Activity:

Inspection and Test Plan

Piping Fabrication and Installation

Industria del Hierro

Description:
Project Name:

Inspection and Testing of Piping


Gulfstream Light Hydrocarbon Project

Unit 9 LHC9

Client:
Contractor:
THE DOW CHEMICAL COMPANY
Industria del Hierro
LHC9

Item

Inspection/Test Stage

Project Location:

El Empalme - Municipio de Panuco,

Ver.

Contract Number:

GUST-50-LHC-K067

Requirement and

Acceptance Criteria

Document Number

ITP-DOW-PI-01

Revision 0

Responsibility

Project Number:

7422

Issue Date:

June - 2014

Scope of Inspection
Sub

IH

Client

Inspection
Record

Frequency

Numbers
Welding Inspection and

Testing

Assign numbers to field

and workshop piping

Reference Procedure SA5-DOW-01-35 for the

welds

welding inspection and testing requirements.

CS

QI

NDE

Weld Checking and

Inspections

Form SA5DOW-0135-01

02

03

04

05

06

07

in each

isometric
requiring

workshop

and field
welds

Weld

Checking

and

Inspection

s daily

Verify that pipe fabrication and installation


2

Pipe Fabrication and

activities are performed in accordance with

Installation

the requirements documented in the


applicable drawings and specifications.

Punching Lines

When Construction indicates the work is


complete, document deficiencies on Punch list

CS

QI

CS

QI

Form SA5DOW-0123-01/02

Form SA5DOW-0123-03

Each

installation

As soon
Work is
complete

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-20-01

Gulfstream Light Hydrocarbon Unit 9

June 2014

Purchase Order No. GUST-50-LHC-K067

Page 2 of 3

Activity:

Inspection and Test Plan

Piping Fabrication and Installation

Industria del Hierro

Description:
Project Name:

Inspection and Testing of Piping


Gulfstream Light Hydrocarbon Project

Unit 9 LHC9

Client:
Contractor:
THE DOW CHEMICAL COMPANY
Industria del Hierro
LHC9

Item

Inspection/Test Stage

Cleaning of Pipe

Project Location:

El Empalme - Municipio de Panuco,

Ver.

Contract Number:

GUST-50-LHC-K067

Requirement and

Acceptance Criteria

Document Number

ITP-DOW-PI-01

Revision 0

Responsibility

Project Number:

7422

Issue Date:

June - 2014

Scope of Inspection
Sub

IH

Client

Inspection
Record

Prior to

Reference Procedure SA5-MAR-01-25 for the

release

for

cleaning of pipe inspection and testing

requirements

Inspection Pre-

Verify that pressure testing and NDE are

Requisites

complete prior to release for cleaning

Inspection

Monitor chemical cleaning process verifying

that it is performed in accordance with

Frequency

cleaning

CS

QI

Form SA5DOW-0125-01

Daily
during

approved project specifications and documents

on the pipe cleaning and verification checklist

activity

Form SA5DOW-0124-01

Pressure Testing of

Verify that required pressure testing has been

Piping Systems

performed and documented

Insulation Inspection

Reference Procedure SA5-MAR-01-33 for the

insulation inspection requirements

Install Insulation

Insulation shall be installed in accordance with

In-process Inspection

No insulation shall begin on a vessel,

equipment, or piping until released by the

for Insulation Activities

appropriate field supervisor.

the applicable drawings and specifications

CS

QI

CS

QI

Each Test

Form SA5DOW-0124-02

Form SA5DOW-0133-02

Package

Each

piece of

line

The DOW Chemical Company

Module Fabrication Quality Manual, SA5-DOW-01-20-01

Gulfstream Light Hydrocarbon Unit 9

June 2014

Purchase Order No. GUST-50-LHC-K067

Page 3 of 3

Activity:

Inspection and Test Plan

Piping Fabrication and Installation

Industria del Hierro

Project Location:

El Empalme - Municipio de Panuco,

Ver.

Description:
Project Name:

Inspection and Testing of Piping


Gulfstream Light Hydrocarbon Project

Unit 9 LHC9

Client:
Contractor:
THE DOW CHEMICAL COMPANY
Industria del Hierro
LHC9

Item

Requirement and

Acceptance Criteria

Inspection/Test Stage

Coatings

Surface Preparation
Inspections

Coating Approval

Contract Number:

GUST-50-LHC-K067

Document Number

ITP-DOW-PI-01

Revision 0

Responsibility

Issue Date:

June - 2014

Scope of Inspection
Sub

IH

Client

Inspections

with the applicable specification

Verify that color/type of coatings has been

Form SA5DOW-0132-01

Coatings application shall not be performed

Form SA5DOW-0132-02

during unacceptable weather conditions that

violate the specification requirements for

CS

QI

Inspect the in-process coating's applications, to

verify that the work meets the requirements in

accordance with the specifications.

Thickness
Verification/Final
Inspection

Frequency

Reference Procedure SA5-DOW-01-32 for the

application.

Inspection
Record

coatings inspection requirements

Verify the surface preparation is in accordance

approved and documented

In-process
Coating/Lining

Project Number:

7422

Check dry film thickness of applied coatings in

sufficient locations to verify the required

thickness has been applied. Perform final

coating inspection after acceptable dry film


thickness is achieved.

Inspection Legend:

P = Perform

I = Inspection

T = Test

R = Review and Approve

W = Witness (Notification of authorized inspection personnel required)

H = Hold (Mandatory, do not proceed without presence of authorized inspection personnel or

signed waiver)

Responsibility Legend:

CS = Industria del Hierro Construction Supervision

CM = Industria del Hierro Construction Manager

QI = Industria del Hierro Quality Inspector

CWI = Industria del Hierro Certified Welding Inspector

RI = Industria del Hierro Receiving Inspector

NDE = Certified NDE Examiner

Form SA5DOW-0132-03

Form SA5DOW-0132-04

Daily
during

life of
activity