You are on page 1of 256

DOWLHC9 PROJECT

PROJECT NO.:

LHC9

P.O. NO.:

GUST50LHCK067

EQUIPMENT TAG NO.(S):

N/A

EQUIPMENT SERVICE TITLE:

N/A

SUPPLIERS NAME:

ICA FLUOR /IH

SUPPLIERS DOCUMENT TITLE.:

Module Fabrication Quality Manual

Revision:

SUPPLIERS DOCUMENT NO.:

SA5DOW01

Date:

AUGUST/2014

A - PROCEED
Authorization to proceed does not relieve Contractor/Supplier of its responsibility
or liability under the Contract and or Purchase Order.

By: Mark Gasper,GAS21753,9/30/2014

S~

~ D E

-U

9 P R O J

D E S C R IP T IO N

01

F luor Q uality M anager


DOW QA

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-00

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

TABLE OF CONTENTS

Tab

Administrative
Procedure No.

SA5-DOW-01-00

Title

Reference
Procedure
Date

Site
Revision

Number

Policy Statement

08/14

01

SA5-DOW-01-01

Foreword

08/14

01

SA5-DOW-01-02

Manual Maintenance and Revision

08/14

01

SA5-DOW-01-03

Organization and Responsibilities

08/14

01

SA5-DOW-01-04

Document Control

08/14

01

SA5-DOW-01-05

Process Control

08/14

01

SA5-DOW-01-06

Monitoring and Measuring Devices

08/14

01

SA5-DOW-01-07

Control of Nonconformances

08/14

01

SA5-DOW-01-08

Corrective Action & Preventive Action

08/14

01

10

SA5-DOW-01-09

Quality Records

08/14

01

11

SA5-DOW-01-10

Quality Audits

08/14

01

12

SA5-DOW-01-11

Personnel Training and Qualification

08/14

01

13

SA5-DOW-01-12

Site Subcontractor Qualification

08/14

01

14

SA5-DOW-01-13

Contractor Quality Requirements

08/14

01

15

SA5-DOW-01-14

Surveillance of Construction Activities

08/14

01

16

SA5-DOW-01-15

Field Receiving & Inspection

08/14

01

17

SA5-DOW-01-16

Turnover

08/14

01

18

SA5-DOW-01-17

Material & Equipment Storage & Maint.

08/14

01

19

SA5-DOW-01-20

Inspection and Testing

08/14

01

20

SA5-DOW-01-21

Structural Steel

08/14

01

21

SA5-DOW-01-23

Piping

08/14

01

22

SA5-DOW-01-24

Pressure Testing

08/14

01

23

SA5-DOW-01-25

Cleaning of Pipe

08/14

01

24

SA5-DOW-01-27

Electrical Inspection

08/14

01

25

SA5-DOW-01-30

Control Systems Instrumentation

08/14

01

26

SA5-DOW-01-32

Coatings

08/14

27

SA5-DOW-01-33

Insulation

08/14

01

28

SA5-DOW-01-34

Fireproofing Inspection

08/14

01

29

SA5-DOW-01-35

Welding Inspection

08/14

01

30

SA5-DOW-01-36

Nondestructive Examination

08/14

01

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-00

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Inspection &
Test
Procedure No.

Title

Reference
Procedure
Date

Site
Revision

Number

31

SA5-DOW-01-37

Positive Material Identification

08/14

01

32

SA5-DOW-01-38

Hardness Testing

08/14

01

The Industria del Hierro Module Fabrication Quality Program for the Gulfstream Light Hydrocarbon

Unit 9 (LHC9) Project is described and documented in this Module Fabrication Quality Manual.

Approved By

August,
2014

Comments of Client

Mario Gutierrez

June, 2014

for Construction

Mario Gutierrez

Date

Rev

Revision Description

Prepared By

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Approved

Approved

Fluor Quality Dept.

Client Quality Dept

Module Fabrication Quality Manual

M odule F abrication

IN D U S TR IA D E L

SA5DOW~01

2 0 1 4 - R ev.01

1 o f 1

G ulfstream
U nit9 ""r"'''"""T

P urchase O rder N o. G U S T ~ 5 0 ~ L H C - K 0 6 7

S A D E C .V .

STATEM ENT

as rlo r.o rm
and federal regulations and

projects and
com ply w ith all

plans and specifications, applicable

gnat re/ ate

aria G u tierrez R am irez, P ro ject


M an ag er

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Module Fabrication Quality Manual SA5-DOW-01-01

August, 2014 Rev.01

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

FOREWORD

The objective of the Module Fabrication Quality Program for The DOW Chemical Company Gulfstream

Light Hydrocarbon Unit 9 (LHC9) Project, is to ensure that Module Fabrication construction is

performed in accordance with the drawings, specifications, applicable local, state and federal

standards and Codes. A further objective is to provide documented evidence that confirms that the

primary objective has been met. The Module Fabrication Quality Control program as delineated in this

manual is tailored to meet the quality surveillance, inspection, testing, and documentation

requirements for construction/installation performed by subcontractors and Industria del Hierro selfperform construction.

The QA/QC Manager will coordinate the construction quality surveillance, inspection, testing, and

documentation activities. He will monitor construction and quality activities to the extent necessary to

provide construction management with adequate confidence that appropriate measures are being

taken to control and achieve quality. The quality activity will emphasize preventing nonconformance

to drawings and specifications but detecting and correcting it should it occur.

When construction or any element of construction is subcontracted, the quality control responsibilities

governing the subcontractor's work are usually delegated to the subcontractor.


The overall
responsibility for verifying quality in construction remains with Industria del Hierro. This is done by

surveillance and audits when the responsibility for quality activities has been delegated to the

subcontractor. The subcontractors are to provide the measures required to achieve the contract

quality requirements. The subcontractor's quality control responsibility is established by procedure

SA5-DOW-01-13 and is stated in their contract.

When Industria del Hierro performs construction activities using our own labor force, the quality

control responsibility remains with Industria del Hierro.


Industria del Hierro supervision and

construction engineering staffs are primarily responsible for the attainment of the quality

requirements established by the drawings, specifications and contract. The supervisory, construction

engineering and quality staffs will perform quality control inspection, testing, surveillance and

documentation activities as outlined in this manual. The primary responsibility for performing quality

workmanship rests with those actually performing the work under the supervision of Industria del

Hierro.

This Module Fabrication Quality Manual is the governing document for the Industria del Hierro quality

system and will be maintained current to achieve project quality objectives.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-02

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev-01

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

MANUAL PREPARATION AND MAINTENANCE

SCOPE

This procedure provides guidance for converting Fluor Corporate Site Quality procedures from Knowledge Online
or share drive to a Module Fabrication Quality Manual for a specific project. It is applicable to Construction

projects.

GENERAL

The Module Fabrication Quality Manual has been prepared to meet the requirements of International Standard

ISO-9001:2000. The bracket symbols ([::---::]) seen throughout these procedures identify changes or additions

that are to be made in converting them to project specific procedures. Other changes are to be made as needed

to be compatible with the project requirements and scope.

Upon assignment of the QA/QC Manager, he begins development of the draft Module Fabrication Quality Manual

(MFQM) to assure conformance to the site-specific requirements. The completed and approved project specific

MFQM should be in place for usage as soon after contract award as possible. As a minimum, parts of the manual

should be developed for control of construction activities before the activities are performed. These activities

usually begin with qualifying and issuing RFQ's to bidders for work to be subcontracted (see SA5-DOW-01-14 and

SA5-DOW-01-13).

Development of Module Fabrication Quality Manual


Each section/procedure identified by SA5-DOW-01-00 is reviewed for consistency and applicability with project

scope. Changes or additions will be required of the following sections as noted:

Inspection and Test Procedures (20 - 40); select the procedures that are applicable to the contracted

work scope. Select the applicable forms from the procedures if all are not needed. Review the

"Responsibilities" Section and modify, if needed, to suit the project organization. Also, the "SelfPerform" or "Subcontracted" Section may be deleted, if not applicable.

Table of Contents/Revision/Date Page (00); Under "Procedure Number" and "Title" change to include

only those procedures used in the project manual.


Under "Revision Date." enter the date, month and year for all initially approved procedures. Enter

appropriate dates for each project revision it undergoes after initial project approval.

Revision dates for all pages of all procedures in the project specific manual should match the

dates in this Table of Contents.

Revisions to the Module Fabrication Quality Manual shall not waive or negate Contract

requirements or mandatory construction codes.

Revision of Module Fabrication Manual


The QA/QC Manager controls the site issue and revision of the Module Fabrication Quality Manual. The manual is

to be revised by procedure. A vertical line in the margin shall identify the revised portions. The revision status

shall be shown on the Title page of the manual. The Table of Contents shall show the revision date of each

revised procedure and shall be reissued for each revision.

The QA/QC Manager and Project Manager should approve each revision by signing the Revision/Approval Page.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The Dow Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-03

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

ORGANIZATION AND RESPONSIBILITIES

This section describes the quality organization for performing activities described by this manual. It

also provides a general description of responsibilities. Specific responsibilities are described in the

individual procedures of this manual.

The Project Manager is responsible for the execution of the project Module Fabrication activities which

includes construction quality. The delegation of authority to the QA/QC Manager for the direction and

coordination of quality activities is made with the objective of maintaining the effectiveness of this

quality program.
The Project Manager shall provide adequate resources and assign sufficient trained personnel to

manage the work and effectively carry out these verification activities, including internal quality audits.

The personnel assigned to these verification activities shall be independent of those having direct

responsibility for the work being performed.

ORGANIZATION
The project organization for Module Fabrication quality personnel are shown on the Module Fabrication

Organizational Chart maintained by the Project Manager.


RESPONSIBILITIES
Quality related activities are conducted by Module Fabrication Quality and other groups. The activities

and persons conducting them will be under the functional control of the QA/QC Manager for the

execution of the activity. Attachment 1- Quality Responsibility Matrix summarizes the activities and the

persons responsible for execution. Primary responsibility for execution and verification of quality-related

activities will be established on the Inspection/Test Plan or procedures.

QA/QC Manager
The QA/QC Manager has the responsibility, authority, and organizational freedom to audit, inspect and

witness construction activities and to verify compliance to contract quality requirements.


This

responsibility includes actions such as assist the construction staff in prevention of quality problems,

identification of quality-related problems should they occur, initiation or recommendation of solutions

and verification of corrective action. In addition, he is responsible for coordination of quality-related

activities within the Construction staff and with the site Client quality representatives. He maintains the

construction quality control procedures and provides technical assistance and training to construction

supervision. He will have an active role in assisting with the prevention of quality problems.

The QA/QC Manager reports directly to the Project Manager.

The Construction staff includes a Construction Engineering to ensure prompt engineering interpretations

and decisions, review of drawings, certificates and other data to be submitted to the Client, and to

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The Dow Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Module Fabrication Quality Manual, SA5-DOW-01-03

August, 2014 Rev.01

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

actively participate in the surveillance of field construction, and to verify compliance to design/engineer

requirements. Construction Engineering will provide assistance to the QA/QC Manager as necessary to

assist in achieving quality objectives.

Under certain conditions, other site groups may execute quality-related activities. In these cases the

activities and persons conducting them will be under the direct control of the QA/QC Manager. Primary

responsibility for execution and verification of quality-related activities will be established on the

Inspection/Test Plan.

Subcontractors
The subcontractor quality organization will be in accordance with the contract requirements and

described in their approved equivalent Module Fabrication Quality Manual.


ATTACHMENTS

Attachments 1 -

Quality Responsibility Matrix

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

Module Fabrication Quality Manual, SA5-DOW-01-03

The Dow Chemical Company

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 1

Page 1 of 6

INDUSTRIA DEL HIERRO S.A. DE C.V.

Quality Responsibility Matrix


Section 1 - STRUCTURAL STEEL

1.1 - Structural Steel

RESPONSIBILITY

ACTIVITY

Construction

QA/QC

Monitor in process steel erection to verify fabrication is correct and erection is in accordance with

drawings. Document fabrication errors on a NCR.

Witness bolting procedure including calibration of torque wrenches and load indicating washers.

Maintain documentation

Inspect the erected steel structure.

Ensure that erected steel structures have coatings installed i.a.w. drawings

Monitor the Contractor's quality activities to verify conformance to requirements for bolt tensioning

procedures.
Schedule final acceptance inspection activities between Contractor and Field Engineering or

construction.

Audit the structural steel documentation to verify correctness of data.

Section 2 - PIPING

2.1 - Shop Fabrication

RESPONSIBILITY

ACTIVITY

Construction

Segregate and store pipe fittings, upon receipt, according to size and material. Identify storage

location with commodity code number.

QA/QC

MM

Pipe will be marked full length with commodity code number.

MM

Maintain documentation

MM

Issue piping materials to Contractors

MM

Inspect special flange faces for correct finish and face protection.

Monitor in-process pipe fabrication activities.

Verify latest edition of piping drawings is being used.

Random check on base material ID on pipe, fittings and spools. Spools shall be clearly identified in

two locations.

Monitor storage of completed spools at pipe shop including preservations.

Monitor pipe identification, documentation and timely performance of NDE.

2.2 - Piping Erection

RESPONSIBILITY

ACTIVITY

Construction

Pipe will be marked full length with commodity code number. Alloy pipe and fittings shall be

additionally color coded. Alloy storage areas shall be clearly identified.

MM

Maintain piping spool identity markings of piping spools fabricated off site.

MM

Verify MTR's are received and that heat numbers correspond. Maintain documentation

MM

Verify PMI requirements are satisfied prior to placement in stock.

MM

Verify correct pipe is issued to Contractor.

MM

Monitor in-process erection I.a.w. drawings. Classify and record spool fit problems.

QA/QC

Ensure face flange protection is maintained.

Monitor proper bolt tensioning.

Monitor correct gasket installed.

Monitor erection to ensure that pipe installations are not subjected to undesirable stress.

Check pipe drawings to assure latest revision in the field.

Construction= Field Engineering or Superintendent


PM=Procurement Manager
MM=Material Manager

X=Primary Responsibility
S=Secondary Responsibility

The Dow Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-03

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 1

Page 2 of 6

INDUSTRIA DEL HIERRO S.A. DE C.V.

Assist Contractor to maintain current piping test status.

Monitor Contractor's activities to established quality control practices.

Monitor in process pipe erection and transfer of heat numbers. Verify that NDE is performed in a

timely manner. Monitor pipe and welding traceability including PWHT, PMI and Hardness Testing.

2.3 - Piping Inspection - Punching

RESPONSIBILITY

ACTIVITY

Construction

QA/QC

Flag deficiencies when not visually obvious.

Enter punch lists into data base.

Check work, noted as complete, on punch lists to assure items were corrected.

Initiate action with Contractor on punching results. Add additional discrepancies to punch list. Initial

and date punch list for each item corrected.

Monitor the Contractor's punching activities.

Verify that punching deficiencies are identified, documented and follow up to verify corrective action is

taken.

Verify that measures are taken to assure NDE, PWHT, PMI and traceability is completed prior to

pressure testing.

2.4 Pressure Testing of Piping

RESPONSABILITY

ACTIVITY

Construction

QA/QC

Monitor pressure testing

Review drawings and specifications to verify pressure test package limits, equipment to be included or

excluded, valves opened or closed and test blind locations.

Verify that the maximum allowable test pressure of the weakest component within the system is not

exceeded.

Verify that all NDE is complete prior to testing.

Verify that shop spool/cut sheets are included in test packages and all NDE, PWHT and welder info is

recorded.

Review Contractor's pressure test package, including marked up isometric drawings indicating test

blind locations, valve position (open/closed) and other information relating to test.

Monitor preparation of test system against test package.

Monitor restoration of the tested system.

Monitor Contractor's pressure testing and documentation activities.

Review test package for completion

Inspect the system prior to testing notifying Contractor of deficiencies. Mark Pressure Test Record,

"Ready to Test". Notify client when acceptable for test. Give permission to proceed with test.

Inspect system under pressure. Verify test pressure and duration of test. Procure test acceptance

signatures from Contractor.

When equipment is included in the test, verify that pressure test does not exceed nameplate.

2.5 - Piping Internal Cleaning

RESPONSIBILITY

ACTIVITY

Construction

QA/QC

Review and approve the cleaning and preservation procedures and the limits agree with drawings.

Establish hold points for witnessing tests.

Monitor preparatory and in-process cleaning activities for compliance with procedures and specs.

Coordinate the monitoring of Contractor inspection and testing activities.

Construction= Field Engineering or Superintendent


PM=Procurement Manager
MM=Material Manager

X=Primary Responsibility
S=Secondary Responsibility

Module Fabrication Quality Manual, SA5-DOW-01-03

The Dow Chemical Company

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 1

Page 3 of 6

INDUSTRIA DEL HIERRO S.A. DE C.V.

Verify the Contractor is preparing documentation as inspections and tests are being performed.

Verify that internal cleaning has been accomplished.

Monitor the Contractor's quality control activities.

Section 3 - ELECTRICAL
3.1 - Electrical

RESPONSIBILITY

ACTIVITY

Construction

QA/QC

Monitor in-process installation of electrical conduit and cable tray, including welding of supports.

Witness initial testing of shielded cable, i.e., insulation resistance test of power cable on reels, continuity

test of reeled instrument cable and resistance and continuity on electrical heat tracing cables.

Monitor in-process cable pulling and installation.

Witness random testing of installed cable, i.e., insulation resistance test on power and instrumentation

cables, continuity and insulation resistance testing on heat tracing and hypot of medium and high
voltage cables.

Verify client is being notified in advance of tests that require witness.

Verify terminal to terminal checks to ensure continuity and correctness of installation.

Verify conduit seals have been poured.

Inspect installation upon completion.

Verify that the Contractor is preparing documentation concurrent with construction as inspection and

testing are performed.

Monitor the Contractor's quality control activities.

Section 4-CONTROL SYSTEMS

4.1 - Control Systems Site Shop Operations

RESPONSIBILITY

ACTIVITY

Construction

Notify construction upon receipt of each instrument shipment for inspection.


For nonconforming items, issue a Damage Report or NCR.

MM

Issue instruments to Contractor.

MM

Inspect each instrument shipment. Deficiencies shall be reported to the Material Manager.

Inspect instrument materials i.a.w.sec.10 & project procedures

Document the receiving inspection.

4.2 - Control Systems Field Operations

QA/QC

MM

RESPONSIBILITY

ACTIVITY

Construction

QA/QC

Monitor the Contractor's in-process instrument installation including racks, panels, consoles, locations,

mounting, process pipe connections, Instrument air tubing, pneumatic signal tubing, heat tracing and
instrument wiring

Witness pressure testing of the instrument piping and tubing documentation.

Witness calibration of test guages.

Monitor continuity tests of instrument cables. Verify that cable terminations are correct.

Witness checks of control system loops. Establish notification system for IMT.

Witness all loop checks

Assure all instrument installation inspections and megger tests are complete

Inspect instrument installations upon completion.

Monitor the Contractor's quality control activities.

Verify documentation procedures are being followed.

Construction= Field Engineering or Superintendent


PM=Procurement Manager
MM=Material Manager

X=Primary Responsibility
S=Secondary Responsibility

Module Fabrication Quality Manual, SA5-DOW-01-03

The Dow Chemical Company

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 1

Page 4 of 6

INDUSTRIA DEL HIERRO S.A. DE C.V.

Section 5 - COATINGS AND INSULATION

5.1 - Coatings

RESPONSIBILITY

ACTIVITY

Construction

QA/QC

Ensure that the paint system is i.a.w. specifications.

Monitor performance of materials preservation activities.

Monitor surface preparation. Verify inspection documentation.

Monitor in-process coatings applications.

Check dry film thickness of applied coatings.

Inspect the workmanship of completed finishes.

Monitor the Contractor's quality control activities.

Verify the Contractor has prepared the QC documentation.

Audit coating documentation.

5.2 - Insulation

RESPONSIBILITY

ACTIVITY

Construction

QA/QC

Monitor performance of material preservation activities.

Monitor in-process installation of the insulation materials.

Verify the Contractor has prepared the quality control documentation

Inspect the completed work.

Document acceptance.

Section 6 - WELDING

6.1 - Pipe Welding

RESPONSIBILITY

ACTIVITY

Construction

Verify the WPS's have been approved by QA/QC department.

Monitor qualification tests of Contractor's welders.

QA/QC

Ensure that welder ID badges have been issued and displayed.

Check Contractors control of welder symbols.

Check Contractor's control of welding consumables.

Monitor in-process welding including consumables, joint preparation, fit-up preheat, interpass heat,

WPS variables and final visual

Verify Contractor is documenting welds on the Daily Welding Report.

6.1 - Pipe Welding

RESPONSIBILITY

ACTIVITY

Construction

Verify completed welds are being documented on piping drawings.

Monitor in-process post weld heart treatment.

Audit welding documentation.

Verify transfer of piping material heat numbers.

6.2 - Structural and Reinforcing Steel Welding

RESPONSIBILITY

ACTIVITY

Construction

Verify the WPSs have been approved by QA/QC department.

Monitor qualification tests of welders.

QA/QC

Monitor in-process welding including consumables, joint preparation and final visual inspection.
Audit welding documentation.

Construction= Field Engineering or Superintendent


PM=Procurement Manager
MM=Material Manager

QA/QC

X=Primary Responsibility
S=Secondary Responsibility

Module Fabrication Quality Manual, SA5-DOW-01-03

The Dow Chemical Company

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 1

Page 5 of 6

INDUSTRIA DEL HIERRO S.A. DE C.V.

6.3 - Piping Nondestructive Examination (NDE)

RESPONSIBILITY

ACTIVITY

Construction

Pre-qualify NDE Contractor

QA/QC

Verify that the NDE Contractor has established procedures that comply with project specifications.
Daily entry of weld data to NEWS program.

Establish and maintain NDE documentation files.

Review Contractor NDE personnel certifications.

Verify approval of NDE Contractor and procedures.

Verify NDE Contractors procedure to provide visual status of welds requiring NDE.
Select welds for examination
Perform Nondestructive examinations

NDE
CONTRACTOR

Review radiographic film, Contractors interpretation and reports.

Verify code compliance for rejected welds.

Maintain a tickler file of rejected welds.

Verify, through audit, welding and NDE records are traceable to the weld.

Verify through NEWS that NDE is completed prior to pressure testing.

Audit the NDE lab

Monitor the NDE Contractors production to verify that welds are examined within 48 hours of

notification.

Verify all field welds are numbered and identified on drawings.

Ensure that weld number and welders symbols are low stress stamped or otherwise marked on pipe.

Ensure that an accurate Daily Welding Report is maintained.

6.4 - Pipe hardness Testing

RESPONSIBILITY

ACTIVITY

Construction

QA/QC

Monitor the Contractor to verify weld identity system and compliance to specification.

Establish confidence that tests are being preformed i.a.w. test equipment instructions.

Verify the Contractors compliance with hardness testing and documentation.

Verify Contractors procedure for visual identification of rejected welds.

Maintain a PWHT tickler file for rejected welds.

Verify hardness testing is complete prior to pressure testing.

Witness tests required by the specifications as performed by Contractor.

Schedule final acceptance inspection activities between the Contractor and the Field Engineer.

Monitor the Contractors quality control activities to verify conformance to requirements for test

frequency, identification and traceability.

Section 7 - FIELD RECEIVING

7.1 - Field Receiving (IMT)

RESPONSIBILITY

ACTIVITY

Construction

Control receiving operations including ID of item to purchase order, verification of quantity and size

examination for shipping protection and damage, maintenance of inspection documentation.

MM

Issuance of periodic receiving reports to Construction Superintendents when technical assistance is

required.

MM

Inspect received material/equipment, providing technical assistance, when requested.

Construction= Field Engineering or Superintendent


PM=Procurement Manager
MM=Material Manager

X=Primary Responsibility
S=Secondary Responsibility

QA/QC

Module Fabrication Quality Manual, SA5-DOW-01-03

The Dow Chemical Company

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 1

Page 6 of 6

INDUSTRIA DEL HIERRO S.A. DE C.V.

7.2 - Field Receiving -Contractor

RESPONSIBILITY

ACTIVITY

Construction

Receive all contractor purchased equipment and materials

MM

Review material test reports against received materials and maintain on file

MM

Issue equipment and materials to the Contractor

MM

QA/QC

Inspect received material/equipment, providing technical assistance when requested

Assure that the contractor performs the equipment and material protection as required by

manufacturers instruction or specification requirements

7.3 - Positive Material Identification (PMI)

RESPONSIBILITY

ACTIVITY

Construction

Notify QA of receipt of material requiring PMI.

QA/QC

MM

Maintain PMI test results with receiving documentation.

MM

Verify receipt of PMI reports from suppliers and fabricators,

MM

Verify Contractor has established a system to maintain material ID through receiving, storage, issue,

fabrication and election.

Implement procedures for PMI.

Monitor contractor's maintenance of piping material identification.

Verify ID marking are accomplished per specification.

Verify controls have been established to prevent the in advertent use of materials failing examination.

Perform PMI as required by specification.

Verify the filing, maintenance and retention of documentation.

Assure that PMI equipment is calibrated.

Section 8 - EQUIPMENT AND MATERIAL PROTECTION

8.1 - Equipment and Material Protection

RESPONSIBILITY

ACTIVITY

Construction

Monitor equipment and material preservation in storage and document.

QA/QC

MM

Monitor Contractors in-process equipment and material protection/preservation activities.

Check Contractors in-process equipment and material

Audit the Contractor Material and equipment protection activities.

Construction= Field Engineering or Superintendent


PM=Procurement Manager
MM=Material Manager

X=Primary Responsibility
S=Secondary Responsibility

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-04

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

DOCUMENT CONTROL

PURPOSE
This practice provides guidelines for site document control management of all

documents, manuals, and electronic files at the Light Hydrocarbon Unit 9 Project

Module Fabrication site.

SCOPE

This practice provides detailed information for work process on the following topics:

Module Fabrication Site Document Control (MFSDC) Group Structure

Site Procedures for Receipt and Distribution of Documents

Miscellaneous Construction Documentation received at Module Fabrication site.

Field Drawing Request Procedure

Site Technical Filing System.

Request For Information

Routine Audits

APPLICATION

This practice applies to all documents that are maintained using ProArc (Document

Management System) which is part of Projects on Line (POL).The information is intended

for all POL users:

Module Fabrication Site document control group members

Project Engineering and Construction personnel

Clients and joint venture partners if applicable

Contractors and equipment suppliers

SITE DOCUMENT CONTROL GROUP STRUCTURE

Module Fabrication Document Control will be one group located in the Empalme

Yard.

Any communications back to Fluor PDDM will be by transmittal via POL file
exchange area and by email.

MFSDC will have direct access to the POL for easy retrieval of latest issued data

along with the ability to run status reports and downloads. No additional data entry

is required by the MFSDC for documents provided by the Fluor PDDM.

MODULE FABRICATION SITE PROCEDURES FOR RECEIPT AND DISTRIBUTION OF DOCUMENTS

Fluor PDDM (Project Document and Data Management) will notify MFSDC technician

when new documents are in POL for distribution. PDDM will send a transmittal via

email and update the respective technicians Activity List in POL. (if you are using

ProArc/POL the site tech will automatically receive a notice from ProArc to check for

documents)

MFSDC technician will receive transmittal and go to ProArc/POL for document

download.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-04

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

MFSDC technician will make hard copies of transmittal and associated documents.
The technician will verify documents for proper control stamps (IFC, IFA,

Preliminary, etc) and Revision Level. Any discrepancies will be noted and brought

to the attention of the Engineering Manager and PDDM for disposition. If no


discrepancies exist the documents will be date stamped received and filed.

MFSDC will make hard copy/electronic distribution to all Module Fabrication

Construction Site personnel/ Contractors per site distribution matrix.

For Module Fabrication Site document distribution Field Transmittals will be

generated using ProArc. Hard copy retention of transmittals will be determined by

Project Manager.

Hard copies of documents will accompany the transmittal to the respective

designees.

Upon receipt of documents/data, Module Fabrication Construction and Contractor

personnel will be required to sign and return to MFSDC an acknowledgement of

receipt.

Contractors will go to POL to download transmittal and documents when notified by

email from Home Office PDDM if electronic distribution is required.

Module Fabrication Construction and Contractor Personnel in addition may have

access to the ProArc/POL database for personal access for read only viewing of
data/documents.

All superseded documents will be stamped VOID. If voided documents are needed

for archiving purposes they will be filed accordingly. If not they will be destroy.

FIELD DRAWING REQUEST PROCEDURE

All requests for documents will be through email to the respective MFSDC

Technician.
A document template will be created for all personnel requiring
documents from MFSDC. See attachment 4.

FOR MISCELLANEOUS DATA/DOCUMENTS RECEIVED AT MODULE FABRICATION SITE

All As-built, Design / Field Sketch, etc and drawings prepared at the Module

Fabrication site will be sent to Home Office PDDM for input into ProArc/Projects On

Line

Maintain other construction engineering logs as may be required (use POL if

possible)

Vendor drawings will be printed as 11X17. These will be filed by Vendor name with

sub-folders as necessary. The hard copies will be maintained in the Document

Control Section.

Warehousing will bring all received documents to MFSDC.


POL.

MFSDC will scan into

REQUEST FOR INFORMATION

When field conditions dictate changes to the design specifications and/or drawings,

a Request for Information (RFI), Form SA5-DOW-01-04-01, will be submitted for

approval to ensure proper control and documentation. RFIs will be initiated by

Authorized Personnel. Project Manager will assign someone to maintain the RFI
Database. RFIs will be forwarded to the Fluor Contracts Manager for submittal to

the Fluor Construction Engineering Manager for evaluation and processing.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-04

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

The Construction Engineer shall describe the condition or design change requested

in terms that can be easily understood by those who review it, including appropriate

references, specific drawings and specifications to illustrate the recommended

change.

To minimize delay in construction, authority for deviation from specifications and

drawings may be acquired by direct communication with the Design Engineer and

the Client pending processing of the RFI. Approval of the Clients construction site

representative should be acquired, if possible.

The Design Engineer and the Client portion of the RFI indicate approval or

disapproval of the field recommended change or recommends alternatives. The

signed original will be returned to the Project Manager for disposition or authority to

proceed.

The Construction Engineer shall maintain a file that contains a full history of the

action and data supporting the approval of each Request for Information.

ESTABLISH AND MAINTAIN SITE TECHNICAL FILING SYSTEM

Each MFSDC Technician will maintain and file hardcopies of construction

engineering reference documents and manuals in separate filing systems.

Adequate storage facilities (such as flat files, file cabinets, etc.) will be provided for

non electronic documents.

Drawings will be filed by Discipline then Drawing number.

ESTABLISH ROUTINE AUDITS

Perform routine audits of field documents to establish that construction is utilizing

the latest drawings and specifications

The audit should include the contractors office prints and also the prints being used

in the field.

MFSDC should generate from ProArc an updated list of all discipline documents

issued for construction to use in the audit. A transmittal log (from ProArc) of all

transmittals issued to the contractor since the last audit should also be generated to

check what documents have been issued / reissued in that time period.

List a date for each month of the entire anticipated job site schedule

List all contractors to be audited including a self audit.

Specify where the audit will take place. Field or office.

Report findings.

Make sure any findings are corrected and reported to QA/QC Manager.

ATTACHMENTS

Attachment
Attachment
Attachment
Attachment
Attachment

1
2
3
4
5

Module Fabrication Site Distribution Matrix

Transmittal Form
Request for Documents Form
Module Fabrication Site Document Control Flow Diagram

Request For Information (RFI) Form Instructions

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-04

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

SAMPLE DISTRIBUTION MATRIX

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-04

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 2

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.


DOCUMENT TRANSMITTAL

To:

Date:
Transmittal No.:
Project:
Contract No.:

Transmitted herewith are:

Preliminary

Prints

Reproducible

Per Your Request

Authorized To Proceed With Construction

Reference Only

Authorized As Noted

Revised as Noted

For Information

Document
Number

Description

Please acknowledge receipt of the above


documents by signing below and returning one
copy of this transmittal form to Company.

Rev.

Date

Very truly yours,

By:
(signature)

(signature)

(printed name of signature)

(printed name of signature)

Title:
Date:
If the above transmitted documents constitute a change in price or schedule to the Contract referred

above, Contractor must notify Company of this change within the period of the time stated in the

Contract.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-04

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 3

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

DOCUMENT REQUEST FORM


Name:

Drawing Number

Date Requested:

Discipline

Control #

Number of
Copies

Size

Please acknowledge receipt of the above documents by signing below and returning one copy of this Request form to SDC.

Received By:

Issued By:
(signature)

(signature)

Title:
Date:
If the above transmitted documents constitute a change in price or schedule to the Contract referred above, Contractor must notify Company of this change
within the period of the time stated in the Contract.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-04

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev01

Purchase Order No. GUST-50-LHC-K067

Attachment 4

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

Module Fabrication Site Document Control Flow Diagram

Resolve with

FLUOR
PDDM

YES

Receive
Documents

From
FLUOR

PDDM

Delivery

Drawings for

Recipients

Discrepancies?

NO

Construction

Area Managers,
Superintendents

Subcontractors

Document
Control

Audit

Date Stamp

and File

File

Reproductions
and/or Originals

Make copies
per Dist.

Chart

Output:
Old Docs to

Document
Control for

Disposition

Report Findings to
QA/QC Manager

Prepare
Transmittals

For On-Site

Distribution

Red Mark
As-Built

Drawings

Distribute
per Site

Distribution
Matrix

MFSDC Make

Copies, Send to

FLUOR PDDM

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-04

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 5

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Request for Information (RFI) Form Instructions


Project Name:

The Project Name (i.e. Butanol)

Project #:

The Project Number (i.e. 00662255)

Date:

The date the Request is originated.

RFI #:

Unique number given to each individual RFI Form.

WBS:

Work Breakdown Structure unique to the Project, if applicable

Work Package No.:

Construction Work Package number, if applicable.

Turnover/Startup System No.:

Turnover/Startup system number, if applicable.

Discipline:

Primary discipline affected by the Request (Civil, Structural, Piping etc.)

Request To:

Enter Name of Individual submitted to (John Doe)

Company/Location

Enter Name of Company and its location of the requested organization

(Industria del Hierro-Tampico)

Phone Number/Email

Enter phone number of the individual submitted to and/or email address

Subject

Enter the subject of the request

Specifications/Documents:

List all issued drawings, documents, and specifications impacted by the

request.

Questions/Description/Conflict: Detail the missing information, discrepancies, questions or conflicts that

must be resolved prior to construction activities continuing in the affected

areas. Attach additional sheets, drawings, or sketches, if further


explanation is required.

Recommended Solution:

Indicate the action that the requestor believes is required to provide an


acceptable solution to resolve the discrepancies and conflicts indicated on
the request. Additional sheets, sketches, digital photos or drawings may be

attached to provide a clear explanation of the intended resolution.

Originated By:

The person originating the request and provided recommended action.

Title:

List the current position of the originator on the project.

Date:

The date the request is submitted for approval.

Originators Company Name

List Company name of the originator

Approval For Originator By

List name of Fluor person approving the request for submission to the

Engineer of Record (Generally, the Fluor Site Engineering Manager will

receive the request and approve its submission to the Design Engineer.)

Title:

List the current position of the approver.

Date:

The date the request is approved for submission

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-04

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 5

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Date Reply Required:

Enter the date in which the resolution of the request must be made in order
not to delay the activities in question

Response

The respondents resolution (generally the Design Engineer, Project


Engineering Manager, CM, or Fluors Construction Engineering Manager) to
the question, information, discrepancy, or conflict.

Respondent:

The signature of the person making the response. (Lead Construction


Discipline Engineer, Construction Engineering Manager or Design Lead
Discipline Engineer, etc.)

Title:

List the current position of the Approver on the project.

Date:

The date the request is approved for transmittal to the Design Engineer.

Approval for Respondent:

The signature of the person reviewing and approving the request prior to
implementation. (This action might require Client approval. If the response

changes the design (AFC Drawings or Specifications) the Engineer of

Record must approve the resolution.)

Title:

List the current position of the Approver on the project.

Date:

The date the request is approved for implementation by the Client or Project

Engineering Manager or designee.

Adequate Closure?

Indicate using the checkbox if the RFI response is acceptable for closure of
the RFI. Generally, the Construction Engineering Manage must respond to
this question.

Cost Impact?

Indicate using the checkbox if the RFI response has a cost impact that will

require an estimate or a request for contractor pricing. If the answer is yes,

indicate the requirement for a SI to be issued to the Contractor.

Schedule Impact?

Indicate using the checkbox if the RFI response has a schedule impact that
will require an adjustment in the contract schedule or a request for

contractor pricing. If the answer is yes, indicate the requirement for a SI to

be issued to the Contractor

Closed RFI and Date Verified:

Inter the name and date the RFI was closed and verified.

Distribution:

List all parties requiring a copy of the completed request once the response
has been received.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The Dow Chemical Company


Gulfstream Light Hydrocarbon Unit 9 Project
Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-04-01

August, 2014 Rev.01

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

REQUEST FOR INFORMATION (RFI)


PROJECT NAME

PROJECT #

WBS (Work Breakdown Structure)

WORK PACKAGE

REQUEST TO (RESPONDENT):

DATE

RFI #

TURNOVER/STARTUP SYSTEM

DISCIPLINE

RESPONDENTS COMPANY/LOCATION

PHONE/EMAIL

SUBJECT:

SPECIFICATIONS/DOCUMENTS/DWGS REFERENCED OR IMPACTED:

QUESTIONS/DESCRIPTION OF CONFLICT:

ORIGINATORS RECOMMENDED SOLUTION:

ORIGINATOR (Sign)

TITLE

DATE

APPROVED (Sign)

ORIGINATORS (SUB) CONTRACTOR COMPANY NAME:

TITLE

DATE

ORIGINATORS (SUB) CONTRACT #:

REPLY REQUIRED BY:

RESPONSE:

RESPONDENT (Sign)

TITLE

DATE

ARE THE QUESTION AND RESPONSE ADEQUATE FOR CLOSURE

OF THIS RFI?

YES

NO

IS THERE A SCHEDULE IMPACT DUE TO THIS RFI?


IF YES, SITE INSTRUCTION TO BE ISSUED

DISTRIBUTION:

APPROVED (Sign)

TITLE

IS THERE A COST IMPACT DUE TO THIS RFI?

DATE

YES

NO

IF YES, SITE INSTRUCTION TO BE ISSUED

YES

NO

THE WORK WAS COMPLETED AS NOTED ON THIS CLOSED

RFI AND VERIFIED BY DATE:

The Dow Chemical Company


Gulfstream Light Hydrocarbon Unit 9 Project
Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-04-02

August, 2014 Rev.01

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

REQUEST FOR INFORMATION LOG


RFI No.

Date

Opened

Originator

Discipline

Date

Closed

Description Of Request

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-05

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A.

DE C.V.

PROCESS CONTROL

SCOPE

This procedure identifies construction work processes that require process control.

GENERAL

For most Module Fabrication production activities, the drawings and specifications provide adequate work

instruction. These may be supplemented with additional instructions to control work sequencing, recording of

installation data, material selection, etc. However, certain construction work processes require special instructions

to establish the controls necessary to achieve planned results of the completed work, for the following reasons:

Quality results of the completed work cannot be fully verified by subsequent monitoring, inspection,

testing or measurement.

Quality deficiencies may only become apparent after the item has entered service or operation.

Validation of Special Processes


"Special processes" are highly dependent on the control of process parameters or the skill of the operator or both

and are characterized by the need for one or more of the following control measures

Written Method Statement or Procedure

Procedure Qualification

Operator Qualification

In-Process Inspection

Special processes encountered on sites include, but may not be limited to:

Welding and Post weld Heat Treatment

Welder Qualification

Nondestructive Examination (including Radiography, Magnetic Particle, Liquid Penetrant, Ultrasonic,

and Positive Material Identification VT, RT, MT, PT, UT, and PMI)

Pressure Testing and Flushing of Piping Systems

Other processes needing procedural control.

Special processes identified must be accomplished and documented under controlled conditions by

appropriately qualified personnel using approved procedures and equipment in accordance with the

governing specifications and the associated referenced codes and standards.

PROCEDURE

QA/QC Manager
The QA/QC Manager shall coordinate with the Construction Manager, to research the project contract

work scope and specifications in order to identify the special processes that will be utilized. If the

processes are to be contracted, ensure that the required control mechanisms, i.e. procedures,

qualifications, etc. are specified in the RFP and implemented before the start of work. Process control

measures and responsibilities shall be identified on the applicable procedures or ITPs (Inspect Test

Plans).

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The Dow Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-06

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

MONITORING AND MEASURING DEVICES

SCOPE

This procedure describes the methods to be used for the control, calibration, maintenance and recall of

inspection, measuring and monitoring equipment used to demonstrate conformance of construction work

activities to the determined requirements. It is not applicable to calibration of permanent plant devices.

NOTE: Monitoring and Measuring Devices will also be referred to as Inspection Measuring and Testing

Equipment (IMTE) throughout this Module Fabrication Quality Manual and both are

interchangeable.

GENERAL

Inspection Measuring and Testing Equipment (IMTE), shall be selected, calibrated and controlled in a

manner which is consistent with the required inspection, testing and examination requirements.

Environmental conditions shall be suitable for the calibrations, inspections, measurements and tests being

carried out.

All IMTE equipment shall be uniquely identified. This unique identification may consist of a manufacturer's
unique serial number along with model number and/or the assignment and application of a unique
Inventory Control Number (ICN).

The handling, preservation, and storage of inspection, measuring and test equipment shall be such that the

accuracy and fitness for use is maintained.

All calibrations shall be performed using certified equipment having a known valid relationship to nationally

recognized standards; where no such standards exist, the basis used for calibration shall be documented.

"Conformance check" means the operations required to ensure that an item of measuring equipment is in a

state of compliance with requirements for its intended use.

Non-adjustable measuring and test equipment is not considered as calibrated equipment. Equipment of this

nature (e.g. cube and proctor molds, measuring tapes, rulers, chains) is subject to a "conformance check"

to dimensional, volumetric or other requirements and does not require any further verification unless

apparent damage or other factors require re-verification.

It is the responsibility of the end-user to comply with the requirements of this section.

IMTE shall be selected utilizing Attachment I "Criteria for the Selection of Inspection, Measuring and Testing

Equipment and Attachment II shall be used for guidance in procurement of calibration equipment and/or

services.

All IMTE calibration requirements shall be identified, on Form SA5-DOW-01-06-04 Calibration Requirements.

This form is used to list the various types of IMTE in use and their associated calibration frequencies,

calibration procedures and tolerances. Calibration procedures, frequencies, and tolerances may be obtained

in conjunction with obtaining the services of an outside calibration vendor or from manufacturers. A

procedure number shall be assigned. If the manufacturer has an assigned number, this should be used.

Calibration procedures are quality records and shall be maintained in site files.
Procedures such as published standards, practices (e.g., ASTM) or written calibration instructions from the

manufacturer may be used.


In the absence of either a published standards practice or adequate

manufacturer's procedure, a written procedure for the calibration method shall be written and approved for

use.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The Dow Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-06

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

In addition to the above, calibration procedures should include at least the following basic information:

Identity of the item to be calibrated using the procedure.

Calibration comparison standards and calibration support equipment to be used.

Provisions to obtain and record "as-found" accuracy measurement prior to any adjustments.

Sequence of operations.

Checks, tests and measurements instructions.

Calibration acceptance tolerances.

Calibration adjustment instructions.

Safety considerations.

Special instructions (when applicable).

Documentation and labeling instructions related to the specific item to be calibrated.

Perform and record (Form SA5-DOW-01-06-03) the calibration in accordance with the above established

calibration procedures and/or contract the services of an outside calibration services vendor.

Upon completion of initial calibration, enter the equipment in the Calibration Assignment Log (Form A5DOW-01-06-01) and record other data required by this log.

History of Use

The end user shall maintain a history of use for IMTE to traceability to previous calibrations, inspections,

measurements and test results when calibration as-found data reveals out-of-tolerance data points.

The history shall be documented using IMTE Sign In/Out-History of Use Log (Form SA5-DOW-01-06-02)

and keep current to record each usage of the IMTE.


If out of tolerance conditions are found, a Nonconformance Report shall be prepared in accordance with

SA5-DOW-01-07.

If out-of-tolerance conditions are found during calibrations/recalibrations an evaluation shall be conducted

to determine if inspection, measurement, test or calibration results obtained with the out-of-tolerance
instrument are still valid.

Evaluations shall be documented, and where required, repetitions of readings shall be compared to original

results.
It is the responsibility of the end user to use calibrated equipment within the environmental operating

range(s) or restrictions/limitations specified by the instrument manufacturer.

NOTE: Temperature or other compensating calculations shall be applied to any inspection, measurement,

test or calibration results when such compensations are specified by the instrument manufacturer

and/or when they can affect the basis of the results obtained.

DOCUMENTATION

Electronic recording of the information that is required by the documentation in this procedure is

permissible. All documents (except labels) generated in accordance with this procedure should be

maintained in appropriate protected files throughout the construction phase of the project, and for the
period of time there after specified (if any) or turned over to the client if required.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The Dow Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-06

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

ATTACHMENTS AND FORMS

Quality Forms:

SA5-DOW-01-06-01

- Calibration Record

SA5-DOW-01-06-02

- IMTE Sign In/Out-History of Use Log

SA5-DOW-01-06-03

- Calibration Data Sheet

SA5-DOW-01-06-04 - Calibration Requirements

ATTACHMENTS

Attachment 1

Criteria for the Selection of Inspection, Measuring and Test Equipment (IMTE)

Attachment 2

Criteria for Procuring Calibration Services

Attachment 3

Recommended Calibration Requirements

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The Dow Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-06-01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014
Page 1 of 1

CALIBRATION RECORD

Revision 01

INDUSTRIA DEL HIERRO S.A. DE C.V.

Equipment/Instrument
Identification No.

Item Description
Size-Range

Manufacturer Model
No.

Manufacturer Serial
No

Calibration Frequency

Calibration Tolerance

Date
Calibrated

Calibration

Due Date

The Dow Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-06-02

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

Revision 01

INDUSTRIA DEL HIERRO S.A. DE C.V.

IM&TE SIGN-IN/SIGN-OUT HISTORY OF USE LOG


IMTE
Description:

I M T E No.:
Name

Badge No.

Date Out

Date In

Area/System/PKG No.

The Dow Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-06-03

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014, Rev. 01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

CALIBRATION DATA SHEET


Area/Location

Unit No.

Project

Job No.

Tag No.

Manufacturer

Description

Model No.

Serial No.

Type

Action

Size

Fail Position

Direct

Reserve

Calibration Range

Calibration Procedure

As Found

Input

Calibration

Output

Input

0%

0%

25%

25%

75%

75%

100%

100%

Output

Mounted

Accessories

Remarks

Calibrated By

Date

The Dow Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-06-04

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014, Rev. 01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

CALIBRATION REQUIREMENTS
END USER

DESCRIPTION

FREQUENCY

PROCEDURE
Visual*

TOLERANCES
1/8"

(2)

Surveyor

Chain

Initial Conformance

Surveyor

Level

6 Months

Surveyor

Transit

6 Months

Surveyor

Tape

Initial Conformance

Surveyor

Distamat

6 Months

Per Procedure

Mechanical

Pressure Gauges

Yearly

5%

(2)

Mechanical

Torque Wrenches

6 Months

5%

(2)

Electrical

Meggars

6 Months

3%

(2)

Electrical

Simpson Multi-Meter

6 Months

3%

(2)

Electrical

Digital Multi-Meter

6 Months

3%

(2)

Millwrights

Calipers

6 Months

.02MM

(2)

Millwrights

Dial Indicators

6 Months

.02MM

(2)

Millwrights

Micrometers

6 Months

.02MM

(2)

Welding

Rod Oven Thermostat

6 Months

5F

Per Procedure
Per Procedure
Visual*

1/8"

(2)

(2)

Notes:
1)

ALL WORN AND/OR DEFECTIVE MEASURING EQUIPMENT IS REMOVED FROM THE SYSTEM AND
DISPOSED OF. RECORDS INDICATING REMOVAL/DISPOSAL DATE ARE MAINTAINED.

2)

THESE TOLERANCES ARE LISTED FOR SITUATIONS WHERE NO OTHER RECOMMENDED


TOLERANCES ARE PROVIDED.

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-06

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 1

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

CRITERIA FOR THE SELECTION OF INSPECTION,

MEASURING AND TESTING EQUIPMENT (IMTE)

1. IMTE includes inspection, measurement and/or testing equipment used to determine final

acceptance.

2. IMTE shall have a manufacturer's stated accuracy (and precision, where applicable) that exceeds

the construction installation inspection, measurement and/or testing tolerance(s).

3. IMTE shall have the durability, stability and appropriate measurement ranges consistent with the

intended use(s).

4. Calibration standards that will be required for the initial and subsequent recalibrations shall be

identified when selecting IMTE. Such calibration standards shall be requisitioned or the services

of a calibration facility with the calibration standards shall be contracted.

NOTE: Obtaining calibration standards or services can usually require more time to procure

than the time required to select and procure the needed IMTE.

5. Purchase requisitions for IMTE, calibration standards, and calibration facility services should

clearly state the requirements for accuracy, precision (where applicable), range, durability and/or

stability, environmental, handling, other applicable technical requirements.

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-06

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 2

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

CRITERIA FOR PROCURING CALIBRATION SERVICES

The following are recommended guidelines for preparing a purchase order for obtaining the services

of a calibration supplier to calibrate Inspection, Measuring and Test Equipment (IM&TE).

1. The following information should be provided to the supplier:

a)
b)
c)
d)

Description and unique identification of each piece of IM&TE;

Assigned calibration interval;

Calibration accuracy required;

Any relevant environmental requirements of use or calibration.

2. The calibration supplier must provide the following information as part of their calibration records:

a) Source of calibration equipment used and current certificate(s) of traceability to a

recognized national standard;

b) Identification of the calibration procedure(s) used (if the procedure is produced by the

calibration supplier, a copy must be furnished, if a recognizable standard i.e. ASTM,

ANSI/ASME, is used no copy is needed).

3. The calibration records supplied by the calibration supplier for each item of IM&TE calibrated

must include:

a) Item identification number;

b) Date of calibration;

c) The records of the "before", "as received" or "as found" condition including actual values

and the "as calibrated" or "as left" values;

d) Identification of the calibration procedure used;

e) Limits of permissible error;

f) Calibration standard used (including serial numbers and certificates) and traceability;

g) Details of any maintenance, servicing, adjustment, repairs or modifications carried out;

h) Identification of person performing the calibration;

i) Identification of person responsible for the correctness of the information provided.

4. The calibration supplier shall seal, using a unique, tamper-resistant system, all adjustment access

points after calibration, where practical. The system used shall provide visual evidence of

tampering.

5. The calibration supplier shall immediately notify the purchaser of any IM&TE discovered to be out

of calibration by more than the stated accuracy tolerance or any piece of IM&TE that shows

indication of tampering. The purchaser shall determine if the calibration process should continue.

6. The calibration supplier shall package and ship each piece of IM&TE in such a manner to preclude

damage and to preserve the calibrated condition.

The DOW Chemical Company

Module Fabrication Quality Manual SA5-DOW-01-06

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 03

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

TYPICAL LISTING OF IM&TE WITH RECOMMENDED

RECALIBRATION FREQUENCY AND TOLERANCES

FREQUENCY

TOLERANCES

SURVEYORS:

CHAIN
LEVEL
TRANSIT
TAPE
DISTAMAT

*
6 MONTHS
6 MONTHS
*
6 MONTHS

VISUAL
PER MFG.
PER MFG.
VISUAL
PER MFG.

1/8"

RECOM.

RECOM.

1/8"

RECOM

MECHANICAL:

PRESSURE GAUGES
TORQUE WRENCHES

YEARLY
6 MONTHS

5% note 1

5%

ELECTRICAL:

MEGGARS
SIMPSON MULTI METER
DIGITAL MULTI METER

6 MONTHS
6 MONTHS
6 MONTHS

3%

3%

3%

MILLWRIGHTS:

CALIPERS
DIAL INDICATORS
MICROMETERS

6 MONTHS
6 MONTHS
6 MONTHS

.02MM

.02MM

.02MM

WELDING:

ROD OVENS

*6 MONTHS

FOR WEAR AND

SERVICE - OVEN

TEMP. 5F OF

SPECIFIED RANGE

CONFORMANCE CHECK IS REQUIRED PRIOR TO INITIAL USE.


ALL WORN AND/OR

DEFECTIVE MEASURING EQUIPMENT IS REMOVED FROM THE SYSTEM AND DISPOSED OF.

RECORDS INDICATING REMOVAL/DISPOSAL DATE ARE MAINTAINED.

THESE TOLERANCES ARE LISTED FOR SITUATIONS WHERE NO OTHER RECOMMENDED

TOLERANCES ARE PROVIDED.

Note:
1)

Test gauges shall be visually checked after every test and re-calibrated if necessary.

2)

All worn and/or defective measuring equipment is removed from the system and disposed of.
Records indicating removal/disposal date are maintained.

3)

These tolerances are listed for situations where no other recommended tolerances are

provided.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-07

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

CONTROL OF NONCONFORMANCES

SCOPE

This procedure describes the methods and responsibilities for controlling nonconforming items to prevent

their inadvertent use or installation when other control methods, inspection reports, surveillance reports
(SA5-DOW-01-14), etc. are considered inadequate. This procedure provides for the identification,

documentation, evaluation, disposition, notification, segregation (prevention of inadvertent use/installation),

and re-inspection of these nonconforming items (excluding ASME Code items).

GENERAL

Types of NCRs
Nonconformances are classified as:

Use as Is- A concession to accept a nonconforming item under proper authority,


including the Client where applicable.

Rework- Action taken on a nonconforming item to make it conform to specified

requirements.

Repair-Action taken on a nonconforming item to eliminate the nonconformity and make it

acceptable for use.

Items Requiring an NCR


Nonconformance Reports are issued when there are:

Deficiencies in materials, finished work or work processes that result in a

condition that does not conform to the specifications and for which there are

no existing procedures or standard trade practices which describe methods

of correction and therefore require engineering disposition.

Deficiencies of a serious or repetitive nonconforming nature as determined

by the QA/QC Manager.

Construction damage has occurred to existing or turned over plant property.

Nonconformance shall be documented using Form SA5-DOW-01-07-01

Responsibility for Identifying Nonconformances


-

Industria del Hierro will issue Nonconformance Reports on self-perform work, when

applicable.

The Construction Subcontractors have the first responsibility for the identification, control,

and disposition of nonconforming items within their Scope of Work. Industria del Hierro
will issue a Nonconformance Report when the Construction Subcontractor has not issued

one. It is not necessary to have more than one Nonconformance Report active on the

identical nonconforming condition.

Inspection personnel usually initiate Nonconformance Reports; however, anyone may

initiate an NCR.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-07

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Control of Nonconforming Items


-

The Construction Manager will take measures to provide holding areas or other methods

for segregating nonconforming items to prevent unauthorized use, mixing with conforming

items or incorporating into future construction. Where physical segregation is not practical,

tagging, marking, or other positive means of identification is acceptable. The QA/QC

Manager may elect to use "HOLD" tags/stickers (Form SA5-DOW-01-07-03) for additional

assurance.

PROCEDURE

Documentation of Nonconformance
-

For materials and equipment identified as nonconforming (per the descriptions in the

"General" section of this procedure), generate a Nonconformance Report (Form SA5-DOW01-07-01) to document the nonconforming item(s). The report is to be processed as

follows:
Initiator

Enter the date the nonconformance is documented.

Enter either Industria del Hierro, the name of the Subcontractor or Vendor to

identify organization responsible for the nonconforming work.

Use the entries in the header of the form to provide unique traceability and

identification to the nonconforming item.

Enter a complete description of the nonconforming condition.

The initiator may propose a disposition, but it is not required.

Enter the root cause of the nonconforming condition as applicable.

The initiator provides the NCR completed as noted above to the QA/QC Manager.

QA/QC Manager
NOTE: Evaluate the report to determine that the described condition is a valid

nonconformance. It is not necessary to have more than one Nonconformance

Report active on the identical nonconforming condition.


If a Construction

Subcontractor has issued the NCR, it should not be duplicated by Industria del

Hierro.

Assign a unique number to the report and enter the number here and on the

"Nonconformance Report Log" (Form SA5-DOW-01-07-02).

If a hold tag is needed, enter the hold tag number and have the hold tag installed

on the item. The hold tag number should be the same as the NCR number. If a

hold tag is not to be used, enter N/A.

The QA/QC Manager provides the NCR completed as noted above to the

Construction Manager.
Also send a copy to the Fluor Site Manager for

nonconformance attributed to a vendor.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-07

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Construction Manager

Evaluate the proposed disposition, modify if necessary, or enter the disposition.

If the nonconforming condition will not be corrected in full conformance with the

applicable specification, (Fluor and Client) shall accept the disposition. In this

case, check "yes" and obtain Engineering approval. Any documentation provided

by Fluor Engineering that supports the disposition should be attached to the NCR

original. For subcontractor NCR's, this approval is obtained through the Fluor

Construction Manager.

If the disposition corrects the nonconformance to full compliance with the

applicable specification, check "no".

After completing the disposition instructions and obtaining the required approvals,

sign and date.

Send the original NCR to the QA/QC Manager and copy to the Construction

Manager.

Upon receipt of the approved NCR disposition, perform the applicable construction

actions specified in the NCR disposition. (Request removals of QC hold tag prior to

performing work, if one has been applied.)

QA/QC Manager (or Inspector)

Upon verification of satisfactory completion of the disposition, sign and date.

Obtain other required approvals as required.

DOCUMENTATION

The QA/QC Manager shall retain all NCRs and the NCR log in the Quality Files.

FORMS

Quality Forms:

SA5-DOW-01-07-01

- Nonconformance Report

SA5-DOW-01-07-02

- Nonconformance Report Log

SA5-DOW-01-07-03

- Hold Tag/Sticker

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

SA5-DOW-01-07-01

August, 2014

Page 1 of 1

Revision 01

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

INDUSTRIA DEL HIERRO S.A. DE C.V.

NONCONFORMANCE REPORT
Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Sub System:

IH

Other

Location:

Hold

Tag

Dwg. No.:

Turnover System:

Yes

No

NCR No.:

Specification:
Date:

Initiated By:
Item

Description:
Description of the

Nonconformance:

Use as is

Disposition

Rework

Repair

Other

Attachments

Yes

No

Repair Method:

Design Eng. Approval Req.

Yes

Construction Engineer

Date

Design Engineer

Action Accepted by Fluor/ Marathon:

Signature :

Date

Action verified:

Signature :

Date

NCR closed by:


QA/QC Manager:

No

Date:

The DOW Chemical Company


Gulfstream Light Hydrocarbon Unit 9 Project
Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-07-02

August, 14 - Rev. 01

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

NONCONFORMANCE REPORT LOG


NCR No.

Subcontractor

Date
Opened

Date
Closed

Description of Nonconformance

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-07-03

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August,2014 Rev.01

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

HOLD TAG/STICKER

HOLD

Hold Tag No._____________________

DO NOT USE

NCR Number_____________________

(DO NOT REMOVE THIS TAG)

(Recommended Color: Red with Green Letters)

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-08

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

CORRECTIVE & PREVENTIVE ACTION

SCOPE

This procedure establishes the method for obtaining and documenting corrective actions for significant

conditions that are adverse to quality. Such as; failure to properly implement procedures, programmatic

failure due to inadequate procedures or failure to correct repetitive problems, e.g., adverse trends identified

by management or the client, NCR's, audits, inspection/test reports, and surveillance reports.

During routine construction and installation of equipment and systems, it is normal to find items requiring

correction. However, when identification and the corrective action process are accomplished by normal
construction process control procedures (e.g. SA5-DOW-01-07) this Corrective Action Procedure would

not be appropriate. In the course of the above, if trends or operating system deficiencies are identified,

this procedure is appropriate.

GENERAL

Definitions
Corrective Action: The corrective/preventive action taken to eliminate the cause(s) of actual/potential

nonconformities. Corrective Action shall be appropriate to the magnitude of the problem and

commensurate with the risks encountered. Site Corrective Action is documented on the Corrective Action

Report Form (SA5-DOW-01-08-01), and controlled by maintaining the Corrective Action Report Log, Form

SA5-DOW-01-08-02.

Significant Condition - operating system and/or procedural deficiencies evaluated by management (as to

the magnitude of the problem and commensurate to the risks encountered) and judged to warrant a

Corrective Action Report (CAR).

Preventive Action - The action taken to eliminate the cause of potential nonconformance. Preventive
Action will be appropriate to the magnitude of the potential nonconformity and commensurate with the

potential risks that may be encountered.

Responsible Manager - The staff member responsible for the group or system with the problem and for

ensuring its timely correction. This will usually be a Discipline Manager.

PROCEDURE

The need for a Corrective Action Report is usually identified by the QA/QC Manager or inspection

personnel; however, any staff member may identify the need for a CAR.

Monthly Trend Report

QA/QC Manager
Prepare a monthly trend report; reference the sample format in Attachment 1.

The report should include an update of the quality-related activities associated with the construction site,

including an evaluation of nonconformances/deficiencies reported during the reporting period.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-08

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Review each type of nonconformance/deficiency reported each month utilizing Form 930 509 F0143 as a

guide. The review will cover data generated since the last reporting period. This review will include data

received from sources such as e.g.:

Client/Management Concerns

Inspection/Test Reports

Surveillance Reports

Audits

Other applicable sources

Group the nonconformance/deficiencies reported by function; e.g. equipment, welding, etc., utilizing

Form SA5-DOW-01-08-03, and conduct an evaluation of those functions which have five (5) or more

nonconformance/deficiencies reported.

This evaluation will include a determination of magnitude of the problem commensurate with the risks

encountered to ascertain if a Corrective Action Report (CAR) is warranted.

Identify any CAR's initiated in the Monthly Trend Report.

Root Cause Analysis

QA/QC Manager
Identify significant Nonconformance and trends and conduct a root cause analysis of each. The root
cause analysis method that may be used that includes the following steps:

1.

Identify the problem

2.

Determine the significance of the problem

3.

Identify the causes (conditions or actions) immediately preceding and surrounding the problem

4.

Identify the reasons why the causes in the preceding step existed, working back to the root cause

(the fundamental reason which, if corrected, will prevent recurrence of these and similar occurrences

throughout the facility).

The primary objective is to determine the direct, contributing and root causes so that effective corrective
actions can be taken that will prevent recurrence.
Initiation of Corrective Action Report (CAR)
Project Personnel
Identify conditions that may warrant a CAR and notify the QA/QC Manager, this is usually accomplished

through normal construction process control procedures.

QA/QC Manager
Evaluate all reported nonconformance/deficiencies reported; reference the monthly trend report section

above. If a CAR is determined to be necessary, initiate form 930 509 F01401 by completing the form

through Part II. The manager responsible for taking the corrective action will assist in preparing Part II.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-08

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Maintain a record of the CAR by completing the Corrective Action Report Log, SA5-DOW-01-08-02 and

send the CAR to the Site Manager.

Construction Manager
Review the CAR and supportive information for concurrence. Make a determination of the adequacy of
the remedial control measures being applied and, if additional control measures are considered

necessary; initiate these through the QA/QC Manager and the manager responsible for taking the

corrective action.

Sign and date the original CAR and return it to the QA/QC Manager.

QA/QC Manager
Forward a copy of the signed CAR to the manager responsible for providing the detailed corrective action

and retain the original.

Responsible Manager
Perform corrective action as specified in the CAR. Notify the QA/QC Manager when corrective action is

completed.

QA/QC Manager
Verify completion of Corrective Action, sign and date Section III. Place completed CAR and attachments

in appropriate records file.

DOCUMENTATION

The QA/QC Manager shall retain the Corrective Action Report and associated attachments in the Quality

Control files.

FORMS

Quality Control Forms:

SA5-DOW-01-08-01

Corrective Action Report

SA5-DOW-01-08-02

Corrective Action Report Log

SA5-DOW-01-08-03

Trend Analysis Investigation Form

ATTACHMENTS
Attachment 1 - Sample Format - Monthly Trend Report

Attachment 2 Response Instruction

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

CORRECTIVE ACTION
REPORT

INDUSTRIA DEL HIERRO S.A. DE


C.V.

Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Sub System:

Fluor

Other

Location:

Date

1.0

Turnover System:

CAR No.

Description Of Deficiency:

Originator

2.0

Result Of Cause Investigation: Estimated Completion Date:

3.0

Corrective Action Required:

Estimated Completion Date:

4.0

Preventive Action Required:

Estimated Completion Date:

Date

QA/QC Manager/Date

Responsible Manager/Date

5.0

Verification of Completed Action

QA/QC Manager/Date

Construction Manager/Date

SA5-DOW-01-08-01
August, 2014

Page 1 of 1

Revision 01

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

CORRECTIVE ACTION REPORT LOG

INDUSTRIA DEL HIERRO S.A. DE C.V.

CAR NO.

DATE

DATE

OPENED

CLOSED

DESCRIPTION

SA5-DOW-01-08-02
August, 2014

Page 1 of 1

Revision 01

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-08-03

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

TREND ANALYSIS INVESTIGATION


Deficiency Group(s) _____________________________________________________________

Finding Reports:

Audit

Surveillance

Nonconformance

1._____________________________________________________________________________

2._____________________________________________________________________________

3._____________________________________________________________________________

4._____________________________________________________________________________

5._____________________________________________________________________________

6._____________________________________________________________________________

Total number of deficiencies in this group:________________

Total number of deficiencies, all groups, during this reporting period:_______________________

_______________________________________________________________________________

Investigation Results:

Identify any CAR's initiated: _____________________________

Investigation Performed by: ______________________________


Title: ______________________________
Date: _____________________________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-08

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

MONTHLY TREND REPORT

GENERAL

Construction activities on-going during reporting period.

Contractors/subcontractors monitored / surveilled during reporting period.

II - NONCONFORMITIES/DEFICIENCIES
PERIOD

DURING

Inspection/Test reports

Surveillances

Nonconformance reports (including subcontractors/contractors)

Audits

Other (includes management/client concerns)

III - TREND
Analysis)

IV -

IDENTIFIED

ANALYSIS

RESULTS

(Reference

CORRECTIVE ACTION REPORTS ISSUED

section

entitled

REPORTING

Monthly

Trend

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-08

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 2

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

CORRECTIVE ACTION
Response Instructions
Corrective Action Report (CAR)
The Responsible Person is required to respond to each CAR within a target of 30 days after
the issue of the CAR. Responses may be provided on the CAR form, or by other written
means. Responses are required to address the following points:
CAR Section 3 Correction of Nonconformity
Provide a detailed explanation of the action that will be taken to resolve the specific
problem identified on the CAR. State when the action has been or will be completed.
Identify other work affected and if additional actions or controls are needed.
CAR Section 4 Corrective Action Section
In addition to correcting the nonconformity, the Responsible Person needs to assess its
severity/impact to see if further analysis is warranted (i.e. determine the root cause and
develop a plan to prevent recurrence).

When evaluating the severity of the nonconformity consideration should be given to its
impact on project cost, schedule or quality issues (e.g. resulting in excessive rework). This
decision is indicated by marking yes or no in section 4 or the CAR.

Root Cause: The underlying reason(s) for the occurrence of the reported nonconformity

will be evaluated and the cause code(s) including an explanation will be stated.

Cause Code

Description

C01

Client Driven

C02

Communication Driven

C03

Equipment or Material

C04

External Phenomenon

C05

Location Driven

C06

Management Driven

C07

Procedure (except procedure not followed)

C08

Procedure/Work Process Not Followed

C09

People Driven

C10

Systems Driven

C11

Work Environment

C99

Other

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-08

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 2

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Plan to Prevent Recurrence: Provide details of corrective actions that have been taken
or will be taken to prevent recurrence of the condition (root cause) that led to the
reported Nonconformity. State when the corrective actions to prevent recurrence have

been or will be completed.


Upon completion, sign and date. If issued electronically, name and date may be typed.

Response Coordination and Processing


Upon completion of sections 3 & 4 of the above reports, route to the QA/QC Manager.
The QA/QC Manager, upon receipt of all responses, provides for follow-up and close-out
where applicable. Closed out CARs (Section 5 Completed) are to be copied to the
Construction Manager.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-09

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev01

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

QUALITY RECORDS

SCOPE

This procedure describes maintenance of construction quality records generated for and/or by construction

subcontractors and/or Industria del Hierro.

GENERAL

Quality records are documented evidence that construction conformed to requirements of the Design

Specifications. Quality records include:

Test and inspection reports

Radiographs

Material and equipment certificates required by specification

Equipment maintenance/preservation records

Designated construction staffs are responsible for the preparation of Quality Control records and are usually

responsible for maintenance and retrievability of the records.

Records that are identified as Confidential in any confidentiality agreement shall be controlled in accordance

with specific procedures established by that agreement.

PROCEDURE

QA/QC Manager
In coordination with the Construction Manager and any other group manager who receives or generates

quality records, identify the quality records that will be retained during construction and identify the

record custodian by job title. Record this information on Form SA5-DOW-01-09-01 (Quality Records

Control).

In coordination with the client and other record custodians, define the Quality records that are to be

submitted to the client upon completion of work and identify this on the Quality Records Control form.

The QA/QC Manager in coordination with the Construction Manager will identify all Quality records (or

copies of records) that will be retained in the Records Retention Center. Identify this on the Quality

Records Control form.

NOTE: Reference Attachment 01 for a sample of a completed Quality Records Control form.

Maintain the Quality Records Control form current and, if possible, before records are received on site or

generated.

Custodian
Establish and maintain a filing system for inspection, testing, and other Quality Control records. The

system shall ensure that records are readily retrievable and protected. The system shall allow the

records required for turnover to be easily separated by turnover packages. The system is to be

identified on the Quality Records Control Form.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-09

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Prior to filing the record the custodian shall review the documents to verify the following:

Documents are appropriate

Documents are complete

Entries are correct

Documents are legible

Documents signed/initialed by authorized person

Review vendor generated documents to verify the records are complete and legible.

The custodian shall resolve any discrepancies noted during the document review with the

originator/originator's supervisor of the document. Resolve any discrepancies with vendor documents

through the Fluor purchasing department.

Corrections to records are accomplished by authorized personnel (i.e. record originator or originator's

supervisor) by striking a single line through the erroneous entry, entering the correct information and

initialing and dating the change.

Turnover
Maintain the records until they are requested by project turnover and/or assigned to the

Records Retention Center.

NOTE: Subcontractors will retain their records until they are requested by Industria del Hierro.

The QA/QC Manager will generate a checklist and verify that all required quality records have

been completed and those designated for turnover are included in the Turnover Package.

All supporting documentation relating to mechanical completion/system turnover will be

retained by Industria del Hierro until system acceptance by Client. After system acceptance by

Client, this documentation will be transferred to Client under separate correspondence.

ATTACHMENTS & EXHIBITS

Attachments
Attachment 01 - Sample Quality Records Control form

Exhibits (Forms):
SA5-DOW-01-09-01 - Quality Records Control

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-09-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

QUALITY RECORDS CONTROL


File
Record Identification

System

Turnover
Package

Custodian

Turnover

Job Title or
Sub Name

Y = Yes

Y = Yes

N = No

N = No

RRC

LOCATOR
Code

Title
Control of Special Process
Calibration Assignment Log
I.M.T.E. Sign In/Out History of Use Log
Nonconformance Report
Nonconformance Report Log
Hold Tag/Sticker
Corrective Action Report
Corrective Action Report Log
Quality Records Control
Audit Finding
Audit Summary
Project Specific Quality Training
Site Contractor Qualification
NDE Contractor Evaluation Record
Surveillance Report
Structural Steel Inspection
Structural Steel Punch List Record
Torque Wrench Calibration Log
Turnover Notice
System Walkdown Notice
Completion Checklist-Civil
Completion Checklist -Electrical/
Instrumentation
Pressure Test Report
Radiographic Request
Weld Repair Request
Weld Repair Request Log
Welder Individual Performance Record
Visual Inspection of Flanges, Gaskets and
Bolting
Open Butt Weld Inspection
Pressure Test Report
Receiving Inspection Checklist
Perm. Plant Mat. & Equip. Inspection List
Insulation Resistance (Instrument Wire and

Cable) Test Record


Conduit and Cable Tray Checklist
Instrumentation Inspection Checklist
Verification Data Sheet
Coating Inspection
Lining Inspection Record

Retention
Period

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-09-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

QUALITY RECORDS CONTROL


File
Record Identification

System

Turnover
Package

Custodian

Turnover

Job Title or
Sub Name

Y = Yes

Y = Yes

N = No

N = No

RRC

LOCATOR
Code

Title

Retention
Period

Thermal Insulation Inspection Weather

Proofing Hot (Pipe and Equipment)

Daily Welding Report


Post Weld Heat Treatment Log
Welder B31.3 Random Radiography
Control Log
Nondestructive Examination Request /

Record
Radiographic Rejectable Defects Statistics
Welding / NDE Status Log
Verification
Testing

of

Training

for

Hardness

Report of Vision Test


Hardness Testing Report
Electrical Punch List Record
Eye Examination

GENERAL NOTES:
Note #1
Note
Note
Note
Note

If the NDE Reports contain data on more than one line, copies of the report shall be placed in each line file to

which it applies.
If radiographs are turned over to the client, maintain the transmittal letter.

This note # is not used for this project.


Reference the Project File Index for Fluor file numbers.
Maintain by Equip. Tag. Number.

#2
#3
#4
#5

FILE LOCATOR CODES:


R1
R3
R5
R7

=
=
=
=

System No.
Equipment No.
By FDCR No.
Line and Sheet

R2
R4
R6

=
=
=

Form No. (by date of completion or alphabetical)


Pour No.

Drawing No.

ACRONYMS:
CEM
CA
NDEC

= Construction Engineering Manager


= Contracts Administrator
= NDE Coordinator

CQM
DE
RRC

= Site (Construction) Quality Manager


= Discipline Engineer
= Records Retention Center

Module Fabrication Quality Manual, SA5-DOW-01-09

The DOW Chemical Company

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Attachment 1

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

QUALITY RECORDS CONTROL (SAMPLE)

Record Identification

Title
Control of Special Process

Custodian
Job Title or

Sub Name

Turnover

System

Turnover

Package

Y = Yes

Y = Yes

N = No

N = No

RRC

File
Locator

Code

Retention

Period

SQM

Calibration Assignment Log

CEM

I.M.T.E. Sign In/Out History of Use Log

SQM

R2

Nonconformance Report

SQM

R2

Nonconformance Report Log

SQM

R2

--

Hold Tag/Sticker

---

--

Corrective Action Report

SQM

R2

Corrective Action Report Log

SQM

R2

Quality Records Control

SQM

R2

Audit Finding

SQM

R2

Audit Summary

SQM

R2

Project Specific Quality Training

R2

SQM

Site Contractor Qualification

CA

R2

NDE Contractor Evaluation Record

CA

R2

Surveillance Report

SQM

R2

Structural Steel Inspection

SQM

R6

Structural Steel Punch List Record

DE

R2

Torque Wrench Calibration Log

SQM

R2

Turnover Notice

CEM

System Walkdown Notice

DE

R1

Completion Checklist-Civil

DE

R1

Completion Checklist -Electrical/


Instrumentation

DE

R1

Pressure Test Report

QCM

R1

Radiographic Request

NDEC

Weld Repair Request

DE

R2

Weld Repair Request Log

DE

R2

Welder Individual Performance Record

DE

R1

R2

R2

(Note 3)

Visual Inspection of Flanges, Gaskets and


Bolting

SQM

R1

Open Butt Weld Inspection

SQM

R1

Pressure Test Report

DE

Receiving Inspection Checklist

SQM

R1

Perm. Plant Mat. & Equip. Inspection List

SQM

R2

Insulation Resistance (Instrument Wire and


Cable) Test Record

SQM

R1

Conduit and Cable Tray Checklist

TS

Instrumentation Inspection Checklist

DE

Verification Data Sheet

DE

Coating Inspection

SQM

Lining Inspection Record

SQM

Thermal Insulation Inspection Weather


Proofing Hot (Pipe and Equipment)

SQM

R2

R1

R1

R1

R1

R1

Module Fabrication Quality Manual, SA5-DOW-01-09

The DOW Chemical Company

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Attachment 1

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Record Identification

Title

Custodian

Turnover

Job Title or

Sub Name

System

Turnover

Package

Y = Yes

Y = Yes

N = No

N = No

RRC

File
Locator

Code

Retention

Period

Daily Welding Report

NDEC

R2

Post Weld Heat Treatment Log

NDEC

R2

Welder B31.3 Random Radiography Control


Log

NDEC

R2

Nondestructive Examination Request / Record

NDEC

R2

(Note 1)

Radiographic Rejectable Defects Statistics

NDEC

R2

Welding / NDE Status Log

NDEC

R2

Verification of Training for Hardness Testing

NDEC

Report of Vision Test

NDEC

R2

Hardness Testing Report

NDEC

R1

DE

R3

NDEC

R2

Electrical Punch List Record


Eye Examination

--

GENERAL NOTES:
Note #1 If the NDE Reports contain data on more than one line, copies of the report shall be placed in each

line file to which it applies.

Note #2 If radiographs are turned over to the client, maintain the transmittal letter.

Note #3 A copies of the radiographic rejectable defects statistics are to be sent to the FCII Manager, Welding

Technology as they are generated.

Note #4 Reference the Project File Index for Fluor file numbers and retention periods.

FILE LOCATOR CODES:


R1
R2
R3
R4
R5
R6
R7

=
=
=
=
=
=
=

System/Work No.

Form No. (by date of completion or alphabetical)

Equipment No.

Pour No.

By FCR No.

Drawing No.

Line and Sheet

=
=
=
=
=
=

Construction Manager

QA/QC Manager

Contracts Administrator

Discipline Engineer

NDE Coordinator

Record Retention Center

ACRONYMS:
CEM
SQM
CA
DE
NDEC
RRC

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-10

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

QUALITY AUDITS

SCOPE

This procedure describes the responsibilities and activities for quality audits of subcontractors and quality

audits of Fluor quality-impacting activities. Audits are performed to determine the effectiveness of the

Module Fabrication Quality Manual and subcontractor quality manual implementation.

GENERAL

Audits described by this procedure are directed at subcontractor and Industria del Hierro self-perform

quality impacting activities that are not under the direct control of the QA/QC Manager.

The QA/QC Manager is responsible for performing these audits. He may self-perform or designate others to

assist with or perform the audits. The procedure section below is based on the audit being performed by an

auditor designated by the QA/QC Manager.

An audit is a planned and documented activity performed to determine, by evaluation of objective evidence,

compliance with the established Module Fabrication Quality Manual and subcontractor quality manual.

PROCEDURE

QA/QC Manager
Establish a schedule for conducting Quality Audits. Refer to Attachments I for schedule examples.
Other formats may be used. The schedule should show the audit dates for all subcontractors or

internal activities to be assessed. Performance on previous audits should influence reaudit schedule.

Develop an audit plan by reviewing the Quality Program (subcontractor's and/or Industria del

Hierros) and identifying the items to be verified. This may be done by marking up an uncontrolled

copy of the procedures or development of a checklist or other methods. It is not necessary to

include activities that are subjected to surveillance (reference Module Fabrication Quality Manual,

Administration Section SA5-DOW-01-14 Surveillance of Construction Activities). Previous audit

results should be considered.

Review and concur with the plan, checklist, marked up procedures or other acceptable method of

identifying items to be verified.

Auditor
Execute the audit in accordance with the established checklist.

When a deficiency is found, investigate to the extent necessary to determine if the deficiency is

isolated. If it is isolated and corrected during the audit, complete steps (1, 2, & 3) of Form SA5DOW-01-10-01 (Audit Finding). Indicate that the deficiency was corrected during the Audit (in Step

4) then sign and date (Step 8) indicating closeout.

If it is not isolated or cannot be corrected during the audit, complete at least through Step 4 as

follows: (The step numbers correspond to the space numbers designated on the form.)

1.

Enter the name of the Contractor or the Industria del Hierro activity being audited as listed on

the Audit Schedule, Attachment 1.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-10

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

2.

Enter the unique audit finding number shown on the schedule.

3.

Enter the date of the audit.

4.

Enter the reference, procedure number, specification number, drawing, etc. and the

requirement that was not complied with.

5.

Describe the deficiency that was noted during the audit.

During and upon completion of the audit, notify the supervisor of the audited area of all deficiencies

found. If a subcontractor is being assessed, verbally inform the subcontractor's representative of all

deficiencies found.

Prepare an audit summary report using (Form SA5-DOW-01-10-02) as an example, summarizing

the audit results, and attach all "Audit Findings" (Form SA5-DOW-01-10-01) and issue the report to

the QA/QC Manager for processing.

Root Cause Analysis

Identify significant findings and conduct and document a root cause analysis of each.
The root cause analysis method that may be used that includes the following steps:

1.

Identify the problem

2.

Determine the significance of the problem

3.

Identify the causes (conditions or actions) immediately preceding and surrounding the

problem

4.

Identify the reasons why the causes in the preceding step existed, working back to the

root cause (the fundamental reason which, if corrected, will prevent recurrence of

these and similar occurrences throughout the facility).

The primary objective is to determine the direct, contributing and root causes so that
effective corrective actions can be taken that will prevent recurrence.
QA/QC Manager
Review and, upon concurrence, sign the audit summary report (From SA5-DOW-01-10-02), attach

all "Audit Findings", and address to the Construction Manager. Review results of the audit.

Additional distribution should be as requested by the Construction Manager.

Maintain files of all audits. These files should include:

Audit Summary with attached Audit Finding Reports and checklist/marked up

procedure.

Copies of objective evidence obtained during the Audit.

Copies of Audit Finding Reports closed upon completion of disposition and verification

and acceptance by an auditor.

QA/QC Manager / Auditee


Assign responsibility for disposition of deficiency and record in Step (5), if it is different from the

proposed disposition, Step (4).

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-10

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Sign and date in Step (6) upon documenting or concurring with the disposition (action taken to

correct the deficiency).

Auditor
Sign and date in step (7) upon acceptance of the disposition.

QA/QC Manager / Lead Auditor


Sign and date in step (7), upon completion and satisfactory verification of action taken to correct

the deficiency.

Generate a status report of all Audit Findings that have not been completed and accepted by the

QA/QC Manager and address it to the Construction Manager.

DOCUMENTATION

Audit summary with attached Audit Findings

Copy of closed audit findings

Root Cause Analysis

ATTACHMENTS & FORMS

Attachments
Attachment 1 - Audit Schedule
Exhibits (Forms)
SA5-DOW-01-10-01 - Audit Finding

SA5-DOW-01-10-02 - Audit Summary

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-10-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

AUDIT FINDING

1)

Project/Contract Number:

Project Name:

Finding Number:
Audit Date:

Auditor(s):
Auditee Personnel Contacted:
2)

A. Reference:

B. Requirement:

Continued on back
3)

Deficiency:

Continued on back
4)

Proposed Disposition:

Expected Completion Date:


5)

Corrective Action Evaluation, and Response:

Disposition (Action taken to correct deficiency)

Completion Date:

6)

Auditee Signature:

Date:

7)

Auditor Concurrence with disposition:

Date:

Continued on back
8)

Auditor Follow-up and Close-out Verification:

Auditor Signature:

Date Deficiency closed:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-10-02

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

AUDIT SUMMARY
Project:

Construction Audit Number:

Client:

Audit Dates:

Project Number:

Report Date:

Audit Location:

Audit Scope:

Summary of Audit Results:

Entry Meeting Date:

Exit Meeting Date:

The entry & exit meeting were conducted with:


A summary of the audit results is as follows:

Quality Manual Principles assessed.

Quality Manual Principles found to be satisfactory.

Deficiencies reported.

Observations for improvement.

Previous Findings and Action Follow-up:

Finding Number

Lead Auditor Signature:

Status (Open or Closed)

Date Closed

Date:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-10

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

Audit Schedule
Audit Number
Scheduled Date
Scope
No

Requirement of System to be verified

1.

Document Structure of the Quality and

Environmental System of the Project

2.

Document and Data Control

3.

Control of Environmental and Quality Records

4.

System Implementation

5.

Internal and External Communication

6.

Competence, Awareness and Training

7.

Contract Revision, Definition of Project Scope,

Services and Resources

8.

Legal Requirements and Others

9.

Environmental Objectives

10.

Project Planning and Control

11.

Project Closing

12.

Communication with the Customer

13.

Design Control

14.

Procurement of Equipment, Materials and

Services

15.

Planning and Control of the Construction

Process and Commissioning

16.

Operational Control

17.

Customer Property

18.

Product Identification and Traceability

19.

Control of Monitoring and Metering Devices

20.

Product Conservation

21.

Customer Guarantees

22.

Emergency Preparation and Response

23.

Internal Quality and Environmental Audits

24.

Environmental Monitoring

25.

State of Inspection and Testing

26.

Non Complying Product Control

27.

Data Analysis

28.

Corrective and Preventive Actions

EXECUTED BY

APPROVED BY

QA/QC Manager

Project Manager

Module Fabrication Quality Manual, SA5-DOW-01-10

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

June, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Attachment 1

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

Audit Schedule
Audit Number
Scheduled Date
Scope
No
1.

Requirement of System to be verified

IA-D-01

IA-D-02

September-2014

January-2015

Quality System

Warehouses

System Procurement

Quality System

Fabrication

Process

IA-D-03
May-2015

Fabrication

Process
Mechanicals

Compliance

Document Structure of the Quality and

Environmental System of the Project

2.

Document and Data Control

3.

Control of Environmental and Quality Records

4.

System Implementation

5.

Internal and External Communication

6.

Competence, Awareness and Training

7.

Contract Revision, Definition of Project Scope,

Services and Resources

8.

Legal Requirements and Others

9.

Environmental Objectives

10.

Project Planning and Control

11.

Project Closing

12.

Communication with the Customer

13.

Design Control

14.

Procurement of Equipment, Materials and

Services

15.

Planning and Control of the Construction

Process and Commissioning

16.

Operational Control

17.

Customer Property

18.

Product Identification and Traceability

19.

Control of Monitoring and Metering Devices

20.

Product Conservation

21.

Customer Guarantees

22.

Emergency Preparation and Response

23.

Internal Quality and Environmental Audits

24.

Environmental Monitoring

25.

State of Inspection and Testing

26.

Non Complying Product Control

27.

Data Analysis

28.

Corrective and Preventive Actions

X = Action

O = No Action

EXECUTED BY

APPROVED BY

QA/QC Manager

Project Manager

Module Fabrication Quality Manual, SA5-DOW-01-11-01

August, 2014 - Rev.01

PROJECT QUALITY TRAINING

EXTERNAL

INTERNAL

PLACE

TRAINING
START DATE

FINISH DATE

START TIME

NAME ATTENDEES

FINISH TIME

EMPLOYEE

NUMBER

JOB TITLE

TOTAL DURATION

DISCIPLINE

MANAGEMENT / COMPANY

ATTENDEE

4
5

10

11

12

13

INSTRUCTOR NAME AND SIGNATURE

COORDINATOR NAME AND SIGNATURE

TOTAL

HRS

SIGNATURE

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-11

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

PERSONNEL TRAINING AND QUALIFICATION

SCOPE

This procedure identifies training in the field quality system requirements for personnel performing construction

activities that affect quality. It covers the methods used for the analysis of supplemental training needs. The

procedure also makes provisions for subsequent qualifications and certification (when required).

GENERAL

Training and orientation are important due to the need for clear definition, communication and understanding of

work requirements that are essential to all construction work processes.

This training is in addition to the routine orientation of quality requirements provided through daily contact and

periodic meetings such as construction planning/review meetings.

PROCEDURE

Project Training Plans:


QA/QC Manager
Develop a training outline targeted at site management and staff members for orientation to this site

quality program.

Notes: This target group should include the Construction Manager, Area Managers, Superintendents and

others as determined by the Project Manager. The Project Manager may elect to invite client

representatives, especially those having a direct interface with the site quality program.

Training for the site management group should provide an overview of Inspection and Testing

Procedures for all disciplines and in depth training in all other sections of this Module Fabrication

Quality Manual.

Develop a training outline, by discipline, targeted at craft personnel for orientation to this site quality

program.

Notes: The target group should include the craft, foremen, general foremen, and superintendents.
Training for the group should provide in depth training in the Inspection and Testing procedures.

It should provide an overview of the other sections of this Module Fabrication Quality Manual.

Determine the training needed for site personnel requiring certifications.


QA/QC Manager/Construction Manager
Develop training outline for training needs identified by procedure SA5-DOW-01-08 "Corrective Action."

Project Training Schedules:

QA/QC Manager

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-11

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Develop site training schedule.

Obtain Project Manager Approval of training schedule. Reschedule training session, as needed, as

additional personnel are assigned to the project.

Provide for instructor, facilities and equipment support.

Instructor
Document the personnel attending on Form SA5-DOW-01-11-01 and attach the Training Outline.

DOCUMENTATION

The QA/QC Manager shall maintain or have maintained all training records in the site project/quality files. Copies

of the records for training of quality personnel for certification purposes shall be forwarded to the FCII Director,

Quality.

FORM

SA5-DOW-01-11-01 - Project Quality Training

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

Module Fabrication Quality Manual, SA5-DOW-01-12

August, 2014 Rev.01

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

SITE SUBCONTRACTOR QUALIFICATION

SCOPE

This procedure describes the initial qualification of site subcontractors. This procedure does not apply to

subcontractors that have been previously approved by Industria del Hierro or the Client/Owner.

GENERAL

When qualifications of site subcontractors include an evaluation of the QC capabilities of the subcontractor,

the evaluation shall be done in accordance with this procedure.

PROCEDURE

Qualification of Subcontractors
Subcontracts Manager
Upon selection of a proposed subcontractor, the Subcontracts Manager shall notify the QA/QC

Manager and request that subcontractor qualification be performed. When Industria del Hierro

construction has designated a person to technically supervise the proposed subcontractor, he/she

shall also be notified.

NOTE: The Subcontracts Manager shall contact the subcontractor relative to obtaining documents,

arranging communications or scheduling meetings and/or visits.

QA/QC Manager/Technical Supervisor

Upon notification (including receipt of subcontractor quality programs), review the

qualifications of the proposed subcontractor based upon the quality requirements to be

included in the Industria del Hierro subcontract. This review may include meetings and/or

visits with the subcontractor candidate.


The QA/QC Manager may use the "Site

Subcontractor Qualification" guidelines (Form SA5-DOW-01-12-01); however, this guide

does not necessarily represent the quality requirements to the subcontractor and therefore

should be used only as an aid to the evaluation.

Upon completion of the subcontractor qualification review, notify the Subcontracts Manager

of the results of the review and perform the actions stated below (as appropriate):

If the subcontractor is not qualified, write a memo to the Subcontracts Manager fully

explaining the exact deficiencies that are required to be corrected along with the specific

recommendations.

If the subcontractor is qualified, complete the "Site Subcontractor Qualification" form and

evaluation record and forward to the Subcontracts Manager.

If the subcontractor is "conditionally" qualified, complete and forward the "Site

Subcontractor Qualification" form as above, however include the specific limitations and/or

actions that will be required.

Process contractor qualification documents in accordance with procedure SA5-DOW-01-04

(Document Control) and procedure SA5-DOW-01-10 (Quality Records).

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

DOCUMENTATION
The subcontractor evaluation records shall be maintained as quality records in accordance with site

procedures.

FORMS

Quality Control Forms:

SA5-DOW-01-12-01

- Site Subcontractor Qualification

SA5-DOW-01-12-02

- NDE Subcontractor Evaluation Record

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 9

INDUSTRIA DEL HIERRO S.A. DE C.V.

SITE SUBCONTRACTOR QUALIFICATION


PROJECT NAME

PROJECT NUMBER

SUBCONTRACTOR

RFP NUMBER

ADDRESS
CITY, STATE, ZIP

P.O. NUMBER

SCOPE OF SUBCONTRACTED WORK

SUBCONTRACTOR QUALITY REP.


(1ST IN CHARGE)

TITLE

PHONE

FAX

SUBCONTRACTOR QUALITY REP.


(2ND IN CHARGE)

TITLE

PHONE

FAX

QUALITY MGMT. REPORTS TO

TITLE

QUALIFICATION APPROVAL

APPROVED

"CONDITIONALLY" APPROVED

NOT APPROVED

REQUIRED ADDITIONAL ACTIONS

EXPLAIN "CONDITIONAL APPROVAL" HERE. CONSIDER ESPECIALLY THE ADDITIONAL COST IF THE____
SUBCONTRACTOR WILL NEED ASSISTANCE IN OPERATION OF THE QUALITY PROGRAM.________________

QA/QC MANAGER

DATE

SUBCONTRACTS MANAGER

DATE

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 9

INDUSTRIA DEL HIERRO S.A. DE C.V.

1.0

2.0

3.0

ORGANIZATION
1.1

Does the subcontractor have a quality control organization?

__________

1.2

Is an organization chart available?

__________

1.3

Does inspection have sufficient authority within the overall organization?

__________

1.4

Is inspection adequately organized and staffed to exercise its responsibilities?_________

1.5

Are inspection reporting channels adequate?

__________

QUALITY PROGRAM
2.1

Does the subcontractor have a quality manual?

__________

2.2

Is the quality manual approved and signed by management?

__________

2.3

Does the subcontractor's management periodically review their Quality


program for effectiveness?

__________

2.4

Are there written procedures or instructions other than the Quality Manual?

__________

2.5

Does the subcontractor have an established and adequate training program for
their personnel?
__________

2.6

Is the program compliant with international quality standards?

__________

DESIGN CONTROL
3.1

3.2

Does the subcontractor have a design plan or procedure that:

1.

Provides for consideration of the design criteria and requirements?

__________

2.

Lists all design documents required, e.g., drawings and specifications?_________

3.

Identifies design responsibilities?

__________

4.

Provides for the inclusion of acceptance criteria?

__________

Does the subcontractor have a procedure for the review and control of design documents

that:
1.

Designates responsibility for design review?

__________

2.

Provides a method of design change control?

__________

3.

Provides for the review of design changes and field changes by responsible
personnel?
__________

3.3

Is design reviewed for suitability of material and processes?

__________

3.4

Are the current revisions of the design documents known and available to
engineering?

__________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 9

INDUSTRIA DEL HIERRO S.A. DE C.V.

4.0

5.0

3.5

Is the results of the design verification resolved according to a controlled and


operative plan?
__________

3.6

Do design changes and corresponding document changes receive an adequate


design verification?
__________

3.7

Is there a mechanism to incorporate field operations and requirement changes


into the design documents?
__________

3.8

Is the design document release to purchasing and/or construction/manufacturing,


controlled and adequate?
__________

3.9

Are required subcontractor documents clearly identified?

3.10

Is the review of required subcontractor documents formalized as a procedure?__________

__________

PROCUREMENT DOCUMENT CONTROL


4.1

Is there an adequate procedure in use for Procurement Document Control?

4.2

Is each procurement document reviewed for the following:

__________

1.

Subcontractor's Quality requirements to their vendors?

__________

2.

Customer's Quality requirements to contractor's vendors?

__________

3.

A check for latest revision of drawings, specification, codes, etc.?

__________

4.

Special packaging and preservation requirements?

__________

5.

Special tests or certifications?

__________

6.

Provisions for audits by subcontractor and/or customer?

__________

7.

A check for the inclusion of design criteria of basis?

__________

8.

Source Inspection requirements?

__________

INSTRUCTIONS, PROCEDURES AND DRAWINGS


5.1

Does subcontractor have a documented system of instructions, procedures


and drawings?

__________

Do instructions, procedures and drawings identify all documents necessary


to perform the work, i.e., codes, standards, etc.?

__________

5.3

What is the approval plan for deviations? Describe

__________

5.4

Do instructions and procedures provide hold points where the documentation


of conformance is provided?
__________

5.5

Do instructions, procedures and drawings exist at work locations?

5.2

__________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 4 of 9

INDUSTRIA DEL HIERRO S.A. DE C.V.

6.0

DOCUMENT CONTROL
6.1
6.2

7.0

8.0

Does subcontractor have a procedure for approval and issue?

__________

Does document control include:

1.

Drawings?

__________

2.

Specifications?

__________

3.

Instructions?

__________

4.

Procedures?

__________

6.3

Is distribution of documents controlled by procedures?

__________

6.4

Are revisions to documents controlled by procedures?

__________

6.5

Are mark-up documents used?

__________

CONTROL OF PURCHASED MATERIAL, EQUIPMENT AND SERVICES


7.1

Are sub-tier suppliers currently evaluated?

__________

1.

Are there adequate procedures in use to define sub-tier supplier quality


requirements?

__________

7.2

Is a survey performed before qualifying a new supplier?

__________

7.3

Does the system provide for audits of supplier's inspection program?

__________

7.4

Is there an approved supplier's list?

__________

7.5

Does subcontractor require his sub-tier suppliers to furnish material certification


and/or inspection reports?
__________

7.6

Does subcontractor perform receiving inspection activity?

__________

IDENTIFICATION AND CONTROL OF MATERIALS, PARTS AND COMPONENTS


8.1

Does the subcontractor have procedures for identification of materials,


parts and components?

__________

8.2

Does the program provide controls to prevent mix of materials?

__________

8.3

Are materials in process traceable to manufacturer's heat treatment number,


lot number or other material where required?
__________

8.4

Does the program provide for specific traceability to piece, part or component?__________

8.5

Is the inspection status of material, part of component easily identified?

__________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 5 of 9

INDUSTRIA DEL HIERRO S.A. DE C.V.

9.0

10.0

CONTROL OF SPECIAL PROCESSES


9.1

Is there an adequate procedure in use to control qualification of special processes?_________

9.2

Are procedures available and adequate for the qualification of special processes
personnel?
__________

9.3

Do procedures identify methods by which measurements will be made,


current, temperature, etc.?

9.4

Do procedures provide for documentation of parameters?

__________

9.5

Are the procedures available at work locations for special processes?

__________

e.g.,
__________

INSPECTION
10.1

10.2

10.3

Are general procedures written for:

1.

Receiving Inspection?

__________

2.

In-Process Inspection?

__________

3.

Final Inspection?

__________

Do written inspection instructions provide inspection personnel with:

1.

Measuring equipment required?

__________

2.

Parameters to be inspected?

__________

3.

Criteria for determining quality conformance or rejection?

__________

4.

Specification of the environment for the inspections (e.g., temperature


controlled, etc.)?
__________

5.

Identification of inspection hold points?

__________

Are purchase orders, drawings, specifications, etc. available to inspection


personnel?

__________

10.4

Is inspection documented by work order, shop traveler, history record, etc.? __________

10.5

Is nonconforming material properly identified and segregated to prevent


unauthorized use?

__________

10.6

Are provisions adequate to permit the customer to designate hold points for
inspections?
__________

10.7

Do source and receiving inspection procedures provide for the


storage and preservation of materials and equipment?

10.8

Is adequate inspection and test equipment available?

proper handling,
__________

__________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 6 of 9

INDUSTRIA DEL HIERRO S.A. DE C.V.

11.0

12.0

10.9

Are inspection procedures and/or instructions reviewed and approved by higher

authority than initiator prior to release?


__________

10.10

Are personnel performing inspections different than those that performed the
activity being inspected?
__________

TEST CONTROL
11.1

Are there written test procedures in existence and used?

__________

11.2

Are accept-reject criteria specified in the test procedure?

__________

11.3

Does procedure provide a list of test instruments to be used?

__________

11.4

Are test results documented and maintained?

__________

11.5

Does inspection perform testing?

__________

11.6

Are there provisions in procedures to permit customer to witness tests?

__________

CONTROL OF MEASURING AND TEST EQUIPMENT


12.1

Does the subcontractor have a program for calibration of inspection and


test instruments?

__________

Does subcontractor have a calibration laboratory or approved source for


calibration of inspection and test instruments?

__________

12.3

Are all inspection and test instruments uniquely identified?

__________

12.4

Are calibration dates and re-calibration due dates marked on tools and instruments?________

12.5

Are tool and instrument record cards maintained?

__________

12.6

Are calibration standards traceable to the N.I.S.T.?

__________

12.7

Does the program assure removal from service of equipment that has exceeded
calibration period?
__________

12.8

Are inspection equipment and calibration standards properly handled and


protected?

12.2

13.0

__________

HANDLING STORAGE AND SHIPPING


13.1

Are there written procedures that describe proper handling of material?

__________

13.2

Are there written procedures that describe proper storage of materials?

__________

1.

Do the procedures specify preservation and environmental conditions


to be maintained during storage?
__________

2.

Are materials stored in such a manner as to

prevent damage?

__________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 7 of 9

INDUSTRIA DEL HIERRO S.A. DE C.V.

13.3
14.0

4.

Is material, having service life, properly dated, stored and rotated in


stock for control of shelf life?
__________

5.

Are obsolete items purged from the stock area periodically?

__________

6.

Are corrosive, toxic or flammable materials properly stored and


segregated?

__________

Is there adequate procedure in use which controls shipping activity?

__________

__________

Are there controls that permits determination of inspection and test status? __________

14.2

Are shop travelers or tags used to show status of inspection or tests?

__________

14.3

Do shop travelers or tags have sign offs at each inspection station?

__________

14.4

Are inspection stamps used?

__________

14.5

Does inspection and test status information become part of final quality
documentation?

__________

NONCONFORMING MATERIALS, PARTS OR COMPONENTS


15.1

Is a written procedure(s) available for the identification and control of


nonconforming items.

__________

15.2

Does procedure(s) specify the identification to be used on item?

__________

15.3

Are nonconforming items segregated and adequately controlled to prevent


their use?

__________

Is there a procedure for advising customer of all nonconformances that are


applicable to the customer's orders?

__________

15.4

16.0

Are storage facilities adequate for the type of materials stored?

INSPECTION AND TEST STATUS


14.1

15.0

3.

CORRECTIVE ACTION
16.1

Is there an adequate procedure in use for control of the corrective action program?_______

16.2

Are causes of deficiencies identified?

16.3

Is there approved documentation for the disposition of the item, scrap, repair
acceptance, etc.?
__________

16.4

Is there a follow-up system to assure expedient response to corrective action


requests?
_________

16.5

Are corrective action summaries reported to management?

16.6

Are records of nonconformity and approved disposition traceable to the item?__________

__________

__________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12-01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 8 of 9

INDUSTRIA DEL HIERRO S.A. DE C.V.

16.7

17.0

Are provisions made for the prompt action on customer's comments resulting from
inspections and audits?
__________

QUALITY RECORDS
17.1

Is there a procedure/system identifying what records are to be maintained? __________

17.2

Are records maintained covering:

1.

Supplier Surveys?

__________

2.

Inspection (Receiving, In-Process, Final)?

__________

3.

Material (plus certification)?

__________

4.

Audits?

__________

5.

Inspection Reports?

__________

6.

Inspection Instructions?

__________

7.

Test Records?

__________

8.

Test Logs?

__________

9.

Failure Reports?

__________

10.

Special Process Certification?

__________

11.

Procedure Qualifications?

__________

12.

Personnel Qualification (NDE, etc.)?

__________

13.

Personnel Qualification - Welding?

__________

14.

Other

__________

17.3

Does the system provide for review of final data packages prior to shipment
of equipment?
__________

17.4

Are record locations defined?

__________

17.5

Are retention periods defined?

__________

17.6

Is disposition of records defined?

__________

17.7

Does the system provide for storage of radiograph film to prevent deterioration
and loss?
__________

17.8

Is customer release obtained before Quality records are destroyed?

__________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-12-01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 9 of 9

INDUSTRIA DEL HIERRO S.A. DE C.V.

18.0

AUDITS
18.1

Is there an adequate procedure/system defining the audit program?

__________

18.2

Is there a planned schedule?

__________

18.3

Is there a checklist provided for each audit?

__________

18.4

Is there a detailed report required for each audit?

__________

18.5

Is follow-up action prescribed (i.e., re-audit of deficient areas)?

__________

18.6

Are there internal quality system audits of:

18.7

1.

Receiving Inspection?

__________

2.

In-Process Inspections?

__________

3.

Final Inspections?

__________

4.

Quality Control Records?

__________

5.

Nonconforming Material Control?

__________

6.

Corrective Action Systems?

__________

7.

Calibration of Inspection Tools and Instruments?

__________

8.

Materials Control?

__________

9.

Drawing and Procedure Control?

__________

10.

Design Control?

__________

11.

Special Processes?

__________

12.

Packaging and Shipping Inspections?

__________

13.

Other

__________

Are audit reports reviewed by management?

__________

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

PROJECT:

COMPANY:

LOCATION:

DATE OF
REVIEW:

REVIEWED BY:

PERSONNEL
CONTACTED:

NDE SUBCONTRACTOR
EVALUATION RECORD

SA5-DOW-01-12-02

August, 2014

Page 1 of 9

Revision 01

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

NDE SUBCONTRACTOR
EVALUATION RECORD

INDEX

1.0

INSTRUCTIONS

2.0

GENERAL
2.1

3.0

NDE METHODS
2.2

PERSONNEL TRAINING AND CERTIFICATION

2.3

QUALITY ASSURANCE PROGRAM

2.4

MANAGEMENT

2.5

NDE PROCEDURES

2.6

RADIOACTIVE MATERIALS LICENSE

2.7

EXPERIENCE HISTORY

SPECIFIC
3.1

NDE METHOD

4.0

CONCLUSION AND REMARKS

5.0

RECOMMENDATIONS

SA5-DOW-01-12-02

August, 2014

Page 2 of 9

Revision 01

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

1.0

NDE SUBCONTRACTOR
EVALUATION RECORD

SA5-DOW-01-12-02

August, 2014

Page 3 of 9

Revision 01

INSTRUCTIONS
1.1

This evaluation is the responsibility of the QA/QC Quality Manager or others


qualified to review nondestructive examination contractors.

1.2

The space to the right of each statement in this document should be completed

with one, two, or three word answers, such as: Yes, No, Satisfactory,
Unsatisfactory or, Does Not Apply, etc.

1.3

If any function of the NDE contractor has not been inspected, indicate to the

right of the appropriate statement by NR (Not Reviewed).

1.4

If additional comments are necessary, use the space available under each

individual statement.

1.5

The conclusions drawn by the examiner should be based only upon observations

and documentation noted in the body of the report.

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

2.0

NDE SUBCONTRACTOR
EVALUATION RECORD

GENERAL
NDE Method Capabilities

Radiography

Magnetic Particle

Other

Ultrasonic

Visual (CWI)

Other

Liquid Penetrant

Eddy Current

Other

2.1

2.2

2.4

Personnel Training and Certification


2.1.1

Does subcontractor have a written practice for the qualification and


certification of NDE personnel?

2.1.2

Does written practice utilize SNT-TC-1A as the basis for the program?

2.1.3

Does written practice properly address examinations required for each


level of certification?

2.1.4

Does initial experience fulfill the requirements of SNT-TC-1A?

2.1.5

Does initial training fulfill the requirements of SNT-TC-1A?

Quality Assurance Program


2.2.1

Does subcontractor have an adequate QA program manual for the


performance ASME Code NDE activities?

2.2.2

List all unsatisfactory portions of subcontractors quality manual.

MANAGEMENT
2.4.1

List key management / supervision personnel and areas of


responsibility:

2.4.2

List NDE Level III personnel certified by examination. Add ASNY

SA5-DOW-01-12-02

August, 2014

Page 4 of 9

Revision 01

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

NDE SUBCONTRACTOR
EVALUATION RECORD

SA5-DOW-01-12-02

August, 2014

Page 5 of 9

Revision 01

certificate number if applicable.

2.4.3

2.5

Does subcontractor have records of specific examinations


administered to Level III personnel certified on the basis of ASNT
examination?

NDE PROCEDURES
2.5.1

Does subcontractor have written procedures for all NDE methods that
will be performed?

2.5.2

How does subcontractor ensure that procedures are updated to


reflect the Code requirements?

2.5.3

Do procedures allow interpretation for acceptance by Level I


personnel?

2.5.4

List Codes and Standards that subcontractors procedures reference:


(except Section I and II)

2.5.5

Does subcontractor have an operating and emergency procedure for


radiographic equipment/work?

2.5.6

What formal radiation training is required for radiographic examination


personnel?

2.5.7

Will subcontractor agree to submit all applicable NDE procedures and

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

NDE SUBCONTRACTOR
EVALUATION RECORD

report forms to FCII for review and authorization?

2.6

RADIOACTIVE MATERIALS LICENSE


Number: ________________________________________________
Approved for: ____________________________________________
Number of Isotopes: _______________________________________

2.7

EXPERIENCE HISTORY
2.7.1

List all past and present work in non-nuclear NDE (include summary
methods performed)

SA5-DOW-01-12-02

August, 2014

Page 6 of 9

Revision 01

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

3.0
3.1

NDE SUBCONTRACTOR
EVALUATION RECORD

SA5-DOW-01-12-02

August, 2014

Page 7 of 9

Revision 01

SPECIFIC
NDE METHOD
3.1.1

Number of certified Level II personnel:

3.1.2

Number of certified Level I personnel:

3.1.3
3.1.4

Number of trainee personnel:


List all applicable equipment (Type, MFG and QTY) used to perform
examinations, obtain results and verify adequacy of test methods.

3.1.5

List all equipment requiring calibration and length of calibration validity:

3.1.6

Describe general condition of equipment:

3.1.7

Additional Comments:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

4.0

NDE SUBCONTRACTOR
EVALUATION RECORD

SA5-DOW-01-12-02

August, 2014

Page 8 of 9

Revision 01

CONCLUSIONS AND REMARKS

The agency does have adequate facilities and qualified personnel to perform the work required
by Industria del Hierro in accordance with contract specifications:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

5.0

RECOMMENDATIONS

NDE SUBCONTRACTOR
EVALUATION RECORD

SA5-DOW-01-12-02

August, 2014

Page 9 of 9

Revision 01

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 7

INDUSTRIA DEL HIERRO S.A. DE C.V.

CONTRACTOR QUALITY REQUIREMENTS

PURPOSE

This practice is for use in establishing Contractor responsibility for Quality Control.

SCOPE

This practice establishes the requirements for Site Contractors.

APPLICATION

This practice should be applied in preparation of the RFP (Request for Proposal) when documented test results

and/or in-process inspection results of Contractor's Work are required, as determined by the Project Manager or

representative.

DEFINITIONS

RFP: Request for Proposal - the inquiry document used to obtain price and schedule information on a

competitive basis for the services required in Industria del Hierro's performance on projects.

Quality Plan for Contractor's Work: A plan that identifies the activities and responsibilities for delivering,

measuring, and documenting compliance to the quality requirements of the contracted work.

QA/QC Manager: The project assigned individual responsible for on-site quality during the Module Fabrication

phase.

Quality Program for Contractor's Work: Established quality implementing procedure for inspection/testing

of the work, including forms for documenting same.

GENERAL

Contractor is responsible for providing services and performing work in accordance with the design and quality

requirements as required by their contract. Industria del Hierros approach to construction management

contracting normally requires each Contractor to staff and perform the inspection activities, with Industria del

Hierro performing surveillance over the Contractor activities.

Based on the capability of Contractor, information obtained during pre-qualifications of Bidders, and project

management preference, Industria del Hierro may elect to either provide the QC procedures to the Contractor

or require the Contractor to provide the procedures. Industria del Hierro also may elect to perform the

inspection.
This practice makes provisions
Attachments, when included in
be required. The Attachments
the Quality Plan for Contractors

for each of the above options by use of Attachments 01 through 05. The

the RFP, provide the Bidder with a description of the quality system that will
plus the Bidders response, when agreed to by Industria del Hierro, become

Work and will become part of the successful Bidders contract.

The following sections of this Practice describe the minimum requirements of Contractor's Quality Control

System for this Scope of Work. The inspections, tests and related actions specified in this section and

elsewhere in the Contract are not intended to limit Contractor's own quality assurance/control procedures that

facilitate overall compliance with requirements of the Contract. Contractor may use its own QA/QC procedures

provided such procedures have been reviewed and accepted by Industria del Hierro prior to start of Work.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 7

INDUSTRIA DEL HIERRO S.A. DE C.V.

The Contractors procedures must address, as a minimum, the information contained in the applicable

attachments to this practice that were included in the Contract.

Quality Control Program

Basic objectives of Contractor's Quality Control (QC) System shall be as follows:

To ensure that all work adheres strictly to all requirements of the Contract and

governing agencies where the work is being performed.

To maintain QC procedures to ensure that tasks performed will comply with the

Contract.

To prevent deficiencies through pre-construction quality control coordination.

To detect and correct deficiencies in a timely manner.

To provide an auditable record of all tests, inspections, procedures, noncompliance and corrections, and any other pertinent data as required.

Verify compliance with Contractors QC


procedures of subcontractors and suppliers.

To provide a basis of measuring Contractors performance for input to Industria

del Hierro Contractor Resource Database.

procedures,

including

those

QC

The Contractor may select either an outside "agency" or in-house personnel to

administer Contractors QC System. In either case, the Contractors on-site Quality


Control staff shall only be responsible for Quality Control. The QC Supervisor (or

person designated as the QC Representative) shall report directly to Contractor's Site

Manager. The Contractors QC staff shall not be involved in the management and/or

control of the construction process. Contractors QC staff members shall interface


with Industria del Hierro, Consultants, as required.

Testing Criteria

Contractor shall perform all testing and inspection of all Work (including materials)

both on and off site as required by the Contract.

Criteria for acceptance are specified in the Contract.

QC Agencies - Selection and Qualification

Contractor shall, if applicable, obtain the services of an accredited Nondestructive


Examination Sub-contractor to perform the tests and examinations required by the
Contract.

Inspectors employed by Contractor's Inspection and Testing Agency shall be specially

qualified to perform required inspection services for the particular classification of

work to be inspected and shall be certified as required by the Contract or governing

agencies where the work is being performed.

Responsibilities of the Contractors QC Supervisor (Representative)

Responsibilities and duties of the Contractors QC Supervisor are:

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 7

INDUSTRIA DEL HIERRO S.A. DE C.V.

To communicate these minimum QC requirements to any suppliers and/or

subcontractors.

To have the authority to stop Work for cause, reject Work, order Work removed,
initiate remedial Work, propose solutions, and reject material not in compliance

with the Contract.

Be present on-site during working hours and assigned "full time" to this Contract.

Contractor shall designate alternate individual(s) to assume responsibilities in the

temporary absence of the QC Supervisor.

Be completely
Specifications.

Establish and implement QC Programs for Contractor and with its various

subcontractors, and monitor their conformance.

Inspect existing conditions prior to the start of new Work segments.

Conduct a pre-construction Quality Control meeting with Contractors responsible

field and office representatives prior to the start of each major item of work
required by the Contract.

Perform in-process and follow-up inspections on each of the work segments to

ensure compliance with the Contract. Upon request, accompany Industria del

Hierro on such inspections.

Coordinate required test, inspections, and demonstrations with Industria del

Hierro or any other authority having jurisdiction. Assure work is accessible for

test or inspection.

Inspect Contractor purchased materials and equipment arriving at the Site to

ensure conformance to the requirements of the Contract. Prepare and submit


documentation as required by the Contract.

Inspect material free-issued to Contractor by Industria del Hierro to ensure

conformance to the requirements of the Contract. Contractor must provide


immediate notification to Industria del Hierro when materials are found to be

damaged or nonconforming.

Identify, report and reject defective Work not in conformance with the Contract.

Monitor the repair or reconstruction of rejected Work and document corrective

action, including all remedial action taken to prevent the re-occurrence of the

defective Work.

If necessary, retain specialists or subcontractors for inspection of Work in areas

where additional technical knowledge is required (mechanical, electrical,

electronics, controls, communications, welding, structural, etc.). Submit

qualifications of subcontractors and specialists to Industria del Hierro for

approval.

Schedule and accompany Industria del Hierro on any Site visits when requested.

Work closely with Industria del Hierro to ensure optimum Quality Control. Attend

meetings as required by Industria del Hierro.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

familiar

with

the

Contract

Scope

of

Work,

Drawings

and

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 4 of 7

INDUSTRIA DEL HIERRO S.A. DE C.V.

Submittals

Contractor shall submit reports detailing the results of each test and describing each

inspection. Submit separate reports for each test and inspection procedure

immediately upon completion of each procedure and test. General QC Requirements

Inspection and test reports, as a minimum, shall include:

Date issued

Date of inspection or test

Project title and number

Testing agency name and address

Name and signature of the inspector/tester

Identification of the product and applicable specification section

Type inspection or test

The results as related to requirements.

Inspection, Measuring and Test Equipment

The Contractor shall provide and maintain all measuring and testing devices.

Laboratory devices shall be calibrated as required by Contract. The standards against

which the measurement equipment is periodically calibrated shall have their accuracy

verified directly by, or through a precise comparison with standards traceable to the

National Institute of Standards and Technology or to a recognized national or

international standard.
EXECUTION

Contractor's inspection shall be adequate to cover all operations, including both

on-site and off-site and will be keyed to the proposed sequence of the Work and shall
include as a minimum at least four (4) phases of inspection for all definable items or

segments of the Work, as follows:

Preparatory Inspection: To be performed prior to beginning any Work on any

definable segment of the Work and shall include:

A review of Contract requirements

Verification that all materials and/or equipment have been tested, submitted,

and accepted

Verification that provisions have been made to provide required control

testing

Examination of the Work area to ascertain that all preliminary Work has been

completed

A physical examination of materials and equipment to assure that they

conform to accepted shop drawings or submittal data and that all necessary

material and/or equipment are available.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Module Fabrication Quality Manual, SA5-DOW-01-13

August, 2014 Rev.01

Page 5 of 7

INDUSTRIA DEL HIERRO S.A. DE C.V.

As a part of this preparatory Work, Contractor's organization will review and

verify that all documents, including but not limited to, shop drawings, submittal

data, method of Quality Control, product data sheets, test reports, affidavits,

certification and manufacturer's instructions have been submitted and accepted

by Industria del Hierro as required herein. Each submittal to Industria del Hierro
shall bear the date and the signature of the Contractor's Quality Control Manager

(or authorized designee) indicating that a review of the submittal and certify it to

be in compliance with the Contract Drawings and Specifications or showing the

required changes.

Initial Inspection: To be performed as soon as a representative segment of the

particular item of Work has been accomplished and to include: examination of the

quality of workmanship and a review of control testing for compliance with

Contract requirements; exclusion of defective or damaged materials, omissions;

and dimensional requirements.

Follow-up Inspection: To be performed daily or more frequently as determined to

be necessary to ensure continuing compliance with the Contract requirements,

including control testing, until completion.

Final Inspection: To be conducted when the Work is substantially complete.

Contractor shall inspect the Work for quality, workmanship and completeness

prior to notification that the item or segment of the Work has been completed.

Specific tests and inspection procedures (including documentation) for each material

or item of Work are specified in the Contract.


Contractors Testing Laboratory shall perform tests according to method(s) of testing

specified in the Contract.

Where the Specifications or applicable Codes stipulate that a material shall conform

to the American Society for Testing Materials (A.S.T.M.) specifications or other

recognized standards, Contractor shall deliver an affidavit or certificate in triplicate,

signed by the manufacturer or supplier that the material furnished conforms to

specifications or standards mentioned. When tests are required, the results of such

tests shall be delivered at no additional cost.

Contractor shall ensure that all work that does not comply with the requirements and
references specified in the Contract scope of work is identified and correctly

dispositioned. All Work installed or fabricated by the Contractor shall be inspected

(i.e., punched) and resolved prior to notifying Industria del Hierro the Work is ready

for final acceptance inspection. Contractor shall record all punch list items (i.e.,
deficiencies) on a punch list record. Material or equipment that is supplied by

Industria del Hierro or Owner, and is found by Contractor to have deficiencies, is to

be immediately identified to Industria del Hierro for corrective action.

Contractor shall not render any Work as inaccesible until all inspections and test have

been completed and accepted by all involved parties, including Industria del Hierro

and the Owner. Any Work that is rendered inaccesable prior to inspection and test by

all involved parties may be made accessible for inspection and test at the Contractors
expense.

Contractor shall package and prepare all inspection and testing documentation for

turnover at the completion of construction. Contractor shall develop turnover

packages, by system as determined or mutually agreed by Industria del Hierro. Each

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Module Fabrication Quality Manual, SA5-DOW-01-13

August, 2014 Rev.01

Page 6 of 7

INDUSTRIA DEL HIERRO S.A. DE C.V.

system file will contain all field inspection and testing records for the components of

the system. Unless otherwise specified, Contractor shall submit the original and as a

minimum two (2) clean, legible copies of all turnover packages to Industria del Hierro

at Mechanical completion or as determined necessary by Industria del Hierro.

Some construction management projects may elect to collect the quality


records daily when mulitply Contractors are involved or when the scope of

work of the Contractor only involves one discipline of a mulit-disciplined

scope of work for completion.

NOTE:

Additional controls for Contractor quality are detailed in Quality Support Practices

SA5-MAR-01-14: Surveillance of Construction Activities and SA5-MAR-01-10: Quality


Audits.

PROCEDURE

Subcontract Manager
-

Initate development of the Quality Plan for Contractors Work by informing the QA/QC
Manager of the project contracting plan and of the scope of work for each Contract and

requesting input for the RFP from the QA/QC Manager.

QA/QC Manager
-

The QA/QC Manager will prepare and complete the applicable Attachments (01 through 04

and/or 05). The Attachments will be modified to address the specific contract scope and
responsibility assignments for Quality. The completed documents will be provided to the
Subcontract Manager for inclusion in the RFP.

Attachments 01 through 04 are needed only if the Contractor will be performing and
documenting inspections/tests or working to process control procedures listed on Attachment

03 that is provided. Affix to this attachment all QC procedures to be provided by Industria


del Hierro. Review the testing and inspection procedures to be included in the RFP and

modify to meet the Bidders work scope.


NOTE: The section of Attachment 03, Quality Procedure Description, will be needed only if
the Contractor will be required to prepare Quality procedures or process control procedures.
The section should be modified to provide a description of only the procedures the Contractor

will be required to prepare. The QA/QC Manager will consult with the Technical Supervisor

(see SA5-DOW-01-05) in determining the process control procedures to be listed in

Attachment 03.

Subcontract Manager
-

Description of Inspection and/or Tests by Industria del Hierro (refer to Attachment 05)

Needed only if inspection/test for all or any part of the Contractors work will be performed or

provided by Industria del Hierro.

Include in the RFP the quality requirements provided by the QA/QC Manager. Upon receipt of

the Contractors Quality Submittal or any exceptions to quality requirements of the RFP,

provide a copy to the QA/QC Manager.

QA/QC Manager
-

Provide comments by memo on the Bidders Quality Submittal (their response to Attachment

04) to the Contracts Administrator with specific recommendations including explanation of


deficiencies that are required to be corrected.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 7 of 7

INDUSTRIA DEL HIERRO S.A. DE C.V.

In evaluating the Bidders submittal requested by Attachment 04, the QA/QC Manager should

consider the following guidelines for the Contractors site quality organization:

Contractor may select either an outside Agency or in-house personnel to administer the

program. In either case, their Quality Manager should report directly to their Site

Manager.

Contractors Quality organization chart shall include sufficient QC personnel staffing levels

as may be necessary to accomplish complete and adequate inspection of work.


Contractors inspection shall be adequate to cover all operations, including both on-site

and off-site, and will be keyed to the proposed sequence of the Work.

Clerical personnel sufficient to accomplish timely submittal of QC reports and other

required documentation shall be provided.

Subcontract Manager
-

Reconcile quality issues and exceptions prior to contract award. Obtain input as needed from

the QA/QC Manager.

Incorporate the agreed to quality requirements into the contract.

After the Notice to Proceed, obtain the procedures listed under Prepared by Contractor of

Attachment 02 and process control procedure of Attachment 03 that were made a part of the

contract and provide these procedures to the QA/QC Manger.

NOTE: These procedures are to be approved by the QA/QC Manager or the Technical

Supervisor (see SA5-DOW-01-05) before the Contractor is authorized to proceed with work

within the procedure scope unless specifically approved by the Project Manager.

ATTACHMENTS

Attachment 01-

Quality Requirements

Attachment 02-

Construction Subcontractor Quality Requirements Checklist

Attachment 03-

QC Procedures Description

Attachment 04-

Quality Submittal Requirements

Attachment 05-

Description of Inspection and/or Testing By Industria del Hierro

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

QUALITY REQUIREMENTS

The Construction Subcontractors are responsible for quality and for implementing the measures

necessary to achieve and document compliance to specified requirements.

The section titled CCQRC (Construction Subcontractor Quality Requirement Checklist) identifies the

QC (Quality Control) procedures required to be included in the successful Bidder's Quality Program

Manual. The inspections, tests, and related actions specified in this section and elsewhere in the

Contract Documents are not intended to limit the Subcontractor's own quality assurance/control

procedures, which facilitate overall compliance with requirements of the Contract Documents.

Procedures "Prepared by Industria del Hierro" are enclosed with the CCQRC. Procedures "Prepared

by Construction Subcontractor" will be required to be submitted to and approved by Industria del

Hierro prior to work, but not with the bid. Once approved, the subcontractor shall obtain Industria del

Hierro approval of changes. Changes will not be permitted if they would, as determined by Fluor

Daniel, result in nonconformance with the Contract requirements. The section titled "QC Procedures

Description" provides a brief description to Bidders of the procedures that are to be developed by the

Subcontractor. The section titled "Quality Submittal Requirements" identifies the information to be

submitted by the Bidder with the bid.

The Construction Subcontractor will initiate, schedule, and coordinate all test and inspections. The

subcontractor is responsible for coordinating the sequence of the work so as to accommodate all

required tests and inspections. When inspection or testing is performed on a sampling basis (less

than 100 percent), Fluor Daniel reserves the right to select the items to be inspected or tested. Fluor

Daniel reserves the right to inspect, or have inspected at source, supplies or services not

manufactured or performed on the Site. Such inspection will not constitute acceptance; nor will it in

any way relieve the subcontractor of responsibility to furnish all required Quality Assurance/Control.

The Subcontractor will ensure that the Industria del Hierro representative is given sufficient time to

witness tests and reinspect work performed by the Subcontractor. The following times are considered

minimum notification:

Concrete placements
Holiday testing
Punching of lines prior to hydrotest
Pressure testing
Acceptance inspection of buildings
Bolt tensioning
DC (Direct Current) High Potential (over 2,000 volt cable)
Motor run-ins
Tests to electrical equipment
Loop checks
Acceptance inspection of vessels and equipment
Other tests

1
4
2
4
2
4
4
4
4
4
1
2

day

hours

days

hours

days

hours

hours

hours

hours

hours

day

hours

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Industria del Hierro will monitor construction and QC activities of the Subcontractor. Industria del

Hierro also will perform auditing of documentation to verify correctness of data, completeness of

coverage, retrievability as filed, timeliness of scheduling, and action taken on inspection and testing

results.

The Construction Subcontractor will schedule and accompany Industria del Hierro on any site visits

when requested, work closely with Industria del Hierro to ensure optimum QC, and attend meetings on

QC issues as required by Industria del Hierro.

The Subcontractor will receive approval of Subcontractor employed Testing and Inspection Agencies,

from the Industria del Hierro QA/QC Manager, prior to them performing any inspections and tests.
Subcontractor employed Testing and Inspection agencies will provide reports simultaneously to the

Subcontractor and Industria del Hierro.

The Construction Subcontractor and the sub-tier Suppliers and Subcontractors are subject to a

qualification survey by Industria del Hierro prior to the start of activities required by the contract to

verify implementation of the required Quality Programs.

Acceptance of the Construction Subcontractor's Quality Program by Industria del Hierro does not

relieve the Subcontractor of the obligation to comply with requirements of the contract documents

including the requirements herein. If the Quality Program is subsequently found to be ineffective or

inadequate in providing acceptable control, Industria del Hierro will require necessary revisions.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Attachment 2

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

CONSTRUCTION CONTRACTOR QUALITY REQUIREMENT CHECKLIST

Procedure Title

1.

Document Control

2.

Identification and Traceability of

Equipment and Material

3.

Process Control

4.

Inspection, Measuring and Test

Equipment

5.

Control of Nonconformance

6.

Quality Control Records

7.

Training

8.

Material and Equipment Handling Storage

and Maintenance

9.

Subcontractor/supplier Quality

Requirement, Qualification, Surveillance


and Audit

10. Inspection and Testing (List Procedures

Title and Form Numbers)

10.1
10.2
10.3
10.4
10.5
10.6
10.7
10.8
10.9
10.10

Prepared by

Contractor

Contractor Forms

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 2

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Procedure Title

Prepared by

Company (Enclosed)

Forms (Enclosed)

1. Document Control

SA5-DOW-01-04

2. Process Control

SA5-DOW-01-05

3. Inspection, Measuring, and Test

Equipment

SA5-DOW-01-06

SA5-DOW-01-06: 01, 02,03, 04

4. Control of Nonconformance

SA5-DOW-01-07

SA5-DOW-01-07: 01, 02, 03

5. Quality Control Records

SA5-DOW-01-09

SA5-DOW-01-09-01

6. Personnel Training and Qualification

SA5-DOW-01-11

7. Contractor/supplier Quality
Requirements, Qualification,
Surveillance and Audit

SA5-DOW-01-13
SA5-DOW-01-14

SA5-DOW-01-13: 01, 02

SA5-DOW-01-14: 01, 02

8. Material and Equipment Handling,

Storage and Maintenance

SA5-DOW-01-17

SA5-DOW-01-17: 01, 02

9. Inspection and Testing Procedures


(List Title and Form Numbers)

SA5-DOW-01-20

SA5-DOW-01-20: 01,02

10. Structural Steel

SA5-DOW-01-21

SA5-DOW-01-21: 01,02

11 Equipment

SA5-DOW-01-22

12 Aboveground Piping

SA5-DOW-01-23

SA5-DOW-01-23: 01,02, 03

13 Pressure Testing

SA5-DOW-01-24

SA5-DOW-01-24-01

14 Cleaning of Pipe

SA5-DOW-01-25

SA5-DOW-01-25-01

15 Electrical Inspection

SA5-DOW-01-27

16 Electrical Testing

SA5-DOW-01-28

17 Control System Instrumentation

SA5-DOW-01-30

SA5-DOW-01-30:

01, 02, 03, 04, 05 y 06

18 Control System Calibration

SA5-DOW-01-31

SA5-DOW-01-31:

01, 02, 03

19 Coatings

SA5-DOW-01-32

SA5-DOW-01-32

01, 02

20 Insulation

SA5-DOW-01-33

SA5-DOW-01-33

01, 02

21 Fireproofing Inspections

SA5-DOW-01-34

SA5-DOW-01-34

01, 02

22 Welding Inspection

SA5-DOW-01-35

SA5-DOW-01-35

01, 02

23 Nondestructive Examination

SA5-DOW-01-36

SA5-DOW-01-36:

01, 02, 03, 04

24 Positive Material Identification

SA5-DOW-01-37

SA5-DOW-01-37:

01, 02, 03

25 Hardness Testing

SA5-DOW-01-38

SA5-DOW-01-38:

01, 02, 03

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Note: When procedures that are "Prepared by Industria del Hierro" are used by the

Contractor, the position titles (QA/QC Manager, Construction Manager, etc.)

stated in the procedures apply to those responsible for the described action in the

Contractor's organization unless " Industria del Hierro " is specifically designated

in the title. The title "client" means Company.

The term Subcontractor, when stated on Industria del Hierro prepared forms

means contractor and/or a subcontractor engaged by Contractor.

FORMS
Quality Control Practice

SA5-DOW-01-10-01
SA5-DOW-01-14-01

Quality Audits
Surveillance of Construction Activities

Page 3 of 3

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 3

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

QC PROCEDURES DESCRIPTION

1.

Document Control

The Construction Subcontractor will prepare procedures to control documents and data that relate

to the control of contracted work. The Construction Subcontractor is responsible for ensuring that

documents provided by Industria del Hierro for construction are maintained to the most up-to-date

revisions. The Construction Subcontractor's control procedure should ensure that all necessary

information is delivered to the proper locations and personnel responsible for the performance of

the work. The procedure will ensure that obsolete documents are promptly removed from all points

of issue or use.

2.

Quality Control Records

The contractor will prepare procedures to collect, index, file, store, maintain, and turn over to

Industria del Hierro the quality control records listed below:

All records required by specifications

Test and inspection reports

Radiographs

Material and equipment certificates required by specification

Equipment maintenance/preservation records

As-built drawings

The contractor will package and prepare all quality records for turnover. Timing of this will be

compatible with Industria del Hierro Document Control System. Turnover packages are to be

developed by system as determined by Industria del Hierro. Each system file will contain field

inspection and testing records for the components of the system. Unless otherwise specified, the

contractor will submit the original and 1 clean, legible copy of all turnover packages to Industria del

Hierro at the completion of construction.

3.

Identification and Traceability of Equipment and Material

The contractor has responsibility for maintenance of the identification of material and equipment

used during construction. Procedures will be developed to describe the methods of maintaining

traceability.

4.

Control of Nonconformance

The contractor is responsible for and will develop procedures for control and disposition of

nonconforming conditions.
Measures will be taken to preclude work containing uncorrected

deficiencies being built upon or concealed until satisfactorily disposition. The contractor will prepare

procedures for documenting and controlling nonconforming items or services. If corrective action of

the contractor does not result in full conformance with contract requirements, the proposed final

disposition will be approved by a designated Industria del Hierro representative.

Measures will be taken to perform the following:

Provide holding areas or methods for segregating nonconforming items to prevent

unauthorized use.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 3

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Maintain records identifying nonconforming items, the nature of nonconformance, its

dispositions, and evidence that the disposition has been satisfactorily completed.

Industria del Hierro also may identify and report nonconformance.


In these cases, a

nonconformance report will be delivered to the contractor who will provide for appropriate closure

action.

5.

Training

The contractor will prepare a procedure for identifying training needs, and will provide for the

training of personnel performing activities affecting quality.


The procedures will provide for

documentation of training. In addition to other training needs identified by the contractor, prior to

the start of each major item of work required by the Contract Documents, a preconstruction Quality

Control meeting with responsible field and office representatives will be conducted to ensure that

quality requirements are understood by those performing the work.

6.

Inspection, Measuring, and Test Equipment

The contractor will provide and maintain all measuring and test devices used to verify compliance to

specifications. The contractor will provide a procedure for controlling calibration of this equipment.

The procedure will specify the intervals and standards against which test and measurement

equipment are checked. The standards against which the measurement equipment is calibrated will

have their accuracy traceable to the National Institute of Standards and Technology or to a

recognized industrial or national standard. Where no such standards exist, the basis used for

calibration will be documented. This equipment will bear a record of the calibration and record of

use logs will be maintained. The contractor's measuring and test equipment will be made available

for use by Industria del Hierro for verification of their accuracy and condition as well as inspection

and test monitoring.

7.

Material and Equipment Receiving, Handling, Storage, and Maintenance

The contractor is responsible for the receipt and control of their purchased material and equipment,

and material and equipment that is issued to the contractor. The contractor may reject faulty or

damaged equipment upon receipt, and should promptly advise the designated Industria del Hierro

Representative for Industria del Hierro issued material / equipment.

Upon issue, the contractor will conduct a program for preventive maintenance of equipment,

including Supplier's recommendations. The equipment protection requirements are established by

Specification. The contractor will keep records of all maintenance performed on this equipment.

The contractor will prepare a procedure for material and equipment receiving, handling, storage,

and maintenance.

8.

Other Subcontractor/Supplier, Quality Requirements, Qualification, Surveillance, and

Audit

The contractor's Suppliers of services, equipment, and materials will be required to meet the same

quality standards required of the contractor. The contractor will perform surveillance of other

lower-tier Subcontractor's and Supplier's quality related operations consistent with the nature and

scope of service or product provided. The contractor will provide a procedure for controlling quality

of the subtier Suppliers/Subcontractors.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 3

Page 3 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

9.

Process Control

The contractor will provide procedures to control work processes. These will include the following:

Welding Procedure Specifications and Procedure Qualification Records

Flushing and hydrotesting procedures

NDE (Nondestructive Examination) Procedures

Welder Qualification Procedures

PWHT (Post Weld Heat Treatment)

NOTE: When personnel certifications are required, they will be made available upon request.

10

Inspection and Testing

Within two weeks of the award of the Contract, the Contractor shall submit to Industria del

Hierro for approval Inspection and Test Plans (ITP) prepared either to Industria del Hierros

format or to the Contractor's own format provided this contains equivalent data. The purpose of

the ITP is for the Contractor to describe on one document the inspection and testing activities

for each definable feature of work. As a minimum the plans shall address the quality control

requirements of the contractual requirements, specifications, and drawings, as well as the

standards and codes referred to therein. However, these requirements are not considered

exclusive, the Contractor being responsible for adding to these minimum requirements to the

extent that the Contractor considers necessary to obtain appropriate quality levels.

Definitions:

Inspection- visual checks of a qualitative nature but also including dimensional

measurements.
Tests- measured verifications of one or more characteristics or of performance, both
being carried out to ascertain whether or not the specified requirements have

been met.
The ITP shall include the following features:

a list of the inspection and test points presented in sequence in the order in which
they are to be performed

for each point, reference to a document stating the acceptance criteria for each
point, the "verification document" i.e. the document to be checked or the one used

to record the result of the inspection or test for each point for both Contractor and

Industria del Hierro, where required, an indication of:

"W" for "Witness Point"

"R" for "Review"

"H" for "Hold Point"

Once the ITP has been approved by Industria del Hierro the Contractor shall apply it. Any

modification must have the written approval of Industria del Hierro.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 4

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

QUALITY SUBMITTAL REQUIREMENTS

The Bidder will submit the following information with the bid:

a)

A description of the proposed on-site organization that will perform Quality


on-site and off-site (if any) reporting of these personnel. Describe the roles
these personnel. Also, provide a man loaded schedule for their project
personnel sufficient to accomplish timely submittal of quality reports
documentation will be provided and shown on this schedule.

activities. Include the

and responsibilities of

assignment. Clerical

and other required

To be acceptable, a Quality representative must be on-site during all working hours. The

Subcontractor must designate alternate individuals to assume responsibilities in the temporary

absence of the Quality Supervisor or when overtime work is being performed.

b)

Identify all anticipated testing that will be contracted.

c)

Identify any QC activities, procedures, and inspection/test plans/reports proposed by the

subcontractor in addition to those required by the Construction Subcontractor Quality Requirements

Checklist.

d)

Exceptions may be taken by the Bidder of quality requirements imposed herein by submitting a brief

statement of justification for each requirement considered not applicable. Industria del Hierro has

the sole right to accept or reject any exception recommended by the Bidder.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-13

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 5

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

DESCRIPTION OF INSPECTION AND / OR TESTING BY PURCHASER

Industria del Hierro will inspect the Contractors work for the following work activities:

Industria del Hierro will provide testing of the Contractor's work for the following activities:

The Contractor is responsible for quality and for implementing the measures necessary to achieve

compliance to specified requirements.

The Contractor shall ensure that the Industria del Hierro representative is given sufficient time to witness

tests and reinspect work performed by the Contractor. The following items are considered minimum

notification:

Concrete placements
Holiday testing
Punching of lines prior to hydrotest
Pressure testing
Acceptance inspection of buildings
Bolt tensioning
DC (Direct Current) High Potential (over 2,000 volt cable)
Motor run-ins
Tests to electrical equipment
Loop checks
Acceptance inspection of vessels and equipment
Other tests

1
4
2
4
2
4
4
4
4
4
1
2

Day

Hours

Days

Hours

Days

Hours

Hours

Hours

Hours

Hours

Day

Hours

When inspection reveals work not conforming to requirements, the Contractor will be informed and will

perform work necessary to achieve compliance.

The Contractor has primary responsibility for quality. The Contractor shall implement the measures

necessary to build quality into the work in accordance with the contract, drawings, and specifications.
Inspection of the Contractor's work by Industria del Hierro does not relieve the Contractor of the obligation

to comply with requirements of the contract documents.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-14

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

SURVEILLANCE OF CONSTRUCTION ACTIVITIES

SCOPE

This procedure describes the responsibilities and activities for quality surveillance of construction activities.

This procedure is applicable to subcontracted construction/installation work awarded by or assigned to

Industria del Hierro for management. It is to be used to oversee the inspection testing and work activities

of subcontractors. This procedure is also be used to verify adequacy of self performed work not requiring

inspection/testing by the QA/QC Manager.

GENERAL

The Contracts Manager shall have the overall responsibility for administration of the subcontracts.

The QA/QC Manager responsible for the quality program at the construction/installation site is responsible

for implementing and managing a program of quality surveillance.

Surveillance is the monitoring by witnessing and observation of the Quality Control Program implementation

during construction/installation work activities.

Surveillance is performed to the extent necessary to provide adequate confidence that appropriate

measures are taken to control and achieve quality.

The responsible Project Manager shall be contacted for final resolution/interpretation of design specifications

or drawing requirements, when a conflict develops between the subcontractor's interpretation and that of

Industria del Hierros Quality Surveillance personnel.

PROCEDURE

QA/QC Manager
-

The QA/QC Manager will assign surveillance responsibilities to inspection personnel.

NOTE: Scope, duration, and intensity of surveillance and/or verification activities shall be

determined by the QA/QC Manager through an evaluation of the scope of the activities

being performed and the quality history of the workers.

Surveillance personnel

Perform periodic surveillance and/or verification activities.

NOTE: The inspector should refer to the applicable inspection/test plans or procedures and use

them for determining surveillance activities. When surveillance is performed on selfperformed or subcontracted activities not addressed by inspection/test procedures; the

work process instructions (usually drawings and specifications) should be used to guide the

inspector.

Indicate the results of the surveillance verification activity (Form SA5-DOW-01-14-01) in the

following manner:

Record on the Surveillance Report those areas or items monitored or reviewed. If no

deficiencies are found during this surveillance, so state (satisfactory), sign, and date report.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-14

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

When a deficiency is found and will need a follow-up inspection to verify conformity,

identify it on the Surveillance Report. Notify the subcontractor of the deficiency and record

the corrective action being taken by the subcontractor to resolve it. When this procedure is

being used for surveillance of self perform work, notify craft supervision of the deficiency.

Sign and forward to the QA/QC Manager for his review.

Follow-up and record the completion of the corrective action, sign and date.

If corrective action is not initiated to resolve the deficiency within fourteen (14) days, notify

the QA/QC Manager. The QA/QC Manager may initiate and process a nonconformance

report if needed.

Nonconformance Reports are issued when there are:

Deficiencies in materials, finished work or work processes that result in a condition that
does not conform to the specifications and for which there are no existing procedures or
standard trade practices which describe methods of correction and therefore require

engineering disposition.

Deficiencies of a serious or repetitive nonconforming nature as determined by the QA/QC

Manager

Construction damage has occurred to existing or turned over plant property.

Nonconformance shall be documented using Form SA5-DOW-01-07-01

QA/QC Manager
Review the results of the surveillance and/or verification activities recorded on the

Surveillance Report and signify review and concurrence by signing and dating.

Advise the Project Manager of serious quality problems.

DOCUMENTATION

All Surveillance Reports shall be retained in the Quality Control files.

ATTACHMENTS & FORMS

Attachments
None

Forms
SA5-DOW-01-14-01 - Surveillance Report

SA5-DOW-01-14-02 Surveillance Report Log

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SURVEILLANCE REPORT

INDUSTRIA DEL HIERRO S.A. DE


C.V.

LOCATION

SUBCONTRACTOR

DATE

SA5-DOW-01-14-01

August, 2014

Page 1 of 1

Revision 01

COMPLETED WORK

yes

INSPECTION CHECKLIST, SPECIFICATION, OR DRAWING USED AS REFERENCE:

DESCRIPTION OF ITEM/WORK INSPECTED:

OBSERVATIONS:

PERSON NOTIFIED OF
DEFICIENCY

,
NAME

CORRECTIVE ACTION:

REMARKS:

IH INSPECTOR/DATE

QA/QC MANAGER/DATE

TITLE

no

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9

Project
Purchase Order No. GUST-50-LHC-K067

SURVEILLANCE REPORT LOG

INDUSTRIA DEL HIERRO S.A.


DE C.V.

REPORT

NO.

INITIATOR

CONTRACTOR

SUBJECT

SA5-DOW-01-14-02

August, 2014

Page 1 of 1

Revision 01

OPEN

CLOSED BY /
DATE

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-15

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

FIELD RECEIVING AND INSPECTION

SCOPE

This procedure describes the practice and methods for performing receiving inspection of permanent plant

material and equipment.

RESPONSIBILITIES Industria del Hierro Self-Perform

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY OF

ACTIVITY

Warehouse receipt of
material/items

Warehouse
Personnel

Overage, Shortage and

Damage(O,S and D)

Per shipment

received

Determine inspection and


storage level requirements

Construction

Engineer

Attachment 1

As project

progresses

Perform quality receipt

inspection

QA/QC Manager

SA5-DOW-01-15-01

As required by

project

Responsibilities - Subcontracted Work

ACTIVITY
Warehouse receipt of
material/items

RESPONSIBILITY

DOCUMENTATION

FREQUENCY OF

ACTIVITY

Subcontractor

Overage, Shortage and

Damage(O,S and D)

Per shipment

received

Determine inspection and

storage level requirements

Subcontractor

SA5-DOW-01-15-02

As project

progresses

Perform quality receipt

inspection

Subcontractor

SA5-DOW-01-15-01

As required by

project

Surveillance

QA/QC Manager

Form SA5-DOW-01-14-01

Per Procedure SA5DOW-01-14

PROCEDURE

Materials Manager
The Materials Manager shall implement use of the Material Manager (MatMan) Industria del Hierro's
reference system for the control and documentation of field receiving activities. And, provide the

necessary resources for data input, installation and maintaining the program throughout the life of the

project.
Receipt of Material/Items:
Warehouse personnel shall perform the initial visual inspection of the materials/items for obvious shipping

damage. If there has been shipping damage, initiate an OS&D Report in accordance with Warehouse

Procedures. Forward a copy of the OS&D Report to the QA/QC Manager for information. The warehouse

staff shall notify the QA/QC Manager upon receipt of items listed on the Permanent Plant Material and

Equipment Inspection List or items where receipt inspection by the Quality Inspector is indicated on the ITP.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-15

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Determine Inspection and Storage Requirements:


Early in the project and continuing throughout the life of the project, the Field Engineering Manager shall

determine which items of permanent plant material and equipment that will require quality/receiving

inspection. The list shall be provided to the QA/QC Manager with a list of items to be inspected, and any

specific inspection and storage requirements.

Quality Receipt Inspection:


Prior to receipt of materials/equipment, the quality inspector shall research the purchase order, change

orders, and specifications to determine the inspections and/or verifications to be performed. Prepare a

Receiving Inspection Checklist/Report, (SA5-DOW-01-15-01) for each item with the attributes to be

inspected or verified.

Upon receipt of material/equipment, perform receipt inspection prior to unloading of the

material/equipment, if possible. If material cannot be inspected prior to unloading, material should be

unloaded and segregated from other material until receiving inspection can be performed.

Inspect the material/equipment and associated vendor documentation for compliance with the requirements

and document the results on the receiving inspection Checklist/Report (SA5-DOW-01-15-01).

If the material/equipment is found to be nonconforming, attach a Hold Tag (SA5-DOW-01-07-03) and

initiate a Non-conformance Report (SA5-DOW-01-07-01).

DOCUMENTATION

Documentation generated as a result of receiving inspection activities are considered quality records shall be

filed and maintained in accordance with approved document control procedure

REFERENCES

SA5-DOW-01-07-01 - Nonconformance Report

SA5-DOW-01-07-03

- Hold Tag

ATTACHMENTS & EXHIBITS

Attachments
Attachment 01

Receiving Inspection Reference

Attachment 02

Overage, Shortage and Damage Report (OS&D)

Exhibits (Forms)
SA5-DOW-01-15-01

- Receiving Inspection Checklist/Report

SA5-DOW-01-15-01

- Permanent Plant Material and Equipment Inspection List

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

FIELD RECEIVING INSPECTION


CHECKLIST / REPORT

Client:

Date:

Project:

Project No.:

Area:

Report No.: ______________

No

Qty

Item
Code

Material Description

Heat No. /

Slab No.

Quality Certificate

Number

SA5-DOW-01-15-01

August, 2014

Page 1 of 1

Revision 01

Remarks / Location

Slab number only apply for plaques

Prepared by

Warehouse
(Name, Date and Signature)

Approved by

Client

Quality Control
(Name, Date and Signature)

(Name, Date and Signature)

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

PERMANENT PLANT MATERIAL


AND EQUIPMENT INSPECTION
LIST

SA5-DOW-01-15-02

August, 2014

Page 1 of 1

Revision 01

EXAMPLE

CIVIL

Civil materials such as:

Structural steel components

Load indicating bolts/washers

Protective coatings

Specialty grouts

MECHANICAL / PIPING MATERIALS

All mechanical equipment such as:

Trays

Piping materials such as:

Alloy Pipe

Valves and fittings

Specialty piping components

Weld Rod

APPROVALS

Civil Manager/Date_______________________________________________

Mechanical Manager/Date____________________________________________________

Electrical Manager/Date____________________________________________

QA/QC Manager/Date

________________________________________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-15

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 1 of 1

Attachment 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

RECEIVING INSPECTION REFERENCE

INSTRUCTIONS: Perform Receiving Inspection with Purchase Order and/or plans and specifications in hand. This

inspection is performed after Receiving Operations by the Material Manager have confirmed identification of item per

Purchase Order, identification of parts shipped separately, quantity and size of item.

BLACK ANCHOR BOLTS


-Damage
-Corrosion

-Fit of Nut & Bolt

-Size Check
BAGGED CEMENT & MOTAR
-Damage
-Deterioration
-Bag Markings

REINFORCING STEEL
-Damage
-Corrosion

-Deformations

-Mill Markings

-Mill Certifications

STRUCTURAL STEEL
(Random Sampling)

-Damage
-Corrosion

-Welding

-Piece Marking

-Connectors

-Dimensional Checks

BUILDING MATERIALS
(Random Sampling)

-Damage
-Corrosion

-Deterioration
-Tagging or Bag Markings

-Shop Coatings

FIELD FABRICATION TANKS


-Damage
-Corrosion

-Edges Prepared for Welding

-Mill Certifications

-Dimensional Checks

SHOP FABRICATED TANKS & VESSELS


-Damage
-Corrosion

-Accessories

-Flange & Opening Protection


-Temporary Supports

-Desiccants

-Shop Coatings

-Dimensional Checks

-Name Plate Data

MACHINERY
-Damage
-Corrosion

-Accessories

-Shipping Protection

-Temporary Supports

-Vendor Instructions

-Flange & Opening Protection


-Name Plate Data
-Shaft Rotation

-Welding

EXCHANGERS
-Damage
-Corrosion

-Flange & Opening Protection


-Shipping Protection

-Temporary Supports

-Fan Blades

-Motors

-Gears

-Desiccants

-Vendor Instructions

-Name Plate Data


-Shaft Rotation

FIRED HEATERS & BOILERS


-Damage
-Corrosion

-Flange & Opening Protection


-Edges Prepared for Welding

-Mill Certifications

-Dimensional Checks

-Name Plate Data


-Welding

-Accessories

-Refractory
SPECIALTY EQUIPMENT
-Damage
-Corrosion

-Flange & Opening Protection


-Edges Prepared for Welding

-Dimensional Checks

-Name Plate Data


-Welding

-Accessories

PIPE
(Random Sampling)

-Damage
-Corrosion

-Shop Coatings

-Pipe Markings

VALVES
(Random Sampling)

-Damage
-Corrosion

-Flange & Opening Protection


-Moving parts

-Valve Markings

FITTINGS
(Random Sampling)

-Damage
-Corrosion

-Piece Markings

ELECTRICAL EQUIPMENT
-Damage
-Corrosion

-Name Plate Data


-Accessories

-Dimensional Checks

-Shipping Protection

-Temporary Supports

ELECTRICAL MATERIAL
(Random Sampling)

-Damage
-Corrosion

-Item Markings

INSTRUMENTS
-Damage
-Corrosion

-Shipping Protection

-Item Markings

-Accessories

COATINGS
-Damage
-Deterioration
-Car Markings

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-15

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Attachment 2

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

OVERAGE, SHORTAGE AND DAMAGE REPORT


PROJECT NAME

PROJECT NO.

REPORT NO.

REPORT DATE

TO BE COMPLETED BY WAREHOUSING
RECEIVED FROM

DATE RECEIVED

PURCHASE ORDER NO.

PURCHASED FROM

FOB POINT

RECEIVED BY (Name of Individual)

WAYBILL NO.

BILL OF LADING

CARRIER
P.O.
ITEM
NO.

CAR INITIAL NO.


QUANTITY
ORDERED (OR
BACKORDERED)

QUANTITY
SHIPPED PER
SUPPLIER

REASON FOR OS&D REPORT


OVER SHIPMENT

QUANTITY
RECEIVED

ERROR RESPONSIBILITY

UNIT

OF

MEASURE

REPAIR ON SITE

SHORT SHIPMENT

RETURN FOR CREDIT

DAMAGED-UNCONCEALED

SUPPLIER

NOT AS ORDERED
DEFECTIVE

CARRIER

OTHER-SEE REMARKS

PACKING LIST NO.

DESCRIPTION

RECOMMENDED DISPOSITION

PURCHASING

RECEIVING REPORT NO.

DAMAGE DUE TO

FAULTY OR INSUFFICIENT

PACKAGING

RETAIN MATERIAL

ROUGH HANDLING

REPLACE

IMPROPER LOADING

ISSUE TO FIELD

OTHER-SEE REMARKS

OTHER-SEE REMARKS
OTHER-SEE REMARKS

ISSUED BY

REMARKS

TO BE COMPLETED BY PROCUREMENT

POSITION TITLE

SHIP TO (Name and Address)

RETURN FOR:
CREDIT
REPLACEMENT

VIA

COLLECT

PREPAID

SUPPLIER CONTACTED

SUPPLIER TO SHIP BALANCE

DAMAGES TO BE JOB REPAIRED

RETAIN MATERIAL

SUPPLIER TO REPLACE:

MATERIAL SHIPPING RECORD TO FOLLOW

DISCARD MATERIAL

NO CHARGE

ISSUE MATERIAL TO FIELD

REBILL

SUPPLIER TO ISSUE CREDIT FILE CLAIM

NO ACTION NECESSARY
ISSUED BY

TO BE COMPLETED BY WAREHOUSING

STOCK

BY

DATE

FIELD

SHIPPED BY (Name of Individual)

DATE

POSITION TITLE

TO BE COMPLETED BY ACCOUNTING
DATE

CLAIM FILED

M.S.R. NO.
REMARKS

REMARKS (or Other Action)

NO CHANGE ORDER NECESSARY

OTHER-SEE REMARKS

REMARKS (Special Instructions)

ISSUE TO

CHANGE ORDER TO BE ISSUED

DATE

CREDIT RECEIVED

DATE

PAYMENT RECEIVED

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

TURNOVER

SCOPE

This procedure establishes the sequence of events leading up to the transfer of care, custody and control of completed

systems or areas from Industria del Hierro to The Client. Industria del Hierro will request The Client's acceptance of

buildings, systems or areas for care, custody, and control.

RESPONSIBILITIES - Self-Performed

ACTIVITY

FREQUENCY OF

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

Determine scope of

system

Turnover Coordinator

Scoped drawings

Prior to start of work

Establish alphanumeric

number and brief scope

Turnover Coordinator

Turnover master listing

Prior to start of work

Commissioning/Start-up,
engineering, construction
management, and The Client

Form SA5-DOW-01-16-01

Three weeks before

mechanical completion

date

Issue walk-down notice

Turnover Coordinator

Form SA5-DOW-01-16-02

Two weeks before

mechanical completion

date

Generate master punchlist

Turnover Coordinator

Form SA5-DOW-01-16-07

Prior to mechanical

completion date

Generate exceptions list

Turnover Coordinator

Exceptions list format site specific

Establish mechanical

completion dates

Generate discipline
checklist
Generate care, custody,
and control package

Turnover Coordinator

Turnover Coordinator

Form
Form
Form
Form

SA5-DOW-01-16-03

SA5-DOW-01-16-04
SA5-DOW-01-16-05
SA5-DOW-01-16-06

Transfer of care custody and

control letter
Form SA5-DOW-01-16-01

Form SA5-DOW-01-16-02

Form SA5-DOW-01-16-03

Form SA5-DOW-01-16-04

Form SA5-DOW-01-16-05

Form SA5-DOW-01-16-06

Prior to mechanical

completion

Prior to turnover of

system or area

System scoping drawings,

elementary or one line

diagram.

Hydro test report.

Equipment list.

Instrument list.

Exceptions list.

Loop list.

Surveillance

QC Inspector

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Form SA5-DOW-01-14-01

Per Procedure
SA5-DOW-01-14

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

Responsibilities - Subcontracted Work

RESPONSIBILITY

Determine scope of
system

Turnover Coordinator /
Subcontractor

Scoped drawings

Prior to start of work

Establish alphanumeric

number and brief scope

Turnover Coordinator /
Subcontractor

Turnover master listing

Prior to start of work

Establish mechanical

completion dates

Commissioning/Startup/

Engineering / Construction

Management / and The

Client

Form SA5-DOW-01-16-01

Three weeks before


mechanical completion

date

Issue walk-down notice

Turnover Coordinator/

Subcontractor

Form SA5-DOW-01-16-02

Two weeks before


mechanical date

Generate master
punchlist

Subcontractor/

Turnover Coordinator

Form SA5-DOW-01-16-07

Prior to mechanical

completion date

Generate discipline

checklist

Subcontractor/

Turnover Coordinator

Form
Form
Form
Form

Prior to mechanical

completion

Generate care, custody,


and control package

Subcontractor/

Turnover Coordinator

Surveillance

QC Inspector

DOCUMENTATION

FREQUENCY OF
ACTIVITY

ACTIVITY

SA5-DOW-01-16-03

SA5-DOW-01-16-04
SA5-DOW-01-16-05

SA5-DOW-01-16-06

Transfer of care, custody, and


control letter

Form SA5-DOW-01-16-01
Form SA5-DOW-01-16-02

Form SA5-DOW-01-16-03

Form SA5-DOW-01-16-04

Form SA5-DOW-01-16-05

Form SA5-DOW-01-16-06

System scoping drawings,

elementary or one line

diagrams

Hydrotest Report

Equipment List

Instrument List

Exceptions List

Loop List

Form SA5-DOW-01-14-01

Per Procedure
SA5-DOW-01-14

PROCEDURE

Determine Scope of System:


-

Determine the areas and process units that make up a system scope boundary.

Once system scoping has been determined, each system will be assigned a name and an alpha-numeric number. A

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Module Fabrication Quality Manual, SA5-DOW-01-16

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

brief description of scope boundary will be generated. This information will be compiled into a master list and

distribution made. Scoped drawing will be prepared to indicate system boundaries. Identify content of turnover

package and initiate package index.

Establish Mechanical Completion dates:


-

Issue Walkdown Notice:


-

Each discipline Manager will generate a checklist to verify all work has been completed as required by drawings and

specifications. The Commissioning / Startup Administrator will generate a checklist to verify that all required quality

records have been completed and those designated for turnover are included in the Turnover Package.

Generate Master Punchlist:


-

When the Industria del Hierro walk down has been completed, a master punch list will be compiled (Form 000 509
F02407).

The master punch list will identify any incomplete items of work and/or errors in design or installation. The master
punch list will be issued to construction and engineering for corrective action.

Approximately two (2) weeks before the established mechanical completion date, the turnover coordinator will

notify The Client that the system is ready for their walk down. A copy of the open items from the master punch list

will be attached to the walk down notice.

Generate the Exception List:


-

Approximately three (3) weeks before the established mechanical completion date for a system, a walkdown notice
for Industria del Hierro will be issued (Form 000 509 F02402)

Generate Discipline Checklist:


-

Mechanical completion dates for systems will be established with input from The Client Management and Industria

del Hierro Commissioning / Startup, Construction, and Engineering. These dates will be used for tracking and

scheduling.

After The Client walk down has been completed, the Commissioning Administrator will schedule a joint meeting
between The Client and Industria del Hierro. The purpose of this meeting will be to reconcile the punch list. Any

items that will impede pre-commissioning/commissioning or cannot be completed after commissioning/start-up shall

be completed prior to the mechanical completion date. These items will be coded Category 1. Any remaining

incomplete items will become items on the exceptions list and be included as part of the transfer of care, custody,
and control package.

The items on the exceptions list will be categorized as 2 or 3 Category 2 items may be completed anytime with the

approval of The Client. Category 3 items are generated by the client/operations, addition to the scope of work or wish
lists items, etc.

Generate Care, Custody, and Control Package:


-

The turnover coordinator will assemble the transfer of care, custody, and control package.
contain, as applicable, (a min) the following documents:

The package will

a) Transfer of Care, Custody, and Control Letter

b) Mechanical Completion Certificate

c) Discipline Managers Checklist

d) System Scoping Drawings

e) Elementary or One-Line Diagrams

f) Hydrostatic Test Report

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 4 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

g) Equipment List

h) Instrument List

i) Exceptions List

j) Loop List

The Client management has ten (10) calendar days to respond to the transfer of care, custody, and control letter.
At time of acceptance, The Client should tag equipment to indicate their control of that system.

The Client shall install lockout-type devices on all isolation equipment such as breakers, valves, etc. Industria del

Hierro may also install lockout devices on system boundary isolation equipment. This action will be necessary to

make safe any equipment or system that has not been completed and custody transferred to The Client.

All supporting documentation relating to mechanical completion/system turnover will be retained by Industria del
Hierro until system acceptance by The Client. After system acceptance by The Client, this documentation will be
transferred to The Client under separate correspondence.

FORMS

Quality Control Forms:

SA5-DOW-01-16-01 Transfer of Care, Custody, and Control Letter

SA5-DOW-01-16-02 - System Walk down Notice

SA5-DOW-01-16-03 - Mechanical Completion Civil Checklist

SA5-DOW-01-16-04 - Mechanical Completion Electrical/Instrumentation Checklist

SA5-DOW-01-16-05 - Mechanical Completion Mechanical Checklist


SA5-DOW-01-16-06 - Mechanical Completion Quality Control Checklist

SA5-DOW-01-16-07 - Master Punch List

SA5-DOW-01-16-08 Interim Turnover Notice

SA5-DOW-01-16-09 Mechanical Completion Certificate

ATTACHMENT

Attachment 01-Sample Turnover Table of Contents

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

Fluor Exceptions

Contract: GUST-50-LHC-K067

DOW-Gulfstream Light Hydrocarbon Project

CATEGORY 2 PUNCH LIST ITEMS

August, 2014

ITEM
NO.
1

DWG. NO.

Rev.01

LOCATION

DESCRIPTION

ITEMS

SIGNED OFF

SIGNED OFF

SIGNED OFF

COMPLETE

WHITE

FLUOR

MAP

INDUSTRIA DEL HIERRO S.A. DE C.V.

The DOW Chemical Company

MODULE L2A01

TURNOVER PACKAGE

SYSTEM #DPR TURNOVER PACKAGE INDEX

1 .0

TRANSFER OF CARE,CUSTODY,CONTROL LETTER

2.0

MECHANICAL COMPLETION CERTIFICATE

3.0

SYSTEM PUNCH LIST

4.0

DISCIPLINE MANAGERS CHECKLIST

5.0

PIPING

6.0

ELECTRICAL

7.0

INSTRUMENTATION

SA5-DOW-01-16-01
INDUSTRIA DEL HIERRO S.A. DE C.V.
Viaducto Rio Becerra No 27, Col. Npoles

Mxico D.F, CP 03810


Project: Gulfstream Light Hydrocarbon Project

Project Number: GUST-50-LHC-K067

Letter No.00XX

The DOW Chemical Company

2301 N. Brazosport

Freeport, Tx - 77541

USA

Attention: Project Site Manager / Fabrication Lead


Dear Project Site Manager / Fabrication Lead

RE: TRANSFER OF CARE, CUSTODY AND CONTROL


This letter is to advise you that effective ____________ all work is essentially complete and ready for the Transfer of

Care, Custody, and Control of System N XX. The respective equipment has been tested, and operation, maintenance,
care, custody, and control are now under the supervision of your personnel.

As per the Contract, upon your acceptance hereof, it is provided that care, custody, and control of System No. XX will

be passed to MAP. Responsibility for any loss or damage to any part of System No. XX is to be assumed by MAP with

insurance liability being transferred from CONTRACTOR and/or their sub-contractors to MAP and their insurers.

Moreover, nothing herein contained, shall be construed as relieving CONTRACTOR of any of its guarantees under the

contract covering system N XX hereby transferred. All warranty and / or guarantee periods for subject equipment

contained in system N XX shall commence upon execution of this acceptance.

Please acknowledge your acceptance and approval of the foregoing by signing and returning two of the enclosed
copies of this letter, or advise in what respect System N XX is not complete.

Yours very truly,

CONSTRUCTION MANAGER

Approved and accepted by MAP:

Dave Jasper
Name

Signature

MAP Director of Major Projects


Title

Date

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16-02

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

SYSTEM WALKDOWN NOTICE


The Client:

SYSTEM NUMBER:
SYSTEM DESCRIPTION:

Industria del Hierro

The Client

Participation in this system walkdown is required by these persons or their designee. The others are

notified for information only.

The system is scheduled for a joint Industria del Hierro /The Client walkdown on ______________.

The walkdown and punchlist must be complete within two (2) days. Punchlist items to assist Industria

del Hierro and The Client in establishing Category 2, 3, 4 & 5 items and tracing their acceptance and

closure.

Please notify me if your discipline can not perform the walkdown as scheduled.

Systems Coordinator ____________________________________

Ext. ___________

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16-03

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

MECHANICAL COMPLETION CIVIL CHECKLIST

The Client:

SYSTEM NUMBER:

SYSTEM DESCRIPTION:

1.

All paving is installed and properly sealed in accordance with the drawings and

specifications.

2.

All structural steel, stairs, and grating is installed in accordance with the drawings

and specifications.

3.

All structural steel base plates are grouted in accordance with the drawings and

specifications.

4.

All structural steel requiring concrete fire proofing is installed in accordance with

drawings and specifications.

5.

All approved gates and other safety devices are installed in accordance with

drawings and specifications.

6.

All bollard posts are installed in appropriate locations in accordance with drawings

and specifications.

7.

All construction debris are removed and the area is in a broom clean condition.

8.

All architectural work, which includes but is not limited to roofing, windows, and

doors, etc., is in accordance with drawings and specifications.

9.

All structural steel, pipes, equipment, and other structures are painted in

accordance with drawings and specifications.

10.

All civil related NCRs that affect this system have been closed.

11. Other

Subcontractor

Industria del Hierro

Client

Name:

Name:

Name:

Signature:

Signature:

Signature:

Date:

Date:

Date:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16-04

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

MECHANICAL COMPLETION ELECTRICAL / INSTRUMENTATION CHECKLIST

The Client:

Contract No.:

SYSTEM NUMBER:

SYSTEM DESCRIPTION:

1.
All electrical/instrumentation installations have been installed in accordance

with design and vendor documents.


2.

All electrical cables have been meggered (and DC hi-pot tested if over 1000v

rating)

3.

All associated switchgear, breakers, transformers, relays, busway, and

distribution equipment has been inspected and/or tested in accordance with

project specifications.

4.

All motors and air cooler fans have been meggered and bumped to check

direction of rotation.

5.

All associated instruments have been calibrated, function tested and/or loop

tested as required by project specifications.

6.

Instruments are calibrated and installed in accordance with design documents.

7.

Instruments and instrumentation tubing are tested as required by code and

specifications.

8.

All electrical/instrumentation related NCRs that affect his system have been

closed.

9.

Other

Subcontractor

Industria del Hierro

Client

Name:

Name:

Name:

Signature:

Signature:

Signature:

Date:

Date:

Date:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16-05

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

MECHANICAL COMPLETION / MECHANICAL CHECKLIST

The Client:

SYSTEM NUMBER:
SYSTEM DESCRIPTION:

1.

Piping is installed in accordance with design documents. Hydro tests have

been completed.

2.

Pipe supports; hangers, guides, anchors, spring cans, etc., have been

installed in accordance with design documents. Travel stops on spring

hangers for water filled piping are to be removed after the applicable piping

system has been filled with water. At this time "cold load setting" shall be

verified. Travel stops on spring hangers for steam or gas filled piping have

been removed by construction and cold load settings have been verified.

3.

Rotating equipment is installed in compliance with vendor and specification

requirements. Cold alignment has been performed and base plates are

grouted.

4.

Maintenance on applicable equipment has been performed.

5.

Temporary lubricants and rust inhibitors have been removed and initial
lubrication is complete.

6.

All vessel internals, packing and desiccants are installed and Fluor's final

closures are completed.

7.

Mechanical related NCRs that affect this system have been closed.

8.

Coatings; paint and insulation complete.

9.

Other

Subcontractor

Industria del Hierro

Client

Name:

Name:

Name:

Signature:

Signature:

Signature:

Date:

Date:

Date:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16-06

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

MECHANICAL COMPLETION / QUALITY CONTROL CHECKLIST

The Client:

SYSTEM NUMBER:

SYSTEM DESCRIPTION:

1.

Turnover notice and the supporting documentation have been received.

2.

Hydrostatic test packages for this system are complete, accepted, and are

included in this system package.

3.

Quality control records for this system are complete and are included in this

system package as required.

4.

All NCRs, that affect this system, are closed and are on file.

5.

Other:

Subcontractor

Industria del Hierro

Client

Name:

Name:

Name:

Signature:

Signature:

Signature:

Date:

Date:

Date:

The DOW Chemical Company


Gulfstream Light Hydrocarbon Unit 9 Project
Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-16-07

August, 2014 Rev.01

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

Page:

Master Punch List

of

TO System:

TO System Description:

Print Date:

Priority 1 Items to be completed before handover of the Package to the next phase
Priority 2 Items may be completed anytime at the approval of Client
Priority 3 Items generated by the Client/operations, Added scope

Groups:

PL

No

Tag/Line/Cable

Raised
By/On

Priorit

Status

PL Item Description & Comments

Group
Resp.

(Disc)

Mat

Eng

Reqd by
Date

VE Vendor
CC Construction
CM Commissioning
SU Start Up

Cleared
By

Verified
Date

By

Dat

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16-08

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

INTERIM TURNOVER NOTICE ___________________

As The Client's Project Manager and duly authorized representative, I hereby issue
in accordance with - Completion and Acceptance - of the Principal Document, this
INTERIM TURNOVER NOTICE for: _________________.
Interim Turnover Package _________________

Under the terms and conditions of:


Contract Number: ___________
Dated: _________
Between the Client and Industria del Hierro.

and certify that Mechanical Completion of the above portion of Work was achieved on
__________________.
A Master Punchlist is attached indicating items which are still incomplete or known to be
deficient and the dates such items are to be finished or corrected. It shall remain asIndustria
del Hierro's responsibility to finish and correct this work by the dates so indicated, as well as

correcting any deficiencies which are uncovered during the startup operations.
The issuance of this TURNOVER NOTICE does not in any way denote The Client's concurrence

that the Facility, or any part thereof, fully conforms to Job Specification nor relieve Fluor from
its obligations under - Warranties and Guarantees. It does constitute The Client's assumption

of care, custody, control and responsibility for the above mentioned portion of the work.
Notwithstanding, all conditions and terms of Contract N. _________ (Amended) are still valid.

The Client/Date

Industria del Hierro/Date

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-16-09

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

Mechanical Completion Certificate


Project No.

MCC No.

Date:

This documents the turnover to and acceptance by the Client of equipment and / or systems listed

below as being mechanically complete in accordance with the established system boundaries.

COMPONENT,SYSTEM, OR SUBSYSTEM
NUMBER

DESCRIPTION

Systems Includes the following:

Exceptions to the above scope

SIGNATURES
Released By: Industria del
Hierro

Date:

Accepted By: Client

Date:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-17

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

MATERIAL AND EQUIPMENT STORAGE AND MAINTENANCE

SCOPE

This procedure defines the requirements for periodic inspection of the storage and maintenance of

designated materials and equipment.

RESPONSIBILITIES - Self-Perform / Subcontracted

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY OF

ACTIVITY

Develop a
material/equipment
storage requirement list

Subcontractor/
Construction or
Engineer

See Attachment 1 for


"Sample" list

Prior to receipt of

material & equipment

Generate the storage


inspection checklist

Subcontractor/
QA/QC Manager

Form: SA5-DOW-01-1701

Prior to receipt of

material & equipment

Inspect storage &


maintenance

Subcontractor/
QA/QC Manager

Form: SA5-DOW-01-1701

Monthly during the life

of the activity

Resolve discrepancies as
appropriate

Subcontractor/
QA/QC Manager

Form: SA5-DOW-01-1701

As required to resolve

discrepancies

Surveillance

QA/QC Manager
(*Note 1)

Form: SA5-DOW-01-1401

Per procedure SA5DOW-01-14

*Note 1: Surveillance is not required if the Industria del Hierro Quality Representative is performing

inspections.

PROCEDURE

Storage Requirement List


-

Storage Inspection Checklist


-

Develop a material/equipment storage requirement list (see Attachment 1 for a sample list)

consisting of protective measures to prevent damage, deterioration, or contamination of

material and equipment.

Using the material/equipment storage requirement list as a guide, generate a Storage

Inspection Checklist (refer to Form SA5-DOW-01-17-01 for a sample).

Inspection of Storage and Maintenance


-

Perform inspections of storage areas, including items stored "In-Place", on a monthly basis.

Document any discrepancies noted during inspections.

Discrepancy Resolution
-

Resolve any noted discrepancies with the appropriate parties.

Perform re-inspection(s) to verify that the noted discrepancies have been corrected.

ATTACHMENTS & EXHIBITS

Attachment

Attachment 01 - Material/Equipment Storage Requirement List (Sample)

Quality Form:

SA5-DOW-01-17-01 - Storage Inspection Checklist

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

SA5-DOW-01-17-01

August, 2014 Rev.01

Page 1 of 1

Revision 01

STORAGE INSPECTION
CHECKLIST

Item: ____________________________________________ Date: ____________________

Storage Area: _____________________________________ Storage Level: _____________________

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.

Are identifications and markings intact?


Are covers, plugs, caps intact?
Are temporary preservatives and coatings intact?
Is desiccant saturated?
Any evidence of physical damage?
Is proper cleanliness being maintained?
Are instrument racks energized as specified?
Are space heaters energized as specified?
Has rotating equipment been rotated as specified?
Has rotating equipment been tested as specified?
Evidence of damage to items hit by a forklift or truck?
Any water damage?
Is dust and dirt excessive?
Are items and materials on cribbing as specified?
Any container items broken or leaking?
Has storage level been maintained?
All original equipment logs and associated data is send to

Fluor Document Control at the Mod Yard?

YES

NO

N/A

____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____

____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____

____

____

____

____

____

____

____

____

____

____

____

____

____

____

____

____

____

____

____

Discrepancies:

Is Re-inspection Required?

Yes __________ No __________

Remarks:

________________________
Inspector

____________________

Date

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-17

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

MATERIAL/EQUIPMENT STORAGE REQUIREMENT LIST

The requirements for storage are divided into four levels with respect to protective measures to prevent

damage, deterioration or contamination of items and materials based upon important physical

characteristics, the ambient conditions during construction installation and operation of the item or material,

as required.

Level A - Items classified to Level A are those that are exceptionally sensitive to environmental conditions

and require special measures for protection from one or more of the following effects: temperatures outside

required limits; sudden temperature changes; humidity and vapors; gravitational (g) forces; physical

damage and air-borne contamination (e.g., rain, snow, dust, slat spray, fumes). The following shall be used

as a guide for classifying items intended for Level A classification:

a.

Special electronic equipment and instrumentation.

b.

Special materials, such as chemicals that are sensitive to environment.

c.

Computers

Level B - Items classified to Level B are those that are sensitive to environmental conditions and require

measures for protection from the damaging effects of one or more of the following: temperature extremes,

humidity and vapors, gravitational forces, physical damage and airborne contamination but do not require

the special protection required for Level A items. The following shall be used as a guide for classifying items

intended for Level B classification:

a.

Instrumentation

b.

Electrical penetrations

c.

Batteries

d.

Welding electrode and wire

e.

Motor control centers, switchgear, and control panels

f.

Motors and generators

g.

Precision-machined parts

h.

Erection spares, such as gaskets, "O" rings

i.

Air-handling filters

Level C - Items classified to Level C are those that require protection from exposure to the environment,

air-borne contaminants, gravitational forces, and physical damage. Protection from water vapor and

condensation is not so important as that for Level B items.

The following shall be used as a guide for classifying items intended for Level C classification:

a.

Pumps

b.

Valves

c.

Fluid Filters

d.

Compressors

e.

Turbines

f.

Instrument cable

g.

Thermal insulation

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-17

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

h.

Fans and blowers

Level D - Items classified to Level D are those that are less sensitive to the environment than Level C.
These items require protection against the elements, air-borne contamination, and physical damage.

The following shall be used as a guide for classifying items intended for Level D classification:

a.

Tanks

b.

Heat exchangers and parts

c.

Accumulators

d.

Demineralizers

e.

Evaporators

f.

Piping

g.

Electrical cable

h.

Structural items

i.

Reinforcing steel

STORAGE REQUIREMENTS

Items assigned a level of storage shall be maintained at this level of storage until they are removed from

storage. Items removed from storage and installed, but not operating, shall have the assigned level of

storage maintained.

Levels of Storage

Environmental conditions for items classified as levels A, B, C, and D described in this procedure shall meet

the following requirements:

Level A - Items shall be stored under those conditions described for Level B items but with any additional

requirements detailed by the manufacturer and/or engineering representative.

Level B - Items shall be stored within a fire-resistant, tear-resistant, weathertight, and well-ventilated

building or equivalent enclosure. Precautions shall be taken against vandalism. This area shall be situated

and constructed so that it will not be subjected to flooding; the floor shall be paved, or equal, and welldrained. Items shall be placed on pallets or shoring to permit air circulation. The area shall be provided

with uniform heating and temperature control, or its equivalent, to prevent condensation and corrosion.
Minimum temperature shall be 40F and maximum shall be 140F or less if so stipulated by the

manufacturer.

Level C - Items shall be stored indoors, or equivalent, with all provisions and requirements as set forth in

Level B items except that heat and temperature control is not required.

Level D - Items may be stored outdoors in well-drained areas marked and designated for storage,

preferable gravel-covered or paved, and reasonable removed from the actual construction and traffic so that

possibility of damage from construction equipment is minimized. Items shall be stored in 4-inch cribbing or

equivalent to allow for air circulation and to avoid trapping water.

Care of Stored Items


Care of items in storage shall be exercised in accordance with the following:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-17

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 3 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

a.

Items in storage shall have all covers, caps, plugs, or other closures intact. When it is necessary to

remove a cover for access purposes, it shall be immediately replaced and properly resealed

thereafter.

b.

Temporary preservatives shall be left intact during storage. Should reapplication of preservatives

be required at the site, only those previously approved shall be used.

c.

Desiccant humidity indicators shall also be monitored, and desiccants shall be changed or

reprocessed when specified.

d.

Instrumentation racks shall be energized as specified by the manufacturer.

e.

Space heaters enclosed in electrical items shall be energized.

f.

Rotating electrical equipment shall be given insulation resistance tests on a scheduled basis.

g.

The shafts of rotating equipment shall be rotated on a periodic basis. The degree of turn shall be 1

1/4 turn so that the parts receive a coating of lubrication where applicable, and so that the shaft

does not come to rest in a previous position.

h.

Implement special instructions issued by the vendor or manufacturer for a particular piece of

equipment.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-20

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

INSPECTION AND TESTING

Definitions

Inspection and tests are defined as follows:

"Inspection" being visual checks of a qualitative nature but also including dimensional measurements.

"Tests" being measured verifications of one or more characteristics or of performance, both being carried

out to ascertain whether or not the specified requirements have been met.

Inspection and Testing Procedures

Inspection and test measures to be applied are presented in this section. These procedures provide for the

inspections and tests necessary to determine that the product is acceptable and for the documentation to record

compliance with the established acceptance criteria. The inspection scope and frequency will be determined on a

case-by-case basis with guidance provided in the "Responsibilities" section of each procedure.

If specifications, vendor manuals, test procedures, codes/standards, or other such documents required by

specifications to be used as acceptance criteria are not readily available to inspection personnel, the QA/QC

Manager may include this information as attachments to these procedures. Attachments may also be used to list

the source documents providing acceptance criteria for tests and inspections within the scope of each procedure.

Inspection and Test Plans

An Inspection and Test Plan (ITP) is a document used to list the quality related activities that pertain to a distinct

scope of work or process.

The ITP shall consist of the following features:

a list of the inspection and test points presented in sequence in the order in which they are to be performed

for each activity, reference to a document stating the acceptance criteria;

for each activity, the "verification document" i.e. the document to be checked or the one used to record the

result of the inspection or test;

for each activity for both Contractor and INDUSTRIA DEL HIERRO, where required, an indication of the scope

of inspection as follows:

I - Inspect

T - Test
W - Witness Point

This indicates an Inspection/Text Activity on the ITP that requires a request for

the presence of the Industria del Hierro Representative.

R Review

This indicates a document review, with or without the presence of the


Inspector in the activity.

H - Hold Point

This indicates an inspection or test which is considered vital to the quality,

integrity and safe functioning of the material or services and which can only be

achieved at this point. It is an Inspection/Test Activity on the ITP that requires

the presence of the Industria del Hierro Representative. The Production/Erection

Process cannot proceed beyond this point until it has been cleared by the

Inspection Industria del Hierro Representative.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-20

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

ITPs may be used to record completion of activities, indicated by sign-off (acceptance). This is normally applicable

to scopes of work encompassing a relatively self-contained unit such as a steam turbine or cooling tower. For

processes such as piping installation, Inspection and Test Plans shall be documented on form SA5-DOW-01-2001.
ITPs may be used in lieu of or in conjunction with Inspection and Test Procedures.

Inspection Cycles

Adequate inspection will be performed to cover required construction operations. The inspection cycle normally

includes preparatory, initial, follow-up and final inspection. This cycle is described below:

Preparatory - Performed prior to beginning work to ensure the prerequisites are satisfied and

requirements understood by those who perform the work. It includes a review of requirements; a check

to assure that all materials and/or equipment are on hand and are approved and that all preliminary work

has been completed.

Initial - Performed at the outset of segments of work to get the work off to a proper start in full

compliance with contract requirements.

Follow-up - Performed daily or as frequently as necessary to assure continuing compliance with contract

requirements.

Final - Inspections that verify the acceptance of completed items. This occurs throughout fabrication and

installation. Acceptance is indicated by use of the inspection checklist referenced by procedures of this

section.

The inspection status of constructed or installed items is normally determined by reference to the inspection or

test reports/checklists included as referenced forms to these procedures. These forms are completed concurrently

with the construction /installation activities.

Deficiencies that are found during inspection, and cannot be corrected at that time, are to be documented on

Surveillance Reports (SA5-DOW-01-14-01), so that they can be tracked to closure. In special cases that are

described by SA5-DOW-01-07 where a NCR is needed, that documentation does not need to be duplicated by a

Surveillance Report.

FORMS

Quality Control Form:

SA5-DOW-01-20-01

- Inspection and Test Plan Form

ATTACHMENTS

Attachment 1

Instructions for completion of the ITP form

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-20

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

Instruction for Preparing the Inspection Test Plan

Field Name

Description

Activity

Identify the general activity or scope of work for the ITP

Description

Identify the specific activity that applies to the ITP

Project Name/Number

Enter project name and number

Client

Enter Client name

Contractor

Enter contractor name (if subcontracted)

Contract Number

Enter contract or subcontract number as applicable

ITP Number

Uniquely Identify the ITP, ITP XXXX

Issue Date/Revision Number Enter the current issue date and revision

Item Number

Used to identify the sequence of the quality-related activity

Quality-Related Activity

Enter a description of the quality-related activity

Requirement and
Acceptance Criteria

Enter the acceptance criteria or reference to the specification or

other standard where the acceptance criteria may be found.

Responsibility

Enter the Industria del Hierro position primarily responsible for

executing Industria del Hierros participation in the activity. Use the

code legend on the bottom of the ITP form to represent the

entities.

Scope of Inspection

Use these fields to specify the level of participation required by the

various entities.

Inspection Record

If an inspection record is to be used to document the inspection

results, enter the form or record number.

Completion Sign-off

Indicate if Industria del Hierro and/or Client signatures are

required.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-20-01

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

Activity:

Inspection and Test Plan

Industria del Hierro

Description:
Client:

Item

Project Name:
Contractor:

Inspection/Test Stage

Project Location:
Contract Number:

Requirement and
Acceptance Criteria

Inspection Legend:
P = Perform
I = Inspection
T = Test
R = Review and Approve
W = Witness (Notification of authorized inspection personnel required)
H = Hold (Mandatory, do not proceed without presence of authorized inspection personnel or
signed waiver)

Project Number:

Document Number
ITP XXXX
Revision X
Responsibility

Issue Date:

Scope of Inspection
Sub

IH

Responsibility Legend:

CS = Industria del Hierro Construction Supervision

CM = ndustria del Hierro Construction Manager


QI = ndustria del Hierro Quality Inspector
CWI = ndustria del Hierro Certified Welding Inspector
RI = ndustria del Hierro Receiving Inspector
NDE = Certified NDE Examiner

Client

Inspection

Record

Remarks

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-21

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

STRUCTURAL STEEL

SCOPE

This procedure describes the functions to be performed in the inspection of the erection of structural steel.

RESPONSIBILITIES - Self-Perform

ACTIVITY

RESPONSIBILITY

FREQUENCY

DOCUMENTATION

Form SA5-DOW-01-21-01

OF ACTIVITY

Verify acceptability of

Interface Structures

QA/QC Manager

Once for each

structure

Erect Structural Steel

Civil Superintendent

Inspect In-process
Structural Steel Erection

QA/QC Manager

Form SA5-DOW-01-21-01

Daily during life of

activity

Perform Final Inspection

QA/QC Manager

Form SA5-DOW-01-21-01

Once per structure

--------

--------

PROCEDURE

Verify Interface Structures:


Prior to structural steel being erected, verify that all interface work such as elevations, conform to the

applicable drawings.

Erection of Structural Steel:


Structural steel shall be erected in accordance with the applicable project specifications.

Assure structures are not loaded prior to sufficient progression of erection and completed bolting has been

accepted.

Welding shall be performed by AWS qualified welders in accordance with weld procedure specifications.

Modifications to steel member shall only take place upon issuance of direction from Design Engineering.

In-Process Inspection of Structural Steel Erection:


Inspect the in-process steel erection to verify that fabrication is correct and erection is in accordance with

the drawings. Inspection shall include checking for plumbness, rectangularity, field welds, bolt tensioning

and touch-up painting.

Visual weld examination shall be performed, Welding Inspection as required.

Document inspections on Form SA5-DOW-01-21-01, Structural Steel Inspection Checklist. Highlighted

steel erection drawings.

When a calibrated impact wrench is used for erection, the calibration shall be witnessed by the QC

Inspector and documented on Form SA5-DOW-01-21-02, Torque Wrench Calibration Log.

When bolting inspection by impact is required, it shall be performed with a separate calibrated inspection

wrench.

When load-indicating washers (LIW) are specified, installation inspection will be performed in accordance

with the sample rate specified.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-21

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Inspect bolts installed by turn-of-nut method in accordance with AISC Section 6, Specification for

Structural joints using ASTM A325 or A490 bolts.

The number of checklist completed should be a sufficient number to clearly indicate full coverage of all

portions of the work on the project as work progresses.

Each checklist generated should represent a well-defined piece of work, i.e., building line, floor, run of

pipe rack, etc.

Perform Final Inspection:


Perform final inspection, in part, or on the total structure.
Structural Steel Inspection.

Document on Form SA5-DOW-01-21-01,

Document deficiencies, for tracking purposes, on Form SA5-DOW-01-14-01, Surveillance Report.

Note: ANSI/AWS D1.1


All completed welds shall be visually examined.

FORMS

SA5-DOW-01-14-01

Surveillance Report

SA5-DOW-01-21-01

Structural Steel Inspection Checklist

SA5-DOW-01-21-02

Torque Wrench Calibration Log

SA5-DOW-01-21-03

Structural Steel Checklist

SA5-DOW-01-21-04

Punch list

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

SA5-DOW-01-21-01

August, 2014

Page 1 of 1

Revision 01

STRUCTURAL STEEL
INSPECTION CHECKLIST

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Drawing No.:
Item

Specification No.:

Description of Check

Subcontractor

FOUNDATIONS
01

Foundation inspections and tests complete.

02

Leveling plate or billet plate grouting complete and checked.

Piles

Soils

Concrete

ANCHOR BOLTS
03

Grade and elevation

04

Anchor bolts condition

05

Base plate condition

06

Bearings surface cleaned and protected

07

Shimming of base plates

FIT-UP
08

Correct numbers location, and size

09

Survey Group checks alignment, plumbness, spacing, and elevation for conformance to erection

tolerances

10

Match of member

11

Members free of distortion

12

Mating surfaces free of paint

BOLTS
13

Correct grade

14

Correct length

15

Correct size

16

All bolts visually inspected to verify evidence of tightening

17

Connections marked indicating statues

18

Bolt tightening method used:

Calibrated Wrench

Turn-of-Nut

Load Indicating Washers

Snap-Off Fasteners

WELDING
19

Welds approved by welding inspector

20

Railings and Ladders installed / inspection complete

21

Grating installed / inspection complete

22

Field coatings checked

23

Fireproofing inspections and tests complete

24

Final inspection complete

Subcontractor

Industria del Hierro

Other

Name:

Name:

Name:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Industria

del Hierro

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

TORQUE WRENCH
CALIBRATION LOG

SA5-DOW-01-21-02

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontracto

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Minimum Fastener Tension (Kips) for:

Dia. inches
1/2
5/8
3/4
7/8
1
1 1/8
1 1/4
1 3/8
1 1/2
Date

Bolt
Size

A325 Bolts
12.6 Kips
20.0 Kips
29.4 Kips
41.0 Kips
53.6 Kips
58.8 Kips
74.6 Kips
89.3 Kips
108.2 Kips

Tension Reading*
Before Adjustment

A490 Bolts

15.8 Kips
26.2 Kips

36.8 Kips
51.5 Kips

67.2 Kips
84.0 Kips

107.1 Kips
127.1 Kips

165.4 Kips

Bolt Tightening Equipment Used:

Calibrated Equipment Used:

Tension Reading*

After Adjustment

* Each tension reading shall be the average of three bolts.

Signature

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

SA5-DOW-01-21-03

August, 2014

Page 1 of 1

Revision 01

STRUCTURAL STEEL
CHECKLIST

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Item

Description of Check

Subcontractor

01

Structural elements (main structure, bulkheads, decks, platforms/

walkways, grating, roof)- installed and checked against drawings

02

Structural elements - plumb, level, aligned

03

All structural supports installed per design and all temporary aids/

brackets removed

04

All temporary aids/ brackets/ steel removed

05

Anchor bolt nuts tight

06

Column base grouted

07

Bolted connections checked

08

Welded connections checked

09

Stairs, handrails, ladders, floor plates in place and per design

10

All penetrations installed, with sleeves/ kick plates of specified size

complete with drain holes as required

11

All welding and NDT work completed and cleared

12

Coatings applied, touch-up complete

13

All temporary bracing color code orange

Industria

del Hierro

Notes:

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

STRUCTURAL STEEL
CHECKLIST

SA5-DOW-01-21-03

August, 2014

Page 2 of 1

Revision 01

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067


INDUSTRIA DEL HIERRO S.A. DE
C.V.

STRUCTURAL STEEL PUNCH

LIST RECORD

SA5-DOW-01-21-04

August, 2014

Page 1 of 1

Revision 01

REFERENCE: DRAWING _______________________________________________________________________________________________

ITEM
NO.

IDENTIFICATION
AND LOCATION

REMARKS

DATE
CORRECTED

SUPERVISORS
APPROVAL

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-0122

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

EQUIPMENT

SCOPE

This procedure defines the inspection, testing and documentation requirements for construction activities for

equipment erection and installation that is either self-performed or subcontracted.

RESPONSIBILITIES - Self-Perform
ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY

_____

As required by the

controlling

documents

OF ACTIVITY

Implement storage,
handling and maintenance
requirement

Construction Engineer/
Craft Supervision

Check anchor bolt


surveying

Construction Engineer

Survey Field Books

Prior to setting
equipment

Check level, alignment and


plumbness

Construction Engineer

Survey Field Books

Prior to setting
equipment

Install/Erect equipment

Mechanical
Superintendent

Form SA5-DOW-01-22-01

Once for each

piece of

equipment

Monitor In-process
Installation Activities

QA/QC Manager

Form SA5-DOW-01-22-01
Form SA5-DOW-01-22-02

Daily during the

life of the activity

Perform final inspection of


installed equipment

QA/QC Manager

Form SA5-DOW-01-22-01
Form SA5-DOW-01-22-02

Once after

installation

completed

Resolve any discrepancies


identified

Construction
Engineering
QA/QC Manager

Form SA5-DOW-01-22-01
Form SA5-DOW-01-22-02

As required to

resolve

discrepancies

Surveillance

Quality Inspection
(Note 1)

Form SA5-DOW-01-14-01

Per Procedure

SA5-DOW-01-14

NOTE 1:

Surveillance is not required if the QA/QC Manager is performing inspections.

PROCEDURE

Client involvement in the witnessing of key aspects of erection, installation and checkout shall be carefully

adhered to and documented by Client signature and date.

Client notification of upcoming witness points will be given in writing a minimum of twenty-four (24) hours

prior to the event.

If required, notify the Client's Representative that final alignment is scheduled.

Implementation of Storage, Handling and Maintenance Requirements:


-

The Construction Manager shall define the storage, handling and maintenance

requirements for each type of equipment for implementation by site personnel. These

requirements apply from receipt until turnover whether in lay down storage or set in place.

Inspect/monitor prescribed equipment preservation activities.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-0122

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Verification of Anchor Bolts, Level, Alignment and Plumbness:


-

Verify/check the anchor bolt locations and elevation, prior to setting the equipment on the

foundation.

Installation/Erection of Equipment:
-

The Mechanical Superintendent shall install/erect the equipment in accordance with the

applicable drawings and specifications.

Verify/check the plumb, alignment and orientation of equipment as well as the openings for

elevation and location, immediately after installation.

Monitor In-process Equipment Installation Activities:


-

Initiate the appropriate Equipment Installation Checklist, for each piece of equipment.
Document the applicable in-process inspections as they are acceptably completed.

Monitor/inspect the in-process installation of each equipment unit. Document inspection as

it is completed on the applicable Equipment Inspection Record.

Inspect for grouting of equipment as required by specification and drawings.

Final Inspection of Installed Equipment:


-

Verify that storage, handling and maintenance requirements are defined and implemented

for each piece of equipment. Monitor these activities on a periodic basis or as required by

specifications.

Perform final equipment inspection at the completion of installation activities. Deficiencies

shall be documented, in the Master Punch List.

Resolve Discrepancies:
-

Resolve exceptions and correct,


Perform/coordinate re-inspections.

deficiencies,

with

Client

in-put

as

required.

ATTACHMENT AND EXHIBITS


Quality Forms:

SA5-DOW-01-22-01

Equipment Installation Checklist

SA5-DOW-01-22-02

Inspection Record Static Equipment

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

EQUIPMENT INSTALLATION

CHECKLIST

SA5-DOW-01-22-01

August, 2014

Page 1 of 1

Revision 01

Inspection & Test Checklist


Item Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Item

Description of Check

Subcontractor

01

Receiving Inspection complete and accepted.

02

All shipping stops, bracing and packaging removed.

03

Rigging and handling. (Attach Rigging Plan)

04

Unit installed according to vendor instructions, undamaged, with

skid location and orientation correct, holding down arrangement


complete and secure.

05

Check vibration mountings are secure and set correctly.

06

Check equipment is level and shim material is to the correct

specification.

07

Item orientation and elevation is correct. Inspect bolting and

anchoring

08

Final alignment and rotation checked.

09

Nameplate details correct and in accordance with the datasheet.

Nameplate securely attached, readable not obscured.

10

Purchased equipment release note available.

11

All shipped loose knocked down items re-installed in accordance

with vendors installation instructions.

12

Where preservation materials are installed, equipment is suitably


marked PRESERVATION INSIDE.

13

Unit clean and free from external damage and all paint work in

good condition.

Industria

del Hierro

Notes:

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-22-02

August, 2014

Page 1 of 1

Revision 01

STATIC EQUIPMENT

INSPECTION RECORD

INDUSTRIA DEL HIERRO S.A. DE


C.V.

Inspection Test Checklist


Tag No.:

Tag Description:
P. O. No.:

Inspection Classification

Turnover System:

Subcontractor:

Subcontractor

Client

Sub System:

Fluor

Other

Location:

Subject

Subcontractor

1.

Verify nameplate data meets description.

2.

Verify preservation integrity (if applicable).

3.

Verify foundation and foundation bolts meet specified requirements.

4.

Verify installation tolerances have been met.

5.

Verify grouting meet specifications.

6.

Verify all internals are correctly installed.

7.

Verify all shipping devices have been removed.

Industria del

Hierro

8. Verify all vents, drains, and instruments con. etc. are installed in

ACC. with
equipment trim isometrics.

9.

Verify alignments of piping connections are correct.

10. Verify coating system meets specified requirements.


11. Verify insulation meets specified equipment.
12. Verify prior to final closing for internal cleanliness.
13. Verify all ladders, platforms, stairways and walkways on correctly

installed.

14. Orientation correct


15. Correct shimming installed
16. Tightness of anchor bolts nuts
17. Grouting completed
18. Sliding plate free (for horizontal vessels only ) & lubricated
19. Trays/down comers/support rings
20. Davits installed (Where applicable )
21. Ready for closure

Subcontractor

Industria del Hierro

Client

Others

Name

Name

Name

Name

Signature

Signature

Signature

Signature

Date

Date

Date

Date

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-23

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

PIPING

SCOPE

This procedure applies to the activities associated with inspection and testing of piping.

RESPONSIBILITIES - Self-Perform Pipe Installation

ACTIVITY
Welding Inspection and

Testing

RESPONSIBILITY
QC Inspector

DOCUMENTATION

Per SA5-DOW-01-35

FREQUENCY OF

ACTIVITY

Per SA5-DOW-01-35

Form SA5-DOW-01-23-01

Inspect on-site pipe

fabrication and
installation

QC Inspector

Cleaning of Pipe

Per SA5-DOW-01-25

Per SA5-DOW-01-25-01

Per SA5-DOW-01-25

Inspect Insulation

Per SA5-DOW-01-33

Per SA5-DOW-01-33-01

Per SA5-DOW-01-33

Pressure Test

Per SA5-DOW-01-24

Per SA5-DOW-01-24-01

Per SA5-DOW-01-24

SA5-DOW-01-23-02

Each installation

SA5-DOW-01-23-03

Responsibilities - Subcontracted Pipe Prefabrication

ACTIVITY
Welding Inspection &

Testing

RESPONSIBILITY
Subcontractor

DOCUMENTATION

Per SA5-DOW-01-35

FREQUENCY OF

ACTIVITY

Per SA5-DOW-01-35

Form SA5-DOW-01-23-01

Inspect on-site pipe

fabrication and
installation

Subcontractor

Cleaning of Pipe

Subcontractor

Per SA5-DOW-01-25-01

Per SA5-DOW-01-25

Inspect Insulation

Subcontractor

Per SA5-DOW-01-33-01

Per SA5-DOW-01-33

Pressure Test

Subcontractor

Per SA5-DOW-01-24-01

Per SA5-DOW-01-24

Surveillance

QA/QC Manager

Form SA5-DOW-01-14-01

During life of activity

SA5-DOW-01-23-02

Each installation

SA5-DOW-01-23-03

PROCEDURE

Welding Inspection and Testing


Reference Procedure SA5-DOW-01-35 for the welding inspection and testing requirements.

If the work is subcontracted, the subcontractor's quality program shall be invoked.

Pipe Fabrication and Installation

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-23

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Verify that pipe fabrication and installation activities are performed in accordance with the

requirements documented in the applicable drawings and specifications.

Use Attachment 1 (Pipe Inspection Reference) as a guide in performing inspections.

Use Form SA5-DOW-01-23-01, SA5-DOW-01-23-02, to document inspection results.

Punching Lines
When Construction indicates the work is complete, document deficiencies on Punch list

Cleaning of Pipe
Reference Procedure SA5-DOW-01-25 for the cleaning of pipe inspection and testing requirements.

Insulation Inspection
Reference Procedure SA5-DOW-01-33 for the insulation inspection requirements.

Pressure Testing of Piping Systems


Verify that required pressure testing has been performed and documented.

ATTACHMENTS & EXHIBITS

Attachments

Attachment 1 - Pipe Inspection References

Quality Forms:

SA5-DOW-01-23-01 - Pipe Inspection Checklist

SA5-DOW-01-23-02 - Visual Inspection of Flanges, Gaskets and Bolting

SA5-DOW-01-23-03 - Punch list

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-23

Attachment 01

August, 2014

Page 1 of 1

Revision 01

PIPING INSTALLATION

CHECKLIST

INDUSTRIA DEL HIERRO S.A. DE


C.V.

SYSTEM I.D.(LINE No./DRAWING No./AREA):


PIPING MATERIAL

PIPE SUPPORTS

LINE SIZE & SCHEDULE

MATERIAL SPEC

FLANGE RATING
FACE FINNISH

OTHER:

PIPING FIT-UP

LEVEL AND PLUMB

JOINT ALIGNMENT

LINE SLOPE PER DWG

ORIENTATION & DIMENSIONS

BRANCH LINE LOCATION

BRANCH LINE REINFORCEMENT

REDUCER TYPE & ORIENTATION

CLEARENCES ADEQUATE FOR EXPANSION


CLEARENCES ADEQUATE FOR INSULATION

PIPE BEND DISTORTION TO SPEC

COLD SPRING PER DWG

OTHER:

FABRICATION COMPLETION
VENTS & DRAINS INSTALLED
VENTS & DRAINS GUSSETED
INSTRUMENT CONNECTIONS
WEEPHOLES IN RE-PADS
WELDING COMPLETE
WELDS ALL STAMPED/MARKED
OTHER:

VALVES PRE-TEST
SPEC & TAG VERIFIED
FLOW DIRECTION VERIFIED
ORIENTATION PER DWG/SPEC
VALVE HANDLES/WHEELS/CHAINS/EXTENSIONS
VALVE BYPASSES
VALVE DRAIN/FLUSH CONNECTIONS
OTHER:

BOLT-UP

SHOES INSTALLED/WELDED

SUPPORTS INSTALLED

SUPPORTS ADEQUATE

ANCHORS INSTALLED

GUIDES INSTALLED

WEEPHOLES IN SUPPORTS

SPRING SUPPORT STOPS REMOVED

EXPANSION JOINT SHIPPING BARS REMOVED

OTHER:

READY FOR PRESSURE TEST

TEST SYSTEM IDENTIFIED

INSTRUMENTS REMOVED/ISOLATED

EQUIPMENT ISOLATED

EXPANSION JOINTS ISOLATED

BLINDS INSTALLED

VALVES IN CORRECT POSITION

ALL JOINTS EXPOSED & NOT PAINTED

SUPPORTED FOR WATER WEIGHT

CALIBRATED TEST GAUGES INSTALLED

TEMPERATURE/HUMIDITY SUITABLE

OTHER:

SYSTEM COMPLETION AFTER TEST

VALVES & IN-LINE ITEMS

BOLT/STUD/NUT SPEC

BOLT LENGTH

GASKET SIZE/SPEC/RATING

TIGHTENED/TORQUED

OTHER:

Contractor

ALL TEST BLINDS REMOVED OR TAGGED


SYSTEM DRAINED/DRIED
IN-LINE INSTRUMENTS INSTALLED
STRAINERS/SCREEENS INSTALLED
FINAL BOLT-UP CHECKED
FLANGES TAPED (IF REQUIRED)
PAINT/TOUCH-UP
OTHER:

HEAT TRACING

TRACER INSULATION SUPPORT CLIPS

TRACER LENGTH &COVERAGE PER DWGS/SPECS

TRACER TUBING (OR ELEC.) SIZE & NUMBER

TRACER BANDED

TRAP DETAILS TO SPECS

SUPPLY/RETURN FLOW TO CORRECT MANIFOLD

TRACER TUBING (OR ELEC.) TESTED

TRACER LEADS (OR WIRING) TAGGED

OTHER:

Industria del Hierro

Client

Name:

Name:

Name:

Signature:

Signature:

Signature:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

SA5-DOW-01-23-01

August, 2014

Page 1 of 1

Revision 01

PIPE INSPECTION
CHECKLIST

Inspection & Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Item

Description of Check

Subcontractor

Industria del

Hierro

General
01

System complies with P and ID's and isometric drawings.

02

Piping fabrication ITR complete and accepted.

03

All field weld inspection and NDE, traceability and history records complete and

accepted.

04

All NDT/stress relieving requirements performed in accordance with

requirements and documented.

05

Correct bolts and gaskets are installed at all mechanical joints.

06

All vents and drains are installed, including vents and drains for testing and are
of correct pressure rating.

07

Piping of correct material, schedule and type.

08

Rating of all forged steel fittings is correct.

09

Check valve materials - (use spec ref. in piping material specification, tags and

nameplates.

10

Branch reinforcements are correct.

11

Compound on screwed connections in accordance with specifications.

12

All pressure connections as per specification.

13

Correct direction of flow through filters and strainers traps, check valves, globe
valves and control valves.

14

All instrument connections installed and any delicate instruments are isolated/
removed from test.

15

All relief valves, bursting disks, and specified control valves have been removed.

16

Check orifice valve tap orientation correct, taps and plugs have been sealing
welded and unused. Tapped holes are plugged and welded.

17

Check orifice flanges have required upstream and downstream clearances, that
bores have been ground and orifice plates have been removed.

18

All thermowells are installed.

19

All pipe supports installed according to drawings and specifications.

20

Gags on spring supports and expansion joints are in position.

21

Check that system is adequately supported such that no spring in pipework


causes stress on pumps or vessel nozzles.

22

All chainwheels and extended spindles installed.

Notes:

Subcontractor

Industria del Hierro

Client

Other

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

VISUAL INSPECTION OF
FLANGES, GASKETS AND
BOLTING

SA5-DOW-01-23-02

August, 2014

Page 1 of 1

Revision 01

Inspection & Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Line/Drawing No.
Item

Line Class

Sheet No.

Description of Check

Subcontractor

01

Flange type and rating

02

Flange preparation and cleaning

03

Flange condition

04

Gasket type

05

Gasket condition and rating

06

Bolting type

07

Bolting size

08

Lubrication

09

Torque sequence correct

10

Torque values verified

11

Identification of torqued connection

12

Rejected items flagged

Rev. No.

Industria del H

Notes:

Subcontractor

Industria del Hierro

Client

Other

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067


INDUSTRIA DEL HIERRO S.A. DE C.V.

SA5-DOW-01-23-03

August, 2014

Page 1 of 1

Revision 01

PIPING PUNCH LIST


RECORD

REFERENCE: DRAWING _______________________________________________________________________________________________

ITEM
NO.

IDENTIFICATION
AND LOCATION

REMARKS

DATE
CORRECTED

SUPERVISORS
APPROVAL

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-24

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

PRESSURE TESTING

SCOPE

This procedure applies to pressure testing of self-perform or subcontractor installed piping systems.

RESPONSIBILITIES - Self-Perform

ACTIVITY

RESPONSIBILITY

Install Piping

Self Perform

Define Test Boundaries

Const. Pipe Eng. /Mech.


Supt.

Provide Preparation /

Const. Pipe Eng.

Test Instructions

Prepare the System for


Testing

Mechanical
Superintendent

Perform Pre-Test
Inspections/Release

Const. Eng./

Perform Test

Mechanical
Superintendent

Verification of Satisfactory
Test Results

Const. Eng./

Provide Restoration
Instructions

Const. Field Eng.

Verify Completion of
Restoration

Const. Field Eng./

Surveillance of Testing and


Restoration

QA/QC Manager

QA/QC Manager

QA/QC Manager

QA/QC Manager

DOCUMENTATION

FREQUENCY OF

ACTIVITY

-----SA-DOW-01-24-01

SA5-DOW-01-24-01

-----Each Test Package

Each Test Package

_____

SA5-DOW-01-24-01

_____

Prior to Test

_____

SA5-DOW-01-24-01

_____

Test Completion

_____

SA5-DOW-01-24-01
SA5-DOW-01-24-01

_____

Each Test

Daily

Responsibilities - Subcontracted

ACTIVITY

RESPONSIBILITY

Install Piping

Subcontractor

Define Test Boundaries

Subcontractor

Provide Preparation /

Const. Pipe Engr.

Test Instructions

Prepare the System for


Testing

Subcontractor

Perform Pre-Test
Inspections/Release

Subcontractor

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

DOCUMENTATION

-----SA5-DOW-01-24-01
SA5-DOW-01-24-01

_____

SA5-DOW-01-24-01

FREQUENCY OF

ACTIVITY

-----Each Test Package

Each Test Package

_____

Prior to Test

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-24

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

ACTIVITY
Perform Test

RESPONSIBILITY
QA/QC Manager
Subcontractor

Verification of Satisfactory
Test Results

Subcontractor

Provide Restoration
Instructions

Const. Pipe Engr.

Verify Completion of
Restoration

Subcontractor

QA/QC Manager

QA/QC Manager
Surveillance of Testing and
Restoration

QA/QC Manager

DOCUMENTATION

SA5-DOW-01-24-01

SA5-DOW-01-24-01

SA5-DOW-01-24-01

FREQUENCY OF

ACTIVITY

Prior to Test

Test Completion

Test Completion

_____

SA5-DOW-01-24-01

SA5-DOW-01-24-01
SA5-DOW-01-14-01

_____

Each Test

Each Test

Daily

PROCEDURE

Define Test Boundaries and Provide Preparation/Test Instructions:


Boundaries should be prepared and provided or made available to those responsible for Preparing the

System for Testing, Performing Pre-test Inspection Release, Performing Test, and Verifying

Satisfactory Test Results - Information should be included in pressure test packages. These packages

are, as much as possible, to be assembled so that they comprise a portion or all of a piping system.

This is required to facilitate system turnover at the end of the job. Each pressure test package shall

contain the following:

Marked up P&IDs indicating extent of test; location and type of blinds; and equipment or

instrumentation to be included or excluded from test.

Piping isometrics for lines included in the test. Isometrics are to indicate location of blinds,

valves open or closed, fill point, vent locations, equipment or instrumentation excluded from

test and locations of required temporary supports.

Instruction items are on Form SA5-DOW-01-24-01. Initiate this form and complete the

instructions through "Test Conditions".

Notes for special test situations.

Instructions for marking temporary test materials for verifying line restoration.

Special instructions and safety precautions when the test medium is a gas or vapor.

Instructions for preventing air entrapment.

Venting instructions.

Test gage location.

Identify all required "witnesses" of test.

Require all joints including welds to be uninsulated and exposed for examination during the

pressure test.

Provide retest instructions after repair of leaks detected by the pressure test.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-24

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

Prepare the System for Testing:


-

Perform Pre-test Inspections/Release:


-

Verify completion and acceptance of any required inspection, post-weld heat treatment, NDE,

hardness testing, PMI, and any other required test/inspections.

Verify piping system has been completely checked (punched out) and preparations for testing

as required by test instructions are complete.

Perform Test:
-

Make preparation for testing as required:

Perform the test in accordance with test instructions.

Verification of Satisfactory Test Results:


-

Upon the attainment of the required hydrostatic test pressure, for at least the minimum

specified time, an inspection shall be made of all joints and connections. The inspection shall

be made while the system is at the required test pressure.

Following the application of the pneumatic test pressure and reduction to the design pressure

the entire line should be walked to determine if there is any audible evidence of leakage. Any

leaks found at the time shall be marked and repaired after first depressuring the line.

After this walkdown, all joints and welds shall be covered with a soap solution in order to

detect any leakage. Soap shall be commercial preparation specifically for leak detection.

If leaks are found by pressure testing, mark their locations.

Complete the Pressure Test Report actual test conditions for Test Media/Metal temperature,

Test Pressure Test Gage Number and Calibration information.

Provide Restoration Instructions:


Instructions to comply with restoration requirements of 000 250 50050 should be provided or made

available to those responsible for restoring the system after pressure testing and for verifying

completion of restoration. Information should include:

Instructions for removal of temporary test material (blanks, blinds).

Positioning of operating blinds.

Draining instructions.

Installation of equipment excluded from field test (valves, orifice plates, expansion joints,

short pieces of pipe, new gaskets, bolts, vessel internals, etc.).

Instructions for removal of temporary supports.

Resetting spring hangers.

Drying of instruments.

Treatment of vent and drain connections.

Cleaning of strainers.

Painting and insulation.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-24

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 4 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

Verification of Line Restoration:


Verify that all restoration activities have been completed and the system(s) or partial system

represented by this pressure test report is complete.

ATTACHMENTS & EXHIBITS

Quality Form:

SA5-DOW-01-24-01

Pressure Test Report

SA5-DOW-01-24-01

Flushing and Testing Certificate

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-24-01

August, 2014

Page 1 of 1

Revision 01

PRESSURE TEST
RECORD

INDUSTRIA DEL HIERRO S.A. DE


C.V.

SYSTEM/SERVICE

TEST PACKAGE NO.

FLOW DIAGRAM NO.

SHEET NO.

OF

TEST REQUIREMENTS
DESIGN CODE

MAX. PRESSURE

TEST MEDIUM

TEST DURATION

LINE NO./ISO Number

LINE

CLASS

SHEET

MIN. PRESSURE

ORIGIN

NDE/PWHT CLEARANCE/DATE

TERMINATION

REMARKS

TEST PACKAGE APPROVED/DATE

TEST INSTRUMENTS
MANUFACTURER

DESCRIPTION

RANGE

ID NO.

DATE OF CALIBRATION

TEST DATA
TIME

TEST PRESSURE

AMBIENT TEMP.

START

FINISH

PRESSURE TEST SATISFACTORILY COMPLETED

CONT./DATE

OTHER/ DATE

IH/DATE

LINE RESTORATION COMPLETED

CONT./DATE

OTHER /DATE

IH/DATE

PIPE TEMP.

REMARKS

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

SA5-DOW-01-24-02

August, 2014

Page 1 of 1

Revision 01

FLUSHING AND TESTING


CERTIFICATE

Inspection & Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Test Description:

Test Number:

P&ID:

Date:

Operational Medium:
Item

Flushing Medium:

Test Medium:

Description of Check

Verified By

01

Limits of test in accordance with the scope listed on attached

test index and marked up P&IDs

02

System prepared for flushing in accordance with the approved

procedure

03

Flushing completed in accordance with the approved

procedure

04

System prepared for testing in accordance with the approved

procedure

05

System tested in accordance with the approved procedure.

(Note 1)

Date

Test Results and Readings

Test pressure at start

Bar G

Ambient temperature at start

Start date and time

Date and Time

Test pressure at end

Bar G

Ambient temperature at end

End date and time

Date and Time

Test duration

Hours

Tested by contractor

Name and Signature

Test witnessed by (Note 2)

Name and Signature

Notes:

1 All test and calibration charts to be signed, verified, and identified with the test number.

2 Where test is not witnessed state NA.

Subcontractor

Industria del Hierro

Client

Other

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-25

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

CLEANING OF PIPE

SCOPE

The purpose of this procedure is to establish the inspection activities necessary to verify the process of

cleaning the interior surface of piping is performed in accordance with approved requirements.

RESPONSIBILITIES - Self-Perform/Subcontracted

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY

OF ACTIVITY

Verify that all pressure

testing & NDE are

complete

QC Inspector

Prior to release for

cleaning

Commence cleaning
operation

Construction Supt./
Subcontractor

SA5-DOW-01-25-01

As required by project

specs

Monitor chemical
cleaning process

QC Inspector

SA5-DOW-01-25-01

Daily during activity

GENERAL

Inspection Pre-Requisites
Verify that pressure testing and NDE are completing prior to release for cleaning.

Inspection
Monitor chemical cleaning process verifying that it is performed in accordance with approved project

specifications and documents on the pipe cleaning and verification checklist (SA5-DOW-01-25-01).

Retain water test report and certificate of conformance and attach to the pipe cleaning and

verification checklist (SA5-DOW-01-25-01).

ATTACHMENTS & EXHIBITS

Quality Form:

SA5-DOW-01-25-01

Pipe Cleaning and Verification Checklist

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

PIPE CLEANING AND VERIFICATION CHECKLIST

INDUSTRIA DEL HIERRO S.A. DE C.V.

Tag Description:

Tag No.:

PO No.:

Inspection Classification

Subcontractor:

Turnover System:

Subcontractor

Client

Sub System:

Industria del Hierro

Other

Location:

Piping Services Group


Identification No.

SA5-DOW-01-25-01

August, 2014
Page 1 of 1

Revision 01

Code

Class

Subcontractor

Matl.

Q.C.

System

Cleanliness

Level

Industria del Hierro

Verified By

Remarks

Date

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-27

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

ELECTRICAL INSPECTION

SCOPE

This procedure applies to inspection of self-perform or subcontracted electrical installations.

RESPONSIBILITIES - Self-Perform

DOCUMENTATION

ACTIVITY

RESPONSIBILITY

OR INSPECTION

REFERENCE

Install electrical items

Electrical Superintendent

Inspect in-process
electrical installation

QA/QC Manager

---------Forms: SA5-DOW-01-27-01

FREQUENCY OF

ACTIVITY

Each electrical item

Daily during life of activity

SA5-DOW-01-27-02

SA5-DOW-01-27-03

Check final electrical


installation

QA/QC Manager

Forms: SA5-DOW-01-27-01
SA5-DOW-01-27-02

Each installation at

completion

SA5-DOW-01-27-03

Surveillance

QA/QC Manager

Form:

SA5-DOW-01-14-01

Daily during life of activity

and at completion

PROCEDURE

Inspect in-process electrical installation activities in accordance with the applicable specifications

and drawings. The appropriate checklist should be initiated and completed to document inspection

activities.

Perform final installation checks in accordance with the applicable specifications and drawings. The

final inspections should be completed on the applicable checklist.

Perform surveillances daily during the life of electrical activities.

REFERENCES

SA5-DOW-01-14-01

Surveillance Report

ATTACHMENTS & EXHIBITS


Quality Forms:

SA5-DOW-01-27-01

Conduit & Cable Tray Checklist

SA5-DOW-01-27-02

Cable Pulling Inspection Checklist

SA5-DOW-01-27-03

Electrical Heat Tracing Inspection Record

SA5-DOW-01-27-04

Electrical Punch List Record

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

CONDUIT AND CABLE

TRAY CHECKLIST

SA5-DOW-01-27-01

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Area/Unit:

Drawing :

Item

Description of Check

Subcontractor

Industria

del Hierro

Cable Tray
Verify the following are in accordance with design documents
01

Supports

02

Grounding

03

Cable spacing

04

Cable tie down

05

Barriers

06

Splice Plates

07

Wall penetrations

08

High voltage labels

Conduits
Verify the following are in accordance with design documents
09

Workmanship

10

Supports

11

Pull joints

12

Expansion joints

13

Bonding jumpers

14

Seals and drains

15

High voltage labels

16

Fittings

Notes:

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

CABLE PULLING
INSPECTION
CHECKLIST

SA5-DOW-01-27-02

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Drawing Number:
Item

Description of Check

Subcontractor

Industria

del Hierro

Verify the applicable attributes listed below:


01

Underground conduit has been swabbed-out

02

Cable tray is free of sharp edges

03

Verify number of bends between pulling points does not exceed specification
requirements

04

Verify cable reel assignment and cutting schedule

05

Verify cable voltage rating, minimum pulling temperature and type of pulling
compound

06

Verify arrows on high voltage cable reels for direction of pulling off reel

07

Megger metal clad cables before pulling

08

Verify instrument cable for continuity and isolation from drain wire before pulling

09

Verify maximum permitted pulling tension not exceeded

10

Megger power and control cable after installation (Record test results on
E76006A)

11

Megger instrument wire and cable after installation (Record test results on
E76007A)

12

Hypot medium and high voltage cable (Record test results on E76008A)

13

Continuity check instrument wire after installation

14

Bend radius of trained cable in accordance with specifications

15

Cable is free of kinks, neat and cable lay is in accordance with drawings

16

Spacing between instrument cable and power cable in accordance with design

17

Cables identified per specification and drawings

18

Cable ends sealed after cutting

Notes:
Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

ELECTRICAL HEAT
TRACING INSPECTION
CHECKLIST

SA5-DOW-01-27-03

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Item

Area/Unit:

Description of Check

Subcontractor

01

Verify identification tag for correctness.

02

Verify continuity check made.

03

Verify megger of cables.

04

Verify heaters stored in dry location.

05

Verify cables are protected from severe blows, weld slag, etc.

06

Verify correct cable is on right pipe in right location.

07

Verify heat transfer cement applied.

08

Verify cable, junction boxes and thermostat installed correctly.

09

Verify thermostat set prior to installing insulation.

10

Verify circuit breakers and fuse rating.

11

Verify installation of labeling and warning signs.

12

Verify conduit pipes are plugged off and pull wires installed, when

applicable (cryogenic tanks).

13

Verify correct heater cable used.

Industria del

Hierro

Notes:

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

ELECTRICAL

PUNCH LIST RECORD

SA5-DOW-01-27-04

August, 2014

Page 1 of 1

Revision 01

REFERENCE: DRAWING _______________________________________________________________________________________________

ITEM
NO.

IDENTIFICATION
AND LOCATION

REMARKS

DATE
CORRECTED

SUPERVISORS
APPROVAL

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-28

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

ELECTRICAL TESTING

SCOPE

This procedure applies to testing of installed electrical construction.


RESPONSIBILITIES Self-Perform

ACTIVITY

RESPONSIBILITY

FREQUENCY OF

ACTIVITY

DOCUMENTATION

Define Test Boundaries

Construction Electrical

Engineer

Each Test Package

Provide Preparation Test


Instructions

Construction Electrical
Engineer

_____

Each Test Package

Perform Electrical Test

Electrical
Superintendent

_____

Each Test Package

Verify Test Results

QA/QC Manager
Electrical Supervisor

Provide Restoration
Instructions

Construction Electrical
Engineer

Verify Completion of
Restoration

QA/QC Manager
/Electrical Supervisor

_____

Form:

SA5-DOW-01-28-01
SA5-DOW-01-28-02
_____

Form:

Test Completion

Test Completion

Each Test Package

SA5-DOW-01-28-01
SA5-DOW-01-28-02

Each Test

PROCEDURE

Define Test Boundaries and Provide Preparation Test Instruction:


-

Boundaries and test instructions provided by Construction Electrical Engineer shall be reviewed by

Inspection Personnel prior to any testing activities.

Notify the IH/Client of testing/inspections


requested/required to witness.

which

they

have

Perform test in accordance with the test instruction provided by Construction Electrical

Engineering.

Utilizing the test instructions and/or drawing(s) required, verify the acceptance of the test.

Document the satisfactory results using the applicable forms contained in this procedure as

Exhibits.

Provide Restoration Instructions:


-

involvement,

Verification of Test Results:


-

their

Test Field Installed Equipment:


-

for

Instructions to comply with restoration requirement of the applicable specification and/or drawing

should be provided by Construction Electrical Engineering.

Verification of System Restoration:


-

Verify that all restoration activities have been completed and the system(s) or partial system

represented by this test package is complete.

ATTACHMENTS & EXHIBITS

Quality Forms:

SA5-DOW-01-28-01

Insulation Resistance (Power, Control Wire and Cable) Test Record

SA5-DOW-01-28-02

Insulation Resistance (Instrument Wire and Cable) Test Record

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9

Project
Purchase Order No. GUST-50-LHC-K067

INSULATION RESISTANCE
(POWER CONTROL WIRE
AND CABLE) TEST RECORD

INDUSTRIA DEL HIERRO S.A. DE


C.V.

SA5-DOW-01-28-01

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Test Equipment:

Test Voltage:

Test Equipment:

Test Voltage:

Ambient
Temperature:
Notes:

Date
C /

1.

Perform Insulation Resistance Test (megger) between each conductor and all other conductors and
metallic sheath for cables with nonshielded conductors. Test between each conductor and shield for
multiconductor cables with shielded conductors. Record lowest reading for each cable.

2.

Use 500V test set for cables rated 300 to 600 volts and 2500V test set for cable rated over 600 volts.

3.

Readings will vary inversely with temperature, and cable length. When Project specifies use of
nd
temperature correction factors, attach 2 sheet with computed values. Indicate on each sheet "Measured"
or "Temperature corrected".

Panel No.

Circuit No.
Feeder No.

Wire

Tagging

Cable Rated
Voltage

*Minimum acceptable Project values


Cable Rated
Voltage

Subcontractor

Wire Or Cable
Quantity

Size

From

To

Insulation
Resistance
(Megohms)*

Resistance For

Test
Duration

Initials

Resistance When Cable

Cable Only

Cable/Wire Size

Connected to Equip

(Megohms)

Or Amperage

(Ohms)

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

NSULATION RESISTANCE
(INSTRUMENT WIRE AND
CABLE) TEST RECORD

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

SA5-DOW-01-28-02

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Test Equipment:

Ambient Temperature:

Test Voltage:

Notes: 1. Record only the lowest value.

2. MP - multi-pair cable, SP - single pair cable.

3. Megger with instruments disconnected.

4. Use 250 volt (or lower voltage, when specified) range on DC test set.

*Minimum Acceptable Project Values

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

Initials

only)

(megohms)

Shield to Conduit

(single pair cables

(megohms)

and armor

(multipair cables only)

Overall Shield to lead

(1)

only)

(megohms)

Shield to Shield

(multipair cables

(1)

(megohms)

Conductor to Shield

(1)

Conductor

(megohms)

Conductor to

cables)

(megohms)

non-shielded

Conductor to

conduit (single pair

(2)

type

Indicate MP or SP

Cable number or

instrument number

5. Readings will vary with temperature and cable length.*

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-30

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

CONTROL SYSTEM INSTRUMENTATION

SCOPE

This procedure applies to the inspection of Control Systems installations and loop check of instrumentation.

RESPONSIBILITIES - Self-Perform

ACTIVITY

RESPONSIBILITY

Inspect received
instruments

Const. Electrical Eng.

Instrument Supt.

Inspect in-process
instrument installation

QA/QC Manager

Inspect completed
instrument installation

QA/QC Manager

Perform Pressure
Testing of Tubing

Instrumentation
Superintendent

Verify Pressure Testing


of Tubing

QA/QC Manager

Test Instrument Cables

Electrical

Superintendent

Verify Instrument Cable


Testing

QA/QC Manager

Perform/Verify Loop
Check

Instrumentation Supt./
QA/QC Manager

DOCUMENTATION

FREQUENCY

OF ACTIVITY

_____

For each instrument

Form

Daily during life of

activity

SA5-DOW-01-30-01
Form

SA5-DOW-01-30-01

Each Instrument

Each Pressure Test

Package

_____

Form
SA5-DOW-01-30-01

Each Pressure Test

Package

_____

Each cable

Form

SA5-DOW-01-30-01

Form

SA5-DOW-01-30-02

Each cable

Each loop

PROCEDURE

Receipt Inspection of Instruments:


The Construction Electrical Engineer and the Instrument Superintendent shall coordinate the receipt

inspection of instruments to support the construction schedule.

In-Process and Completed Instrument Installation Inspections:


Assure the instrument, if required by specification, is calibrated prior to installation. Inspect the inprocess installations.

Using a Mechanical Flow Diagram and Instrument Specification Data Sheet, perform a completed

inspection prior to pressure testing. Document on Form SA5-DOW-01-30-01.

Test Equipment Tubing:


Verify the instrument tubing is properly installed, is not supported from uninsulated hot or cold

pipes and adequately supported. Pressure test shall be conducted in accordance with specifications

and the Instrument Specification Data Sheet.

Test Instrument Cables:

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-30

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Verify the instrument electrical installation inspections and megger tests are complete and

acceptable.

Loop-Check Verification:
Verify all installation inspections, pressure testing and continuity checks have been completed and

documented.

Notify the Client Representative, if requested to do so, prior to the loop check.

Verify the loop check, which generally consist of operating all instruments in the loop. Document

the final loop check on Form SA5-DOW-01-30-02.

ATTACHMENTS & EXHIBITS

Quality Forms:

SA5-DOW-01-30-01

Instrumentation Inspection Checklist

SA5-DOW-01-30-02

Instrument Loop Inspection Checklist

SA5-DOW-01-30-03

Instrument Installation (Local Instrument) Checklist

SA5-DOW-01-30-04

Orifice Plates Inspection Checklist

SA5-DOW-01-30-05

Loop Mechanical Completion And Acceptance Record

SA5-DOW-01-30-06

Calibration Data Record

SA5-DOW-01-30-07

Punch List

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

SA5-DOW-01-30-01

August, 2014

Page 1 of 1

Revision 01

INSTRUMENTATION
INSPECTION CHECKLIST

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Area/Unit:

Loop No.:
Drawing(s)

Item

Description of Check

Subcontractor

Industria del

Hierro

Verify the following attributes:


01

Instruments mounted at proper height.

02

Instrument stands secure and vibration free.

03

Correct piping/tubing materials used.

04

All tubing trays and supports per details.

05

All air supply and process tubing connected to proper parts per details.

06

All tubing fitting nuts torqued per specifications.

07

Good workmanship used in tubing installation and neat in appearance.

08

Signal/power leads have proper separation and angle of intersection.

09

Tubing/piping pressure tested prior to heat tracing or insulating.

10

Loop checked per specification.


ANY DISCREPANCIES NOTED ABOVE AS FOLLOWS:

Punch List Items from Above List

Subcontractor

Industria del Hierro

Date Cleared

Client

Other

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

INSTRUMENT LOOP
INSPECTION CHECKLIST

INDUSTRIA DEL HIERRO S.A. DE C.V.

SA5-DOW-01-30-02

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Area/Unit:

Cable No.:

Junction Box No.:

Cable Type:

Color/Loop No.:

Item Description of Check

01

02

03

Measuring Element

Impulse Lines

Field Instrument

04

Panel Instrument

05

Control Valve

06

Solenoid Valve

07

Air Supplies

08

Transmission

09

Temperature

10

General

Subcontractor

Installation Correct

Tappings Position Correct

Location Correct

Materials Correct

According to Hook-Up

Traced

Pressure Tested

Materials Correct

Local Indicator Working

Power Supply Correct

Air Supply Correct

Correct Installation

Correct Installation

Industria del

Hierro

Weather Protected

Air Supply Correct

Power Supply Correct


Correct Installation

Limit SW Tested

Positioner Checked

Size & Type Correct

Stroke Tested

I/P Transducer Checked

Correct Installation
Other (indicate)

Correct Installation
Other (indicate)

Size & Type Correct

:________________

Blown Clear & Leak Tested

:________________

Pneumatic Lines Tested

Insulation Checked (C-C, C-G)

Continuity Checked
T/C or RTD Checked

Continuity Checked

Correct Cable

Loop Impedance Checked

Support Correct

Earthing Correct

Tagging/Marking Correct

Notes:

Subcontractor

Industria del Hierro

Client

Other

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

INSTALLATION CHECK
SHEET (LOCAL
INSTRUMENTS)

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

SA5-DOW-01-30-03

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist


Tag No.:

Tag Description:
P. O. No.:

Inspection Classification

Turnover System:

Subcontractor:

Subcontractor

Client

Sub System:

IH

Other

Location:

Instrument Tag
No.:

Range

Witness

Date

Instrument Tag
No.:

Range

Witness

Date Subcontractor

IH

1.

Verify correct instrument is installed at correct P.I.D. location, including correct tag number and model

number

2.

Verify integrity of process installation (no open plugs etc.)

3.

Verify all instruments have been calibrated (certificates available, stickers on instruments)

4.

Verify accessibility

5.

Verify correct gasket materials installed

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

ORIFICE PLATES

INSPECTION CHECKLIST

SA5-DOW-01-30-04

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist

Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Item

Area/Unit:

Description of Check

Subcontractor

01

Install orifice with sharp edge upstream

02

Bevel edge, if any, must face downstream

03

Make sure gaskets on each side of orifice do not obstruct orifice bore

04

Identification tab on square edge plates must face upstream

05

Verify correct labelling

06

Verify orientation of pressure taps per specification of process

07

Visually inspect for damage

Notes:

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

IH

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067


INDUSTRIA DEL HIERRO S.A. DE C.V.

LOOP MECHANICAL

COMPLETION

AND ACCEPTANCE RECORD

SA5-DOW-01-30-05

August, 2014

Page 1 of 1

Revision 01

Inspection Test Checklist


Tag No.:

Tag Description:
P. O. No.:

Inspection Classification

Subcontractor:

Turnover System:

Subcontractor

Client

Sub System:

IH

Other

Location:

AREA

INSTRUMENT LOOP TAG NO.

LOOP SCHEMATIC DRAWING NO.

FLOW DIAGRAM DRAWING NO.

This Loop

is mechanically complete in accordance with

Drawings and Specifications.

INDUSTRIA DEL HIERRO / DATE:

OTHER / DATE:

This Loop

has been checked within the parameters listed

on the instrument loop drawing, and/or mechanical flow diagram, and is acceptable.

INDUSTRIA DEL HIERRO / DATE:

OTHER / DATE:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

CALIBRATION DATA RECORD

TagNum:

Description:

Manufacturer:

Serv Descr:

PO #:

Model No.

Calibration Range:
(Operating Range)

Material No:

SA5-DOW-01-30-06

August, 2014

Page 1 of 1

Revision 01

Serial No:
Startup System:

Calibration Method:

Cable Data

TEST EQUIPMENT

SERIAL NUMBER

CALIBRATION DUE DATE

*
*
*
*

INPUT
Value

INSTRUMENT OUTPUT
Units

As Found

Desired

DCS/MARK VI
As Left

Indication

REMARKS (Repairs, Restrictions, or Calculations):

Source: Engineering Database

Tag Added On:

Calibrated By:

Calibrated On:

Loop Shot By:

Loop Shot On:

This loop is mechanically complete in accordance with Drawings and Specifications, and has been checked within parameters listed on loop drawing or

Elementary Diagrams and/or Mechanical Flow Diagrams, and is acceptable.

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067


INDUSTRIA DEL HIERRO S.A. DE C.V.

INSTRUMENTATION

PUNCH LIST RECORD

SA5-DOW-01-30-07

August, 2014

Page 1 of 1

Revision 01

REFERENCE: DRAWING _______________________________________________________________________________________________

ITEM
NO.

IDENTIFICATION
AND LOCATION

REMARKS

DATE
CORRECTED

SUPERVISORS
APPROVAL

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-31

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

CONTROL SYSTEM CALIBRATION


SCOPE

This procedure applies to calibration of instruments for control systems.

RESPONSIBILITIES - Self-Perform

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY OF

ACTIVITY

Inspect Instrument

Calibration Technician/

QA/QC Manager

SA5-DOW-01-31-01

Each Instrument

Test and Calibrate

Instruments

Calibration Technician/

QA/QC Manager

SA5-DOW-01-31-01

SA5-DOW-01-31-02

SA5-DOW-01-31-03

Each Instrument

Surveillance Test Equipment

QA/QC Manager

000 509 F0221

Periodically throughout

life of project

RESPONSIBILITIES - Subcontracted Work

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY OF

ACTIVITY

Inspect Instrument

Subcontractor

SA5-DOW-01-31-01

Each Instrument

Test and Calibrate

Instruments

Subcontractor

SA5-DOW-01-31-01

SA5-DOW-01-31-02

SA5-DOW-01-31-03

Each Instrument

Surveillance Test Equipment

QA/QC Manager

000 509 F02201

Periodically throughout

life of project

PROCEDURE

Inspect Instrument:
-

Inspect each instrument for apparent damage. Verify the tag number, nameplate data, material,

scale, range, etc., against the information contained on the appropriate Instrument Specification

Data Sheet, and enter data on Form SA5-DOW-01-31-01.

Damaged or nonconforming instruments shall be segregated and/or tagged to prevent inadvertent

use or installation until acceptable disposition is obtained.

Instrument Test and Calibration:


-

Based on the requirements in the applicable Design Specifications, applicable manufacturer's

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-31

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

recommendations and client requirements calibrate the instruments and document on Form SA5DOW-01-31-01.

Test Equipment Surveillance:


-

Perform surveillance of calibration activities on a periodic basis throughout the life of the project.
Verify the Master Equipment used for calibration has calibration stickers on the instruments that

indicate date of last check and date of next check with traceability to the National Institute of

Standards and Technology.

FORMS

Quality Control Form:

SA5-DOW-01-31-01 Calibration Record

SA5-DOW-01-31-02 Calibration Data Sheet

SA5-DOW-01-31-03 Instrumentation Inspection Checklist

SA5-DOW-01-31-04- Instrument Calibration Sheet

SA5-DOW-01-31-05- Safety Valve Tracking Sheet

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-31-01

August, 2014
Page 1 of 1

Revision 01

CALIBRATION RECORD

INDUSTRIA DEL HIERRO S.A. DE C.V.

Equipment/Instrument
Identification No.

Item Description
Size-Range

Manufacturer Model
No.

Manufacturer Serial
No

Calibration Frequency

Calibration Tolerance

Date
Calibrated

Calibration

Due Date

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-31-02

August, 2014

Page 1 of 1

Revision 01

CALIBRATION DATA
SHEET

INDUSTRIA DEL HIERRO S.A. DE


C.V.

Identification and Name plate

Area/Location

Unit No.

System

Job No.

Tag No.

Manufacturer

Description

Model No.

Serial No.

Type

Size

Calibration Range:

Material

Required Accuracy

Input Range

Output Range

Trip Points:

Calibration

Procedure:

ACTUAL READINGS

As Found

Input

As Left

Output

Input

Output

0%

0%

25%

25%

50%

50%

75%

75%

100%

100%

Remarks

TEST EQUIPMENT

Calibration

Manufacturer

ID / SN

Calibration Due Date

Calibrated By

Date

QC Verification

Date

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

SA5-DOW-01-31-03

August, 2014

Page 1 of 1

Revision 01

INSTRUMENTATION
INSPECTION CHECKLIST

Inspection Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Area/Unit:

Loop No.:
Drawing(s)

Item

Description of Check

Subcontractor

IH

Verify the following attributes:


01

Instruments mounted at proper height.

02

Instrument stands secure and vibration free.

03

Correct piping/tubing materials used.

04

All tubing trays and supports per details.

05

All air supply and process tubing connected to proper parts per details.

06

All tubing fitting nuts torqued per specifications.

07

Good workmanship used in tubing installation and neat in appearance.

08

Signal/power leads have proper separation and angle of intersection.

09

Tubing/piping pressure tested prior to heat tracing or insulating.

10

Loop checked per specification.


ANY DISCREPANCIES NOTED ABOVE AS FOLLOWS:

Punch List Items from Above List

Subcontractor

Industria del Hierro

Date Cleared

Client

Other

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-31-04

August, 2014

Page 1 of 1

Revision 01

INSTRUMENT CALIBRATION
SHEET

INDUSTRIA DEL HIERRO S.A. DE


C.V.

A INSTRUMENT CALIBRATION SHEET


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Turnover System:

Subcontractor:

Subcontractor

Client

Sub System:

IH

Other

Location:

Instrument Calibration Sheet

Date:

Technician:

Area:

Tag Number:

Loop Service:

Manufacturer:

Model:

Serial No.:

Process Range and Units:

(scfm, gpm, psig, F, etc.)

Transmitter Input Range and Units:

(in H20, psig, etc.)

Transmitter Output Signal

For Flow Instruments:

Chart Factor:

Orifice Plate Bore:

Chart Scale: (circle one)

Integrator Factor:

Linear Square Root - Combination

For Differential Pressure Instruments:

Fill Fluid:

For I/P Transducer

Suppression:

Fluid Type:

Input

Elevation:

Specific Gravity:

Output

Test Equipment

Used

Input Standard
Percen
t

Input

Value

Serial No.

Manufacturer

Output
As Found

Model No.

Description

Calibrated

Due

Date

Notes

As Left

% Error

0
25
50
75
100
Percent Error Calculation:

Percent Error =

As Found Output Correct Output


Span Output

Remarks:

Fluor Acceptance:

Date:

Client Acceptance:

Date:

x 100

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-31-05

August, 2014

Page 1 of 1

Revision 01

SAFETY VALVE TRACKING


SHEET

INDUSTRIA DEL HIERRO S.A. DE


C.V.

SAFETY VALVE TRACKING SHEET


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

IH

Other

Sub System:

Manufacturer
Model No.

Serial No.

Calibration Tag Verification

Date Checked:

Pressure Setting
Calibration Date
System Status

Pre-Hydrotest
Post-Hydrotest
Reinstatement
Complete

Calibration Tag Verification

Date Checked:

Pressure Setting
Calibration Date
System Status

*
Pre-Hydrotest
Post-Hydrotest
Reinstatement
Complete

Calibration Tag Verification

Date Checked:

Pressure Setting
Calibration Date
System Status

*
Pre-Hydrotest
Post-Hydrotest
Reinstatement
Complete

* Calibration date at turnover must be within 60 days of start up of the unit.


Subcontractor

Industria del Hierro

Client

Name:

Name:

Name:

Signature:

Signature:

Signature:

Date:

Date:

Date:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-32

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

COATINGS

SCOPE

This procedure describes the inspection, testing, and documentation required to be performed for subcontracted

or self-perform construction activities for coatings.

Responsibilities - Subcontracted Work


ACTIVITY

FREQUENCY

RESPONSIBILITY

DOCUMENTATION

Inspect surface

preparation

Subcontractor

SA5-DOW-01-32-02

Daily during life of activity

Verify color/type
coatings approved

Subcontractor

SA5-DOW-01-32-02

SA5-DOW-01-32-05

As required by applications

Inspect in-process
coating/lining

Subcontractor

SA5-DOW-01-32-02

SA5-DOW-01-32-05

Daily during life of activity

Subcontractor

SA5-DOW-01-32-02
SA5-DOW-01-32-06

As required to verify thickness

requirements

Inspect completed
coatings

Subcontractor

SA5-DOW-01-32-02

SA5-DOW-01-32-06

_____

Follow-up any
deficiencies identities

Subcontractor

SA5-DOW-01-32-05
SA5-DOW-01-32-06

As required to close-out

deficiencies

Check Thickness

OF ACTIVITY

PROCEDURE

Surface Preparation Inspections:


-

Verify the surface preparation is in accordance with the applicable specification. (Form SA5DOW-01-32-05)

Protect adjacent areas to coating operations from sandblasting and paint overspray.

Coating Approval:
-

Verify that color/type of coatings has been approved and documented. (Form SA5-DOW-01-3205)

Assure pot life of coating products are not exceeded prior to application. (Form SA5-DOW-0132-05)

In-process Coating/Lining Inspections:


-

Coatings application shall not be performed during unacceptable weather conditions that violate

the specification requirements for application.

Inspect the in-process coating's applications, to verify that the work meets the requirements in

accordance with the specifications.

Thickness Verification/Final Inspection:


-

Check dry film thickness of applied coatings in sufficient locations to verify the required

thickness has been applied.


Document the inspections on Forms SA5-DOW-01-32-02 Coatings Inspection, SA5-DOW-01-32-05 Painting Checklist, and SA5-DOW-01-32-06

Coating Inspection Record. Perform final coating inspection after acceptable dry film thickness

is achieved.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-32

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Test applied linings in sufficient locations to verify proper surface profile, thickness or lining

continuity, using test equipment designated in the specifications. Document the inspections on

Form SA5-DOW-01-32-02.

When specifications establish application restrictions for temperature and humidity, perform

checks with certified hygrometer and temperature indicator prior to starting each day's work.

Follow-up of Deficiencies:
Inform supervision of any discrepancies on a daily basis. Immediate corrective action

should be taken.

FORMS

Quality Forms:
SA5-DOW-01-32-01

Sandblast technician and painter qualification

SA5-DOW-01-32-02

Inspection, preparation and application of anticorrosive coating systems.

SA5-DOW-01-32-03

Anticorrosive coating materials storage.

SA5-DOW-01-32-04

Weather conditions record.

SA5-DOW-01-32-05

Painting Checklist.

SA5-DOW-01-32-06

Coating Inspection Record.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-32-01

August, 2014

Page 1 of 1

Revision 01

SANDBLAST TECHNICIAN AND


PAINTER QUALIFICATION

INDUSTRIA DEL HIERRO S.A. DE


C.V.

QUALIFICATION FOR WORKERS USING SAND-BLASTING

NAME: __________________________________COMPANY:________________________________DATE____________

AREA: ____________________________ELEMENT TEST PERFORMED______________________________________


PROJECT: _____________________________________________________________ CONSECUTIVE N:____________
ELEMENT TEST PERFORMED: __________________________________________
1.- EQUIPMENT FOR SAND-BLASTING

Screen

NO

YES

Traps
For water and oil

YES

NO

2.- SAND-BLASTING AND PREPARATION OF SURFACE


Blast

Metal almost white

Anchorage section

Commercial

White metal

Relative Humidity

3.- RESULT

ACCEPTED

REJECTED

_____________________

Quality control
Name, date and signature

QUALIFICATION FOR PAINTERS

NAME: ___________________________________COMPANY: _______________________________DATE__________

AREA: ___________________________________ PROJECT: ______________________________


ELEMENT TEST PERFORMED: _____________________________________________________

COAT TYPE GRADE____________________________________

COAT LOT: ________________________________

I APPLICATION METHOD

II TEMPERATURE AND THICKNESS


Surface temperature ________C

With air

By sprinkling

Relative humidity__________ %
W/O air

Humid thickness ___________MLS


Dry thickness _____________MLS

III USE OF EQUIPMENT AND RECIPIENTS WHERE THE PAINT IS MIXED

YES

Nordson
Clean recipients
Proper mixture

4.- RESULT

NO

Overlapping between each coat _________%


Moisture separator_________

ACCEPTED

REJECTED

________________

NOTE: To be qualified the worker using sandblasting and the painter


shall receive training according to the applicable procedure.

Quality control
Name, date and signature

INSPECTION, PREPARATION
AND APPLICATION OF

ANTICORROSIVE COATING
SYSTEMS

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

PROJECT:

SA5-DOW-01-32-02

August, 2014

Page 1 of 2

Revision 01

DATE:

EQUIPMENT AND/ OR ELEMENTS


SURFACE TREATMENT
MANUFACTURER:

CONTRACTOR:
SHELF LIFE:

LOT No.

FINISH COLOR ACCORDING TO SPECIFICATION:


SPECIFICATION USED:

SURFACE PREPARATION

PREPARATION TYPE (ACCORDING SPECIFICATIN):


RELATIVE HUMIDITY (%):

STANDAR DEPTH OF ANCHOR (Mm) MILS:

ABRASIVE TYPE USED:

MAXIMUM TIME PASSED BETWEEN PREPARATION AND APLICATION:

SURFACE TREATMENT APLICATION

PRIMARY

INTERMEDIATE

FINISHED

STANDARD DRY THICKNESS (ACCORDING TO


SSPC-PA-2):
% H.R. DURING APLICATION:
SUBSTRATE TEMPERATURE:
ENVIRONMENT TEMPERATURE:
WINTER SPEED:
APLICATION METHOD:

DETECTED DEFECTS ACCORDING TO SPECIFICATION:

OBSERVATIONS:

INSPECTIONATED BY:

NAME, DATE AND SIGNATURE

SUPERVISED BY:

CLIENT:

NAME, DATE AND SIGNATURE

NAME, DATE AND SIGNATURE

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

INSPECTION, PREPARATION
AND APPLICATION OF

ANTICORROSIVE COATING
SYSTEMS
ADHERENCE TEST

ANCHOR PROFILE (REPLICA TAPE)

SA5-DOW-01-32-02

August, 2014

Page 2 of 2

Revision 01

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

ANTICORROSIVE COATING MATERIALS STORAGE

INDUSTRIA DEL HIERRO S.A. DE C.V.

INSPECTION LOCATION:____________________

__________________________________________

WORKSHOP:_________ FIELD:_____________

RECOMMENDED TEMPERATURE FOR STORAGE

PRIMARY (Lot)
BASE :

__________________

EXTINGUISHER

INTERMEDIATE (Lot)
BASE :

__________________

FINISHED (Lot)
BASE :

CATALYTIC:____________

CATALYTIC:____________

EXPIRY:__________________

EXPIRY:__________________

EXPIRY:__________________

BASE :

__________________

INTERMEDIATE (Lot)
BASE :

__________________

BASE :

CATALYTIC:____________

EXPIRY:__________________

EXPIRY:__________________

EXPIRY:__________________

__________________

INTERMEDIATE (Lot)
BASE :

__________________

FINISHED (Lot)
BASE :

__________________

CATALYTIC:____________

CATALYTIC:____________

CATALYTIC:____________

EXPIRY:__________________

EXPIRY:__________________

EXPIRY:__________________

______________________________

REMARKS

__________________

CATALYTIC:____________

BASE :

DATE BY WEEK

FINISHED (Lot)

CATALYTIC:____________

PRIMARY (Lot)

STORAGE AND
HOUSEKEEPING

__________________

CATALYTIC:____________

PRIMARY (Lot)

SA5-DOW-01-32-03

August, 2014
Page 1 of 1

Revision 01

_________________________________

CONSTRUCTION

QUALITY CONTROL

NAME, DATE AND SIGNATURE

NAME, DATE AND SIGNATURE

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

WEATHER CONDITIONS RECORD

INDUSTRIA DEL HIERRO S.A. DE


C.V.

WEATHER CONDITIONS RECORD


DAY OF

THE
MONTH

SUBSTRATE TEMPERATURE
START

MIDDAY

ENVIRONMENT TEMPERATURE

AFTERNOON

START

SA5-DOW-01-32-04

August, 2014
Page 1 of 1

Revision 01

MIDDAY

AFTERNOON

RELATIVE HUMIDITY (%)


START

MIDDAY

AFTERNOON

MONTH:
MAX. WINTER SPEED
START

MIDDAY

DEW POINT

AFTERNOON

START

MIDDAY

AFTERNOON

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
NOTE: WHEN CONDITIONS ARE NOT SUITABLE DURING THE BEGINNING, THE NORMAL START HOUR WILL BE INDICATED IN OBSERVATIONS / REMARK.

VERIFIED BY

INSPECTED BY

_____________________________

_______________________________

CONSTRUCTION
NAME, DATE AND SIGNATURE

QUALITY CONTROL

NAME, DATE AND SIGNATURE

REMARKS

The DOW Chemical Company

SA5-DOW-01-32-05

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

Re ision 01
Revision

INDUSTRIA DEL HIERRO S.A. DE C.V.

PAINTING CHECKLIST

Tag Description:

Tag N:

Module N:

P. O. N:

Tornover System:

Contractor:
C
ontractor:

S b S

Sub-System:

Work Package:

Area / Unit:

Item

Description of Check

Subcontractor

Fluor

Verify use of correct painting materials:

01

Trade name and manufacturer

02

02

Grade

03

Manufacturer's data sheets

04

Protection for applied paint

05

Guarantees

06

Pot or shelf life

07

Correct colors

Inspect
I

nspect painting application:

application:
08

Surface preparation

09

Method of application

10

Number of coats

11

Thickness of dry film

Ascertain workmanship:

12

Evenness of applied coat

13

Brush marks, sags runs, etc.

14

Cleanliness of area upon completion

Notes:

Subcontractor

Industria del Hierro

Fluor / Client

Name:

Name:

Name:

Signature:

Signature:

Signature:

Date:

Date:

Date:

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

P h
Purchase
O d No.
Order
N GUST50LHCK067

GUST 50 LHC K067

SA5-DOW-01-32August, 20

P
Page
1 o

Revision

INDUSTRIA DEL HIERRO S.A. DE C.V.

COATINGS INSPECTION RECORD

Tag Description:

Tag N:

Module N
N::

P. O. N:
N :

Turnover

Turnover
System:
System:

SubSystem

Contractor:

Type of Object:

Piping

Item

Description of Check

Subcontractor

Fluor

01
Coating by appoved manufacturer

Structural Steel

02
Surface preparation SSPCSP value

Equipment

Surface dry
dryfree
free from condensation
03 Surface

03

Tank Exterior

Paint mixed, thinned and applied in accordance with


04
manufactures specification

Tank Interior
Concrete

BrushSprayRoller
05
Concrete Surfaces dry and prepared per specification

Object Location:
Outdoors

06
Primer in accordance with specification
07
Finish coat is acceptable

Indoors

08
Workmanship acceptable

Conditions:

Mon
AM
PM

Tues
AM
PM

AM

Batch No

Part A
Part B

Coat
No

Wed
PM

Thurs
AM
PM

Fri
AM

PM

AM

Sat

PM

Relative humidity %

Substrate Temperature
Substrate

Ambient Temperature
Dew Point

Brandname Paint

Surface
No

Application Method

DFT Average

Notes :

Subcontractor
S b t t
Name:
Signature:
Date:

I d t i del
Industria
d l Hi
Hierro

Name:
Signature:
Date:

Fl
Fluor
/ Client
Cli t
Name:
Signature
Date:

-06

014

off 1

1
01

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-33

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

INSULATION

SCOPE

This procedure describes the inspection activities for subcontracted insulation installation.

RESPONSIBILITIES - Subcontracted Work

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY

OF ACTIVITY

Coordination of Release

for Insulation

Construction

Engineering

Form SA5-DOW-01-33-01

Each piece of

equipment, line or

structure

Install insulation

Subcontractor

_____

Each piece of

equipment, line or

structure

Inspect in-process

installation

Subcontractor/

QA/QC Manager

Form SA5-DOW-01-33-01

Each piece of

equipment, line or

structure

Inspect completed

installation

Subcontractor/

QA/QC Manager

Form SA5-DOW-01-33-01

Each piece of

equipment, line or

structure

Surveillance

QA/QC Manager

Form SA5-DOW-01-14-01

Per Procedure

SA5-DOW-01-14

NOTE 1:

Surveillance is not required if the Fluor Site Quality Manager is performing

inspections.

PROCEDURE

Release for Insulation:


-

Install Insulation:
-

The construction engineer will issue the "Release for Insulation" (Form SA5-DOW-01-3301) to the insulator and QC, for sign-off prior to insulation. At this time all work will be

verified as complete including; hydrostatic tests and punch list items requiring completion,

prior to insulation.

Insulation shall be installed in accordance with the applicable drawings and specifications.

In-process Inspection for Insulation Activities:


-

No insulation shall begin on a vessel, equipment, or piping until released by the appropriate

field supervisor.

Obtain a copy of the written release, (Form SA5-DOW-01-33-01), for the insulation to be

installed.

Verify the insulation materials are free from damage and shelf life has not expired.

Monitor the in-process installation activities to verify that insulation materials are installed in

accordance with drawings, specifications, and manufacturer's recommendations.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-33

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Completed Installation Inspection:


-

Inspect the completed insulation for workmanship and damage.

Verify the installation conforms to applicable drawings and specifications, and document on

Form SA5-DOW-01-33-01.

ATTACHMENTS & EXHIBITS

Quality Forms:

SA5-DOW-01-33-01

Equipment Thermal Insulation Inspection Checklist

SA5-DOW-01-33-02

Piping Thermal Insulation Inspection Checklist

INSPECTION REFERENCE

INSULATION AND TRACING


Verify insulation materials are free from damage

Verify insulation materials shelf life has not expired

Insulation support clips installed.

Clearances adequate for insulation.

Electrical tracing installed.

Steam tracing installed.

Correct number of tracers.

Tracer size correct.

Tracer lengths correct.

Trap detail correct.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

EQUIPMENT THERMAL

INSULATION INSPECTION
CHECKLIST

SA5-DOW-01-33-01

August, 2014

Page 1 of 2

Revision 01

Inspection Test Checklist

Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

Fluor

Other

Sub System:

Area/Unit:

Release for Insulation

Engineer:

Date

Inspector:

Date

Item

Description of Check

Insulation Materials
01

Proper materials

02

Verify insulation materials are free from damage

03

Verify insulation materials shelf-life has not expired

Hot Vessels and Equipment


04

Proper material thickness used

05

Proper application at stiffener rings

06

Nameplates left exposed

07

Proper banding and breather springs used

08

Proper use of filler and/or mastic materials

Cold Vessels and Equipment


09

Proper material thickness used

10

Proper insulation of attachments

11

Proper contraction joint at support rings

12

Nameplates left exposed

13

Proper banding used

14

Proper use of filler, joints seals and vapor seal

Tank insulation Hot


15

Proper spacing of welded pins for support

16

Proper banding used (insulation/jacketing)

17

Proper expansion system

18

Proper lapping vertically and horizontally

19

Proper use of S clips

Subcontractor

IH

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

Item

EQUIPMENT THERMAL

INSULATION INSPECTION
CHECKLIST

Description of Check

SA5-DOW-01-33-01

August, 2014

Page 2 of 2

Revision 01

Subcontractor

20

Vertical support bars used on 50 diameter and larger

21

Proper flashing used per specification details

22

Proper roof (build up) application over insulation

Weatherproofing Hot Equipment


23

Proper use of weather proofing mastic at fittings

24

Proper banding of metal jacket

25

Proper use of S clips on vertical runs

26

Corrugated jacketing on vessel

27

Proper lap and metal screw spacing

28

Proper main shield on vertical vessels

Weatherproofing Cold Equipment


29

Proper use of vapor barrier mastic paint jacketing

30

No use of screws on cold work except on standing seam systems

Acoustical Lagging
31

Proper material thickness used

32

Proper application at stiffener

33

Nameplates left exposed

34

Proper banding and breather springs used

35

Proper use of filler and/or mastic materials

Removable Covers
36

Proper stenciling or tagging for identification

Notes:

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

IH

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

PIPING THERMAL
INSULATION INSPECTION
CHECKLIST

SA5-DOW-01-33-02

August, 2014

Page 1 of 2

Revision 01

Inspection Test Checklist

Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Area/Unit:

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

Fluor

Other

Sub System:

Release for Insulation

Engineer:

Date:

Inspector:

Date:

Item

Description of Check

Insulation Materials
01

Proper Materials

02

Verify insulation materials are free from damage

03

Verify insulation materials shelf-life has not expired

Insulating Hot Piping


04

Proper material thickness used

05

Flanges, flanged valve bodies, bonnets and flanged fittings insulated

06

Minimum clearances between insulation and adjacent surfaces

07

45 degrees to vertical runs properly supported

08

Service over 850 F shall be in two layers

09

Joints staggered and proper wire ties

10

Expansion joints spacing horizontal runs correct

11

Proper clearance at flange breaks

12

Tubing properly insulated

13

Proper use of filler and/or mastic materials

Insulation Cold Piping


14

Proper material thickness used

15

Proper insulation of attachments

16

Contraction joints at specified intervals

17

Proper cradle diameter at supports

18

45 degrees to vertical runs properly supported

19

Proper use of joints sealer for single and multiple layer applications

20

Proper taping or banding used

21

Proper use of filler materials, sealer and/or vapor barriers

Weatherproofing Hot Piping

Subcontractor

IH

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

Item

PIPING THERMAL
INSULATION INSPECTION
CHECKLIST

Description of Check

SA5-DOW-01-33-02

August, 2014

Page 2 of 2

Revision 01

Subcontractor

22

Proper use of weather proofing mastic at fittings

23

Proper banding of metal jacket

24

Proper use of S clips on vertical runs

25

Proper lap and metal screw spacing

26

Proper main shield on vertical vessels

Weatherproofing Cold Piping


27

Proper use of vapor barrier mastic paint jacketing

28

No use of screws on cold work except on standing seam systems

Removable Covers
29

Proper stenciling or tagging for identification

Notes:

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

IH

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-34

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

FIREPROOFING

SCOPE

This procedure prescribes the quality control methods used to verify conformance to design requirements

during application of fireproofing.

This procedure covers the following classifications of materials:

a)

Shotcrete (gunite)

b)

Sprayed Fibrous

c)

Sprayed Cementitious

d)

Magnesium Oxychloride (sprayed or troweled)

e)

Intumescent or Subliming Mastic

RESPONSIBILITIES - Self-Perform

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY OF

ACTIVITY

Form

Coordinate release for

fireproofing

Discipline Construction

Engineer

SA5-DOW-01-34-01

Daily

SA5-DOW-01-34-02

Install fireproofing

Discipline Construction

Engineer

Inspect in-process

installation

Discipline Construction

Engineer

Inspect completed

installation

QC Inspector

----Form

SA5-DOW-01-34-02

Form

SA5-DOW-01-34-01

-----

Each installation

Each installation

PROCEDURE

The following steps shall be performed as required by conditions, before preparation, and application of

fireproofing.

Surfaces to be Fireproofed are released as follows:


-

The discipline construction engineer will initiate a Release for Application of Fireproofing

(Form SA5-DOW-01-34-01) for surfaces to be fireproofed.

The discipline construction engineer shall be responsible for technical oversight, mix design

approval, and qualification of application equipment and crew performance.

Install Fireproofing:
-

Assure that the mix design, equipment type, and crew qualifications have been approved.

Review the Release for Application of Fireproofing for authorization to start work.

Fireproofing Subcontractor shall observe recognized safety rules during the work and shall

use safe practices including materials, equipment/tools, and rigging/scaffolding.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-34

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Inspect In-Process Installation:


-

Inspect surfaces to be fireproofed for cleanliness. Oil, grease, loose rust, scale, dirt, and

other foreign matter shall be removed to assure adequate bonding.

Inspect areas not to be fireproofed to assure that they are adequately protected.

Monitor application of fireproofing materials to assure the following:

a)

Areas not to receive fireproofing are protected from contamination.

b)

Fireproofing materials are applied evenly, without mounds, bald spots, sags, or

runs.

Inspect completed installation:


-

Inspections are to be performed and documented on the Fireproofing Inspection Checklist

(Form SA5-DOW-01-34-01).

Inspections shall be performed in a timely manner and coordinated with construction and

subcontractor schedules and activities.


a)

Cured surfaces contain no cracks, blisters, or delaminating.

b)

At least once for every 100 square feet assure that the dried thickness is as

required for the fire-rated protection as shown on the project drawings.

Construction supervision shall be kept informed of the inspection/test activity status

including any nonconforming materials or work.

Nonconformances shall be reported and disposed in accordance with SA5-DOW-01-07.

Surveillance of contractor activities:


-

Verify that materials delivered/brought to the site meet the requirements of the Project

specifications.

Verify that materials are stored in accordance with the manufacturers recommendations.

Verify that equipment to be used is in accordance with the material manufacturers

recommendations.

Verify that any required samples of each type of fireproofing are applied to representative

surfaces to establish workmanship standards (Form SA5-DOW-01-34-02).

FORMS:

Quality Control Forms:

SA5-DOW-01-34-01

Release for Application/Inspection of Fireproofing Checklist

SA5-DOW-01-34-02

Fireproofing Inspection Preconstruction Checklist

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

FIREPROOFING INSPECTION

RELEASE FOR APPLICATION

OF FIREPROOFING &

INSPECTION CHECKLIST

SA5-DOW-01-34-01

August, 2014

Page 1 of 1

Revision 01

Inspection & Test Checklist


Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Turnover System:

Work Package:

IH

Other

Sub System:

Area/Unit:

Release

Area Designation:
From Elevation:

To Elevation

Requested By:

Date

Exclusions/Remarks:

Date

Discipline Engineering Release


Inspection
Drawings:
Work Inspected:

Item

Description of Check

Subcontractor

01

Protection of areas not to be fireproofed

02

Area(s) of surface(s) to be fireproofed

03

Surface preparation

04

Type of fireproofing

05

Brand name (if applicable):

Normal Concrete

Intumescent

Insulating Concrete

Proprietary

Fluor

Concrete grade:

06

Application method:

Gunned

Trowelled

(not for brickwork)

Formed

Others

07

Skirt fireproofing required:

08

Anchorage/reinforcement

09

Slump test performed

10

Compressive strength cylinders prepared

11

Finished/cured surface

12

Material thickness required

13

Material thickness attained

14

Sealing of joints/seams

15

Inside

Outside

Cleanliness

Subcontractor

Industria del Hierro

Client

Others

Name:

Name:

Name:

Signature:

Signature:

Signature:

Name:
Signature:

Date:

Date:

Date:

Date:

The DOW Chemical Company

FIREPROOFING INSPECTION
PRECONSTRUCTION
CHECKLIST

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

SA5-DOW-01-34-02

August, 2014

Page 1 of 1

Revision 01

Inspection & Test Checklist


Tag No.:

Tag Description:
P. O. No.:

Inspection Classification

Turnover System:

Subcontractor:

Subcontractor

Client

Sub System:

IH

Other

Location:

This checklist is to be filled out to document shotcrete panels made for mix design approval and subsequent panels
made to qualify each application crew (i.e. nozzleman, delivery equipment operator and hoseman).

Fireproofing Material and Mix Proportions


Used:

Panel Size and Description of Reinforcement:

Positions of Panel as
Shot:

A- Horizontal

B Vertical

C - Overhead

Note: Clearly identify each panel with A, B or C, date completed, material used nozzleman.

Panel
No.

Position

Subcontractor

Nozzleman

Delivery Equipment

Operator

Industria del Hierro

Material Used

Client

Date
Completed

Others

Name

Name

Name

Name

Signature

Signature

Signature

Signature

Date

Date

Date

Date

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

WELDING INSPECTION

SCOPE

This procedure applies to inspection of welds from joint preparation through final acceptance for welding

performed to the following codes/standards:

ASME B31.1, "Power Piping"

ASME B31.3, "Chemical Plant and Petroleum Refinery Piping"

ANSI/AWS D1.1, "Structural Welding Code, Steel"

RESPONSIBILITIES - Self-Perform

ACTIVITY
Assign numbers to field
pipe welds
Weld Checking and

Inspections

RESPONSIBILITY
QA/QC Manager

Welder Foreman

(Non ASME Code)

DOCUMENTATION

Each piping isometric


drawing (*note)
Form SA5-DOW-01-35-01

Daily Welding Report


Form SA5-DOW-01-35-02

FREQUENCY OF

ACTIVITY

Each isometric

requiring field welds

Daily

Weld Heat Treatment Log

Form SA5-DOW-01-35-01

Daily Welding Report

Certified Welding

Inspector

Daily

Form SA5-DOW-01-35-02

Weld Heat Treatment Log

Form SA5-DOW-01-35-08

100% of Welds

Visual Inspection

*Note: Assigning numbers to Field welds will be necessary only when welds have not been pre-numbered

electronically by the Piping Design System.

Responsibilities - Subcontracted Work

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

Assign numbers to field


pipe welds

Subcontractor

Weld Checking and

Inspections

Subcontractor

Form SA5-DOW-01-35-01

Daily Welding Report

Welding Foreman

Form SA5-DOW-01-35-02

(Non ASME Code)

Each piping isometric

drawing

FREQUENCY OF

ACTIVITY

Each isometric

requiring field welds

Daily

Weld Heat Treatment Log

Subcontractor

Certified Welding

Inspector

Form SA5-DOW-01-35-01

Daily Welding Report

Daily

Form SA5-DOW-01-35-02

Weld Heat Treatment Log

Form SA5-DOW-01-35-08

100% of Welds

Visual Inspection

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

PROCEDURE

Assign Numbers to Field Pipe Welds


Develop a weld map by assigning identity numbers to all pipe field welds on the isometric drawings,

including site pipe shop fabrication welds, prior to the start of work.
Number the welds

consecutively in the direction of flow, starting with the first weld on each isometric sheet as No. 1,

continuing through the last weld on that sheet. If the drawings break at a weld, and the weld

appears on both drawings, assign the number on the upstream drawing. If additional welds must

be added later to facilitate actual fabrication, the weld locations shall be identified with the next

available consecutive number until all additional welds between design welds are identified. A log

may be used to identify the weld numbers already assigned to insure that no duplication of weld

numbers occurs. The inside weld of a slip on flange will carry the suffix "S".

Attachment welds, such as shoes or other supports shall be numbered with the next available

number using the prefix "X". In the case of a reinforcing pad, all welds will refer to the field weld

number joining the branch to header pipe. Use the prefix "PB" and "PH" for pad to branch and pad

to header respectively.

When straight run pipe is being double jointed on the ground, and it is not certain to which line it

belongs, then use the prefix "DJ' before these field welds. Maintain a separate log of "DJ" welds

and assign unique numbers starting with DJ-1. "DJ" welds are marked at 180 intervals. Weld

maps shall accurately show the final location of all "DJ" welds.

Note:

Welder, NDE, PMI, PWHT information/results need not appear on the weld map but must

be readily traceable to the weld map and placed with the weld map at system completion.

Certain things need to be emphasized: Remember, it is of primary importance to assign a unique

weld number to all field welding. Once this number is assigned, do not change it for any reason.
Do not renumber isometrics to keep the weld numbers consecutive in the direction of flow. Use the

next available number for any alterations or additional welds. If a portion of piping containing

assigned welds is cut out of a system and discarded do not reuse these weld numbers but note on

the isometric that these welds are void and show the new welds on the current isometric revision.
Cut shop welds will be assigned field weld numbers.

The isometric drawing will have a traveler (form 79205) attached to each drawing with the

corresponding weld numbers. This traveler shall be signed off by the QC inspector throughout the

duration of the project. The traveler and isometric will be given to the field Foreman before the

start of any work.

Verify by QA/QC Manager and Sub QC before start of any welding

Check the Welding Procedure Specifications (WPS) and Procedure Qualification Records (PQR) to

verify that all procedures required are on the job-site.

The welders qualification record is checked to confirm that qualification essential variables are within

the essential variables of the welding procedure to be used in production.

Maintain a copy of each welders qualification record. Document welder qualification on Welders
Qualification Test Record.

Verify each Welder has been qualified to correct welding procedure prior to start of welding.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

Visual Check
In-process checking and surveillance of fabrication/erection welding is considered part of the

foreman's normal supervisory duties, and includes: verifying correct welder qualification, materials

verification, control of welding consumables, joint preparation, fit-up, preheat, interpass heat, weld

procedure variables, weld condition between passes, and the appearance of all finished welds.

Acceptance criteria are provided by the applicable attachment to this procedure.

For all welds in piping systems and for all other welds requiring post weld heat treatment or NDE,

the foreman will prepare a "Daily Welding Report" (SA5-DOW-01-35-01) for completed welds to

indicate his daily production and to document his visual check and acceptance of each weld. The

foreman's signature on this form indicates his acceptance. The foreman provides these reports

daily to the Certified Welding Inspector. The CWI should be inspected 100% of welds and report

them in the Visual Examination of Weld Report (Form SA5-DOW-01-35-08)

If a weld is repaired because of rejected radiography, the identity of the repaired weld will maintain

the identification number previously assigned except the designation "R1" shall be added after the

joint number. A suffix shall designate subsequent repairs of the same welds, such as R2 and R3,

until the weld is determined to be acceptable by radiographic examination. If welds are completely

cut out the suffix shall be C1, C2, etc.

The foreman should identify the first two welds made by a new welder, welding on a system

requiring random RT, by noting in the "Remarks" section "1st weld" or "2nd weld" so that these

welds can be examined by radiography to confirm welding proficiency in production.

Inspection and Acceptance by the Certified Welding Inspector


Except as noted below, a minimum of 5% of groove welds shall have fit-up inspection by the

inspector. Each welder's work is to be represented. This percentage is to be increased, if

necessary, to satisfy the inspector that acceptable workmanship is being achieved. The inspector

should normally be able to achieve adequate fit-up inspections without establishing hold points, but

he may request hold points for fit-up inspection of specific joints.

The inspector will indicate those joints on which he performed fit-up/final inspection and initials the

visually inspected block on the form. The inspector's signature on the Daily Welding Report

indicates his acceptance of the completed weld(s). Acceptance criteria are specified by the

applicable attachment to this procedure.

The inspector should also verify that the Daily Welding Report has been accurately completed and

the listed weld joints have been identified with the welder's stamp. The inspector provides these

reports daily to the NDE Coordinator for scheduling of NDE.

If the inspector considers any of the reported welds to be unacceptable, he will inform the Area

Superintendent. If it weld is not repaired prior to turning in the Daily Welding Report.

Exceptions to the level of inspection described by this paragraph is provided below:

Unless other wise specified by the Client, inspection (By Certified Welding Inspector) is not

required for welds in B31.3 Category D piping systems if welds in the system will not be

subjected to radiography.

For ASME B31.3 Category "M", "Severe Cyclic Conditions", longitudinal butt welds and "High

Pressure Piping". In addition to the above, all material shall be verified and all fit-ups shall

be inspected by the Certified Welding Inspector.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 4 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

GENERAL

Completion of Post Weld Heat Treatment will be documented on "Post- weld Heat Treatment Log"

(SA5-DOW-01-35-02). The log is to be provided to the NDE Coordinator for scheduling hardness

test if required.

Temporary attachments shall be properly removed and areas visually examined.

For welded branch connections, perform final weld examination of the branch connection pressure

weld prior to the addition of any reinforcing pad or saddle. For welds that will be inaccessible for

inspection due to the fabrication process (e.g.; jacketed pipe, etc.) perform a visual inspection

before fabrication renders these welds inaccessible.

ATTACHMENTS & EXHIBITS

Quality Forms:
SA5-DOW-01-35-01
SA5-DOW-01-35-02
SA5- DOW-01-35-03
SA5-DOW-01-35-04
SA5-DOW-01-35-05
SA5-DOW-01-35-06
SA5-DOW-01-35-07
SA5-DOW-01-35-08

Daily Welding Report

Postweld Heat Treatment Log

Welder B31.3 Random Radiography Control Log

Nondestructive Examination Request / Record

Radiographic Rejectable Defects Statistics

Welding NDE Status Log

Welders Qualification Log

Visual Inspection

Attachments

Attachment
Attachment
Attachment
Attachment
Attachment
Attachment
Attachment

1
2
3
4
5
6
7

Frequency of Visual Examinations

Weld-o-let and Sock-o-let Attachments

ANSI B16.11 Forged Steel Fittings

ASME B31.1 Acceptance Criteria

ASME B31.3 Acceptance Criteria

ANSI/AWS D1.1 Acceptance Criteria

Numbering of Pipe Weld Joints

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

DAILY WELDING REPORT

INDUSTRIA DEL HIERRO S.A. DE


C.V.

Subcontractor
Unit

Line No.

SA5-DOW-01-35-01
August, 2014
Page 1 of 1
Revision 01

Area

Line
Class

Sheet
No.

Weld No.

Type

Weld

Size

Wall

Thick.

Welder

Symbol

Process
Root

Bal

Foreman

Date

Welding
Inspector

Date

Visual

Insp.

Remarks

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

Tag Description:

Tag No.:

P. O. No.:

Inspection Classification

Subcontractor:

Subcontractor

Client

Sub System:

IH

Other

Location:

Log No.

Line No.

Line Class

Sheet

No.

Mark

No.

Turnover System:

Weld No.

Weld

Type

Circuit

No.

Welding
Supervisor:

Date

Inspector
:

Date

Subcontractor

SA5-DOW-01-35-02

August, 2014

Page 1 of 1

Revision 01

POSTWELD HEAT TREATMENT

LOG

Industria del Hierro

Completion

Date

Fluor

Client

Name

Name

Name

Name

Signature

Signature

Signature

Signature

Date

Date

Date

Date

Initials

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

WELDER NDE LOG

Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-35-03
August, 2014
Page 1 of 1
Revision 01

% RT CLASSES

INDUSTRIA DEL HIERRO S.A. DE C.V.

WELD

LINE

LINE

NO.

NUMBER / DWG NO.

CLASS

WELDER

SHT.

NO

SIZE

SCH.

DATE

RT

WELDED

DATE

PASSED

YES

NO

SYMBOL:

R1

DATE

PASSED
YES

NO

R2

DATE

PASSED

CUT

OUT

YES

NO

DATE

NEW

NO

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

NONDESTRUCTIVE
EXAMINATION REQUEST /
RECORD

SA5-DOW-01-35-04

August, 2014

Page 1 of 1

Revision 01

Inspection & Test Checklist

Type Examination

Radiographic
Liquid Penetrant

Ultrasonic
Hardness

Testing

Magnetic Particle

PMI

Examination Data

Line No./Spool Sheet:


Location:
P No./Material:
Pipe Size/Schedule:
Acceptance criteria (code):

Weld No.

Welder Symbol

Date
NDE Completed

Weld No.

Welder Symbol

Date

NDE Completed

NDE Coordinator/Date

Note:

The Following Identification Shall Be Plainly And Permanently Included On The Radiographic Film:
Project No., Line No., Weld No., Welder Symbol, Date Of Radiography.

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

Process

RADIOGRAPHIC

REJECTABLE DEFECTS
STATISTICS

Reporting Period

From

SA5-DOW-01-35-05

August, 2014

Page 1 of 1

Revision 01

To

Rejectable Butt Welds

This Reporting Period


Number Of Butt
Welds Radiographed

Number Of Butt
Welds Rejected

Accumulative Job Totals

Percent

Rejected

Number Of Butt
Welds Radiographed

Number Of Butt
Welds Rejected

Percent Rejected

Rejectable Defect Classification

This Reporting Period

Accumulative Job Totals

Lack of Fusion

Lack of Fusion

Cracks

Cracks

Undercut

Undercut

Incomplete Penetration

Incomplete Penetration

Concave Root

Concave Root

Slag Inclusions

Slag Inclusions

Porosity

Porosity

Elongated Indication

Elongated Indication

Remarks

General Notes:

1. This exhibit is to be used to track weld quality levels as determined by butt weld radiography.

2. Keep separate records for each weld process, controlling code, random or 100% radiography.

3. Report high or increasing defect rates or repetitive defect types to the QA/QC Manager and the Construction
Manager.

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE C.V.

Line No.

Weld No.

Line Class
Welder

Symbol

Date

Welded

WELDING NDE STATUS


LOG

Sheet No.
RT/UT

Accept

Date

PT/MT

Accept

Date

SA5-DOW-01-35-06

August, 2014

Page 1 of 1

Revision 01

Revision

PWHT

Date

BH

Date

Remarks

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-35-07
August, 2014
Page 1 of 1
Revision 01

WELDERS QUALIFICATION LOG

INDUSTRIA DEL HIERRO S.A. DE C.V.

WELDER NAME

WELDER

SYMBOL

DATE
QUALIF.

QUALIFICATION
PROCEDURE

LIMITATIONS
PROCESS

ELECTRODE

POSITION

THICKNESS
RANGE

DIAMETER
RANGE

REMARKS

SA5-DOW-01-35-08

The DOW Chemical Company

June, 2014

Gulfstream Light Hydrocarbon Unit 9 Project

VISUAL EXAMINATION OF WELDS

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1 - Rev.01

Report No.:

REPORT

Date:

Contractor:

INDUSTRIA DEL HIERRO S.A. DE C.V.

PROJECT No.

Welding Procedure No.

Code

Examination Data

Visual Examination Method

Surface Cleaning Method

(metodo de examinacion visual)

(Metodo de limpieza de la superficie)

Direct (Directa)

Grinding (Esmerilado)

Remote (Remota)

Solvent cleaning
(Limpieza con solvente)

ILUMINATION TYPE (Tipo de Iluminacion:)

Machining (Maquinado)

As Welded

(Como quedo despues de soldar)

ARTIFICIAL (artificial)

NATURAL (Natural)

WELD No.

DRAWING No.

ISO No.

DIAMETER

THICKNESS

EVALUATION

Soldadura No

(Plano No.)

(Isom. No.)

(Diametro)

(Espesor)

(Evaluacin)

A = Aceptable

Vo. Bo. Q. C. / NDE

Brushing (Cepillado)

REMARKS (Observaciones)

N = No aceptable

E V A L U A T O R

Level (Nivel)
II

Name and Sign (Nombre y firma)

Name and Sign (Nombre y firma)

Form 08 Visual Inspect_1

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

FREQUENCY OF VISUAL EXAMINATIONS

1.0

ASME B31.1

A.

Boiler External Piping

All completed welds shall have a visual examination.

B.

Non Boiler External Piping

All completed welds shall have a visual examination.

2.0

USAS B31.2

2.1

3.0

All completed welds shall have a visual examination

ASME B31.3 (1)

A.

Category "D" Fluid Service

Visual examination shall be performed to the extent necessary to satisfy the examiner that

components, materials, workmanship and welds conform to the requirements.

B.

C.

"Normal Service Conditions"

1.

Sufficient welds, materials and components shall be examined to satisfy the

examiner that they conform to specifications and are free from defects and

damage.

2.

At least 5% of completed welds shall be examined. Each welder's work shall be

included.

3.

Examine 100% of completed longitudinal welds, except those in components made

from a listed specification (i.e., A53B welded pipe, A234 welded fillings).

4.

Random examination of the assembly of threaded, bolted, and other joints for

conformance to engineering requirements.

5.

Random examination of alignment, guides, supports, and cold spring.

6.

Examination of erected piping for defects or deviations from engineering design.

7.

When pneumatic testing is performed, all threaded, bolted, and other mechanical

joints shall be examined.

"Severe Cyclic Conditions"

Same as #B above except all fabrication shall be examined.

D.

"Category "M" Fluid Service

Same as #B above except all fabrication shall be examined.

E.

High Pressure Piping

Same as #B above except all fabrication shall be examined.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

NOTE(1):

4.0

5.0

In-process weld examination frequency shall be to an extent such that the

examiner is satisfied requirements are being met, except where in process

inspection takes the place of random radiography required by B31.3 for Normal

Fluid Service or Category "M" Fluid Service. The in-process examination in lieu of

random radiography must be approved by the Engineer or Owner and shall include

a final visual examination.

ASME B31.4

4.1

All piping components shall be examined for damage prior to fabrication.

4.2

All weld joints shall have a fit up, root pass, and final visual examination.

4.3

All completed welds shall be cleaned and examined prior to coating operations.
Irregularities that could damage the pipe coating shall be removed.

ASME/ANSI B31.5

Sufficient welds, materials, and components shall be examined to satisfy the examiner that they

conform to specifications and are free from defects and damage.

6.0

ASME B31.8

Sufficient welds, materials, and components shall be examined to satisfy the examiner that they

conform to specifications and are free from defects and damage.

7.0

ANSI/ASME B31.9

Sufficient welds, materials, and components shall be examined to satisfy the examiner that they

conform to specifications and are free from defects and damage.

8.0

ASME B31.11

Sufficient welds, materials, and components shall be examined to satisfy the examiner that they

conform to specifications and are free from defects and damage.

9.0

ASME B96.1

Sufficient welds, materials, and components shall be examined to satisfy the examiner that they

conform to specifications and are free from defects and damage.

10.0

AWWA D100 (Identical to AWS D5.2)

Sufficient welds, materials, and components shall be examined to satisfy the examiner that they

conform to specifications and are free from defects and damage.

11.0

ANSI/AWS D1.1

All completed welds shall have a visual examination.

Module Fabrication Quality Manual, SA5-DOW-01-35

The DOW Chemical Company

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

Attachment 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

ACCEPTANCE CRITERIA

W ELD O LETA N D SO CK O LETFnniTN G SA TTA CH M EN T

TRANSVERSE VIEW - REDUCING-SIZE WELDOLET OR SOCKOLET FITTINGS

REQUIRED WELD DEPOSIT FOR REDUCING-SIZE WELDOLET OR

SOCKOLET FITTING. WELD SURFACE BC SHOULD BE PARALLEL

W ITH LONGITUDINAL CENTERLINE OF FITTING AND SHOULD

MAKE A SMOOTH TRANSITION AT POINT C.

LONGITUDINAL VIEW - REDUCIN -SIZE WELDOLET OR SOCKOLET FITTINGS

REQUIRED WELD DEPOSIT FOR REDUCING-SIZE W ELOOLET OR

SOCKOLET. W ELD SURf-ACE SHOULD BE LEVEL W ITH SURFACE

AB AND SHOULD MAKE A SMOOTH (NOT ABRUPT) TRANSITION

INTO THE SURFACE OF THE PIPE AT POIN T C.

Page 1 of 1

Module Fabrication Quality Manual, SA5-DOW-01-35

The DOW Chemical Company

August, 2014 Rev.01

Gulfstream Light Hydrocarbon Unit 9 Project

Attachment 3

Purchase Order No. GUST-50-LHC-K067

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

A C C E P T A N C E C R IT E R IA

A N SI B 16.11 FO R G E D ST E E L F IT IIN G S
Socket-w elding or
threaded adapter

S ocket-w elding or
threaded half coupling

H eader or N

pipe

H eader or run pipe

8rench connection using forged 118elsocket-w elding or threaded


adeptfi for prw aure and tem perature conditions greeter than
perm itted for A N SI 816.11 forged steel fittings

8rench connection using A N SI 816.11 forged 11881

lO C ket-w elding or threaded half coupling


[S ee N ote (1)]
N O TE :

(1) R efer to Para. 104 .3.1 (C .2) for branch connections not requiring reinforcem entcalculations.

TYP IC A L FU LL PEN ETR ATIO N W ELD BRANCH CO NNECTIO NS

FO R N PS 3 AN D S M A LLE R H A LF C O U PU N G S OR AD APTER S

Socket-w elding or
threaded fitting

H eader or run pipe

3/16 in. (0.6 m m l m in

I.-

tw [see P ara. 104.3.1 (C .2)]

TY P IC A L P A R TIA L PEN ETR ATIO N W ELD BRANCH CO NNECTIO N

FOR NPS 2 AND SM ALLER FITTING S

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 4

Page 1 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

ACCEPTANCE CRITERIA
ASME B31.1

1.0

ASME B31.1

1.1

In process examination shall meet the following:

A.

All base materials shall be identified as to type and grade (i.e.; A106B, SA516 G70,

etc.) and for Boiler External Piping per the Quality Control System Manual, B & PV

code work (i.e.; heat number).

B.

Joint preparation and cleanliness shall be in accordance with the WPS.

C.

Check welder qualification, base material for conformance to the WPS.

D.

Welding filler materials shall be in accordance with the WPS. For ASME Code

Stamped items, filler materials shall be traceable by heat and lot number.

E.

Preheating prior to cutting or welding (including tacking) shall be in accordance

with the WPS.

Note:

For piping of over 3% nominal Chromium content fabricated to B31.1,

visual for cracks after preheat is interrupted and restarted as permitted by

the WPS.

F.

Fit-up, including misalignment of butt welds, shall be in accordance with the WPS.
Internal misalignment shall not exceed 1/16 inch unless the piping design

specifically states a different allowable misalignment, in which case, the

misalignment over 1/16 inch shall be tapered to a 30 degree minimum angle.

G.

Tack welds shall be made by qualified welders.

H.

Tack welds that are to be incorporated into the final weld shall be visually

examined and be free of cracks, slag, porosity, lack of fusion, cold lap, internal

undercut, excessive penetration, and the ends prepared by grinding.

I.

The backside of double welded joints shall be backgouged to sound metal and

visually examined prior to welding.

J.

Each weld pass shall be free of porosity, slag, cold lap, cracks and other indications

that would compromise weld quality.

K.

Arc strikes shall be properly removed and areas visually examined.

L.

Welding end transitions shall provide for a 3 to 1 taper, across the weld, with

respect to the base metal on each side of the weld.

Note: Longitudinal butt welded joints shall be aligned within 1/16 inch and inside

surface shall not be tapered. The resulting weld joint and tapered areas

shall not be thinner than the non tapered base material.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 4

Page 2 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

M.

1.2

The depth of insertion of a pipe or tube into a socketweld fitting shall be at least

1/4". Before welding, there shall be at least 1/16" clearance between the end of

the pipe and the internal shoulder of the socketweld fitting.

A final visual weld examination shall be in accordance with the following:

A.

No porosity allowed.

B.

No linear indications such as cracks, lack of fusion, cold laps or lack of penetration.

C.

No slag or weld spatter (including base material).

D.

No unfilled craters allowed (with or without associated shrinkage defects).

E.

No under filled (weld cap) areas.

F.

Root concavity shall not reduce the weld below the base material thickness.

G.

As-welded surfaces are permitted; the surface of the welds shall be sufficiently free

from coarse ripples, grooves, overlaps, abrupt ridges, and valleys to allow for

proper interpretations of NDE and to avoid stress raisers.

H.

Undercut shall not exceed 1/32 inch and shall not reduce the wall thickness below

minimum wall requirements (i.e., .875 X nominal wall for schedule pipe, the

minimum ordered wall thickness of minimum wall pipe, and nominal wall

minimum, minus .01 inch for nominal wall ordered pipe).

I.

Any offset of outside butt welding surfaces shall be faired to a 3:1 taper over the

width of the weld.

J.

The butt welding ends of items or fittings shall provide a gradual change in

thickness from the item or fitting to the adjoining item.

K.

Welding end transitions shall be as follows:

1.
2.

3.

L.

The wall thickness in the transition region is not less than the minimum

wall thickness of the adjoining pipe.

Sharp re-entrant angles and abrupt changes in slop in the transition region

are avoided.

There is a gradual transition between the two items. The slope of the

transition to the weld does not exceed 3:1 and from the weld does not

exceed 3:1.

Butt weld reinforcement thickness shall meet the following:

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Attachment 4

Page 3 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

MAXIMUM REINFORCEMENT (in)

Thickness of Base

Metal Inches

>750F

350-750F

Up thru 1/8

1/16

3/32

3/16

Over 1/8 thru 3/16

1/16

1/8

3/16

Over 3/16 thru 1/2

1/16

5/32

3/16

Over 1/2 thru 1

3/32

3/16

3/16

1/8

1/4

1/4

5/32

See Note 5

See Note 5

Over 1 thru 2
Over 2

Notes:

<350F

1.

For double welded butt joints, the limitation on reinforcement


given above shall apply separately to both inside and outside

surfaces of the joint.

2.

For single welded butt joints, the reinforcement limits given above

shall apply to the outside surface of the joint only. Internal

reinforcement shall not exceed 1/16 inch for the GTAW process

nor 3/32 inch for the SMAW process.

3.

The thickness of weld reinforcement shall be based on the

thickness of the thinner of the materials being joined.

4.

The weld reinforcement thicknesses shall be determined from the


higher of the abutting surfaces involved.

5.

The greater of 1/4 inch or 1/8 times the width of the weld in

inches.

M.

Fillet weld sizes shall meet drawing requirements. Weld leg length for socket, slipon flanges and socket fittings shall be 1.09 times the pipe wall thickness for the

hub thickness, whichever is less. Weld sizes for branch connections may be found

in Figure A.

N.

For seal welding of threaded joints, the exposed threads shall be entirely covered

by the seal weld.

Each weld shall be identified with the welders symbol or traceable by

documentation.

O.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 4

Page 4 of 4

INDUSTRIA DEL HIERRO S.A. DE C.V.

FIGURE A

ASME B31.1
WELDED BRANCH DETAILS

NOTES:

These sketches show minimum acceptable welds. Welds may be larger than those shown

here.

tc = the smaller of 1/4" or .7 x Tb

Tr = nominal thickness of reinforcement, in.


tmin = the smaller of Tb or Tr
Tb = nominal thickness of branch wall
Th = nominal thickness of header wall

Detail (1) w = Tb + tc
Detail (2) w = Th + tc
Detail (3) w = Tr + tc or Tb + tc

Detail (4) w = Th + Tr + tc
Detail (5) w = Tb + tc
w = Governing thickness for determining Postweld Heat Treat.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 5

Page 1 of 6

INDUSTRIA DEL HIERRO S.A. DE C.V.

ACCEPTANCE CRITERIA
ASME B31.3

1.0

ASME B31.3, CHEMICAL PLANT AND PETROLEUM REFINERY PIPING

1.1

In process examination shall meet the following:

A.

All base materials shall be identified as to type and grade (i.e., A106B, SA516 G70,

etc.).

B.

Joint preparation and cleanliness shall be in accordance with the WPS.

C.

Check welder qualifications, base material for conformance to the WPS.

D.

Welding filler materials shall be in accordance with the WPS.

E.

Preheating prior to cutting or welding (including tacking) shall be in accordance

with the WPS.

F.

Fit-up, including misalignment of butt welds, shall be in accordance with the WPS.
Any misalignment of butt welds, exceeding the WPS, shall be tapered to a 30

degree maximum angle. The resulting weld joint and tapered areas shall not be

thinner than the non tapered base material.

G.

Tack welds shall be made by qualified welders.

H.

Tack welds that are to be incorporated into the final weld shall be visually

examined and be free of cracks, slag, porosity, lack of fusion, cold lap, internal

undercut, excessive penetration, and the ends prepared by grinding.

I.

The backside of double welded joints shall be backgouged to sound metal and

visually examined prior to welding.

J.

Each weld pass shall be free of porosity, slag, cold lap, cracks and other indications

that would compromise weld quality.

K.

Arc strikes shall be properly removed and areas visually examined.

L.

For branch on pipe connections, the opening through the pipe shall align with the

bore of the branch within 1/8 inch or one-half the branch wall thickness, whichever

is less.

M.

The depth of insertion of a pipe or tube into a socketweld fitting shall be at least

1/4". Before welding, there shall be at least 1/16" clearance between the end of

the pipe and the internal shoulder of the socketweld fitting.

N.

When accessible for visual inspection, the internal condition of the root pass shall

meet Figure A, B, or C as applicable.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 5

Page 2 of 6

INDUSTRIA DEL HIERRO S.A. DE C.V.

1.2

Final Visual Weld Examination shall be in accordance with the following:

A.

Final Visual Weld Examination shall be in accordance with Figure A and B for

"Nominal Service Conditions", "Severe Cyclic Conditions" and Category "D" Fluid

Service.
Category "M" fluid service shall be inspected to "Normal Service

Conditions" of Figure A and Figure B. "High Pressure Piping shall be examined in

accordance with Figure C.

B.

Fillet weld sizes shall meet drawing requirements. Weld leg length for socket and

slip-on flanges shall be a minimum of 1.4 times the pipe wall thickness or the hub

thickness whichever is less.

C.

For socket welding fittings, other than flanges, the minimum weld leg lengths shall

be 1.25 times the pipe wall thickness or 1/8 inch, whichever is greater. Weld sizes

for branch connections may be found in Figure D.

D.

For seal welding of threaded joints, the exposed threads shall be entirely covered

by the seal weld.

E.

Perform Visual Weld Examination prior to other nondestructive examinations and

post weld heat treatment. In addition, piping constructed of P3, P4, or P5

material, perform a final visual weld examination after postweld heat treatment.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

June, 2014

Purchase Order No. GUST-50-LHC-K067

Attachment 5

INDUSTRIA DEL HIERRO S.A. DE C.V.

FIGURE A

ASME B31.3

WELD ACCEPTANCE CRITERIA

Page 3 of 6

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

June, 2014

Attachment 5

INDUSTRIA DEL HIERRO S.A. DE C.V.

FIGURE B

ASME B31.3

WELD ACCEPTANCE CRITERIA NOTES

Page 4 of 6

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

June, 2014

Attachment 5

INDUSTRIA DEL HIERRO S.A. DE C.V.

FIGURE C

ASME B31.3

WELD CRITERIA NOTES AND WELD CRITERIA FOR TABLE K341.3.2A

Page 5 of 6

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

June, 2014

Attachment 5

Page 6 of 6

INDUSTRIA DEL HIERRO S.A. DE C.V.

FIGURE D

ASME B31.3

WELDED BRANCH DETAILS

NOTES: These sketches show minimum acceptable welds. Welds may be larger than those shown here.

tc = the smaller of 1/4" or .7 x Tb


Tr = nominal thickness of reinforcement, in.

Detail (1) w = Tb + tc

tmin = the smaller of Tb or Tr

Detail (2) w = Th + tc

Tb = nominal thickness of branch wall

Detail (3) w = Tr + tc or Tb + tc

Th = nominal thickness of header wall

Detail (4) w = Th + Tr + tc
Detail (5) w = Tb + tc

w = Governing thickness for determining Postweld Heat Treat.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 6

Page 1 of 1

INDUSTRIA DEL HIERRO S.A. DE C.V.

ACCEPTANCE CRITERIA
ANSI/AWS D1.1

1.0

ANSI/AWS D1.1, "STRUCTURAL WELDING CODE-STEEL"

1.1

1.2

In process weld examination shall meet the following:

A.

Joint preparation shall be in accordance with the WPS.

B.

Fit-up, cleanliness and alignment of butt welds shall be in accordance with the

WPS. Backing bar gap shall not exceed 1/6 inch.

C.

Fillet weld fit-up gap shall meet the WPS unless otherwise specified on the

drawing. If the gap is greater than 1/16 inch, the leg of the fillet weld shall be

increased by the amount of the root opening.

D.

Check welder qualification, filler material for conformance with the WPS.

E.

For butt welding parts of unequal thickness, the joint preparation shall provide for

a transition at a taper not-to-exceed 1:2 1/2. Chamfering of the parts shall be a

specified on the drawing, otherwise the taper shall be accomplished across the

weld joint.

F.

Parts to be butt welded shall not exceed a mismatch of 10% of the thinner of the

two members being joined, but in no case more than 1/8".


In correcting

misalignment, the parts shall be drawn in to a slope greater than 1/2 inch in 12

inches. In addition, where the thickness of the two members being joined differ,
the weld and/or base materials are to be tapered to a smooth transition with a slop

not-to-exceed 1 inch 2 1/2 inches.

Final Visual Weld Examination shall be in accordance with the following:

A.

No porosity.

B.

No linear indications such as cracks, lack of fusion, cold laps.

C.

No slag or weld spatter (including base material).

D.

No craters.

E.

No under filled areas.

F.

Undercut shall not exceed 0.010 inches unless otherwise specified by Engineering.

G.

Butt weld reinforcement shall not exceed 1/8 inch.

H.

Convexity of a fillet weld shall not exceed .07 times the actual width, plus .06 inch.

I.

Any offset of outside surfaces shall be faired to a 1:2 1/2 taper over the width of

the weld.

J.

In any single continuous fillet weld the actual size may be less than the specified

size by not more than 1/16 inch provided that the undersize portion does not

exceed 10 percent of the weld length. On web-to-flange welds on girders, no

underrun is permitted at the ends for a length equal to twice the width of the

flange.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 7

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

NUMBERING OF PIPE WELD JOINTS

All pressure retaining welds and attachment welds to pressure piping shall be given a unique number which

will serve to identify all data concerning the weld.

1.0

Field Welds - All pressure retaining piping welds and attachment welds shall be numbered. Upon

receipt of the isometric drawings or layout piping plans, the Project Quality Control Welding

Inspector shall (if possible) pre-number all field welds. If this pre-numbering proves impractical,

the Welding Inspector shall assign weld numbers as the welds are made. A Log may be used to

identify the weld numbers already assigned to ensure that no duplication of weld numbers occurs.

Certain things need to be emphasized: Remember that it is of primary importance to assign a

unique weld number to all field welding. Once this number is assigned, do not change it for any

reason. Do not renumber isometrics to keep the weld numbers consecutive in the direction of flow.
Use the next available number for any alterations or additional welds. If a portion of piping

containing assigned welds is cut out of a system and discarded do not reuse these weld numbers

but note on the isometric that these welds are void and show the new welds on the current
isometric revision. Cut shop welds will be assigned field weld numbers. If the shop weld and mark

piece can be identified, not this in the remarks portion of the Daily Welding Report.

1.1

SOCKET WELDS, HALF COUPLINGS, WELDOLETS (UNDER 2")

All socket welds shall be numbered by isometric drawing. Each sheet shall start with weld

1 and be numbered with the flow. In the event that additional welds are added, use the
next numbers not previously used on each sheet for the new welds. In this manner all

socket welds will have a single digit or two digit weld number.

Half couplings and weldolets (under 2") shall also have a single digit or two digit weld

number assigned by isometric drawing. In other works, the numbering of a series of half

coupling on a header will be welds 1,2,3 etc. on the main header line number which shows

these welds.
The socket welds on lines running from these half couplings will be

numbered as described above, for each line number.

1.2

BUTT WELDS, BRANCH CONNECTIONS (2" AND OVER), WELDOLETS (2" AND OVER) ETC.

All butt welds, mitre welds, branch connections (2" and over), weldolets (2" and over) and

slip-on flanges shall have a three digit weld number running consecutively throughout all

lines contained in the modification. Each modification shall begin with weld 001 and

numbered with the flow to the end of the line. Additional lines should continue with the

next number and progress until all such welds are numbered. A log attached to the field

welding isometric package should readily identify the last weld number used. If additional

welds are needed, the next unused numbers will be assigned and logged.
On

modifications where it is not practical to prenumber the welds, the next consecutive
number, as determined by the log, shall be used as the welding progresses.

1.3

ATTACHMENT WELDS

Attachment welds shall be numbered using the nearest (upstream) piping weld as a part of

the weld number with the next final number of the welds numbered. In other words, a

shoe welded between welds 021 and 022, if it is necessary the recording will be numbered

with the number 29, if the last number of the weld numbered was 28. Additional

attachment welds in this area or another area will be numbered 30, 31, etc.

2.0

Pipe Shop Welding - All welds on piping fabricated in the Site Pipe Shop shall be given a unique

number by the Pipe Shop Supervisor prior to fabrication. All mark pieces shown on an isometric

drawing shall be assigned consecutive numbers beginning with the lowest numbered mark piece

and numbered with the flow until all shop welds on all mark pieces on the isometric have been

identified.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-35

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 7

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Any additional welds on any mark piece shall be given the next unassigned number on the

isometric. In other words the first weld on the first mark piece will be "SW1" and continuing

throughout all mark pieces on the isometric drawing. Thus the unit number, line number sheet

number, mark piece number and weld number will constitute a unique weld identification as

required.

2.1

Double Jointed Welds - All random length piping being welded by the Site Pipe Shop into

double (or triple) lengths for ease in field erection shall be given a unique number. If the

line number and line class are unknown at the time of fabrication these welds shall be

given consecutive four digit weld numbers prefixed by "DJ". A log shall be maintained by

the Pipe Shop Supervisor of the "DJ" weld numbers used to prevent duplication of weld

numbers. All "DJ" weld numbers shall be hard stamped or etched across the weld in two

locations 120 apart, 60 either side of the welders stamp. These "DJ" welds shall be

radiographed 100 and stockpiled for eventual use.


These welds will be tracked as

"Unassigned Welds" and transferred when the actual modification, line number and class

are known.

All random length piping being double (or triple) jointed in the Site Pipe Shope where the
modification number, line number and line class are known at the time of fabrication shall

be given consecutive three digit shop weld numbers beginning with SW100 and numbered

consecutively within that particular modification. These welds will be subject to the normal

shop weld NDE requirements and welder control based on the line class requirements.
These weld numbers shall be hard stamped or etched as described above with the

exception of "DJ" prefix which will be "SW" in this case.

All random length piping double (or triple) jointed in the field for installation on a particular

modification where the line number and line class are known shall be given consecutive
field weld numbers within the modification. These numbers shall be hard stamped or

etched by the Piping Supervisor for eventual location in the piping system. These welds

shall be subject to the normal NDE and welder control for the line class at the time of

production.

2.1.1

Piping Drawings

All field welds on pressure piping (both pressure retaining and attachment welds)

shall be accurately located on the isometric drawing (or plot plan). Since other

records will show the welder and the date or production (Daily Welding Report,

Line Welding and NDE Record) this information is not necessary to include on the

drawing.

Double joint ("DS") random length pipe welds shall be accurately shown on the

isometric, rack, or plot plan drawings in relation to the field tie-in welds.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-36

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

NONDESTRUCTIVE EXAMINATION

SCOPE

This procedure describes the activities and controls for performing nondestructive examination of weldments

when specified by project requirements. Methods within the scope of this procedure include Radiographic

Testing (RT), Ultrasonic Testing (UT), Magnetic Particle Test (MT), Liquid Penetrant Test (PT), Positive Material

Identification Test (PMI) and Hardness Test (HT).

Responsibility Subcontracted Work

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY OF

ACTIVITY

Perform RT, UT, MT,


PT, PMI, HT

NDE Coordinator /
Subcontractor

Technical Supervision of
NDE

NDE Coordinator /
Subcontractor / QAQC

Manager

Selection for NDE and


Status Maintenance

NDE Coordinator or
delegate to

subcontractor

Coordinate Weld
Repairs

QC Inspector /
Subcontractor

Report as specified in the


approved NDE Procedure

_____

NEWS program.

_____

Per specification

_____

Per specification

Each rejected weld

GENERAL

NDE subcontractor personnel performing RT, UT, MT, PT, and PMI are to be qualified and certified to

the requirements of NDE international standards. Personnel performing hardness tests must be trained

in the use of the equipment and procedures but do not require certification.

Perform RT, UT, MT, PT, PMI, HT

Volumetric Nondestructive Tests should be completed and results reported within 24 hours after

the welds are reported as complete. For special circumstances, such as the start of the welding

program, or when the NDE Contractor does not have a jobsite laboratory, welds requiring

radiography may be accumulated, but in these cases there should not be a backlog of more

than ten (10) welds.

Other NDE methods should be completed as soon after the NDE request as practical.

Weld Selection and Status Maintenance includes:

Obtain a weld map and post the status of NDE for line classes requiring 100% NDE by a specific

method or for individual welds requiring NDE by specification. Also post the status of welds

that have been postweld heat treated. Alternately, may also be kept for each isometric sheet.
Either of these documents is to provide for accountability that all welds on the line were

examined and accepted.

Using the "Daily Welding Report" and the Post Weld Heat Treatment Log, select the welds for

NDE as they are completed.

Examine the selected welds for surface contour that may interfere with the NDE method.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-36

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Notify the NDE Contractor or the QC inspector if self-performed, of the required NDE, by

submission of a copy of the Nondestructive Examination Request/Record. Maintain the original

to verify completion of NDE.

Maintain a tickler file of rejected welds. The NDE Coordinator's copy of the NDE Report shall

remain in the tickler file until the repair for that weld is noted as accepted on a subsequent

report. At that time, the reports of the original and repaired weld and the radiographic film for

both welds, shall all be placed together in the file. The acceptance date shall be logged on the

isometric sheet or line sketch.

The NDE Reports (annotated with NDE Coordinator review) and the Radiographic film shall be

traceable to the weld location shown on the spool drawing or pipe line sketch.

Selection of Welds under a random radiographic program includes:

Select welds for random radiography to satisfy ASME B31 requirements from individual welder

histories established on the "Welder B31.3 Random Radiography Control Log. Welds to be

radiographed for random radiography must be selected from sample lots. For simplicity, it is

suggested that sample lots be established as 20 welds for 5% radiography.

Select the first two welds made by a welder on a system requiring random radiography to

confirm the welder's proficiency in production. These two production welds shall not be counted

as part of the random radiography sample lot. This should be waived if other welds made by

the welder were radiographed.

Identify the welds to be radiographed by spray-painting a yellow band around the

circumference of the pipe adjacent to the welds, or any other identification near to the weld.

Note:

Notify the Foreman of the welds selected for radiography.

Log the radiographic examination results for random radiography. Post the completed welds

reported by the foreman, the date reported, and the results of radiography on the Weld Map.
Notify the Foreman and QC Inspector of the results.

Spray paint a blue band around the circumference of the weld adjacent to the accepted welds,

or any other identification near to the weld. Identify the rejected welds with a red band or any

other identification near to the weld. When the repair is acceptable, the red band will be

covered by blue or any other identification near to the weld.

Note:

For random radiography, when a weld is rejected, select two previous similar welds by the

same welder, from a specified sample lot, for additional radiography, in compliance with ANSI

B31.1. The selection shall be made from the welder's history. The welds are to be selected

from the sample lot used to select the initial weld.

Selection of welds and maintenance of status can be performed using the computer program

NEWS. In this case, the forms for manual weld tracking do not need to be maintained and the

status does not need to be maintained on the spool drawing or pipe line sketch. It is

recommended that the NEWS program be used for projects with 200 or more joints to be

radiographed.

Issue periodic weld reject rate reports for welds examined by radiography. When statistical data

indicates high or increasing reject rates, the Construction Manager and the QA/QC Manager

shall be informed.

A different method of noting accepted and rejected welds and welds requiring

examination may be developed by the NDE Coordinator.

A different method of noting accepted and rejected welds and welds requiring

examination may be developed by the NDE Coordinator.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-36

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 3 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

This section also applies if UT is substituted for RT.

NOTE: Information RT shall not be performed on welds that have been capped out.

Coordination of Weld Repairs includes:

For those welds which have been rejected, determine the exact location, extent, and nature of

the defect.

Consult with the welder and foreman on defect cause and prevention and repair technique.

When the weld has been repaired, have the weld reported on the "Daily Welding Report" to

schedule radiography of the repair. Identify the repaired weld with the identification number

previously assigned, except the subscript R1 shall be added after the designation. Subscripts

shall designate subsequent repairs of the same welds, such as R2 and R3, until the weld is

determined to be acceptable by radiographic examination.

ATTACHMENTS AND EXHIBITS

N/A

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-37

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 1 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

POSITIVE MATERIAL IDENTIFICATION EXAMINATION

SCOPE

This procedure describes the activities and controls for performing Positive Material Identification (PMI) examination

of specified alloy and other special materials in accordance with the requirements of The DOW Chemical Company

LHC9, Refining Best Practice, Positive Material Identification of Alloy Piping Systems. (MAP PMI)

RESPONSIBILITY All Materials Supplied by Fluor

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

FREQUENCY

Warehouse Receiving

Warehouse /Supervisor

Receiving Inspection

QC Inspector

_____

On-going

Perform PMI

NDE Supervisor

MAP PMI

Per MAP Best Practice

Perform Color Coding

Warehouse Supervisor

MPC color coding of piping

materials

Identification

Supervisor

_____

On-going

Document Results

Supervisor

Form SA5-DOW-01-37-01

Form SA5-DOW-01-37-02
Form SA5-DOW-01-37-04

Each test

Technically Supervise

PMI

QAQC Manager

_____

_____

Resolve Accept and

Rejects

QAQC Manager

MAP PMI

Per Rejects

On-going

GENERAL

Warehouse Receiving Inspection


-

Industria del Hierro Quality Control shall be responsible for receiving inspection to confirm that all

incoming alloy and special materials are received with the required positive material identification

(PMI) performed, with PMI identification coding in place, and, when specified, with PMI

documentation confirming identity verification conformance. (Note: material test reports do not

satisfy the requirement for PMI documentation.)

Nonconforming items (alloy or special materials for which the required PMI has not been

performed, items without the required PMI identification coding in place, and/or items without PMI

documentation) shall be placed in a Quarantine area or tagged Hold until such time as the

nonconformance is resolved. The Material Manager shall be responsible for obtaining disposition

for incoming items found to be nonconforming.

The QA/QC Manager shall be notified of any alloy or special materials identified at initial

Warehouse Receiving as nonconforming.

NOTE: Do Not release nonconforming or indeterminate materials, components, or equipment for

use in the facilities being constructed.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-37

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 2 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Subcontractor Receiving Inspection


Each Subcontractor is responsible to ensure that all items supplied to him by Fluor/Client meets the

requirements of the Project LHC9 Best Practice. Nonconforming items (alloys for which the required PMI

has not been performed, items without the required PMI identification coding in place, and/or items without
PMI documentation) shall be placed in a Quarantine area until such time as the nonconformance is

resolved. Fluor shall be responsible for obtaining disposition for incoming items found to be nonconforming.

Perform Positive Material Identification


-

PMI will be performed by trained personnel whose ability to successfully operate the PMI test

equipment has been documented by test.

Non-destructive methods used for PMI testing shall be capable of identifying the material

quantitatively.
Acceptable test equipment for non-destructive PMI testing is listed below:

Portable x-ray fluorescence analyzers. Use is limited to the following instruments or

their equivalents unless Fluor/Client Site Quality Manager gives prior approval. The QA/QC

Manager may designate another instrument as equivalent based on demonstrated and

documented performance testing.

Niton

Metorex X-MET 880, X-MET 960 or X-MET 2000.

SpectroPORT Model TP-07 or TFO-02, Specto Test F.

Metroex ARC-MET 900 or ARC-MET 930.

PMI of Alloy Piping


-

Extent of PMI shall be per the MPC Best Practice

All field installed alloy piping will be 100% PMI verified in the as installed position. Each spool

and the weld will be verified and results documented on the fabrication spool drawing/isometric,

listed on the PMI point sheet and marked with the appropriate verification color by the PMI

Technician as each point is analyzed. See Attachment 1 for complete instruction.

PMI of Welding Wire (Bare)


-

Bare wire shall be purchased in unopened manufacturers containers.

Each container must have the AWS Classification, heat and lot number clearly marked.

Filler metal certification is required.

Coated electrodes do not require PMI checks prior to use. Deposited filler metal (SMAW) must be

PMI checked in the as welded condition.

Identification
-

Each item (pipe spool, plate, weld, fitting, valve, etc.) that has been verified shall be marked using

MAP Best Practice (See Attachment 01) and shall be identified with the following color codes: See

Attachment 02

Items which cannot accommodate this identification shall be individually tagged with the above.

Paints/Markers used for applying color code for PMIV are controlled by the QA/QC Manager.

Each fabricated spool must have verification marks applied to each component and weld by the PMI

Technician.

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-37

Gulfstream Light Hydrocarbon Unit 9 Project

August, 2014 Rev.01

Purchase Order No. GUST-50-LHC-K067

Page 3 of 3

INDUSTRIA DEL HIERRO S.A. DE C.V.

Pipe and fittings should be painted with a stripe that is parallel with the axis of the pipe.

Welds shall be marked along their circumference perpendicular to the axis of the pipe so that the

verification markings will be visible when the pipe spool is installed.

Small connections and short branches should be painted through their entire length.

Document Results
-

Technically Supervise PMI will include:


-

Ensuring that only properly trained personnel conduct PMI testing in accordance with a procedure.

The QA/QC Manager shall have overall responsibilities for the implementation of this PMI Program

and conformance to the MAP Best Practice.

Verification of PMI
-

Document PMI test results on the appropriate Positive Material Identification (PMI) Inspection

Reports.

The MAP may witness initial calibration/standardization of the PMI equipment at the start of each

work period and observe PMI testing randomly during the work period to assure compliance with

this procedure.

Resolved Accept and Rejects


-

If the PMI test results fall outside of the acceptable ranges, the item will be rejected.

All rejected materials shall be isolated in a "Quarantine" area, tagged "REJECTED", and a

Nonconformance Report initiated.

When an item from a representative sample is rejected:

a)

100% of the remaining components from which the sample was taken shall be examined.

b)

100% of the components from the next two lots shall be examined.

c)

If no further components are rejected in a) or b), above, the extent of examination shall return

to that specified in the MPC Best Practice. Rejected items shall be returned to Fluor.

REFERENCES

Quality Control Forms:

SA5-DOW-01-37-01 -

PMI Inspection Record

SA5-DOW-01-37-02 -

Bulk Material Positive Material Identification Record

SA5-DOW-01-37-03 -

Pipe Spool Positive Material Identification Record Point Sheet

SA5-DOW-01-37-04 -

Weekly PMI Log

ATTACHMENTS

Attachment 01

PMI Procedure for the Field

Attachment 02

Color Code System

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-37-01

August, 2014

Page 1 of 1

Revision 01

PMI INSPECTION RECORD

INDUSTRIA DEL HIERRO S.A. DE


C.V.

Inspection & Test Checklist


Tag No.:

Tag Description:
P. O. No.:

Inspection Classification

Turnover System:

Subcontractor:

Subcontractor

Client

Sub System:

IH

Other

Location:

PMI Request By:


Signature:

Date:

Purchase Order Number:

PMI Equipment Used:

PMI Performed By:

Signature:

Date:

PMI Performed By:

Signature:

Company Performing PMI:

PMI Will Be/Was Performed At:

Examination Results/By Material Identification

Item Or
Tag No.

Sample Size

Material

Mill Cert. No. Heat Number

Description

Examination Results/Analyzed Material

Item Or
Tag No.

Sample Size

Material

Mill Cert. No. Heat Number

Chemical Composition Percentage

Cr Mo Ni Mn Ti

Address Of Supplier Responsible For Rejection (s)

Additional Information

Manhours And Loss Incurred From Rejections, Etc.

PMI Supervisor

Signature/Date

Fe Co Cu Nb W

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

SA5-DOW-01-37-02
August, 2014
Page 1 of 1
Revision 01

BULK MATERIAL PMI RECORD

INDUSTRIA DEL HIERRO S.A. DE


C.V.

Inspection & Test Checklist


Calibration/Standardization

Chemical Composition Percentage


Cr

Company:

Mo

Ni

Mn

Ti

Fe

Co

Fluor Inspector:

Cu

Nb

Print Name:

Standard

Signature:

Analyzed

Date:

Purchase Order Number:

PMI Performed by (Print Name):

Fabricators Pipe Spool Drawing (s):

Signature/Date:

Location Where PMI Performed

PMI Analyzer Manufacturer &


Model:

Item
No.

QTY

Line Item Description Type,


Size, Rating

Material
Type

Body

Bonnet

Stem

Material Verified PMI

Accept

Reject

Remarks

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project

SA5-DOW-01-37-03
August, 2014
Page 1 of 1
Revision 01

PIPE SPOOL POSITIVE MATERIAL IDENTIFICATION


RECORD POINT SHEET

Purchase Order No. GUST-50-LHC-K067


INDUSTRIA DEL HIERRO S.A. DE

C.V.

Inspection & Test Checklist


Tag No.:

Tag Description:
P. O. No.:

Inspection Classification

Turnover System:

Subcontractor:

Subcontractor

Client

Sub System:

IH

Other

Location:

Calibration/Standardization

Chemical Composition Percentage


Cr

Company:

PMI
Points
of
of
of
of
of
of
of
of
of
of
of
of
of

Line Number
and Class

Mo

Ni

MN

Ti

FE

Fluor Inspector:

Co

Cu

Nb

Print Name:

Standard

Signature:

Analyzed

Date:

MK #

Sheet
#

Rev.
#

PMI Results
Accepted

Rejected

PMI Technician
Print

Signature

Marathon Ashland Representative


Print

Signature

Date

The DOW Chemical Company

SA5-DOW-01-37-04
August, 2014
Page 1 of 1
Revision 01

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067

WEEKLY PMI LOG

INDUSTRIA DEL HIERRO S.A. DE C.V.

Calibration/Standardization Witnessed
Start of Work Period

Date

Number of Points
Witnessed # of #

of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of
of

Job #

Sketch #

PMI Technician

Remarks

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-37

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

PMI Procedure for the Field

1.0

Piping:

(a)

PMI Verification is dependent on the ability of Inspection to see the verification marking on each
component and to compare visual verification with the listing of each component on a point sheet

and spool drawing or field/shop isometric.

(b)

These point sheets must be signed by the PMI technician who performed the tests.

(c)

The verification marking should be a color that is not associated with other activities, (i.e.

material color code, dismantling, blinding, etc.).

(d)

The DOW Chemical Company has designated colors to be used as verification markings on the

Refinerys most widely used alloys. (See Attachment 2). These colors shall be listed in the PMI

plan as per this attachment. In cases where an alloy is to be used that are not listed in

Attachment 2, the alloy should be assigned a pre-determined color and included in the PMI plan

as such.

(e)

All PMI locations must have PMI verification color markings and the PMI Technician must apply
the markings at the time of actual PMI testing. Each component should be marked with a
dot of the appropriate color marking.

(f)

The markers used for PMIV are controlled by Quality Control Department. The QA/QC Manager

will issue them to the PMI technician at the point of fabrication or work site.

1.1

All fabricated spools shall be PMI checked before installation.

1.2

PMI shall be performed at the fabrication shop, job-site, or designated lay-down area by a
qualified PMI Technician.

1.3

Each check must be sequentially recorded, as each point is analyzed, not after the fact.
procedure for PMI should be as follows:

The

1.

Obtain or make the drawing.

2.

Make the point sheet.

3.

Compare the drawing to point sheet while performing PMI to verify all components are

listed. (If the PMI technician finds a point not listed on the point sheet, he should PMI

the point and list it on the bottom of the point sheet as a sub-listing of the previous
point. Example: a weld between points 5 and 6 would be numbered 5a).

4.

PMI the component and record results on the point sheet.

5.

Color-code the component.

6.

Repeat sequentially for the next component.

2.0

Drawings:

2.1

Shop spool drawings or field isometric drawings must indicate all components.

2.2

The spools drawings, isometrics and point sheets must be signed off as follows:
1.

PMI Company

2.

PMI Technician name in print and date

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-37

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 1

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

3.

PMI Technician signature

2.3

Completed spool drawings, isometrics and point sheets must be attached to Inspection isometrics
(if available).

2.4

Number of PMI points for Piping Welds:

2.5

Welds requiring PMI shall be inspected according to the following:

1.

Automated welding---one sample from each girth or long seam.

2.

Manual welding---one sample from each girth seam < 24 in. diameter.

3.

Manual welding---two samples from each girth seam equal to or > 24 in. diameter.

4.

Autogenous welded pipe and fittings---PMI verification of base metal only.

5.

Semi-automatic welding in the 1 G (rotated) position---one sample from each girth seam.

3.0

Ring Joint Gaskets:

3.1

Ring joint gaskets (alloy) must be PMI tested and marked prior to installation.

3.2

The PMI Technician should place a single diameter paint mark on each ring adjacent to the

alloy designation of the ring gasket.

3.3

All ring joint gaskets must be checked out of the designated holding facility by the piping job

supervisor or foreman.

3.4

PMI Verification will be dependent upon the placement of the ring gasket in the flange so that

the Inspector can see the paint marking and the alloy designator for the ring.

4.0

Valves:

4.1

All alloy valves will be PMI tested in two (2) locations (Valve body and Bonnet).

5.2

The PMI Technician will mark each location with the designated verification color.

6.0

Welding Wire (Bare):

6.1

Bare wire shall be purchased in unopened manufacturers containers.

6.2

Each container must have the AWS Classification, heat and lot number clearly marked.

6.3

Filler metal certification is required.

6.4

The greatest of 5% or 5 pieces of welding wire shall be PMI checked from each container.

6.5

Coated electrodes do not require PMI checks prior to use. Deposited filler metal (SMAW) must

be PMI checked in the as welded condition.

7.0

Non-Conformances:

7.1

If there is a component in a PMI system that does not meet the necessary chemistry, that
component must be flagged with a color of flagging tape that does not conflict with other colors
designated for NDE or PWHT. The PMI Technician must inform the Fluor Site Quality Manager

immediately of any non-conformances and these must be corrected by the fabricator/erector as a

matter of priority.

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-37

Gulfstream Light Hydrocarbon Unit 9 Project

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Attachment 2

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Pipe Fitting and Forgings Color Code System


Purpose:

To show control of all A.S.M.E section I and B31.3 material during storage and assembly.

Scope:

To identify all piping classes and fittings with an identifying color to facilitate fabrication and

erection.

Color Codes:

All piping classes and fittings to be used at the Gulfstream Light Hydrocarbon Unit 9

Project shall be color coded upon receipt as follows:

Piping
Class/Grade
SA-106 Gr. B
SA-53 Gr. B
SA-335-P11 (1 )
SA-335-P22 (2 )
SA-335-P91

Color
Red

Yellow

Green

Orange

White

Fittings
SA-105/234-WPB
SA-234-WPC
SA-182-F11/SA-234-WP11
SA-182-F22/SA-234-WP22
SA-182-F91/SA-234-WP91

Red

Yellow

Green

Orange

White

Stainless
304 / 304L
316 / 316L
321

Red

Black

Blue

Pipe Schedules

Sch
Sch
Sch
Sch

40
80
160
XXS

Pink

Brown

Gold

Silver

Studs

A193 - B16
- B7

Yellow (on end only)*


Red *
* supplier color code

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-37

Gulfstream Light Hydrocarbon Unit 9 Project

June, 2014

Purchase Order No. GUST-50-LHC-K067

Attachment 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

SAMPLE COLOR CODING

1) Piping and nipples:

HT-

2) Fittings:

HT-

HT-

Page 2 of 2

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-

Gulfstream Light Hydrocarbon Unit 9 Project

38

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 1 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

HARDNESS TESTING

SCOPE

This procedure describes the functions to be performed in the performance of hardness testing.

RESPONSIBILITIES

ACTIVITY

RESPONSIBILITY

DOCUMENTATION

Review Job

Specification for

Hardness Testing

Requirements

QA/QC Manager

Prior to start of work

Hardness Testing
Equipment

QA/QC Manager

Prior to start of work

Personnel Training &

Vision Test

QA/QC Manager

Preparation of Surface

to be Tested

Piping Superintendent

Perform Hardness

Testing & Report

Results

Quality Inspector

SA5-DOW-01-38-01

SA5-DOW-01-38-02

FREQUENCY OF

ACTIVITY

Yearly or each

application

Each test location

SA5-DOW-01-38-03

As required by code or

specification

PROCEDURE

Review Job Specification for Hardness Testing Requirements


-

Hardness Testing Equipment


-

Assure that the personnel performing the hardness testing have been trained in the use of the
equipment or have used the equipment within one (1) year and have a current vision test (Jaeger
1 at 12 inches minimum within one (1) year).

Preparation of the Surface to be Tested


-

Obtain the hardness testing equipment required or contract with a supplier of hardness testing
services.

Personnel Training & Vision Test


-

Obtain a copy of the Code/Job Specification requirements prior to the start of work.

Assure that the surface to be tested is buffed / filed to a relatively flat smooth texture to avoid
erroneous measurements which may result from a coarse surface. Care must also be taken to
assure that any grinding or other mechanical working does not generate sufficient heat to affect
the material hardness.

Perform Hardness Testing & Report Results

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-

Gulfstream Light Hydrocarbon Unit 9 Project

38

Purchase Order No. GUST-50-LHC-K067

August, 2014 Rev.01

Page 2 of 2

INDUSTRIA DEL HIERRO S.A. DE C.V.

Perform the hardness testing in accordance with the equipment manufacturer's written procedure

as required by the code or job specification. For hardness testing in the weld heat affected zone
(HAZ), the test instrument indenter shall not be greater than three (3) millimeters across the tip.

Report hardness testing results. For local hardness testing on welded joints, three tests shall be
conducted at each location required by code or job specification. Each reading shall be reported

and the average for the three shall be computed and reported on Form SA5-DOW-01-38-03.

FORMS

Quality Control Forms:


SA5-DOW-01-38-01 -

Verification of Training for Hardness Testing

SA5-DOW-01-38-02 -

Report of Vision Test

SA5-DOW-01-38-03 -

Hardness Testing Report

INDUSTRIA DEL HIERRO S.A. DE C.V. Confidential

Module Fabrication Quality Manual

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

This is to verify that

VERIFICATION OF
TRAINING FOR HARDNESS
TESTING

SA5-DOW-01-38-01

August, 2014

Page 1 of 1

Revision 01

has been trained in the use of the Hardness

Testing Equipment described below or has successfully used this equipment within the past year.

Description of Equipment:

Construction Manager/QAQC Manager

Date

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

SA5-DOW-01-38-02

August, 2014

Page 1 of 1

Revision 01

REPORT OF VISION TEST

Employee Name:

Social Security or Employee Number:

Type Chart Used:

Jaeger J1 @ 12" min.

Jaeger J2 @ 12" min.

Snellen Equivalent to J1 @ 12" min.

Snellen Equivalent to J2 @ 12" min.

Near Vision Results:

Left Eye

Right Eye

Passed

Failed

Corrected

Uncorrected

Remarks/Comments:

Printed Name, Signature And Title Of Test

Administrator

Date Of Test

(Month

(Day)

(Year)

The DOW Chemical Company

Gulfstream Light Hydrocarbon Unit 9 Project


Purchase Order No. GUST-50-LHC-K067
INDUSTRIA DEL HIERRO S.A. DE
C.V.

HARDNESS TEST REPORT

SA5-DOW-01-38-03

August, 2014

Page 1 of 1

Revision 01

Inspection & Test Checklist


Project

Project No.

Drawing No.

Applicable Code/Spec

Date

Test Equipment Type/Proc.

PWHT

Before After

Weld No.

Weld
Type

Material
Base Mat'l

Weld Metal

Size And

Thickness

Hardness Test Results

Readin

#1

#2

#3

BM

WM
HAZ
BM
WM
HAZ
BM
WM
HAZ
BM
WM
HAZ
BM
WM
HAZ
BM
WM
HAZ
Remarks

EQUIPMENT OPERATOR (PRINT)/DATE

QC INSPECTOR (SIGN)/DATE

Ave.

You might also like