Professional Documents
Culture Documents
CHAPTER 1
INTRODUCTION
1.1
GENERAL
The construction industry is traditionally divided into three sub-sectors.
Much building waste is made up of materials such as bricks, concrete and wood
damaged or unused for various reasons during construction. Observational
research has shown that this can be as high as 10 to 15% of the materials that go
into a building, a much higher percentage than the 2.5-5% usually assumed by
quantity surveyors and the construction industry. Since considerable variability
exists between construction sites, there is much opportunity for reducing this
waste. Certain components of construction waste such as plasterboard are
hazardous once land filled. Plasterboard is broken down in landfill conditions
releasing hydrogen sulfide, a toxic gas. There is the potential to recycle many
elements of construction waste. Often roll-off containers are used to transport the
waste. Rubble can be crushed and reused in construction projects. Waste wood
can also be recovered and recycled. Government or local authorities often make
rules about how much waste should be sorted before it is hauled away to landfills
or other waste treatment facilities. Some hazardous materials may not be moved,
before the authorities have ascertained that safety guidelines and restrictions have
been followed. Among their concerns would be the proper handling and disposal
of such toxic elements as lead, asbestos or radioactive materials.
1.1.1 Construction Waste
Waste is a product or material that is unwanted . Waste is also can be
defined as any materials by product of human and industrial activity that has no
residual value .Construction waste can be clustered into two groups namely the
physical and non physical waste.
Physical construction waste can be defined as a mixture of inert and noninert materials arising from construction, excavation, renovation, demolition,
roadwork and other construction-related activities. Similarly defined by Shen et
al. and Kofoworola and Gheewala , construction and demolition waste is
generally defined as waste which arises from construction, renovation and
demolition activities including land excavation or formation, civil and building
construction, site clearance, demolition activities, roadwork, and building
renovation. But some defined as solid waste and consists of concrete debris,
different types of bricks and blocks, various kinds of tiles, steel reinforcement,
wood, plastic materials and paper, as well as gravel and soil . Research has also
interpreted in physical construction waste as waste origins and can be found in.
1.1.1.2 Non Physical Waste
On the other hands, waste can be defined as non-value adding works. The
term non value-adding activity is used to differentiate between physical
construction waste found on-site and other waste which occurs during the
construction process. This type of waste also mentions by other researcher as
intangible waste, in-directs waste or non-physical waste. Womack and Jones
describe waste as any human activity that absorbs resources but creates no value,
such as mistakes that require rectification, production of items no one wants,
process steps that are not needed, unnecessary movement of employees, and
people waiting for the conclusion of upstream activities. Furthermore, Koskela
also describe waste as any inefficiency that results in the use of equipment,
materials, labour or capital in larger quantities. In other words, waste in
construction is not only focused on the quantity of waste of materials on-site, but
also related to several activities such as overproduction, waiting time, material
occurs in the office or job site trailer, when looking for files, reports, reference
books, drawings, contracts, or vendor catalogues.
Inventory. This includes uncut materials, work in process, and finished
fabrications. Some contractors claim that they have no inventory because they
job-cost all material. While this may work for accounting, if the material is not
yet installed and isnt being used by the customer, its waste. This waste includes
spare parts, unused tools, consumables, forms and copies, employee stashes, and
personal stockpiles. One could argue that the unfinished facility is inventory and
is waste until operational. Waste is everywhere in construction and has been for
hundreds of years. This is not a statement of blame, just fact. It is so much a way
of life that most construction managers dont even sees it. They accept waste as
inevitable and unpreventable and add it into the cost of the job. Thus, the
customer pays for it. However, some construction companies dont accept waste
as a necessary part of doing business. They attack it through the application of
lean.
1.1.2 SIGNIFICANT CAUSES
Overproducing: Occurs when a subcontractor wants to maximize his daily
productivity to request more payments not realizing that he has
overstepped on the work of somebody elses. This may lead to partial
demolition and rework to get back on schedule. Example: drywall
contractor installs drywall before electrician has completed circuits.
Idle time: Poor coordination results in lost/idle time in projects. Example:
For a concrete pour for a slab, if poor coordination results in late delivery,
waiting laborers to direct the pour result in wasted labor expense.
or workers that have a needed skill for the work). Also occurs if resources
become unavailable after the task has started and continuing the task.
Not speaking and not listening: Not listening is caused by the command
and control style of leadership in which those in power are disinclined to
listen to those who are closest to the problem. Not speaking arises as a
conditioned response from overt or implied signals that by saying
something contrary to the prevailing beliefs of management, one will be
labeled as going against the grain, or a complainer or troublemaker.
There are 5 selected significant factors placed the highest ranked or key position
among the other factors and they are;
1.
2.
3.
4.
5.
1.2 OBJECTIVES
The objectives of the study are:
1. To identify the risks in the construction project.
2. To identify critical waste variables and the associated waste
causes.
3. To quantify different types of waste present in construction sites.
4. To propose ways to minimize them based on lean construction
principles.
2008). Lean construction recognizes that desired ends affect the means to achieve
these ends, and that available means will affect realized ends (Lichtig 2004).
Essentially, lean construction aims to embody the benefits of the Master Builder
concept (Abdel Hamid et al. 2008).
Lean construction (LC) is a method of production aimed at reducing costs,
materials, time and effort. Essentially, the methodology is to minimize the bad
and maximize the good. Using the principles of lean-construction, the desired
outcome would be to maximize the value and output of a project while
minimizing wasteful aspects and time delay. This outcome is produced when
standard construction approaches are merged with a clear and concise
understanding of project materials and information and two sets of management
archetypes, planning and control. This may seem complex to understand, but the
essence of this system to use what is necessary without extra. This can only be
done by strategic planning and action by a management group and with the help
and aid of all workers. It should be understood that lean construction is a
philosophy with principles and ideologies, but it is not a concrete plan of action
with set tools and methods. LC principles are the same throughout the many
different schools of thought. The basic principles include: creating a predicable
atmosphere based on planning and data, reducing the overflow of waste from
careful planning and increasing the communication flows between the customer
and the project at hand. Lean is a way of thought based on the notion that less is
more.
"One can think of lean construction in a way similar to mesoeconomics.
Lean construction draws upon the principles of project-level management and
upon the principles that govern production-level management. Lean construction
recognizes that any successful project undertaking will inevitably involve the
10
11
12
3. Reduce costs
1.4 HISTORICAL DEVELOPMENT
The first emergence of lean thinking was by Eiji Toyoda and Taichii Ohno,
who recognised inefficiencies within the mass production models developed by
Henry Ford and the Ford Motor Company. Initially, Toyoda and Ohno,
recognised a large quantum of waste within the production models used in the
Ford Motor factory. Toyoda and Ohno recognised seven definable areas of waste
within the Ford production system being:
1. Overproducing.
2. Idle Time Waste.
3. Transporting/conveyance waste.
4. Processing Waste (waste in work itself).
5. Inventory waste (having unnecessary stock on hand).
6. Wasted operator motion (using unnecessary motion).
7. Producing defective goods (waste of rejected production)
These barriers essentially acted as the catalyst for the development of the
Toyota Production model and subsequently lean Production/Organization.
Stemming from these ideals, lean construction draws on similar principles to be
applied to the construction process. Identifiably, the construction process at its
most basic level (physical) is layered with inefficiency (waste) in standard
practice. The seven key barriers to efficiency align with significant recognizable
deficiencies within construction practice (physical) including:
1. Oversupply based on push system.
2. Down-time/delays.
3. Delivery scheduling delays and inadequacies.
13
14
15
critical in the schedule. The key is to plan only work that is ready, regardless of
when it should be performed. This is like pulling the cord on Toyotas assembly
line. In essence, the foreman says, Stop, we will not do the work that is not ready
to be done. Typically, construction work is driven by schedule, not task
readiness; project managers drive the subcontractors to start work that isnt ready.
This usually causes the crew to spend additional time returning later to finish the
task. This wastes time and resources. The weekly work plan is the foremans
commitment plan, and because its made up of tasks ready to be done and
committed to by the foreman, it has a much higher likelihood of being completed
within that week. After each weeks work, the last planner identifies any
constraints that kept him or her from doing the work as planned. These
constraints are analyzed in a weekly coordination meeting, and action is taken to
prevent future occurrences. Part of this weekly learning cycle is measuring the
percentage of work completed. Phased planning takes place several times,
depending on the complexity of the building project. The look-ahead and weekly
work plan, as well as the constraints analysis, are done weekly and represent
current best knowledge of the jobs progress. The LPS provides the necessary
tools for planning and controlling projects. In LPS, planning is what needs to be
done and how it will be done; control is about making it happen. The LPS helps
shield the crews from the variability common to construction and keeps them
focused on installation.
1.5.2 5S
Masaaki Imai says, If one is not doing 5S, one is not doing lean.
In construction, 5S: Sort. Grunau implemented the first S by separating
the material and tools found in the yard into two groups: using and not
16
using. Any material or tool that fell into the second group was disposed of
in the most economical way. The items in the using group were set in
order by identifying a specific home for each item.
Sort- Grunau implemented the first S by separating the material
and tools found
in the yard into two groups: using and not using. Any material or tool that
fell into the second group was disposed of in the most economical way.
Set in order- The items in the using group were set in order by
identifying a specific home for each item. These locations were
visually marked.
Shine- sweep or shine was done to keep the area clean and return
used tools or equipment to the designated locations.
Standardize- Next the team looked at ways to standardize the work
area.
Sustain- The last S is self-discipline (or sustain). Here the team
looked at ways to maintain the gain it had made in the yard. has
been applied in the shop with great success. After applying 5S, one
manager reported, It was like night and day to see the difference.
1.5.3 KANBAN
A basic Kanban (signboard or billboard- is a concept related to
Lean and just-in-time (JIT) production) -approach has been used in
construction, both in the field and shop, to signal the need to refill
consumables. When one bin of bolts or screws is empty, the second bin
replaces it. The empty bin becomes a signal to refill it by placing it in a
designated location. In the bottom of the bin is a card that has the bolt type,
part number, quantity to be ordered, and the suppliers contact information.
17
reduction)
events
that
have
been
used
successfully
in
18
19
20
21
work is pushed though the system at the convenience of the operators and
so you produce outputs that are not required. Most services react to
customer demand and so pull the work through the system.
Seek Perfection
As the first four principles are implemented you should get to
understand the system ever better and from this understanding you should
generate ideas for more improvement. A lean system becomes yet leaner
and faster and waste is ever easier to identify and eliminate. A perfect
process delivers just the right amount of value to the customer.
1.7 APPLYING LEAN CONCEPT TO CONSTRUCTION
The following diagram shows the 4 important spheres of construction, that
is four areas of work in Construction Phase:
Client
Information
Procurement
Site Construction
22
Client
Site
Constructio
n
Informatio
n
Procureme
nt
These are continuous over time and totally different in nature and output
performance. They are also general areas of activity: the actual process varies
widely in practice, which in itself a huge source of confusion and
misunderstanding. The client dominates the first sphere in any project, being both
customers for the final product but also the first source of information about what
the product needs to be. The relationship continues as the project progresses in a
series of exchanges until the client is able to take possession of their building or
engineering structure. How well this is accomplished is critical to the success of
any project. The next sphere is about the generation of Information. It begins with
exchange of information between sides and Clients needs like:
Client- Main Contractor- Engineer-Supplier or vice versa
So these all leads on to the design process, which moves through a number of
repetitions and begins to involve members of the Supply Chain who give their
technical and logistic skill. Parallel to, integrated with and dependent on the
design
processes are the Cost-Estimating and Program-Planning process.
23
Client
Procurement
Site
Construction
Information
Procurement comes next, connecting those people and companies who will
actually supply the materials, components, people and plant to perform the
project. This, like everything else in Construction, is not a straightforward set of
sequential activities. Various suppliers are often required to contribute to the
Technical Design for the structure and will be engaged early on in the project.
The Lean Principles can only be applied fully and effectively in construction by
focusing on improving the whole process. This means all parties have to be
committed, involved and precisely work to overcome obstacles and faults that
may arise from traditional contractual arrangements.
1.8 SOFTWARES USED
Quantum XL
Minitab
SPC XL
SIGMA XL
Data Lyzer spectrum
Quality Window by Busitech
SDI Tools
1.9 BENEFITS
1.
Using fewer materials and having less waste can greatly reduce all around
costs. Although the philosophy of lean construction is focused on overall
reduction, not just for profit, utilizing this methodology has shown to
increase the bottom line.
24
2.
3.
Fewer accidents and a higher rate of safety through increased worker focus
and understanding.
4.
5.
6.
7.
8.
9.
10.
1.10 DRAWBACKS
1. In order for this method of construction to be effective, all areas of
management, along with the workers, have to be in accordance with the
plan. If there is a break in the chain, the lean methodology cannot work.
2. Getting everyone onboard with a new production method isnt easy, and
some people may be ambivalent about change.
25
26
27
CHAPTER 2
LITERATURE REVIEW
1. Implementation of lean construction techniques for minimizing the risks
effect on project construction time
Usama Hamed Issa; Alexandria Engineering Journal (2013) 52, 697704
The construction projects involve various risk factors which have
various impacts on time objective that may lead to time-overrun. This study
suggests and applies a new technique for minimizing risk factors effect on time
using lean construction principles. The lean construction is implemented in this
study using the last planner system through execution of an industrial project in
Egypt. Evaluating the effect of using the new tool is described in terms of two
measurements: Percent Expected Time-overrun (PET) and Percent Plan
Completed (PPC). The most important risk factors are identified and assessed,
while PET is quantified at the project start and during the project execution using
a model for time-overrun quantification. The results showed that total project
28
time is reduced by 15.57% due to decreasing PET values, while PPC values
improved. This is due to minimizing and mitigating the effect of most of the risk
factors in this project due to implementing lean construction techniques. The
results proved that the quantification model is suitable for evaluating the effect of
using lean construction techniques. In addition, the results showed that average
value of PET due to factors affected by lean techniques represents 67% from PET
values due to all minimized risk factors.
2. Site Implementation and Assessment of Lean Construction Techniques
O. Salem, J. Solomon, A. Genaidy, and M. Luegring; Lean Construction
Journal 2005 Vol 2 # 2 October 2005
The goal of this paper is to test the effectiveness of some lean
construction tools, in particular, those tools that can be applied in medium size
construction firms. Due to the success of the lean production system in
manufacturing, the construction industry has adapted lean techniques to eliminate
waste and increase profit. A field study was conducted to evaluate the
effectiveness of some lean construction techniques including last planner,
increased visualization, daily huddle meetings, first run studies, the 5s process,
and fail safe for quality. The data collection methods included direct observations,
interviews, questionnaires, and documentary analysis. The effectiveness of the
lean construction tools was evaluated through the lean implementation
measurement standard and performance criteria. It was found that last planner,
increased visualization, daily huddle meetings, and first run studies achieved
more effective outcomes than expected. However, the results of implementation
of 5s process and fail safe for quality did not meet the expectations of the tool
champions and the research team. It was found that there is need for behavioral
changes and training for effective use of lean tools. Most of the lean construction
29
tools selected for the project are either ready to use, or are recommended with
some modifications.
3. Applying lean thinking in construction and performance improvement
Remon Fayek Aziz, Sherif Mohamed Hafez; Alexandria Engineering Journal
(2013) 52, 679695
The productivity of the construction industry worldwide has been
declining over the past 40 years. One approach for improving the situation is
using lean construction. Lean construction results from the application of a new
form of production management to construction. Essential features of lean
construction include a clear set of objectives for the delivery process, aimed at
maximizing performance for the customer at the project level, concurrent design,
construction, and the application of project control throughout the life cycle of the
project from design to delivery. An increasing number of construction academics
and professionals have been storming the ramparts of conventional construction
management in an effort to deliver better value to owners while making real
profits. As a result, lean-based tools have emerged and have been successfully
applied to simple and complex construction projects. In general, lean construction
projects are easier to manage, safer, completed sooner, and cost less and are of
better quality. Significant research remains to complete the translation to
construction of lean thinking in Egypt. This research will discuss principles,
methods, and implementation phases of lean construction showing the waste in
construction and how it could be minimized. The Last Planner System technique,
which is an important application of the lean construction concepts and
methodologies and is more prevalent, proved that it could enhance the
construction management practices in various aspects. Also, it is intended to
30
develop methodology for process evaluation and define areas for improvement
based on lean approach principles.
4. Lean six sigma principal in construction: a literature review related to
abstract
SUNIL V. DESALE , DR. S. V. DEODHAR Department of Civil Engg,
SSVPS B S Deore College of Engineering, Dhule , India, Department of Civil
Engineering, , SVITS Indore (M.P),India; ISSN: 0975 6744| NOV 12 TO
OCT 13 | Volume 2, Issue 2
The critical objective of construction industries nowadays is to
complete a project within a stipulated time and cost through process
standardization, minimization of waste, and organizational potential and efficient
use of resources by using recent techniques such as Lean six sigma. Lean six
sigma in construction was found to be rigorously studies most of the literature has
focused on the application of Lean six sigma applied in the variety of fields hence
the main aim of this paper is to conduct rigorous review and to identify the
potential aspects of their application in Indian construction management. Most of
the construction companies face poor client satisfaction due to non completion the
work as per the required standard and specification. For the industry to increase
its profit margin and remain competitive in the market, completion of a project as
stipulated is crucial. In this paper efforts are made to establish complete analysis
of 51 papers with data base search from major publishers including Science
Direct, Emerald and Google Scholars. This paper reviews the published literature
related to six sigma or lean six sigma in construction from start to date. The
statistical calculation consist of the response from the year 2003 up to 2012 they
include number of publications in the respective years and after a pilot study a
sample of 51 Papers were considered and statics is done .Six sigma refers to the
minimization of variation through proper work flow maintenance and it leads to
31
32
33
34
Mohd Arif Marhani, Aini Jaapara, Nor Azmi Ahmad Baria, Mardhiah
Zawawib; Procedia - Social and Behavioral Sciences 101 ( 2013 ) 90 99
Lean construction (LC) is excellent in managing the construction process
and achieving the by eliminating waste. The objectives of this paper are to
provide with fundamental knowledge of LC and highlight the barriers of its
implementation. The literature reviews has been conducted through relevant
databases. It was found that there is a need for more holistic approaches to be
adopted in LC implementation such as health and safety, and six sigma. A
systematic training and research are also found vital to provide good interaction
and collaboration with the stakeholders. LC is also capable to enhance
sustainability in construction thus the quality of life for future Malaysian
construction industry.
9. Lean Construction: From Theory to Implementation
O. Salem, M.ASCE; J. Solomon; A. Genaidy; and I. Minkarah, M.ASCE;
This article compares the techniques developed for lean
construction with those developed for lean manufacturing. Lean manufacturing
and lean construction techniques share many common elements despite the
obvious differences in their assembly environments and processes. Manufacturing
plants and construction sites are different in many ways that might explain why
lean production theories and practices do not fully fit the construction industry.
Though many lean construction tools and elements are still in an embryonic state,
lean construction techniques are gaining popularity because they can affect the
bottom line of projects. Additionally, this paper presents a study of a construction
project in which specific lean construction elements were tested. Each technique
was evaluated in terms of its impact on the performance of the project. Based on
35
the findings of the study, a new lean assessment tool is proposed to quantify the
results of lean implementations. The assessment tool evaluates six lean
construction elements: last planner, increased visualization, huddle meetings,
first-run studies, five Ss, and fail safe for quality. This paper provides a simple
and comprehensive approach that is transferable to any construction project.
10. An Application of Lean and Six Sigma Principle for Constructional
Process Improvement in Indian Organizations
Research Scholar, Department of Civil Engineering, SSVPS B S Deore
College of Engineering, Dhule, India Professor, Dean Civil Engineering
faculty , SVITS Indore, (MP).India; Volume : 3 | Issue : 4 | April 2013 | ISSN
- 2249-555X
Keywords India has seen tremendous growth in construction and
infrastructure sector in last decade. To achieve a double digit growth in
construction sector, a continuous effort should be taken. Such a growth
opportunity can be leveraged for competitiveness by adapting the principals and
various tools of learn and six sigma management for min or zero wastage. Delays
were rampant in construction earlier and now costs are often too high for quality
that is given. With increasing competition from domestic and international
construction forms innovation has raised up for the implementations, adaptation
of Lean Concepts Seems to have higher potential for the construction industry.
This paper highlights the real issues contrasting construction organizations and
explores the potential of Lean and Six Sigma construction concepts in
construction industry in India. Lean Construction and Six Sigma or related
concepts have been successful acceptance in the Automobile sector in many
countries. But still the same has yet to be used in Construction rigorously. This
paper will focus on this emerging concept called Lean Construction based on
36
the basic Principles of management and special tools and techniques to achieve
those desired goals of better productivity and better profit margins.
CHAPTER 3
METHODOLOGY
37
LITERATURE SURVEY
DEFINING THE OBJECTIVES
DATA COLLECTION
IDENTIFICATION OF RISKS
ANALYZING THE RISKS
IMPLEMENTATION OF LEAN CONSTRUCTION TECHNIQUE
MONITORING THE RESULTS
CONCLUSION
38
within the organization. They are responsible for providing the logistics and
informational resources that will be needed for the successful completion of the
project. They also select the project and identify the scope of the projects to be
worked on. They identify the team that should work on the project, and work to
remove barriers that may block the success of the project. Most companies go on
to use a classification methodology similar to the one created by Motorola to
describe the abilities of their six sigma user. For example, classifications like
Green Belt (part-time user) or Black Belt (full-time user) are common. Each level
requires an improved mastery of the six sigma tools and skill set, as well as the
roles and responsibilities of the individual in the improvement process. The
objective is to create a methodology for defining the skill set of the users. The
Master Black Belt is the guru of the six sigma methodology. This individual
works as a coach, leader, and teacher for the other individuals on the team. The
Black Belt is the change agent for the six sigma process. This individual is a high
performer and has a dedicated position that is responsible for six sigma projects.
The Green Belt is a specially trained member of the team and usually sits on a
function-specific part of the organization. The Green Belt works under the Black
Belt on specific aspects of the six sigma projects. The Yellow Belt represents the
remainder of the organization, which has been trained on some of the basic skills.
These individuals are working their way towards becoming knowledgeable in the
six sigma process. Each of the successful six sigma users have customized the
process to fit their own culture and methodology. In order to accomplish this, it is
important to identify the key business goals and objectives of the organization,
and then to adapt the six sigma methodology and philosophy to fit this goal set.
We need to develop an action plan identifying how we are going to focus the six
sigma tool so as to focus on the big returns and avoid any waste in investment.
39
Hence, it is useful to identify the areas where six sigma performs well. These
include:
3.1.2 METHODS
Six sigma is not an all or nothing venture. Six sigma is a collection of tools
and you pick selectively from those tools in order to gain the desired result. It is
also not an increase in the level of organization bureaucracy. In fact, if use
properly, it will reduce the level of bureaucracy within the organization. Six
Sigma projects follow two methodologies inspired by Demings Plan-Do-CheckAct Cycle;
DMAIC is used for projects aimed at improving an existing
business process. DMAIC is pronounced as duh-may-ick
DMADV is used for projects aimed at creating new product or
process designs. DMADV is pronounced as duh-mad-vee.
DMAIC:
D- DEFINE THE SYSTEM
40
41
produce. The cycle time to complete work on each station is often less than the
takt time in order to ensure that the customer is never short of product. Although
theoretically you want to match cycle time to takt time to avoid building
inventories and over-sizing equipment, the reality is that demand is dynamic and
never precisely known and also process disruptions such as unplanned downtime
can occur. Thus, in practice, it is generally understood that cycle time needs to be
slightly less than takt time.
DEFINITION:
Assuming a product is made one unit at a time at a constant rate during the net
available work time, the takt time is the amount of time that must elapse between
two consecutive unit completions in order to meet the demand.
Takt time can be first determined with the formula:
Where
T = Takt time, e.g. [work time between two consecutive units]
Ta = Net time available to work, e.g. [work time per period]
D = Demand (customer demand), e.g. [units required per period]
Net available time is the amount of time available for work to be done. This
excludes break times and any expected stoppage time (for example scheduled
maintenance, team briefings, etc.).
IMPLEMENTATION:
42
The product moves along a line, so bottlenecks (stations that need more
time than planned) are easily identified when the product does not move on in
time.
The takt leaves only a certain amount of time to perform the actual value
added work. Therefore there is a strong motivation to get rid of all non valueadding tasks (like machine set-up, gathering of tools, transporting products, etc.)
Workers and machines perform sets of similar tasks, so they don't have to
There is no place in the takt system for removal of a product from the
assembly line at any point before completion, so opportunities for shrink and
damage in transit are minimized.
Downsides of takt time organization include:
When customer demand rises so much that takt time has to come down,
quite a few tasks have to be either reorganized to take even less time to fit into the
shorter takt time, or they have to be split up between two stations (which means
another station has to be squeezed into the line and workers have to adapt to the
new setup)
When one station in the line breaks down for whatever reason the whole
line comes to a grinding halt, unless there are buffer capacities for preceding
stations to get rid of their products and following stations to feed from. A built-in
buffer of three to five percent downtime allows needed adjustments or recovery
from failures.[1]
Short takt time can put considerable stress on the "moving parts" of a
43
Tasks have to be leveled to make sure tasks don't bulk in front of certain
stations due to peaks in workload. This decreases the flexibility of the system as a
whole.
2.VALUE STREAM MAPPING
Value stream mapping is a lean-management method for analyzing the current
state and designing a future state for the series of events that take a product or
service from its beginning through to the customer. At Toyota, it is known as
"material and information flow mapping". It can be applied to nearly any value
chain.
1.
Create a charter, define the problem, set the goals and objectives, and select the
mapping team. Socialize the charter with the leadership team.
2.
Draw while on the shop floor a current state value stream map, which
shows the current steps, delays, and information flows required to deliver the
target product or service. This may be a production flow (raw materials to
consumer) or a design flow (concept to launch). There are 'standard'symbols for
representing supply chain entities.
3.
Assess the current state value stream map in terms of creating flow by
eliminating waste.
4.
44
5.
APPLICATIONS:
Value Stream Maps are usually drawn using a set of standard symbols, some of
which can be seen here. Value stream mapping has supporting methods that are
often used in Lean environments to analyze and design flows at the system level
(across multiple processes). Although value stream mapping is often associated
with manufacturing, it is also used in logistics, supply chain, service related
industries, healthcare, software development, product development, and
administrative and office processes.
In a build-to-the-standard form, Shigeo Shingo suggests that the value-adding
steps be drawn across the centre of the map and the non-value-adding steps be
represented in vertical lines at right angles to the value stream. Thus, the activities
become easily separated into the value stream, which is the focus of one type of
attention, and the 'waste' steps, another type. He calls the value stream the process
and the non-value streams the operations. The thinking here is that the non-valueadding steps are often preparatory or tidying up to the value-adding step and are
closely associated with the person or machine/workstation that executes that
value-adding step. Therefore, each vertical line is the 'story' of a person or
workstation whilst the horizontal line represents the 'story' of the product being
created. Value stream mapping is a recognised method used as part of Six Sigma
methodologies
3.NON VALUE ADDED (NVA) TIME
Non value added time is a management term loosely related to the Lean
Manufacturing movement as codified in the 1980s by a landmark MIT study of
the automobile industry, which explained lean production for the first time. No
Value Added programs can be formal or whimsical. Generally, they involved
seeking input and opinion from every level of the organization about rules,
45
processes or process elements which are said to be no value added. In one form,
the proponent of an activity accused of being NVA must defend it, or suspend it.
In a milder form, the proponent (or process owner) of an activity accused of being
NVA is simply informed that it is seen in that light. Oddly, this milder form is
often effective because in a large organization, the original reason for an activity
can be long forgotten, similar to cabooses which came into use in the 1830s, but
eventually had no useful purpose and became NVA. Some claim that this NVA is
a jibe at Net Value Added accounting methods, which were held in low esteem by
some Lean advocates, and high esteem by others.
Non Value Added activities in a process includes any step that;
i.
ii.
iii.
iv.
v.
and inventory or
vi.
46
Most manufactures try to eliminate all unnecessary production costs and wasted
time. This makes their production time leaner and also makes customers happier.
Companies can provide price if they run production operations smoothly and
efficiency. One way managers measures the efficiency of the production time is
by looking at the time.
5. VALUE ANALYSIS
STEP 7: MONITORING THE RESULTS
STEP 8: CONCLUSION
CHAPTER 4
CONCLUSION
47
REFERENCE
Research Scholar,
48
49