FGD Shutdown -Major Activity from 08.03.2016 to 20.03.

2016 (12 days)


S No
1
2
3
4
5
6
7
8
9

Major Activity
RCC tank draining
Scaffolding in RCC tank
Cone cleaning (Hard coating removal)
Epoxy coating and sand blasting
Scaffolding removal
Bottom cleaning
oxidization header assembly
tank filling
FGD in line

Days

Responsibility
2 Process
1 Mech
2 Process
2.5 Mech
1.5 Mech
0.5 Process
1.5 Mech
1 Process
12 Days

Date
08.03.16

20.03.16