Professional Documents
Culture Documents
EQUIPMENT CAPABILITIES
10. 2 ½ T-Dump Truck (a) Hauling Common Borrow Base Course 2.5
cu.m./trip
(b) Hauling Selected Borrow Base Course 4.0
cu.m./hr.
© Hauling Concrete Batch Class ‘A’ 1
Batch/trip
11. Buggy (a) Hauling Concrete Mix 0.17
cu.m./trip
12.Wheel Borrow (a) Hauling Aggregates 0.17
cu.m./trip
(b) Hauling Concrete Mix 0.05
cu.m./trip
13. Water Truck (a) Watering
1000sq.m./trip
14. Concrete Mixer (a) Mixing Concrete 9 cu.m./hr.
15.Rock Crusher (a) Crushing mixed sand & gravel 30
cu.m./hr.
16. Concrete Vibrator (a) Vibrating Concrete Mix 40
cu.m./hr.
17. Concrete Floor Finisher (a) Finishing Concrete Floor 140
cu.m./hr.
18.Percussioned Drilling (a) Drilling Hard Rock 0.23 m./hr.
(b) Drilling Loose Rock 0.30 m./hr.
© Drilling Limestone 0.38 m./hr.
Activity Productivity
1) Excavation Cu.m./man-day (throwing dist. in
m.)
Soil Type 0-4m. 4-6m. 6-
8m.
a) Loose,rot sticky soil 5.0-6.0 4.5-5.5 3.5-
4.5
b) Firm soil 3.5-4.5 3.4-4.0 2.5-
3.5
c) Very hard soil, hard soil mixed 2.0-3.0 1.8-2.5 1.7-
2.5
with stones
2) Loading Cu.m./man-day
Type of soil
a) Loose 4.50-5.50
b) Firm 2.50-4.00
c) Hard 1.50-2.50
If the length of the culvert exceeds 6 meters, the number of man-days has to be
increased accordingly.
Culvert laying- this task consist of the excavation of the trench preparing the bed,
laying of culvert, backfilling & compaction. Number of man-days required varies
with the volume of the excavation and the soil type.
In these cases, the work split over two or more days. First the trench should be
excavated and then the preparation of the bed, the laying, backfilling and compaction
is done. Only 3 times. Therefore the volume of the excavationhas to be limited
following rates and then applicable:
I. MECHANIZED ASPECT
A. CLEARING AND GRUBBING
Dozer Production
Horse Dense of Vegetation ( No. of Trees/Hectares )
Power 0-50 51-100 101-200 201-250
251&>
120 360 250 190 160 130
140 420 290 220 185 150
160 480 330 255 210 170
180 540 375 285 240 195
200 600 420 310 265 215
B. EXCAVATION ( Common Materials )
B.1 CRANE
Tonnage’s Capacity ( cu.m./hr.) Bank Volume
Canal Structure Creek
15 15 10 10
20 20 15 15
25 25 20 20
30 30 25 25
B.2 DOZER
Horse Production ( cu.m./hr.) Bank Volume
Power Canal Structure
120 30 15
140 35 20
160 40 25
180 45 30
200 50 35
B.3 BACKHOE
Bucket ( cu.m.) Production ( cu.m./hr.) Bank Volume
Canal Structure Creek
0.50 20 15 15
0.75 30 20 20
1.00 40 30 30
1.25 50 40 40
1.50 60 45 45
C. QUARRYING
Dozer ( H.P.) Production (cu.m./hr.) Bank Volume
Common Aggregate Cobbles/Boulders
140 55 60 27
160 60 65 29
180 65 70 31
200 70 75 33
ATTACHMENT No. 2
D. LOADING
Bucket ( cu.m.) Production ( cu.m./hr.) Bank Volume
Common Aggregate Cobbles/ Boulders
1.0 50 55 35
1.5 75 80 55
2.0 100 110 75
2.5 125 135 90
3.0 150 165 110
E. SPREADING
Grader ( H.P.) Road ( cu.m./hr.) cmp.
Common Aggregate
80-100 60 70
100-125 70 80
125-150 90 100
150-175 100 110
H. EMBANKMENT COMPACTION
Capacity ( cu.m./hr.) Compacted Volume
Tons Self-Propelled
Tamp. Foot drum Vib. drum
10 80 60
12 90 70
15 120 90
K. DEMOLITION OF CONCRETE
160 CFN Compressor & two (2) Jack Hammer
Capacity- 8.00 cu.m./day for massive concrete
-12.00 cu.m./day for slab & wall
L. DRIVING OF PILES
Steel Pipes: Crane 25 tons with 2-tons drop hammer, Capacity = 8 L.M./Hr.
Concrete Piles : Crane 25 tons with 2500 kgs. Pile hammer, Capacity = 2.00
L.M. per Hr., 4.00 LM/Hr. for thick & thin concrete piles.
N. MANUAL ASPECT
A. Excavation
A.1. Common Materials
Capacity ( cu.m./day) Bank Volume & Depth of Excavation
Type of Work ( meter )
Farmditchs 3.00 2.50 2.00
Canal 2.50 2.00 1.75
Structure 2.00 1.75 1.50
E. QUARRYING
Capability cu.m./day/man
ATTACHMENT No. 2
F. DEMOLITION OF CONCRETE
Slab & Wall 0.50 cu.m./man-day
Massive Concrete 0.20 cu.m./man-day
G. SCREENING OF AGGREGATES
Gravel 4.00 cu.m./day/man
Sand 6.00 cu.m./day/man
H. MANUAL BACKFILL
Capacity : 3.00 cu.m./man
J. SPREADING OF AGGREGATE
Capacity : 2.50 cu.m./day/man
L. GROUTED RIPRAP
Crew : 1- Foreman, 2- Mason, 10- Laborers, & 1- L.E. Operator
Capacity : 7.50 cu.m./day
N. CONCRETE LINING
Crew : 1- Foreman, 2- Mason, 1- L.E. Operator, 10- Laborers with one (1)
bagger mixer
Capacity : 4.50 cu.m./day
P. CONCRETE WORKS
P.1. Fabrication, Placing & Dismantling of Forms
Crew : 2- Carpenters & 4- Laborers; Capacity : 3.50 cu.m./day for 3000 psi
Crew : 1- Carpenter & 1- Laborer; Capacity : 4.50 cu.m./day Canal lining
ATTACHMENT No. 2
OTHER MATERIALS
Class Type of Strength F. Lumber ½ pl. wd. Tie wr. Nail
Structure kgs. bd.ft/cu.m. pcs/cu.m. kgs.cu.m kgs/cu.m
A Bridge/Flume 211 40 1.00 1.25%RSB 2.50
A Siphon/Box Cul. 211 25 1.25 1.205 RSB 2.00
A Other Str. @ inc 211 25 1.25 1.10% RSB 2.00
A 211 5 0.10 - 0.50
B 200 5 - - 0.25
A 211 15 0.40 1.00%RSB 1.50
B 200 5 0.10 1.005RSB 0.50
A 211 5 - - 0.25
Note: The total contract price should be equal to or less than the total COA estimate
plus 10% in order to sustain a finding of reasonableness otherwise the contract price
will be deemed excessive.
Lumpsum
Installations:
Timber:
Walling/Sliding :
Covering 30 sq.m./man-days
Framing, Studs 12 cu.m./man-days
( Multiply by the no. of days Double walling)
Ceiling Joist and Hangers 16 sq.m./man-days
Ceiling Boards ( 4’ x 8 ‘ Ply Wood) 30 sq.m./man-days
Windows sashes :
Jambs Fabrication 4 sq.m./man-days
Frames Fabrication 2 sq.m./man-days
Jambs Installation 14 sq.m./man-days
Frames Installation 10 sq.m./man-days
Doors :
Jambs Fabrication/Installation 2.5 sq.m./man-days
Door Fabrication/Installation 1 panel/man-days
Paintings :
Paint Rollers 125 sq.m./man-days
Paint Brush 50 sq.m./man-days
Neutralizer 100 sq.m./man-days
Truss Fabrication 0.25 truss/man-days
Purlins Installaation 60 L.M./man-days
Fascia Boards 0.05 cu.m./man-days
Roof Coverings ( G.I. sheets ) 35 pcs./man-days
Concrete Works :
Concrete Pouring 0.30 pcs./man-days
Rebars 20-30 kgs/man-days
Finishing:
Rough Finish 10 sq.m./man-days
Plain/Fine Finish 8 sq.m./man-days
CHB Filling/Laying 6-8 sq.m./man-days
ATTACHMENT No. 2
A. CEMENT MORTAR
Table -1 Quantity of Cement and Sand for CHB Mortar per Square Meter
Wall
Size of CHB No.per sq.m. 40 Kg. Mixture Cement Bags
A B C D Sand
4 x 8 x 16 12.5 0.525 0.394 0.328 0.0438
6 x 8 x 16 12.5 1.013 0.759 0.633 0.0844
8 x 8 x 16 12.5 1.500 1.125 0.938 0.1250
Table-2 Quantity of Cement and Sand for Plastering per Square Meter
40 kg. Cement Bags
Mixture Class 16 mm thk. 20 mm. thk. 25 mm. thk.
A 0.288 0.360 0.450
B 0.192 0.240 0.300
C 0.144 0.180 0.225
D 0.120 0.150 0.188
Sand 0.016 0.020 0.025
Table-3 Quantity of Cement, Sand, and Gravel for CHB Footing per Meter
Length