Professional Documents
Culture Documents
Contingency Allocation For Large Infrastructure Projects Large Infrastructure Projects Using at Risk
Contingency Allocation For Large Infrastructure Projects Large Infrastructure Projects Using at Risk
Presented By
Francisco Cruz, PMP, PMI-RMP
Mitul Parikh, PE, PMP
PMA Consultants
Agenda
Overview of PMA
The Case for Risk Analysis
Risk Analysis Approach for Large Infrastructure Projects
Final Remarks
Slide 2
PMA - Clients
Slide 3
Over 250 cost & schedule risk assessments conducted across five continents for on &
offshore drilling and production facilities, refining and chemical plants, pharmaceutical
and solar manufacturing facilities, power and co-gen plants, and infrastructure projects
Slide 4
(i.e., tunnels, airports, bridges, and ports)
60%
55%
Industrial Relations
Others
57%
36%
34%
21%
17%
15%
Achieving Productivities
6%
Lack of Approvals
D i
Design
C
Creep
Time Delay
19%
Achieving Productivities
57%
Weather
32%
Design Creep
Contractual Disputes
36%
Time Delay
Lack of Approvals
40%
Contractual Disputes
Weather
4%
g Process
Commissioning
2%
13%
2%
Others
26%
19%
Overrun is constant for the 70-year period covered by the study; cost estimates have
not improved over time.
Slide 5
End Usage
Expected
Accuracy
Range
Project
Definition
V
0% to 2%
Concept Screening
-50% a +100%
IV
1% tto 15%
St d or Feasibility
Study
F
ibilit
-30%
30% a +50%
50%
III
10% to 40%
-20% a +30%
II
30% to 70%
Control or Bid/Tender
-15% a +20%
-10% a +15%
200
50
80
90
130
115
100 Ud (Actual)
Slide 6
Alarming Data
Inaccuracy is constant for the 30-year period covered by the study; forecasts have not improved over time
Slide 7
Source: CATO Institute, Tax & Budget Bulletin, No. 17, 2003; FHWA - Predicted and Annual Impacts of New
Starts Project 2007; Flyvbjerg,
Flyvbjerg B.
B - Survival of the Unfittest
Unfittest, 2009
Characteristics.
Explanations.
1. Overestimate Benefits
1. Technical
2. Underestimate Cost
3. Political-Economic
Source: FHWA - Predicted and Annual Impacts of New Starts Project 2007
Slide 9
Organizational Vision
Scope
Integrated
Project
Deliveryy
Cost
Risk Analysis
is not a
Discrete Event
Schedule
Risk
Slide 10
Preliminary &
Detailed Planning
Execution
Closure
Amount
att Stake
St k
Amount at Stake
Typical Risk Events per Phase
Unavailable
Subject
j
Matter Experts
Poor Definition of
Problem
Unclear
Obj ti
Objectives
Buy-in
(by Competitive
Bidding)
No Risk
Management
g
Plan
Hasty Planning
Poor Specifications
Unclear Scope of
Work
No Management
Support
Poor Role Definition
Inexperienced Team
Unskilled Labor
Material Availability
A ailabilit
Strikes, Weather
Scope Changes
Changes in
Schedule
Regulatory
Requirements
OSHA / EPA
Compliance
Poor Quality
Unacceptable to
Client
As-Built
Changes
Cash Flow
Problems
Source: Project Management a Systems Approach to Planning, Scheduling & Controlling, 7th edition
Harold Kerzner, PhD
Slide 11
Schedule
Development,
Estimate
Review
Quantitative
Risk
Analysis
Increasing standardization in
templates, procedures, style
Clear recipe to integrate Risk
Components
Stricter adherence to organization
project management standards
Project Managers actively seek
risk support
Slide 12
Risk Monitoring
& Control
Project
Communication
Summarize
Increasing standardization in
templates, procedures, style
New risk components being
integrated
Risk
Identification &
Prioritization
Risk Response
Planning
Risk
Quantification
Project
j
Document Review
Clarity in Scope
Assumptions.
Qualitative Assessment
Better Estimates.
Recognition and
transparency in project
challenges.
Better Schedules.
Brainstorming and
innovative solutions.
Quantitative Analysis
y
Risk based, documented
project contingencies.
SMART support
pp to p
project
j
change management.
Slide 14
SRA
Range
Summarize
Simulate
Prioritize
Review
Simulate
Model
Identify
RMP
Summary
Sequences
Sequences,
Probabilistic
Branching
Durations of
Critical
Activities
Model
Identify
Project Scope,
Estimate Issues,
Project Assumptions,
CPM & GPM Schedules, Possible Risks &
Response Plans
Estimates
E
Execution
ti Pl
Plans &
Strategy
Range
CRA
@Risk
Cost Breakdown,
Variables, &
Distributions
Reports,
Graphics,
Options to
R
Respond
d tto
risks
Identify Risks
Qualitative Risk Assessment
Scope
Price
Schedule
Productivity
Technology
Selection
Design Options
Level of Definition
Equipment Design
Environmental
Onsite/Offsite
Site Layout
Demolition
Market Conditions
Equipment
Vendors
Materials
Labor Rates
Exchange Rates
Engineering Rates
Indirect/Overhead
Construction
Equipment
Release of Work /
Approval
Periods
Procurement
Periods
Equipment/Material
Delivery
Work Area
Restrictions
Coordination with
j
Other Projects
External
Constraints
Vendor/Contractor
Resources
Near Operating
Areas
Workforce Quality
Labor Productivity
Turnaround Timing
Contract Strategy
Weather
Conditions
Manpower Density
Shift
Work/Overtime
Other
Contracting
Strategy
Joint Ventures
Communication
Permitting
Political
Influences
Slide 16
Risk Management
Planning
R i
Review
Process
Risk Monitoring
& Control
Project
Communication
Summarize
Risk Response
Planning
Risk
Identification &
Prioritization
Risk
Quantification
Slide 17
Risk Thresholds
Figure 1: Defined Conditions for Probability Scales of a Risk
Probability
Low
Medium
High
Very High
0% 10%
11% to 30%
31% to 50%
51% to 70%
>70%
Figure 2: Defined Conditions for Impact Scales of a Risk on Major Project Objectives
Project
Objective
Very Low
Very Low
Low
Medium
Cost
Insignificant
Cost Increase
<2% of TPC
2 7%
2-7%
Increase
Time
0-2
Week
Time Increase
Scope
Scope
S
Decrease
Barely
Noticeable
Quality
Quality
Degradation
Barely
Noticeable
High
Cost
8 15%
8-15%
Increase
Very High
Cost
>15%
15%
Cost
Increase
7-12
Week
Time Increase
13-18
Week
Time Increase
>18
Week
Time increase
Minor Areas of
Scope Affected
Major Areas of
Scope Affected
Scope
S
Reduction
Unacceptable
to PA
Project
P
j t Does
D
not
Satisfy
Original Intent
at Completion
Only
Most
Demanding
Specs Not Met
Degradation
Requires
PA
Approval
Quality
Reduction
Unacceptable
to PA
Major Re-work
Required
to
Complete
Project
Project team
defines
thresholds to
classify risks
and reduce
subjectivity
Slide 18
Prioritization
5.00
4.00
3.00
2.00
1.00
1.00
VL
Probability-Impact
Score Legend
High = > 9
Med = 5 - 9
Low = 1 - 4
10.00
8.00
6.00
4.00
2.00
2.00
L
Threats
15.00
12.00
9.00
6.00
3.00
3.00
M
I
Impact
t
20.00
16.00
12.00
8.00
4.00
4.00
H
25.00
20.00
15.00
10.00
5.00
5.00
VH
Tolerance is
used to define
Ri k appetite
Risk
tit off
the organization
Tolerance Thresholds
Slide 19
Risk Register
Sample
S
l Risk
Ri k Register
R i t used
d tto prioritize
i iti risks
i k and
d subsequently
b
tl input
i
t
in the quantitative model.
Slide 20
Risk Monitoring
& Control
Process
Project
j
Communication
Risk
Identification &
Prioritization
Summarize
Risk Response
Pl
Planning
i
Risk
Q
Quantification
tifi ti
Slide 21
Schedule Validation
NetPoint - GPM Alternative to CPM
Slide 22
Ranging Considerations
Quantitative Risk Assessment
Do the potential outcomes fit
the normal, triangular or beta
distribution function?
Would a different distribution
function be better, such as
discrete/uniform or compound?
Does the deterministic
schedule duration or the cost
estimate
ti t truly
t l representt th
the
most likely outcome for that
y
activity?
Slide 23
Slide 24
Hits
80
60
40
20
0
17/06/2017
100% 29/01/2020
95% 23/09/2019
90% 31/07/2019
85% 08/07/2019
80% 14/06/2019
75% 21/05/2019
70% 01/05/2019
65% 10/04/2019
60% 21/03/2019
55% 01/03/2019
50% 19/02/2019
45% 31/01/2019
40% 17/01/2019
35% 31/12/2018
30% 13/12/2018
25% 26/11/2018
20% 06/11/2018
15% 15/10/2018
10% 13/09/2018
5% 31/07/2018
0% 15/02/2018
Cumulative Frrequency
Analy sis
Iterations:
1000
Statistics
Minimum:
Maximum:
Mean:
Bar Width:
15/02/2018
29/01/2020
21/02/2019
month
Highlighters
g g
50%
80% - Determinis...
Deterministic (03...
80%
90%
19/02/2019
892
<1%
14/06/2019
31/07/2019
30/10/2018
Distribution
st but o (sta
(startt o
of interval)
te a )
57%
43%
42%
33%
22%
14%
12%
12%
12%
Slide 26
57%
40%
32%
RD11 - FHWA Design Exception for substandard geometry may not be received b...
31%
17%
RD1 - Design Package for Design Build may take longer than expected
14%
11%
9%
Slide 27
Distribution Analyzer
y
- Helps
p determine impact
p
of each risk on project
p j
schedule
Distribution Analyzer
Removing RD1 - Finish Date
Removing RC14 - Finish Date
Variation:144
Variation:73
Variation:82
Variation:175
Variation:5
Variation:54 Variation:85
Variation:119 Variation:25
Variation:59
60%
Variation:72
Variation:127
40%
20%
0%
22/ 09/ 2017
Slide 28
C u m u lative P ro b ab ili ty
80%
Slide 29
Strikes
Impact of Politics
Slide 30
Slide 31
Slide 32
Slide 33
Slide 34
Slide 35
OverallProjectCompletion
Variability(Probabilistic
Dates DeterministicDates)
Deterministic
Contingency =(Probabilistic
Date DeterministicDate)X
IndirectCosts(i.e.,$10,000/day)
P10
587
$5,870,000
MostLikely P50
746
$7,460,000
P90
908
$ 9,080,000
OPRA Oracle Primavera Risk Analysis
Slide 36
Total cost
Risk Basedcostcontingency
Deterministic Estimate
$ 250,000,000
P10
$265,277,700
$15,277,700
MostLikely P50
$273,829,600
$23,829,600
P90
$ 283,200,200
$33,200,200
Slide 37
Slide 38
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
Total
Construction
$0
$0
$25,000
$60,000
$65,000
$80,000
$20,000
$0
$0
$0
$250,000
Inflation
$0
$0
$1,500
$5,400
$7,800
$12,000
$3,600
$0
$0
$0
$30,300
$0
$0
$26,500
$65,400
$72,800
$92,000
$23,600
$0
$0
$0
$280,300
Engineering Staff
$7,000
$11,800
$13,000
$1,180
$1,180
$950
$950
$0
$0
$0
$36,060
$3,000
$3,000
$8,000
$4,000
$5,000
$5,000
$5,000
$0
$0
$0
$33,000
$10,000
$14,800
$21,000
$5,180
$6,180
$5,950
$5,950
$0
$0
$0
$69,060
Administrative Costs
$200
$296
$420
$104
$124
$119
$119
$0
$0
$0
$1,381
Project Contingency
$816
$1,208
$3,834
$5,655
$6,328
$7,846
$2,374
$0
$0
$0
$28,059
$11,016
$16,304
$25,254
$10,938
$12,632
$13,915
$8,443
$0
$0
$0
$98,500
$11,016
$16,304
$51,754
$76,338
$85,432
$105,915
$32,043
$0
$0
$0
$378,800
$11,016
$27,320
$79,073
Direct Costs
Indirect Costs
Empirical
Contingency
Allocation
Slide 39
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
Total
Construction
$0
$0
$30,000
$50,000
$54,000
$62,000
$24,000
$20,000
$10,000
$0
$250,000
Inflation
$0
$0
$1 800
$1,800
$4 500
$4,500
$6 480
$6,480
$9 300
$9,300
$4 320
$4,320
$4 200
$4,200
$2 400
$2,400
$0
$33 000Risk
$33,000
$0
$0
$31,800
$54,500
$60,480
$71,300
$28,320
$24,200
$12,400
$0
Based
Contingency
$283,000
Allocation
Engineering Staff
$7,000
$11,800
$13,000
$1,180
$1,180
$950
$950
$950
$950
$0
$37,960
$3,000
$3,000
$8,000
$4,000
$5,000
$5,000
$5,000
$5,000
$5,000
$0
$43,000
$10,000
$14,800
$21,000
$5,180
$6,180
$5,950
$5,950
$5,950
$5,950
$0
$80,960
Administrative Costs
$200
$296
$420
$104
$124
$119
$119
$119
$119
$0
$1,619
Project Contingency
$800
$900
$4,500
$6,080
$9,500
$12,000
$3,500
$3,000
$2,000
$0
$42,280
$11,000
$15,996
$25,920
$11,364
$15,804
$18,069
$9,569
$9,069
$8,069
$0
$124,859
$11,000
$15,996
$57,720
$65,864
$76,284
$89,369
$37,889
$33,269
$20,469
$0
$407,859
$11,000
$26,996
Direct Costs
Indirect Costs
Additional
Overhead
Expenses
Slide 40
Slide 41
Risk
Management
Planning
Review
Process
Risk Monitoring
& Control
Project
Communication
Risk
Identification
Summarize
Ri k R
Risk
Response
Planning
Ri k
Risk
Quantification
Slide 42
Slide 43
* The results in the above chart are for illustration purposes only. They do not reflect current risk activity
Contingency Management
$25,000
Contingency Rundown
Plan
Contingency Rundown
Actual
$20,000
$15,000
$10,000
$5,000
$6 900
$6,900
$0
$5,100
Financial Period
Slide 45
Final Remarks
Slide 46
References
Survival
S
i l off th
the U
Unfittest:
fitt t Wh
Why th
the W
Worstt IInfrastructure
f t t
G
Gets
t Built
B ilt
And What We Can Do About It, Oxford Review of Economic
Policy, vol. 25, no. 3, 2009, pp. 344-367
Slide 47
Questions ?
Slide 48
Contact Information
Francisco Cruz
Senior Engineer
fcruz@pmaconsultants.com
Mitul Parikh
Senior Engineer
mparikh@pmaconsultants.com
Slide 49