Professional Documents
Culture Documents
CONTENTS
CONTENTS.................................................................................................................1
LIST OF TABLE..........................................................................................................3
LIST OF FIGURE........................................................................................................3
CHAPTER 1
INTRODUCTION........................................................................................................4
1.1
Introduction........................................................................................................4
1.2
Problem Statement.............................................................................................5
1.3
Objective............................................................................................................6
1.4
Project Scope.....................................................................................................7
1.5
Report Outlines..................................................................................................7
CHAPTER 2
LITERATURE REVIEW..............................................................................................8
2.1
Introduction........................................................................................................8
2.4
Hydro-thermal generation................................................................................10
2.4.1
2.4.2
2.5
2.5.1
2.5.2
2.5.3
2.6
Summary..........................................................................................................14
CHAPTER 3
METHODOLOGY.....................................................................................................15
3.1
Introduction......................................................................................................15
3.2
Problem Formulation.......................................................................................17
3.2.1
3.2.2
3.3
Objective Function...........................................................................................18
3.3.1
System Constraints.......................................................................................20
3.3.2
Transmission Losses....................................................................................21
3.4
3.4.1
3.5
CHAPTER 4
RESULT AND ANALYSIS........................................................................................30
4.1
Introduction..................................................................................................30
4.2
4.3
4.4
Summary......................................................................................................34
CHAPTER 5
CONCLUSION...........................................................................................................35
5.1
Conclusion...................................................................................................35
REFERENCES...........................................................................................................36
LIST OF TABLE
DETAILS
PAGES
31
32
33
33
LIST OF FIGURE
DETAILS
PAGES
16
24
25
32
32
CHAPTER 1
INTRODUCTION
1.1 Introduction.
Economic Load Dispatch (ELD) is the main function in power consumption system
for application of optimum power generation. The main objective of ELD is to
minimize cost in power generation and at the same time its need to meet the power
demand of system and operational constraint. Hence, solve an economic dispatch
problem properly and efficiently [1]. In practical power systems, minimizing the total
operation costs is very important. Thus, the ELD technique is applied for allocating
power generation among the committed units so that the total generation cost of the
system is minimized and satisfying all the constraints. [2][3]. It is a method to
schedule power generator outputs with respect to the load demands and to operate a
power system economically, so as to minimize the operation cost of the power
system [4].
Nowadays, have a various power generation system to generate electricity
such as hydroelectric, wind generation, solar generation, fossil fuel power plant and
etc. Most of generation in power system has substantial advantages in generation
stability, easier for generation planning and no limits on locations but their produces
much problem of economic cost [3]. Moreover, this research is targeted of hydro and
thermal power generation system while considering the short-term and long-term
scheduling problem.
The electric power systems mostly produced from conventional nonrenewable energy source that contains both thermal and hydro plants. The
combinations of hydro and thermal generation plant aimed to meet the total power
demand depend on power consumption, hence it similarly focusing on minimize the
total cost. [5]. To minimize that cost especially in optimization problem, it must be
control and operate that function as well as possible to stabilize the power
consumption [6].
Artificial Bee Colony (ABC) algorithm is stochastic finding that defined by
Dervis Karaboga in 2005 that imitate the behavior of bee colony where it consists of
three categories which are employed bees, onlooker bees and scout bees. The number
of employed bees is equal to them number of food sources around the hive. The first
half of the colony consists of the employed artificial bees and the second half
includes the onlookers. For every food source, there is only one employed bee. In
other words, the number of employed bees is equal to the number of food sources
around the hive. The employed bee whose food source has been exhausted by the
bees becomes a scout [7][8]. .The employed bee whose food source has been
abandoned becomes a scout. In ABC algorithm the position of food source
determines the solution and the amount of nectar represents the fitness of the
respective solution [9][10].
1.2
Problem Statement
Economic Load Dispatch (ELD) is one of the important issues need to concern in
planning and operational the power system especially related with hydro and all
thermal generation.
ELD in the power system is coordinate the total of power and energy that
used for reduce economical cost. On electrical power generation is necessary the
highest cost of installation, fuel cost, workers, resources and maintenance [1]. Hence,
the problem occurs due to load dispatch that unstable electrical energy in term of
load power system and operational constraints. Optimal load dispatch gave more
advantage in many aspect especially on efficiency and linearity of energy produced
[6], in that case, it can reduces more cost and increase the energy saving consumption
while avoiding the causes of irregular energy production.
In the generation system has a several problem especially the optimal cost
and to meet the total load demand, the problem are considering the hydro-thermal
generating unit. To determine the optimal generation level for each thermal and
hydro plant to meet the total load demand over a scheduling period. This is to
determine, optimally, which of the thermal generating units should run and how
much power is generated by the hydro and thermal plants so as the total operating
cost are minimized. The total cost to be minimized is subject to various control and
operational constraints.
On this project, the method of Artificial Bee Colony (ABC) algorithm is used
for solve the ELD problem of hydro and thermal generation. ABC algorithm is
stochastic finding that defined by Dervis Karaboga in 2005 that imitate the behavior
of bee colony where it consists of three categories which are employed bees,
onlooker bees and scout bees [10]. ABC algorithm is one of the meta-heuristic that
used for solve the problem of function multi-objective and non-linear problem.
1.3
Objective.
The major objective of this research is to investigate the best method for ELD of
hydro and thermal generation. Its measurable objectives are as follows:
1. To formulate the problem of hydro and thermal generation for ELD by using
Artificial Bee Colony (ABC) algorithm.
2. To investigate the performance of ABC algorithm for solving ELD problem
of Hydro-Thermal Generation.
3. To compare ABC algorithm with existing result of others algorithm in term of
optimal cost and quality performance.
1.4
Project Scope.
This project is primarily concerned with the ELD problem that occurs on hydro and
thermal generation. Scopes of this project are:
1. Several references of literature review from IEEE journal, articles and
reference books.
2. Application of ABC algorithm to solve the ELD problem of hydro-thermal
generation by using MATLAB software.
3. Investigate the performance of ABC algorithm based on optimal cost in term
of solution quality and statistical result.
1.5
Report Outlines
Chapter 2 presents the ELD and ABC algorithm. The different methods of constraint
handling such as repairing infeasible solution method and penalty function are also in
this chapter.
Chapter 3 discusses the details methodology used in this project. The general
ELD formulation and development of ABC algorithm for solving ELD problem are
explained. It also explains the constraint handling method for ELD problem.
Chapter 4 presents the result and analysis of this research. The result are
obtained by comparing the two constraint handling method in such as the optimal
result, convergence characteristic, robustness and comparison with existing method.
Chapter 5 concludes the objectives of this project where the objectives of this
project are achieved. A recommendation is written in order to improve the upcoming
research.
CHAPTER 2
LITERATURE REVIEW
2.1 Introduction
In this chapter will be discussed about the literature review of Economic Load
Dispatch (ELD) problem and the several method that were used to solve it problem.
The various methods have been to generate an energy which are hydro, wind, solar
and fuel power plant. Increasing of power demand will produces high cost of
operation and planning. The operation cost of power system has becomes an
important issues due to increase power demand and fuel cost. One of the options is to
operate the committed generator units efficiently and economically based by
performing Economic Load Dispatch (ELD) optimization [3][4].
In this research is to commit the generation of hydro unit and all thermal units
with optimal schedule for supply with require load demand in minimum cost while
satisfying all system constraint. Additionally, have more previous optimization
method that are used to solved ELD problem which is Genetic Algorithm (GA),
Particle Swarm Optimization (PSO), Firefly Algorithm (FA), Differential Evolution
(DE), Evolution Programming (EP) and Artificial Bee Colony (ABC) algorithm.
10
Hydro-thermal generation
2.4.1
The scheduling period of the short-term hydro-thermal problem can range from 1 day
to 1 week [5] [14]. The solution to the short-term problem is to determine the hourby-hour scheduling of all available generation in order to obtain the optimal
economic production cost over the scheduling period.
The short-term hydro-thermal scheduling (STHTS) optimization problem is
treated considering the optimal allocation of available hydro and thermal electrical
energy for the duration of a scheduling period of time [5]. The objective of hydrothermal scheduling is to determine the generation level for each committed hydro
and thermal unit in such a way that the total operating cost is minimized while
satisfying various operational constraints [15].
The short-term problem can be categorized into two main groups which are
the fixed-head and variable-head. The first group is associated with plants with large
capacity reservoirs while variable-head reservoirs have limited amounts of water.
The short-term hydro-thermal scheduling problem is discussed extensively in the rest
of this chapter as it is the main focus of this thesis [16].
11
2.4.2
Optimization method has been employed to solve different ELD problems. There two
types of optimization method which are the traditional method and the meta-heuristic
method. Traditional numerical model methods are applicable if the function between
operating cost and fuel or heat are piecewise linear and increasing categorically [18].
In order to overcome this issue, the meta-heuristic approaches based on tabu
search, Hopfield, hill climbing, evolutionary computation, swarm intelligence, and
ant/bee colony optimizations can outperform [18]. Meta-heuristic method such as
Particle Swarm Optimization (PSO), Genetic Algorithm (GA), Bacterial Foraging
Optimization (BFO) and Artificial Bee Colony (ABC) algorithm are promising and
still evolving in this field. Some of those techniques have been modified to enhance
their solution performance or to overcome other limitations.
2.4.3
12
the behaviour emergent from socially organized populations known as swarms. The
particles change their positions by flying around in a multi-dimensional search space
until a relatively unchanged position has been encountered, or until computational
limitations are exceeded [13].
Saumendra Sarangi [20] used the PSO for solve the ELD problem to find out
the advantages of application of the evolutionary computing technique and PSO in
particular to the economic load dispatch problem also to find out the minimum cost.
The effectiveness of PSO has tested by using the data of 3 and 6 generating units.
The results are compared with the traditional technique and GA, PSO seems to give a
better result with better convergence characteristic.
2.4.4
13
2.4.5
Artificial Bee Colony (ABC) is one of the most recently define algorithm by Dervis
Karaboga in 2005 [10] [21]. It is a swarm based a stochastic search algorithm which
imitates the scrounging behaviour of honeybees. In ABC, the colony of artificial bees
consists of three groups of bees which are employed bees, onlookers and scouts. In
other words, the number of employed bees is equal to the number of food sources
around the hive. The employed bee whose food source has been abandoned becomes
a scout [22]. In ABC algorithm the position of food source determines the solution
and the amount of nectar represents the fitness of the respective solution.
Jianzhong Zhou, Xiang Liao, Shuo Ouyang, Rui Zhang, Yongchuan Zhang
[23] have been proposed the Multi-objective artificial bee colony algorithm for shortterm scheduling of hydrothermal system. The goal of multi-objective short-term
hydrothermal scheduling (MOSHS) is to minimize the both fuel cost and exhaust gas
emission of hydrothermal system by determining the water releases of hydropower
unit in each scheduling interval while satisfying the various complex constraints
including power balance, generation limits, storage and discharge limits and
hydraulic network balance. In order to solve the problem, the consideration of
interconnected system which including four cascaded hydropower units and three
thermal units has been used to verify the effectiveness of the proposed MOABC
method. The simulation results show that the proposed MOABC can obtain better
schedule results with less fuel cost and environment pollution, more close to the true
Pareto front and better diversification of non-dominated solutions compared to other
existing methods [23].
14
1.5 Summary
As a summary for this chapter, there are two generating unit that needs to considered
in term of short-term or long-term scheduling which are hydro and thermal
generation unit. Additionally, the meta-heuristics method also to consider for solves
the ELD problem. Have two major objectives must be considered to achieve the
optimal minimization cost and committed the total load demand. Several method are
reported in literature related with solving ELD which are Particle Swarm
Optimization (PSO), Genetic Algorithm (GA), Firefly Algorithm (FA) and Artificial
Bee Colony (ABC) algorithm that method for optimization ELD. To finish the
research, the existing methods that discussed are follows as a references for
investigate the optimization ELD problem.
15
CHAPTER 3
METHODOLOGY
Introduction
This chapter discusses the methodology used in this study. The first section describes
the steps involve, follows by ELD problem formulation and then PSO. The fourth
and fifth part describes constraints handling in ELD. This methodology plays an
important role in implementing this research study accordingly. The details of the
methodology are explained in detail in this chapter. The MATLAB software is used
to simulate the ELD problem.
In the methodology, collecting information about a topic related to the project
is done. The theory of the projects studied in any listing formulas do. Moreover, the
method used for this final year project also is described in the methodology. Finally,
the results of which comparing constraint handlings are expected to be highlight and
explained.
16
The research of this project is focusing based on the flowchart in Figure 3.1.
Problem Formulation of
ELD
Comparison the performance of ABC with other method to achieve the best solution of ELD in term
Conclusion
17
Problem formulation related with objective function where it needs to considered the
ELD of hydro and thermal generating unit based on several constraints which are
Long-term and Short-term hydro thermal scheduling. There are several things to be
considered on problem formulation which are economic load dispatch (ELD), Shortterm hydro thermal scheduling (STHTS) with considered losses and losses neglected.
Hence, the objectives function of the constraints in term of Load Balance and
Thermal and Hydro generating capacity limits.
3.4.1
Economic Load dispatch (ELD) is generation allocation problem and defined as the
process of calculating the generation of the generating units so that the system load is
supplied entirely and most economically subject to the satisfaction of the constraints
[24]. The objective of solving ELD problem is minimizing the generation cost rate
and to meet the load demand of a power system over some appropriate period while
satisfying various generators constraints.
Minimize
F T = F i( P i )
i=1
where:
FT
Ng
respectively
= The number of committed generators.
(3.1)
18
The formulation expressed above is for the basic model of the conventional
ELD problem. It should be noted that the results of the ELD solution of an allthermal system can be applied to a hydro-thermal system by considering an
equivalent thermal characteristics.
3.4.2
MH
Ng
thermal generating
to determine the active power generation level of each of the hydro and thermal
plants over the scheduling period T.
19
T
FT = F i ( P gi ( t ) ) dt
0 i=0
(3.2)
where:
Pgi ( t )
of the
i TH
Fi ( P gi ( t ) ) =a i Pgi ( t ) +b i P gi ( t )+ c i
(3.3)
where,
ai , bi
and
ci
b) Hydro Model
As mentioned above, there is no fuel cost associated with the hydro power
generation. The input-output characteristics of a hydro-electric generating unit is
formulated as a water discharge rate in terms of its reservoirs effective water head
and the output active power as defined by the Glimn-Kirchmayer model [17][5].
q j (t )=K(h j ) ( P Hj ( t ) )
where,
(3.4)
20
q j (t )
= Independent functions
= Constant of proportionality.
The short-term hydro thermal scheduling consists of 2 types which are fixedhead reservoir and variable-head reservoir. For the variable-head reservoir, the
variable of
(h j )
(h j )
q j (t )=K ( P Hj ( t ) )
(3.5)
For the scheduling period, the amount of water available for each hydro plant is
limited by a pre-specified quantity
Vj
q j ( t ) dt=V j
(3.6)
where,
q j (t ) = Water discharge rate for the reservoir j at time t
Vj
q jk
q jk = j P 2Hj + j PHj + j
k
where,
q jk
(3.7)
21
th
hydro plant
j
PHj
3.4.3
System Constraints.
Load balance equation: The total power generation must meet the total load
demand over the scheduling period
MH
P gi ( t )+ P Hj ( t ) P D ( t )P L (t)
i=1
ii.
j=1
(3.7)
Thermal and hydro generation capacity limits: The maximum and minimum
power of the thermal and hydro generating plants are expressed as the
following inequality boundary constraints:
Pgi (t)min P gi(t ) Pgi (t)max
(3.8)
(3.9)
where,
min
Pgi
22
min
PHj
3.4.4
Transmission Losses
PL
generation. The function of loss formula and its simplest form is known as Georges
formula [6]:
Ng
Ng
PL = . P gi B ij P j
i=1
The parameters
B ij
(3.10)
j=1
obtain a more accurate loss formula, a linear term and a constant is added to the
expression of (3.9) to form what is referred to as Krons loss formula [25]:
Ng
Ng
Ng
PL = . P gi B ij P j + Bi 0 P gi B00
i=1
j=1
i=1
(3.11)
PL =[ P g 1+ P g 2+ P gNg ]
][ ]
B11 B12
B1 Ng Pg 1
B21 B22
B2 Ng Pg 2
23
+ [ Pg 1 P g 2 P gNg ]
[]
B01
B02
+ B00
B0 Ng
(3.12)
The B-coefficients mainly depend on the operating condition of the system. They are
usually assumed to be constant parameters, unless the system operating state of a
new generation scheduling is significantly different from the base case.
The loss formulas defined by Equations (3.9), (3.10) and (3.11) are applied to
model the transmission network losses. Accordingly, the Krons B-coefficients loss
formula is expressed as follows:
N g+ M H
PL (t)=
N g+ M H
i=1
j=1
Ng
(3.13)
where,
Pi ( t ) = Power generation of thermal plant
P j ( t ) = Power generation of hydro plant
B ij
Artificial bee colony (ABC) algorithm was first proposed by Karaboga [39] to solve
single objective optimization problems. Similar to other intelligent swarm
optimization technique, it imitates the foraging behaviour of honey bees.
Additionally, ABC use the three operators to search the optimal solution in feasible
region which named employed bees phase, onlooker bees phase and scout bee phase.
In this paper ABC algorithm inspired by foraging behaviour of honey bees
proposed to solve economic load dispatch problems is presented and the
effectiveness of proposed algorithm to hydro and thermal generation units having
cost function consists of transmission losses either considered or neglected. In ABC
24
algorithm the position of food source determines the solution and the amount of
nectar represents the fitness of the respective solution.
In ABC algorithm, the colony of artificial bees contains three groups of bees:
employed bees, onlookers and scouts [10]. First half of the colony consists of the
employed artificial bees and the second half includes the onlookers. For every food
source, there is only one employed bee. In other words, the number of employed bees
is equal to the number of food sources. The employed bee of an abandoned food
source becomes a scout. The search carried out by the artificial bees can be
summarized as follows:
i.
Employed bees determine a food source within the neighbourhood of the food
ii.
iii.
iv.
chosen by themselves.
An employed bee of which the source has been abandoned becomes a scout
and starts to search a new food source randomly.
25
Selection
Figure 3.2: Behaviour of honeybee foraging for nectar.
(i)
It can be a scout and starts searching around the nest spontaneously for a
No
foodchosen
due to some
motivation
oremployed
possible external
clue (S).
All
onlookers
distributed?
Determine neighbours of the
foodinternal
sources
by the
bees
(ii)
It can be a recruit after watching the waggle dances and starts searching
for a food source (R).
Yes
After finding the food source, the bee utilizes its own capability to memorize
Memorize
position
of best
food source
the location and then immediately starts
exploitingthe
it. Hence,
the bee
will become
an
No
employed forager. The foraging bee takes a load of nectar from the source and
returns to the hive, unloading the nectarFind
to a the
foodabandoned
store. Basically,
order to
foodinsources
understand the principle of ABC algorithm, the flowchart in Figure 3.3 as follows:
Produce new positions for the abandoned food sources
Yes
Final food positions
26
3.4.5
Step1:
Step in Algorithm
27
(3.14)
where,
max
Xj
Step 2:
Number of food source sites is equal to the number of employed bees. An employed
bee produces a modification on the position of the food source (solution) in her
memory depending on local information (visual information) and finds a
neighbouring food source, and then evaluates its quality.
V ij =X kj + ij (X ij X kj )
(3.15)
where,
k
= {1, 2 D}
Step 3:
If a parameter value produced by this operation exceeds its predetermined
boundaries, the parameter can be set to an acceptable value. In this work, the value of
the parameter exceeding its boundary is set to its boundaries. If
max
X i= X i
Step 4:
and if
min
Xi<X i
then
min
X i= X i
max
Xi>X i
then
28
After producing
Vi
Vi
(3.16)
where,
fi
Step 5:
After the source is evaluated, greedy selection is applied and the onlooker bee either
memorizes the new position by forgetting the old one or keeps the old one.
Step 6:
Allow the employed bees to share the food information with onlooker bees. For
maximization problems, the cost function can be directly used as a fitness function. A
greedy selection is applied between
X ij
and
V ij
depending on fitness values representing the nectar amount of the food sources at
X ij
and
V ij
. If
X ij
29
P i=
f i ti
N
f i tn
(3.17)
n=1
where,
f i t i = Fitness value of the solution i which is proportional to the nectar amount of
the food source in the position i.
N = Number of food sources which is equal to the number of employed bees.
Step 9:
In ABC, Providing that a position cannot be improved further through a
predetermined number of cycles, then that food source is assumed to be abandoned.
The value of predetermined number of cycles is an important control parameter of
the ABC algorithm, which is called limit for abandonment. The food source
abandoned by its bee is replaced with a new food source discovered by the scout,
which represents the negative feedback mechanism and fluctuation property in the
self-organization of ABC.
Step 10:
.Abandonment criteria: Limit and scout production. Assume that the abandoned
source is
with
X ij
X ij
. Check for an abundant solution, and (if exists) initiate a new food-
30
1.9 Summary
In this project of solving the Economic Load Dispatch problem of hydro and thermal
generation is focusing on the Short Term Hydro Thermal Scheduling with
transmission losses consideration and transmission losses neglected by using
Artificial Bee Colony (ABC) Algorithm. This algorithm used as the constraint
formulation in order to solve the ELD problem. Hence, it compared the ABC
algorithm with existing result of others algorithm in term of optimal cost and quality
performance.
31
CHAPTER 4
4.1 Introduction
Economic Load Dispatch (ELD) is to determine the generation level for committed
hydro and thermal unit in such way that the total operating cost is minimized while
satisfying various operation constraints. In this project, ABC algorithm is use for
solving ELD problem that consists of two case studies. Case study 1 is investigating
the performance of ABC by using test system of 6 generating unit. For the case study
2 will be continue for hydro-thermal generating unit and applied the ABC to solve
ELD problem.
32
ai
bi
Parameter
ci
units i
$ / MW 2 h
$ / MW h
$ /h
MW
MW
1
2
3
4
5
6
0.1525
0.106
0.02083
0.0356
0.0211
0.0179
38.54
46.20
40.159
38.31
36.33
38.27
756.80
451.40
1049.99
1234.50
1658.60
1356.70
10
10
35
35
130
125
125
150
225
210
325
315
Pmin
gi
Pmax
gi
The losses are considered in this system by using the loss formulation in equation
(3.12). The B-loss coefficients are as follows:
B=104
1.40
0.17
0.15
0.19
0.36
0.22
0.17
0.60
0.13
0.16
0.15
0.20
0.15
0.13
0.65
0.17
0.34
0.19
0.19
0.16
0.17
0.71
0.30
0.25
0.26
0.15
0.24
0.30
0.60
0.32
0.22
0.20
0.19
0.60
0.32
0.85
Pg1
(MW)
157.480
3
Pg2
(MW)
119.4241
Pg3
(MW)
405.274
Pg4
(MW)
242,468
Pg5
(MW)
155.415
Pg6
(MW)
135.041
The result obtained shows the performance of ABC to minimize cost and power
losses. The system was tested for 5 times randomly and the result of operational cost
shows:
Ploss (PW)
Cost ($/h)
= 623.7277 PW
= 67,145 $/h
33
The performance of the ABC algorithm to solve ELD problem of 6 generating units
shows with the graph in Figure 4.1. The graph indicates the convergence of best cost
optimization of 6-generating units
Cost optimization ($/h)
FT
FH
FH
P1
P2
P3
PD
34
The optimal generations obtained based on the data in tables 4.3 and table 4.4 with
considered the power demand used for analysis.
Table 4.3: Data System of Five Generating Unit
Hour
1
2
3
4
5
6
PD (MW)
30
33
35
38
40
45
Hour
7
8
9
10
11
12
PD (MW)
50
59
61
58
56
57
Hour
13
14
15
16
17
18
PD (MW)
60
61
65
68
71
62
Hour
19
20
21
22
23
24
PD (MW)
55
50
43
33
31
30
(4.1)
The discharge rates of two reservoirs in term of hydro power produced by the two
plants are as follow:
Hydro
Volume of water (
Discharge rates ( M . f / h
M.f
Plant 1
573.916
Plant 2
803.488
B=10
[]
0.0
B 0= 0.0
0.0
B 00=0.0
(4.2)
35
4.4 Summary
This chapter as a pre result of this project, by focussing on economic load dispatch
problem of hydro and thermal generation system and to applied the ABC algorithm
to solve them. To overcome the objective, ABC will be applied to solve ELD
problem of hydro and thermal generation system with several constraints.
36
CHAPTER 5
CONCLUSION
5.1 Conclusion
In this project, ABC algorithm is used for solving Economic Load Dispatch (ELD)
problem of hydro and thermal generating unit. There have a system of 6 generating
unit to investigate the performance of ABC algorithm to solve ELD problem. On this
PSM 1, the project is more focussing on Study Case 1 that is an investigate the
performance of ABC algorithm for solving ELD problem of Thermal Generation unit
which means the performance was shows in graph and the result data. For the PSM
2, it will be continue the research based on case study 2 of ELD problem for hydro
and thermal generation unit to achieve the project objective.
5.2 Recommendation
This project supposedly to solve Economic Load Dispatch (ELD) problem of hydro
and thermal generation by using ABC algorithm, in order to achieve this project, the
research of hydro thermal generating units via ABC needs to compares with more
other algorithm to ensure it the best result.
37
REFERENCES
[1]
[2]
[3]
[4]
[5]
I. A. Farhat and M. E. El-Hawary, Multi-Objective Short-Term HydroThermal Scheduling using Bacterial Foraging Algorithm, in Electrical Power
and Energy Conference (EPEC), 2011 IEEE, 2011, pp. 176181.
[6]
[7]
38
[8]
[9]
[10]
[11]
[12]
[13]
[14]
[15]
[16]
[17]
[18]
[19]
39
[21]
D. C. Secui, A new modified artificial bee colony algorithm for the economic
dispatch problem, Energy Convers. Manag., vol. 89, pp. 4362, 2015.
[22]
[23]
[24]
[25]
[26]
[27]