date, then the due date is set
to the due date of the first due date of all the rules. The work orders forecasted for
CAB005_CM for the First due date option is shown below :

When the schedule based on is the Last Due date , then the due date is set to
the last due date of all rules. The scheduled work orders for schedule CAB005_CM
is shown in the next screenshot

20 eAM Preventive Maintenance

List Dates

The list dates provides users the flexibility to define a PM schedule by listing all the
specific due dates on which the work orders should occur, instead of defining rules
in the PM schedule. The PM engine then generates work orders on these list dates.
List dates and day/runtime interval are mutually exclusive.
PM Schedule CAB003_CM is defined for asset CAB003. The Schedule type is List
dates and under the List Dates tab , the dates on which the work orders are
required are listed out.

Generate Preventive Maintenance Work Orders program

In the previous simulations, the Forecast Work order form was used to forecast
and implement the work orders. The advantage in the Forecast Work order form
is the possibility of viewing the scheduled orders before implementing them.
Another way to create work orders using the PM schedule is to launch the
Generate Preventive Maintenance Work Orders concurrent program (
Navigation : Preventive Maintenance  Generate Work orders). This program
considers only the Default PM schedule for generating the work orders and does
not consider any other PM schedule.
The mandatory parameter passed to this program is the cutoff date. Area, asset
Category, item type (Asset or Rebuildable), maintained group and Maintained
number are other filters that could be passed here.

21 eAM Preventive Maintenance

After the Generate Preventive Maintenance Work Orders concurrent request


completes, the WIP Mass Load program is launched to generate the work orders
forecast by the Generate Preventive Maintenance Work Orders request.
The work orders generated for the Asset CAB003 is shown below :

SUPPRESSION

Other Activities can be suppressed with the current Activity in the scheduling
definition. You can enter suppression activities for a Maintained Number/Activity
combination.
To illustrate this functionality, asset CAB006 and activities Cab maintenance and
Cab Engine Overhaul is used. Here the simulation set is Cab_Simulation and
the Default check box is not marked. The schedule definitions are shown below :

22 eAM Preventive Maintenance

Schedule CAB006_CS is defined for the CAB006- Cab maintenance combination.


The Day interval defined for this schedule is 5 days.

Schedule CAB006_CEO_CS is defined for the CAB006-Cab Engine Overhaul


combination. The Day interval defined for this schedule is 4 days.

23 eAM Preventive Maintenance

CASE I : No Suppression defined


When no suppression is defined, the work orders forecasted for the asset CAB006
are :
Cab maintenance Activity

Cab Engine Overhaul


Activity

Schedule Start Date


1

06-DEC-2004

11-DEC-2004

16-DEC-2004

21-DEC-2004

26-DEC-2004

Schedule Start Date


1

05-DEC-2004

09-DEC-2004

13-DEC-2004

17-DEC-2004

21-DEC-2004

25-DEC-2004

29-DEC-2004

CASE II: Suppression Defined


Suppression is defined to suppress Cab Engine Overhaul Activity by Cab
maintenance activity (Navigation : Preventive Maintenance Suppression)

When the forecast Work order is run , the following work orders are forecasted:
Cab Engine Overhaul Activity
Cab maintenance Activity
Schedule Start Date
Schedule Start Date
1

06-DEC-2004

11-DEC-2004

16-DEC-2004

21-DEC-2004

26-DEC-2004

05-DEC-2004

10-DEC-2004

15-DEC-2004

20-DEC-2004

25-DEC-2004

30-DEC-2004

24 eAM Preventive Maintenance

The second work order forecasted under the Cab Engine Overhaul activity is on
10th Dec, 2004 and not on 9th December. This is because when a parent activity
suppresses a child activity, it means that the child activity will be performed when
the parent activity is done, i.e., the cab Maintenance activity performed on the
cab also includes Cab engine Overhaul activity.

Keeping the above in mind, the Cab Engine Overhaul activity is done on the 05th
Dec, 2004 but a Cab Maintenance activity is done on 6th Dec, 2004 which also
includes the Cab Engine Overhaul activity. The next work order for Cab Engine
Overhaul is scheduled 4 days from 06th Dec, 2004 , i.e., 10th Dec, 2004. The same
logic holds good for the other work orders forecasted under the cab Engine
Overhaul activity.
Tolerance In Days

Tolerance In Days is mentioned in the scheduling window to define the


minimum interval in days that suggested Work Orders dates are spaced from each
other.
The tolerance considers suppression.
CASE III: Suppression defined in Case II and a tolerance of 2 days set in
CAB006_ CS schedule and null tolerance set in CAB006_CEO_CS schedule
When the work orders are forecasted, the suggested dates is the same as in Case II
CASE IV : Suppression defined as in Case II and a tolerance of null days set
in CAB006_ CS schedule and 2 days tolerance set in CAB006_CEO_CS
schedule
The work orders forecasted for this case is shown below

25 eAM Preventive Maintenance

Work orders forecasted for Cab Maintenance activity are


06 DEC-2004
11-DEC-2004
16-DEC-2004
21-DEC-2004
26-DEC-2004
Work order forecasted for Cab Engine Overhaul activity is
30-DEC-2004
No other work order is forecasted for Cab Engine Overhaul activity as work
orders exist for the parent activity ,Cab Maintenance
The CAB006_CS and the CAB006_CEO_CS schedules were set as default and the
Generate Preventive Maintenance Work Orders concurrent request was
submitted. The log file generated by the request is provided in Appendix A

PREVENTIVE MAINTENANCE TEMPLATE

The previous schedules were created individually using the Preventive


Maintenance (Schedule Definition) window. The other way to define schedule is
to use the Preventive Maintenance (Template definition) window. A PM
Template is a schedule, defined for a Maintained Group (Asset Group or
Rebuildable Item)/Activity association. When the PM template functionality is
used, a new PM Schedule is automatically created for a newly created Maintained
Number (asset or rebuildable) for the Maintained Group. All PM Template
attributes are copied over to the PM Schedule for the Instance.
The steps used to create the PM template are the same as mentioned under the PM
schedule definition.
CONCLUSION

This paper covers the setup and functionality of preventive maintenance using a
hypothetical business scenario and test cases. The work orders were forecasted or
created after ensuring that no work orders exist in the system for the asset-activity
combination for the forecasted period.

26 eAM Preventive Maintenance

APPENDIX A: LOG FILE CREATED BY THE GENERATE PREVENTIVE


MAINTENACE WORK ORDER CONCURRENT REQUEST

Parameters passed to Generate Preventive Maintenance Work Orders  Cut off


date : 31-Dec-2004, "Item Type" : Asset and "Maintained Number" : CAB006. Log
file generated is posted below:
+---------------------------------------------------------------------------+
Oracle Enterprise Asset Management: Version : 11.5.0 - Development
Copyright (c) 1979, 1999, Oracle Corporation. All rights reserved.
EAMPMSDU module: Generate Preventive Maintenance Work Orders
+---------------------------------------------------------------------------+
Current system time is 04-DEC-2004 09:36:44
+---------------------------------------------------------------------------+
**Starts**04-DEC-2004 09:36:45
**Ends**04-DEC-2004 09:36:50
Start of log messages from FND_FILE
+---------------------------------------------------------------------------+
Starting my log at Sat Dec 04 09:36:48 MST 2004
select msn.inventory_item_id, msn.serial_number
from mtl_serial_numbers msn, mtl_system_items msi
where msn.current_organization_id = msi.organization_id
and msn.inventory_item_id = msi.inventory_item_id
and msi.organization_id = ? and msi.eam_item_type = 1

and

msn.current_status != 4
and msn.maintainable_flag = 'Y'

and msn.serial_number = ?

found a serial ...


&&&&&&&&&&&&&&&&&&&&&&&&&&&&
Initializing PMSchedule ...
&&&&&&&&&&&&&&&&&&&&&&&&&&&&
* The last service start and end dates are: 2004-12-01 00:00:00.0, 2004-1201 00:00:00.0
ruleType == PMConstants.DAY_INTERVAL_RULE
---- putting in the node: pm with id: 542--&&&&&&&&&&&&&&&&&&&&&&&&&&&&
Initializing PMSchedule ...

27 eAM Preventive Maintenance

* The last service start and end dates are: 2004-12-01 00:00:00.0, 2004-1201 00:00:00.0
ruleType == PMConstants.DAY_INTERVAL_RULE
---- putting in the node: pm with id: 463----- This PM's parentPM's Suggestions: --* The Day interval is: 5.0
************************
* The dueDate is :2004-12-06 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-11 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-16 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-21 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-26 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-31 00:00:00.0
******** PM Schedule Details ******************
PM: 463

association ID : 2636

leadTime : 0.0 reschedulingPoint : 1


nonScheduled : falseDay Interval Rule: Every [5.0]
********** Work Order Suggestions for PM 463**********
associationID: 2636
Create new work order
The timestamp is: 2004-12-06 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-11 00:00:00.0

28 eAM Preventive Maintenance

associationID: 2636
Create new work order
The timestamp is: 2004-12-16 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-21 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-26 00:00:00.0
--- This PM's parentPM's Suggestions: --associationID: 2636
Create new work order
The timestamp is: 2004-12-06 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-11 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-16 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-21 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-26 00:00:00.0
-------------------------* The Day interval is: 4.0
************************

29 eAM Preventive Maintenance

* The dueDate is :2004-12-05 00:00:00.0


* The Day interval is: 4.0
************************
* The dueDate is :2004-12-10 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2004-12-15 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2004-12-20 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2004-12-25 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2004-12-30 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2005-01-03 00:00:00.0
******** PM Schedule Details ******************
PM: 542

association ID : 2635

leadTime : 0.0

reschedulingPoint : 1

nonScheduled : false Day Interval Rule: Every [4.0]


********** Work Order Suggestions for PM 542**********
PARENT's suggestion...
associationID: 2635
Create new work order
The timestamp is: 2004-12-06 00:00:00.0
PARENT's suggestion...
associationID: 2635
Create new work order
The timestamp is: 2004-12-11 00:00:00.0
PARENT's suggestion...

30 eAM Preventive Maintenance

associationID: 2635
Create new work order
The timestamp is: 2004-12-16 00:00:00.0
PARENT's suggestion...
associationID: 2635
Create new work order
The timestamp is: 2004-12-21 00:00:00.0
PARENT's suggestion...
associationID: 2635
Create new work order
The timestamp is: 2004-12-26 00:00:00.0
associationID: 2635
Create new work order
The timestamp is: 2004-12-30 00:00:00.0
Begin to try to reschedule existing work orders for PM 463
End of trying to reschedule existing work orders for PM 463
Begin to try to reschedule existing work orders for PM 542
End of trying to reschedule existing work orders for PM 542
+---------------------------------------------------------------------------+
End of log messages from FND_FILE
+---------------------------------------------------------------------------+
Executing request completion options...
Printing output file.
Request ID : 2540122
Number of copies : 0
Printer : noprint
Finished executing request completion options.
+---------------------------------------------------------------------------+
Concurrent request completed successfully
Current system time is 04-DEC-2004 09:36:50
+---------------------------------------------------------------------------+

31 eAM Preventive Maintenance

Enterprise Asset Management (eAM) Preventive Maintenance


December 2005
Author: Arockiaraj Irudayasamy, Karthikeyan Balasubramaniam
Co-Author : Vinay Srinath
Contributing Authors: N/A
Oracle Corporation
World Headquarters
500 Oracle Parkway
Redwood Shores, CA 94065
U.S.A.
Worldwide Inquiries:
Phone: +1.650.506.7000
Fax: +1.650.506.7200
www.oracle.com
Oracle Corporation provides the software
that powers the Internet.
Oracle is a registered trademark of Oracle Corporation. Various
product and service names referenced herein may be trademarks
of Oracle Corporation. All other product and service names
mentioned may be trademarks of their respective owners.