33% found this document useful (3 votes)
5K views4 pages

Estimating Labor Requirements

The document provides labor estimates for various masonry works including concrete pouring, finishing, laying bricks and tiles. It lists the productivity rates of laborers for these tasks in units completed per day. It also gives man-hours required by carpenters and laborers for different construction elements like walls, footings and slabs. Manual labor capabilities per hour for masons and carpenters are provided for specific tasks. Man-hours for concreting various structural components using different methods are also estimated.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
33% found this document useful (3 votes)
5K views4 pages

Estimating Labor Requirements

The document provides labor estimates for various masonry works including concrete pouring, finishing, laying bricks and tiles. It lists the productivity rates of laborers for these tasks in units completed per day. It also gives man-hours required by carpenters and laborers for different construction elements like walls, footings and slabs. Manual labor capabilities per hour for masons and carpenters are provided for specific tasks. Man-hours for concreting various structural components using different methods are also estimated.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Estimating Labor Requirements
  • Capabilities and Manhours
  • Concreting Work Details

ESTIMATING LABOR REQUIREMENTS: MASONRY WORKS

LABOR ESTIMATE
1. CONCRETING OF PLAIN FLOORING:
2 MEN POUR 1.2 CU.M. CONCRETE/ DAY
2. CONCRETING OF REINF. FLOORING:
2 MEN POUR 0.84 CU.M. CONCRETE/ DAY
3. CONCRETING OF COLUMN AND BEAM:
2 MEN POUR 0.50 CU.M. CONCRETE/ DAY
4. FINISHING OF FLOORING (ROUGH)
2 MEN FINISHES 72 SQ.M./ DAY
5. FINISHING OF CHB JOINTS:
2 MEN FINISHES 420 PCS./DAY
6. PLASTERING OF CHB:
2 MEN PLASTERS 8 SQ.M./DAY
7. LAYING OF CHB:
2 MEN LAY 100 PCS./DAY
8. LAYING OF GLAZED TILE 4 X 4
2 MEN LAY 100 PCS./DAY

CAPABILITIES OF MANUAL LABOR PER HOUR


UNIT
1. 1 MASON
& 1 HELPER
2. 1 CARPENTER
& 1 HELPER

TYPE OF WORK

CAPABILITY

a. LAYING OF CHB & ADOBE

22 PCS.

b. CEMENT FINISH

28 SQ.M.

a. ERECTING FORMS

1.85 SQ.M

b. REMOVING FORMS

1.86 SQ.M.

MANHOURS PER SQUARE METER


ITEMS

MANHOURS
CARPENTER

LABORER

TOTAL

0.70

0.40

1.10

2. FOUNDATION OF PILE CAPS

1.50

0.65

2.15

3. GRADE BEAM OR FTB

0.75

0.40

1.15

4. WALLS GROUND TO 8 HIGH

1.10

0.72

2.92

5. WALLS TO 8-16 HIGH

1.21

.90

1.99

6. WALLS 16-20 HIGH

1.35

0.90

2.25

1. CONTINOUS WALL TYPE


(CHB)

7. COLUMNS

1.22

0.80

2.02

8. BEAMS AND GIRDERS

1.90

1.22

3.12

9. ELEVATED SLABS

1.15

1.16

2.31

0.70

0.90

1.60

(WORD SHORES)
10. ELEVATED SLABS
(ADJUSTED SHORES)

CONCRETING
MANHOURS
ITEMS

LABORER

CARPENTER

OPTR.

OILER

TOTAL

0.05

0.05

5.20

CONTINOUS WALL TYPE FTGS.


-JOB MIX

5.10

-CHUTE

0.75

- BUGGLES

0.98

0.05

0.80
0.98

SPREAD TYPE FOOTINGS


-JOB MIX

5.10

-CHUTE

0.86

- BUGGLES

1.14

0.05
0.07

0.05

5.20
0.93
1.14

FOOTING TIE BEAM


-JOB MIX

5.10

-CHUTE

0.90

- BUGGLES

1.48

0.05

0.05

0.07

5.20
0.97
1.48

FOUNDATION OR BASEMENT WALLS


-JOB MIX

5.10

0.05

0.05

-CHUTE

0.90

- BUGGLES

1.48

1.48

8.51

8.51

0.07

5.20
0.97

COLUMNS
-BY HAND
AND PULLEY
-PORTA LIFT

6.35

0.08

0.08

6.51

0.16

0.16

2.34

- CRANCE, BUCKET & BUGGLES


2.02
RETAINING WALL TO 10 HIGH
-BY HAND

12.71

12.71

AND PULLEY
-PORTA LIFT

10.60

0.08

0.08

10.76

- TOOLED JOINT FINISH


3.67

1.22

4.89

4.00

0.47

4.47

- GLAXED TILES 6.38

2.13

8.51

0.47

4.47

- PLAIN CEMENT FINISH (LOUVER BLOCKS)

- RUBBED CONCRETE
4.00

You might also like