Professional Documents
Culture Documents
Equipment Capabilites
Equipment Capabilites
Type of equipment
1. Bulldozer (D8)
Average Capabilities
a.) Clearing
b.) Stripping
c.) Excavation
1.) Common Soil
2.) Slightly hard Materials
d.) Quarrying
107 Common Materials
108 Aggregates
Boulders
200 Needs Screening
e.) Pushing
2. Road Grader
3. Payloader
Loading
4. Crane Shovel
5. Sheep Foot Roller
11. Buggy
500 sq.m./hr.
200 sq.m./hr
45 cu.m/hr.
25 cu.m./hr.
50 cu.m./hr.
40 cu.m./hr.
15 cu.m./hr.
3 cu.m./hr.
300 cu.m./hr.
50 cu.m./hr.
30 cu.m./hr.
Loading
35 cu.m./hr.
a.) Static Rolling
15 cu.m./hr.
(12 passes 15 cm. lift)
b.) Vibratory Rolling
135 cu.m./hr.
(6 passes 20 cm. lift)
a.) Static Rolling
24 cu.m./hr.
(6 passes 20 cm. lift)
a.) Vibratory Rolling
24 cu.m./hr.
(6 passes 20 cm. lift)
a.) Static Rolling
24 cu.m./hr.
(6 passes 20 cm. lift)
b.) Vibratory Rolling
72 cu.m./hr.
(6 passes 60 cm. lift)
a.) Hauling Common Borrow 3.5 cu.m./hr.
Base Course
b.) Hauling Selected Borrow 5.0 cu.m./hr.
c.) Hauling Concrete Batch
2 Batch/trip
Class A
a.) Hauling Common Borrow 2.5 cu.m./trip
Base Course
b.) Hauling Selected Borrow 4.0 cu.m./trip
Base Concrete Batch
1.0 Batch/trip
Class A
a.) Hauling Concrete Mix
0.17 cu.m./trip
Water Truck
Concrete Mixer
Rock Crusher
Concrete Vibrator
Concrete Floor Finisher
Percussion Drilling
Above that height, it is preferable to have a separate group of leaders whose output
must be matched with that of the excavators.
Soil Type
a.) Loose
b.) Loose
c.) Loose
III.
For Item 106 Excavation for Structures
Activity
Productivity
1.) Excavation
Depending on the type of soil
There use similar productivity
Data as those used for Excavation
In Item 105
IV.
For Item 110 Foundation Fill
Activity
1.) Backfilling and Tamping
Productivity
3 cu.m./man-day
GREASE
OIL#10
2 lbs.
1 liter
1 lb.
1 liter
1 lb.
1 liter
1 lb.
1 liter
2 lbs./wk. 1 liter
1 lb.
1 liter
0.5 lb.
78
10 -13
In these cases, the work split over two or more days. First the trench should be
excavated and then the preparation of the bed, the laying, backfilling and compaction is
done. Therefore the volume of the excavation to be limited following rates and then
applicable:
Soil Type
Productivity
a.) Hard Soil
3.50 cu.m./man-day
b.) Very hard, stony
2.00 cu.m./man-day
After completion of the trench approximately 4 man days are needed to lay 6
rings, backfill and compact to finish road level.
I. MECHANIZED ASPECT
A. CLEARING AND GRUBBING
Dozer
Production
Horse Power
Dense of Vegetation (No. of Trees/Hectare)
0 50 51 100 101 200 201 250 250 above
120
360
250
190
160
130
140
420
290
220
185
150
160
480
330
255
210
170
180
540
375
285
240
195
200
600
420
310
265
215
MANUAL ASPECT
A. Excavation:
A.1 Common Materials
Capacity (cu.m./day)Bank Volume & Depth of Excavation
Type of Work
(meter)
Farm Ditchs
3.00
2.50
2.00
Canal
2.50
2.00
1.75
Structure
2.00
1.75
1.50
A.2 Slight Hard Materials (Ind.)
Type of Work
Capacity (cu.m./man-day) Bank Volume
Canal
1.00
Structure
0.75
B. LOADING CAPABILITIES OF FIVE (5) LABORERS
Sand & Common Cobbles Boulders Cement R.S. Bars Lumber Plywood
Gravel
Cu.m./hr cu.m./hr. cu.m./hr. cu.m./hr. bags/hr kgs/hr. bd.ft./hr. pcs./hr.
4
5
3.5
3
3
6,000
4,000
2.5
C. UNLOADING CAPABILITIES OF FIVE (5) LABORERS
Sand & Common Cobbles Boulders Cement R.S. Bars Lumber Plywood
Gravel
Cu.m./hr cu.m./hr. cu.m./hr. cu.m./hr. bags/hr kgs/hr. bd.ft./hr. pcs./hr.
6
6
5
4
300
7,000
4,000
2.5
D. CUT, BEND & PLACE RSB
Structure
1 Steelman & 1 Helper with bar cutter
Canal & others
80 kgs./day
E. QUARRYING
Capability
Sand & Gravel
3.50
cu.m./man-day
Cobbles
Boulders
2.50
2.00
F. DEMOLITION OF CONCRETE
Slab and Wall
Massive Concrete
0.50 cu.m./man-day
0.20 cu.m./man-day
G. SCREENING OF AGGREGATES
Gravel
Sand
4.00 cu.m./man-day
6.00 cu.m./man-day
H. MANUAL BACKFILL
Capacity : 3.00 cu.m./man-day
I. LAYING OF MATERIALS (cu.m./man-day)
Cobbles 2.00
Boulders 1.50
J. SPREADING OF AGGREGATE
Capacity - 2.50 cu.m./man-day
K. RUBBLE MASONRY (Concreting)
Crew: 1 Foreman, 2 Mason, 10 Laborers, 1 Light Equip. Oper.
Capacity: 6.00 cu.m./day
L. GROUTED RIPRAP
Crew: 1 Foreman, 2 Mason, 10 Laborers, 1 Light Equip. Oper.
Capacity: 7.50 cu.m./day
M. CONCRETE HALLOW BLOCK: Setting Capacity sq.m./day
Crew: 1 Mason, 2 - Laborers
Fence
Building
4 CHB
14
10
6 CHB
10
8
N. CONCRETE LINING
Crew: 1 Foreman, 2 Mason, 1 Light Equipt. Oper.
10 Laborers with one bagger mixer
Capacity: 4.50 cu.m./day
O. INSTALLATION OF STEEL GATES
Crew: 1 Mason & 5 Laborers
16 X 16 to 24 X 24
Above 24 X 24
2 assy/day
1 assy/day
P. CONCRETE WORKS
P.1 Fabrication, Placing & Dismantling of Forms
Crew: 2 Carpenters, 4 Laborers, Capacity: 3.50 cu.m./day for 3000psi
Crew: 1 Carpenter, 1 Laborer, Capacity: 4.50 cu.m./day canal lining
P.2 Concreting and Curing Capability
P.2.a. With concrete mixer
Crew: 1 Foreman, 2 mason, 1 L.E. Operator, 8 Laborers
Class A : 3.50 cu.m./day
Class B : 3.70 cu.m./day
Class C : 3.50 cu.m./day
Lean Concrete : 4.50 cu.m./day
Capability
Fabrication
15
11
9
6
5
3
4
Installation
16
11
12
10
8
6
7
Sand
Gravel Boulder
cu.m./cu.m.
0.45
0.50
0.90
1.00
0.48
0.96
0.225 0.45
0.35
0.05
0.10
0.50 1.00
-
1.00
-
F. Lumber 1/2Plywd.
bd.ft./cu.m. pcs./cu.m.
40
1.00
25
1.25
25
1.25
5
0.10
5
15
0.40
5
0.10
0.75
1.00
1.00
Tie Wire Nails
kgs/cu.m kgs/cu.m
1.25%RSB 2.50
1.20%RSB 2.00
1.10%RSB 2.00
0.50
0.25
1.00%RSB 1.50
1.00%RSB 0.50
211
0.25
Sand
Cu.m./sq.m.
0.046
0.089
Description
Rate per Day (PhP)
Komatsu, D80A-12DD 180Hp
9,160.00
75 TCM,Clark, 1.53 cu.m.
10,010.00
Capacity, 151 Hp
Mitsubishi MG 500 170 Hp
8,808.00
Japan & other Make,
9,016.00
10 cu.m. Capacity
Ingersoll Rand SP48 MI Tons
8,701.00
All models, Truck mounted,
11,296.00
Standard mechanically operated
31 35 Tons
Komatsu PC 120, Capacity 90 Hp
9,656.00
Japan Make 3.8 cu.m., 46 cu.m
8,528.00
Capacity 175 Hp
Gas/Diesel Engine, CFM 20 Hp
1,376.00
12 Hp Engine Driven
1,648.00
Worthington 34 (Basic Equipment Only)
3,320.00
Little Ford Sprasmaster
5,784.00
Description
Rate per Day (PhP)
Domag D8 22
5,067.00
Two Tons w/ Pile Hammer
100.00
Stanley, hydraulic w/o power unit
294.00
Gas/Diesel Driven 250 Amps., 185 Hp
300.00
1 Bagger
298.00
Gas/Diesel Driven
341.00
Husquama, 2100 CD w/o Blade
180.00
All makes, 500 - 1000 gals.
1,773.00
All models 3.5 4 size
119.00
With Cement Silo Manual
5,113.00
/mo. X rated cap. In
Cu.m./hour
Walling/Sliding:
Covering
30 sq.m./man-days
Framing, Studs
12 cu.m./man-days
(Multiply by the no. of days Double Walling)
Ceiling Joist and Hangers
16 sq.m./man-days
Ceiling Boards (4X8 Plywood)
30 sq.m./man-days
Window sashes:
Jamb Fabrication
4 sq.m./man-days
Frames Fabrication
2 sq.m./man-days
Jambs Installation
14 sq.m./man-days
Frames Installation
10 sq.m./man-days
Doors:
Jambs Fabrication/Installation
2.5 sq.m./man-days
Door Fabrication/Installation
1 panel/man-days
Paintings:
Paint Rollers
125 sq.m./man-days
Paint Brush
50 sq.m./man-days
Neutralizer
100 sq.m./man-days
Truss Fabrication:
0.25 truss/man-days
Purlins Installation
125 sq.m./man-days
Fascia Board
0.05 cu.m./man-day
Roof Coverings (GI Sheets)
35 pcs./man-days
Concrete Works:
Concrete Pouring
0.30 pcs./man-days
Rebars
20 30 kgs./man-days
Finishing
Rough Finish
10 sq.m./man-days
Plain/Fine Finish
8 sq.m./man-days
CHB Filling/Laying
A. Cement Mortar
Table 1. Quantity of Cement and Sand for CHB Mortar per square meter wall
Size of CHB
No. per sq.m.
40 Kg. Mixture Cement Bags
A
B
C
Sand
4X8X16
12.5
0.525
0.394
0.328
0.0438
6X8X16
12.5
1.013
0.759
0.633
0.0844
8X8X16
12.5
1.500
1.125
0.938
0.1250
B. Mortar for Plastering
Table 2. Quantity of Cement and Sand for Plastering per square meter
40 kg. Cement Bag
Mixture Class
16 mm thick 20 mm thick 25 mm thick
A
0.288
0.360
0.450
B
0.192
0.240
0.300
C
0.144
0.180
0.225
D
0.120
0.150
0.188
Sand
0.016
0.020
0.025
Aggregate
Sand
Gravel
cu.m.
cu.m.
0.015
0.030
0.018
0.035
0.020
0.040
0.020
0.050
0.030
0.060
0.034
0.068
0.038
0.075
0.045
0.090
0.040
0.080
0.050
0.100
0.060
0.120