Project:

EPIC OF BLOCK 4 SUBMARINE


PIPELINES & ASSOCIATED RISER
Contract Number

File No:

CFT/DG/45/10/545B

PPLN-PL-DAT-1-545B-27-00

DATA SHEET FOR BARRED TEE


( DOC No. PPLN-PL-DAT-1-545B-27-00 )

01
02/01/2012
Re-issued For Construction
AS
PKL
PKL

00
09/12/2011
Issued For Construction
AS
YH
PKL

A2
16/11/2011
Issued For Approval
AS
SP
PKL

A1
28/09/2011
Issued For Review
AS
SP
PKL

EPIC OF BLOCK 4 SUBMARINE


PIPELINES & ASSOCIATED RISER

Page 2 of 9

DATA SHEET FOR BARRED TEE


PPLN-PL-DAT-1-545B-27-00

Rev.
Date
Issue Purpose
Prepared By JPK
Checked By JPK
Approved By JPK
Approved By ME
Approved
Total pages: 9
Category
Code
Client Rep.

Dragon Oil
Client:

Contract Code
545B
Description
Document Type
DAT
Offshore Installation

General

Area Code
Discipline Code
Classification Code
Country Code
Cluster Number
Serial Number
Sheet Number

PPLN
PL
DAT
1
545B
27
00

Rev. 01
Date: 02/01/2012

Table of Contents
1. INTRODUCTION........................................................................................................................................5
1.1
1.2
1.3
1.4
1.5
1.6

PROJECT DESCRIPTION.............................................................................................................................5
DEFINITIONS.............................................................................................................................................5
ABBREVIATIONS.......................................................................................................................................6
SCOPE OF DOCUMENT..............................................................................................................................6
UNIT.........................................................................................................................................................6
HOLD REGISTER.......................................................................................................................................6

2. DATA SHEET...............................................................................................................................................7
3. REFERENCES.............................................................................................................................................9

SAFETY HEALTH AND ENVIRONMENTAL ISSUES

No.

DESCRIPTION OF ISSUE

POTENTIAL MITIGATION
MEASURE

Document Review Comments Sheet


Project

: EPIC of Block 4 Submarine Pipelines & Associated Riser

JPK / Client Job No:

: 140254.01/ CFT/DG/45/10/545B

Document Title

: Data Sheet for Barred Tee

Document Number:

: PPLN-PL-DAT-1-545B-27-00

Issue / Revision:

: 00

Section

Section 2
Data Sheet

Comments
(Reviewer)

Date:

02/01/2012

Action Undertaken
(Originator)

Reference Company comments from MOM-545B-DTS-049


PPLN-PL-DAT-1-0545B-27-00 Data Noted and incorporated.
Sheet for Barred Tee with reference to
Doc. No. PPLN-PL-RPT-1-545B-21
"Wall Thickness Design", please update
the wall thickness value in table on sheet
7, row: "Mating pipeline, NPS 10".

Closed
Out
(Y / N)

Section

Comments
(Reviewer)

Action Undertaken
(Originator)

Closed
Out
(Y / N)

1.

INTRODUCTION
1.1 Project Description
Dragon Oil (Turkmenistan) Ltd, (DOTL) here-in after, called as Company is engaged in exploration &
production in Lam and Zhdanov Fields located about 35 km off Turkmenistan in the Caspian Offshore.
The company is having Production Sharing Agreement with the Turkmenistan Government for 25 years.
The LAM and Zhdanov fields produce oil and condensate together with associated gas from a series of
stacked reservoir sandstones.
With alignments of company growth and future plan and based on the production forecast, Block 4
manifold platform and subsea pipelines are required to be installed to receive production from
surrounding platforms.
For this purpose, DOTL had invited proposals from prospective bidders for EPIC of Block 4 Riser
Platform and Submarine Pipelines. Further, this EPIC Contract divided into two packages for Riser
Platform and Submarine pipelines. Momentum Engineering (Dubai) has been awarded the EPIC Contract
for Subsea Pipelines and Associated Riser. Momentum Engineering has appointed JP Kenny Ltd (Abu
Dhabi) as Sub-contractor to perform Detailed Engineering associated with subsea pipelines, associated
risers and topside hook-up to existing or new facilities designed by others. This project consists of the
following pipelines:

Sr. no.

Item detail

10 multiphase Subsea pipeline from Zhdanov A to Block 4

12 multiphase Subsea pipeline from Block 4 to Tee point on 30 Trunkline

6 multiphase Subsea pipeline from Zhdanov 25 to Tee point on 30 Trunkline

14 multiphase Subsea pipeline from Lam C to Lam 28

14 multiphase Subsea pipeline from Lam C to Lam B

1.2 Definitions

COMPANY

DRAGON OIL TURKMENISTAN LTD

CONTRACTOR

MOMENTUM ENGINEERING

SUB-CONTRACTOR

The party, which provides services to perform the duties specified by


CONTRACTOR/COMPANY (J P KENNY for Detailed Engineering).

SUPPLIER/VENDOR

The party, which manufactures and/or supplies equipment, technical


documents/drawings and services to perform the duties specified by
CONTRACTOR/COMPANY.

SHALL

Indicates a mandatory requirement.

SHOULD

Indicates a strong recommendation to comply with the requirements of this

document
PROJECT

EPIC Of Block 4 Submarine Pipelines and Associated Riser

WORK

All activities associated with EPIC PROJECT

1.3 Abbreviations
API
ASME
ASTM
ID
MSS
MTO
OD
SI
SMYS
WPHY
WT

American Petroleum Institute


American Society of Mechanical Engineers
American Standard for Testing and Material
Internal Diameter
Manufacturers Standardization Society
Material Take-Off
Outside Diameter
Systme International
Specified Minimum Yield Strength
Welded/Wrought Pipe High Yield
Wall Thickness

1.4 Scope of Document


This document summarizes the technical requirements for Barred Tees for use in the Block 4 Submarine
Pipelines and Associated Riser project.
1.5 Unit
The International System of Units (SI) shall be adopted throughout the project unless otherwise specified.
1.6 Hold Register
The HOLD items are summarised in the below Table.

Section

Description

Action

2.

DATA SHEET

GENERAL INFORMATION
Location

Topside

Design life

25 years

Rating class

600

Nominal diameter/bore

As per the mating pipeline

Design code/standard

MSS SP-75, ASME B16.9

Pipeline design code

ASME B31.8

Reference linepipe code

API 5L

Design temperature

85C

Design pressure

50 barg

Corrosion allowance

3 mm

End connection

Butt-welding on all ends per ASME B16.25

End finish

Bevel prep per API 5L

Process fluid

Multi-phase oil/water/gas

Weld ends to suit

Depends on linepipe size of NPS 10 or 14 pipeline


with appropriate WT per document no. PPLN-PLDAT-1-545B-23-00

Mating pipeline

NPS 10

273.1 mm OD, 247.7 mm ID, 12.7 mm WT, API


5L X-52, 360 MPa SMYS

NPS 14

355.6 mm OD, 330.2 mm ID, 12.7 mm WT, API


5L X-60, 415 MPa SMYS

Internal diameter of runpipe


Number of Bars
Location reference per P&ID

Line no. reference

Barred Tee tag no.

within 0 mm to 1.5 mm (0 to 0.059 inches) of the


nominal dimension of the connecting pipe
NPS 10

NPS 14

NPS 10

Z00A-PR-PID-1-545B-01-01, B004-PR-PID-1545B-03-01

NPS 14

L00C-PR-PID-1-545B-01-01, L00C-PR-PID-1545B-02-01, L028-PR-PID-1-545B-01-01, L00BPR-PID-1-545B-01-01

NPS 10

10-PR-D013-002-H

NPS 14

14-PR-D013-012-H, 14-PR-D013-001-H, 14PR-D013-002-H

NPS 10

Z00A-BT001, B004-BT001

NPS 14

L00C-BT001, L00C-BT002, L028-BT001, L00B-

BT001
Quantity

Refer to MTO
MATERIAL

Body
Pup Extension

NPS 10 mating pipeline

MSS SP-75 WPHY 52

NPS 14 mating pipeline

MSS SP-75 WPHY 60

NPS 10 mating pipeline

MSS SP-75 WPHY 52

NPS 14 mating pipeline

MSS SP-75 WPHY 60

Bars

ASTM A283 or equivalent


INSPECTION & TESTING REQUIREMENTS

Impact testing

API 5L

Tensile tests

API 5L

Macro/hardness tests

ASTM E92

NDT

As per Section 10.0 of specification document no.


B004-PP-SPE-1-XXXX-01-00

Hydrostatic test

95% SMYS hoop stress based on min. WT of


mating pipe

Certification of material test reports

As per ISO 10204 : Type 3.1

MISCELLANEOUS REQUIREMENTS
External surface protection

As per project specification document no. B004PP-SPE-1-XXXX-05-00

IDENTIFICATION, COLOURS AND MARKING


Marking and identification specification

As per MSS SP-25

Notes:
1. This data sheet shall be used in conjunction with specification document no. B004-PP-SPE-1XXXX-01-00.

2. Weld beveling to suit pipeline wall thickness.

3. REFERENCES
1. Doc. No. PPLN-PL-DBS-1-545B-01-00, Basis of Design for Block 4 Pipelines.
2. Doc. No. PPLN-PL-DAT-1-545B-23-00, Data Sheet for Anti-Corrosion Coated Line Pipe.
3. Specification No. B004-PP-SPE-1-XXXX-01-00, Specification for Barred Tee.
4. Specification No. B004-PP-SPE-1-XXXX-05-00, Specification for Painting and Coating.
5. API Specification 5L, Specification for Line Pipe 43rd Edition, October 2004.

Document Checklist
Project

: EPIC of Block 4 Submarine Pipelines & Associated Riser

JPK / Client Job No:

: 140254.01/ CFT/DG/45/10/545B

Document Title

: Data Sheet for Barred Tee

Document Number:

: PPLN-PL-DAT-1-545B-27-00

Issue / Revision:

: 01

Date:

02/01/2012

Checklist
(Write N/A if not applicable)
Numerical Accuracy
Title Sheets
Contents Format
Introduction/Document Scope
Summary, Conclusions, Recommendations
Assumptions
Legibility
Diagrams Clear
Units
Tables Clear And Complete
Sheet Headings (Inc. Signatures)
Referenced Documents Checked
Drawings Referenced
Drawing Consistent With Document
Sheet Numbering
Design Premise Compliance
Client Specification Compliance
Attachments/Appendices
Scope Of Work/Ctr Compliance
Contractual Requirements
Originator Qualified And Experienced
Checker Qualified And Experienced
Consideration Of Construction
Consideration Of Operations/ Inspection/Maintenance
Consideration Of Health Safety And Environmental Issues
Design Review Function (Small Projects, If Required)
Check Copy Correct

Originator
Self Check
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )
( )

Checker

( )
( )
( )

( )
( )
( )

(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(
(

)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

Signed:
Originator

Checker

Proj. Eng. / Approver

QA Checker

Approver

QA

( )
( )
( )

( )

( )
( )
(
(
(
(
(
(
(
(
(

)
)
)
)
)
)
)
)
)

( )