Professional Documents
Culture Documents
Class Schedule
Lecture 1
Lecture 2
Lecture 3
Lecture 4
Lecture 5
Lecture 6
Lecture 7
Lecture 8
:
:
:
:
:
:
:
:
09th
10th
11th
12th
13th
14th
15th
16th
Dec
Dec
Dec
Dec
Dec
Dec
Dec
Dec
TUE
WED
THU
FRI
SAT
SUN
MON
TUE
trainings@windowslive.com
0548 582 754
7-10 pm
7-10 pm
7-10 pm
3-10 pm
3-10 pm
7-10 pm
7-10 pm
7-10 pm
BCS , M.IT
PMP , RMP
MCTS , MCPD
Lean Six Sigma Green Belt Certified
Work Experience
15+ Years of Working & Project Management
Experience
150+ Project Management Workshops
Already trained 4000+ Industry Professionals
trainings@windowslive.com
0548 582 754
Cartoons Time
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Diploma Holders
Work
Experience
Project
Management
Training
35 PDUs of Project
Management Training
Exam
Ref : www.pmi.org
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Prometric Centers
Medina
Jeddah
Riyadh
Dammam
trainings@windowslive.com
0548 582 754
Prometric Centers
trainings@windowslive.com
0548 582 754
Prometric Centers
trainings@windowslive.com
0548 582 754
Until you obtain plan approval, you dont need to put changes to it
through change control.
b. Change control makes sure that only approved changes can make it into
the approved plan.
c.
Only one person needs to approve the Project Management Plan and
thats the Project Manager.
d. Its important for the entire team to buy into the Project Management
Plan for it to be successful.
trainings@windowslive.com
0548 582 754
a.
Until you obtain plan approval, you dont need to put changes to it
through change control.
b. Change control makes sure that only approved changes can make it into
the approved plan.
c. Only one person needs to approve the Project Management Plan and
thats the Project Manager.
d. Its important for the entire team to buy into the Project Management
Plan for it to be successful.
Answer: C
Its not enough that the Project Manager approves of the Project Management Plan; it needs to be
approved by all of the stakeholders in the project. Everyone on the team should feel comfortable with the
processes that are going to be used to do the work.
trainings@windowslive.com
0548 582 754
$59,210
b. $80,000
c.
$84,210
d. $109,210
trainings@windowslive.com
0548 582 754
a. $59,210
b. $80,000
c.
$84,210
d. $109,210
Answer: A
This question is asking you to create a forecast using Estimate To Complete (ETC), which uses CPI (Cost
Performance Index) to project how much money is likely to be spent for the rest of the project. The first
step is to plug the numbers into the formula EAC = BAC / CPI, which yields EAC = $80,000 / .95 =
$84,210. Thats how much money youre likely to spend on the project. Now you can figure out ETC =
EAC - AC = $84,210 - $25,000 = $59,210.
[BAC = Budget at Completion, EAC = Estimate at Completion, AC = Actual Cost]
trainings@windowslive.com
0548 582 754
10
b. 11
c.
16
d. 17
trainings@windowslive.com
0548 582 754
a. 10
b. 11
c.
16
d. 17
Answer: A
Its just easy to calculate the late finish (LF) of an activity in a network diagram. Look at the following
activity, take its LS (late start), and subtract one. If theres more than one following activity, use the one
with the lowest LS. So for activity F in the question, the following activities are G, with an LS of 17, and H,
with an LS of 11. So the LF of F is 11 - 1 = 10.
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
300,000
267,367
250,000
# PMPs
221,144
200,000
175,194
150,000
100,000
102,047
76,550
52,443
50,000
40,343
1,000
-
1,900
2,800
4,400
6,415
10,086
18,184
27,052
1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
Year
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
PROJECT MANAGEMENT
The application of skills and methodologies that
allow to deliver a project on time, within
budget and to the specifications.
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Project Characteristics
Temporary
Have some objectives to meet.
Progressive Elaboration ( Means more details
become available with the passage of time)
Are done to
grab some opportunity,
market demand,
capacity building,
technological advancement
regulatory requirements.
trainings@windowslive.com
0548 582 754
KNOWLEDGE AREAS
Scope Management
Time Management
Cost Management
Quality Management
HR Management
Communication Management
Risk Management
Procurement Management
Stakeholder Management
Integration Management
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Scope Management
Processes required to ensure that the project includes all
the work required, and only the work required, to
complete the project successfully.
1. Plan Scope Management
2. Collect Requirements
3. Define Scope
4. Create WBS
5. Validate Scope
6. Control Scope
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Time Management
Describes the processes required to ensure timely completion
of the project.
1. Plan Schedule Management
2. Define Activities
3. Sequence Activities
4. Estimate Activity Resource
5. Estimate Activity Durations
6. Develop Schedule
7. Control Schedule
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Cost Management
Describes the processes required to ensure that the
project is completed within the approved budget.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Quality Management
Describes the processes required to ensure that the
project will satisfy the needs for which it was
undertaken.
1. Plan Quality Management
2. Perform Quality Assurance
3. Control Quality
( What is the difference between QA and QC )
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Human Resource Management
Describes the processes required to make the most effective use
of the people involved with the project.
1.
2.
3.
4.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Communications Management
Describes the processes required to ensure timely and
appropriate generation, collection, dissemination, storage, and
ultimate disposition of project information.
1.Plan Communications Management
2.Manage Communications
3.Control Communications
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Risk Management
Describes the processes concerned with identifying,
analyzing, and responding to project risk.
Project management
Knowledge Areas
Project Procurement Management
Describes the processes required to acquire goods
and services from outside the performing organization.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Stakeholder Management
.
1. Identify Stakeholders
2. Plan Stakeholder Management
3. Manage Stakeholder Engagement
4. Control Stakeholder Engagement
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Integration Management
Processes required to ensure that the various elements of
the project are properly coordinated.
Below are the process in Integration Management
Knowledge Area
1. Develop Project Charter
2. Develop Project Management Plan
3. Direct and Manage Project Execution
4. Monitor and Control Project Work
5. Perform Integrated Change Control
6. Close Project or Phase
trainings@windowslive.com
0548 582 754
Process Groups
Project management processes can be organized into five groups:
Initiating processes: recognizing that a project or phase should begin
and committing to do so.
Planning processes: devising and maintaining a workable scheme to
accomplish the business need that the project was undertaken to
address.
Executing processes: coordinating people and other resources to carry
out the plan.
Controlling processes: ensuring that project objectives are met by
monitoring and measuring progress and taking corrective action when
necessary.
Closing processes: formalizing acceptance of the project or phase and
bringing it to an orderly end.
trainings@windowslive.com
0548 582 754
Process Groups
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Thank You
trainings@windowslive.com
0548 582 754
Scope
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Simple Example:
Lets say we have two activities
a) Make Biryani ( Duration = 60 Min)
b) Make Raita ( Duration = 10 Mins)
Project Start time = 08:00 pm
trainings@windowslive.com
0548 582 754
Simple Example:
Lets say we have two activities
a) Make Biryani ( Duration = 60 Min)
b) Make Raita ( Duration = 10 Mins)
Project Start time = 08:00 pm
Activity Duration
Name ( Mins)
ES
EF
LS
LF
Float
Biryani
60
08:00
09:00
08:00
09:00
Raita
10
08:00
08:10
08:50
09:00
50
Flaot is the amount / duration by which you can delay an activity without affecting
the project target completion date.
trainings@windowslive.com
0548 582 754
Simple Example:
Lets say we have two activities
a) Make Biryani ( Duration = 60 Min)
b) Make Raita ( Duration = 10 Mins)
Project Start time = 08:00 pm
Activity Duration
Name ( Mins)
ES
EF
LS
LF
Float
Biryani
60
08:00
09:00
08:00
09:00
Raita
10
08:00
08:10
08:50
09:00
50
60 Minutes is the project duration. The path containing make Biryani is the critical
path, longest path, and the shortest duration in which you can complete this project
trainings@windowslive.com
and is called as critical path.
0548 582 754
Example Project
Activity Name
Duration ( days)
Predecessor
None
None
14
D,F
12
B,C
G,H
trainings@windowslive.com
0548 582 754
Network Diagram
start
trainings@windowslive.com
0548 582 754
Network Diagram
start
trainings@windowslive.com
0548 582 754
Network Diagram
H
I
end
start
E
trainings@windowslive.com
0548 582 754
Network Diagram
D
G
A
F
I
start
end
H
B
trainings@windowslive.com
0548 582 754
G
A
F
I
start
end
H
B
Path 1 A - D - G - I
Path 3 A - C - H - I
Path 2 A E - F - G - I
Path 4 B - H - I
G
A
F
I
start
end
H
B
Path 1 A - D - G - I
24 Days
Path 2 A E - F - G - I 26 Days
Path 3 A - C - H - I
23 Days
Path 4 B - H - I
20 Days
Predecessor
None
None
14
D,F
12
B,C
G,H
ES
EF
LS
trainings@windowslive.com
0548 582 754
LF
Float
Forward Pass
Activity Duration (
Name
WEEKS) Predecessor
ES
EF
None
None
10
14
D,F
11
24
12
B,C
10
21
G,H
25
26
LS
LF
Float
Backward Pass
Activity Duration (
Name WEEKS) Predecessor
ES
EF
LS
LF
None
None
12
12
10
10
10
14
D,F
11
24
11
24
12
B,C
10
21
13
24
G,H
25
26
25
26
Float
Float
Activity Duration (
Name WEEKS) Predecessor
ES
EF
LS
LF
Float
None
None
12
12
10
10
10
14
D,F
11
24
11
24
12
B,C
10
21
13
24
G,H
25
26
25
26
Predecessor
ES
EF
LS
LF
Float
None
10
10
14
D,F
11
24
11
24
G,H
25
26
25
26
Second Example
Activity Duration (
Name WEEKS) Predecessor
None
B,E
E,G
C,F,H
ES
EF
LS
LF
Float
Second Example
Activity Duration (
Name WEEKS) Predecessor
ES
EF
None
13
B,E
10
15
E,G
10
16
C,F,H
17
19
LS
LF
Float
Second Example
Activity Duration
Name ( WEEKS) Predecessor
ES
EF
LS
LF
None
2,3,5
10 , 9
13
10
16
9 , 10
B,E
10
15
11
16
E,G
10
16
10
16
C,F,H
17
19
17
19
Float
Second Example
Activity Duration (
Name WEEKS) Predecessor
ES
EF
LS
LF
Float
None
13
10
16
B,E
10
15
11
16
E,G
10
16
10
16
C,F,H
17
19
17
19
Example
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
SV = EV PV
CV = EV AC
SPI = EV / PV
CPI = EV / AC
EV is coming first
For Variance its Minus
For Index is division
For Schedule other operand is PV
For Cost other operand is AC
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754