You are on page 1of 92

ValueEngineeringStudy

Report

TH952A,RobertStreetImprovements
SP190884
September1013,2013

MinnesotaDepartmentofTransportation
395JohnIrelandBlvd
St.Paul,MN55155


Disclaimer:
Theinformationcontainedinthisreportistheprofessionalopinionsoftheteammembersduringthe
ValueEngineeringStudy. Theseopinionswerebasedontheinformationprovidedtothe teamat the
timeofthestudy.Astheprojectcontinuestodevelop,newinformationwillbecomeavailable,andthis
information willneed tobeevaluatedonhowitmayaffecttherecommendationsandfindingsin this
report.Allcostsdisplayedinthereportarebasedonbestavailableinformationatthetimeofthestudy
andunlessotherwisenotedarein2013dollars.

Thisreportwaspreparedby:

HDREngineering,Inc.
701XeniaAvenueSouth,Suite600
Minneapolis,MN55416

TableofContents
ValueEngineeringSummary................................................................................................................1
Introduction..............................................................................................................................................1
VERecommendations...............................................................................................................................1
Introduction.........................................................................................................................................3
ProjectBackground...................................................................................................................................3
VEStudyTiming........................................................................................................................................4
ScopeoftheVEStudy...............................................................................................................................4
VETeamMembers....................................................................................................................................4
ProjectDescription..............................................................................................................................5
Introduction..............................................................................................................................................5
ConstraintsandControllingDecisions......................................................................................................6
StakeholderConcerns...............................................................................................................................6
InvestigationObservations.......................................................................................................................7
ProjectCostEstimate................................................................................................................................7
ProjectSchedule.......................................................................................................................................7
InformationProvidedtotheVETeam......................................................................................................8
ProjectAnalysis...................................................................................................................................9
SummaryofAnalysis.................................................................................................................................9
CostModel................................................................................................................................................9
PerformanceAttributes............................................................................................................................9
PerformanceAttributeMatrix................................................................................................................12
FunctionalAnalysis..................................................................................................................................12
FASTDiagram..........................................................................................................................................13
Speculation........................................................................................................................................15
Evaluation..........................................................................................................................................17
Recommendations.............................................................................................................................28
PerformanceAssessment........................................................................................................................28
Recommendations..................................................................................................................................30
DesignConsiderations.............................................................................................................................30
VERecommendationNo.1UseTrafficBarrels.......................................................................................33
VERecommendationNo.2Contractor/BusinessWeeklyMeetings......................................................37
VERecommendationNo.3aRelocateUtilitiesFirst...............................................................................41
VERecommendationNo.3bRiskMitigationSeparateWaterMainContract.....................................49
VERecommendationNo.4InnovativeContracting...............................................................................55
AppendixA........................................................................................................................................61
RobertStreetImprovements
ValueEngineeringStudyReport

TableofContentsi
September1013,2013

ValueEngineeringRecommendationApprovalForm.............................................................................61
AppendixB........................................................................................................................................65
VEStudyAgenda.....................................................................................................................................65
AppendixC........................................................................................................................................67
VEStudyAttendees.................................................................................................................................67
AppendixD........................................................................................................................................71
VEStudyReportOutPresentation.........................................................................................................71
AppendixE.........................................................................................................................................83
ValueEngineeringProcess......................................................................................................................83
PreVEStudy............................................................................................................................................83
ValueEngineeringJobPlan.....................................................................................................................83
PerformanceBasedResults....................................................................................................................85
Introduction........................................................................................................................................85
Assumptions........................................................................................................................................86
Step1DeterminetheMajorPerformanceAttributes.....................................................................86
Step2DeterminetheRelativeImportanceoftheAttributes.........................................................87
Step3EstablishthePerformanceBaselinefortheOriginalDesign.............................................87
Step4EvaluatethePerformanceoftheVERecommendations.....................................................87
Step5ComparethePerformanceRatingsofRecommendationstotheBaselineProject..........87
Reporting.................................................................................................................................................88

RobertStreetImprovements
ValueEngineeringStudyReport

TableofContentsii
September1013,2013

ValueEngineeringSummary
Introduction
Thisvalueengineering(VE)reportsummarizestheeventsof
the study conducted for the Minnesota Department of
Transportation (MnDOT) and facilitated by HDR
Engineering,Inc.
The subject of the VE Study was TH 952A, Robert Street
Improvements, SP 190884. The study was conducted
September 1013, 2013 with the presentation of findings
heldSeptember13,2013.
The primary objective of the team through application of
theVEJobPlan(seeAppendixE)wasto:

ValueSummary
ProjectCost:$22.0million
NumberofRecommendations:4
NumberofApprovedRecommendations:4
RecommendedCostSavings:$0.20million
ApprovedCostSavings:$0.20million
RecommendedScheduleSavings:6months
ApprovedScheduleSavings:6months
TotalNumberofTeamMembers:6
MnDOTEmployees:4
Others:2

ApplytheprinciplesandpracticesoftheVEJobPlan Facilitator: HDREngineering,Inc.


Conducted a thorough review and analysis of the
project
Brainstormedandevaluatepossibleimprovementopportunities
Used a fresh set of eyes to search for new/innovative approaches to constructability,
constructionstagingandtrafficcontrol
Identifypotentialvalueaddedandcostsavingopportunities.

VERecommendations
TherecommendationsarebrieflydescribedbelowandaredescribedindetailintheRecommendations
sectionofthereport.
1UseTrafficBarrels

$0.20Msavings

Replacethetemporaryconcretebarrierwithtrafficbarrelstoseparatetrafficfromtheworkzoneandto
delineatebusinessaccess.Thisrecommendationmitigatesconstructionimpacts.
2Contractor/BusinessWeeklyMeetings

NotQuantified

Have the contractor designated someone, most likely the foreman or superintendent, who will give
weeklyupdatestobusinessownersoftheexpectedworkforthatweek.Thisrecommendationmitigates
constructionimpacts.
3aRelocateUtilitiesFirst

Reduces6monthsofconstructionduration

Develop an order of work or first order of work contract provision that requires completing the
installation of the water main work along with the proposed sanitary sewer pipe and manhole
replacements prior to starting work within that section of Robert Street. This recommendation
mitigatesconstructionimpactsandwillreducetheoverallcontractduration.

RobertStreetImprovements
ValueEngineeringStudyReport

ValueEngineeringSummary1
September1013,2013


3bRiskMitigationSeparateWaterMainContract

Reducesriskofdelay

Ifrightofwayacquisitionisdelayed,thenadvertiseandletaseparateconstructionprojectspecifically
fortheinstallationofthewatermainassociatedwiththeRobertStreetImprovementProject.Thisisa
response strategy to the risk that the rightofway will not be acquired by the project letting in April
2014andthattheprojectwillbedelayeduntiltherightofwaycertificationisapprovedbyFHWA.This
recommendationmitigatesconstructionimpactsandmitigatesanidentifiedprojectrisk.
4InnovativeContracting

Reduces6monthsofconstructionduration

To receive the best value for the project, incorporate innovative contracting methods within the
designbidbuild project delivery to reduce the overall duration of the project. This recommendation
mitigatesconstructionimpactsandwillreducetheoverallprojectduration.
In addition to the recommendations above, the VE Team generated several ideas that they felt were
importantenoughtobedocumentedasdesignconsiderationsforfurtherconsiderationbytheProject
Team.ThesedesignconsiderationsaresummarizedintheRecommendationssectionofthereport.

The VE Team wishes to express its appreciation to the project design team and management for the
excellent support they provided during the study. These recommendations and other ideas provided
willassistinthemanagementdecisionsnecessarytomovetheprojectforward.

BlaneLong,CVS,CCT
VETeamLeader

RobertStreetImprovements
ValueEngineeringStudyReport

ValueEngineeringSummary2
September1013,2013

Introduction
This report summarizes the events of the VE Study conducted for MnDOT and facilitated by HDR
Engineering,Inc.ThesubjectofthestudywastheTH952A,RobertStreetImprovementsSP190884.

ProjectBackground
Robert Street is a trunk highway facility (TH 952A) owned by MnDOT and provides the major north
souththoroughfareforWestSt.Paul.Theroadwayisclassifiedasaminorarterial.Theprojecttermini
isMendotaRoadtothesouthandAnnapolisStreettothenorth.Theexistingconfigurationbetween
Mendota Road and Butler Avenue, Robert Street is a 5lane undivided roadway with no on street
parking. From Butler Avenue to Annapolis Street, Robert Street is a 3lane undivided roadway with
parkingonbothsides.

Figure1ProjectLocation
RobertStreetImprovements
ValueEngineeringStudyReport

Introduction3
September1013,2013

VEStudyTiming
The study was conducted September 1013, 2013. The project was at 60% design at the time of the
study.

ScopeoftheVEStudy
ThescopeoftheVEStudywastoverifyorimproveuponconceptsbeingproposedfortheproject.To
accomplishthis,theVETeam:

AppliedtheprinciplesandpracticesoftheVEJobPlan
Conductedathoroughreviewandanalysisoftheproject
Brainstormedandevaluatedpossibleimprovementopportunities
Used a fresh set of eyes to search for new/innovative approaches to constructability,
constructionstagingandtrafficcontrol
Identifiedpotentialvalueaddedandcostsavingopportunities.

VETeamMembers
TheVETeamincluded:

MichaelArseneau
TiffanyDagon
CurtissKallio
BlaneLong

JoshMetcalf
AlminRamic

Design
Traffic
Construction
VETeamLeader
Design/Construction
Geometrics

RobertStreetImprovements
ValueEngineeringStudyReport

Introduction4
September1013,2013

ProjectDescription
Introduction
Robert Street (Trunk Highway 952) is the main north/south transportation route through the heart of
thecommercialbusinessdistrictinWestSt.Paul.Itisanapproximately2.4mileroute,classifiedasanA
Minor Arterial Street and is under the jurisdiction of the Minnesota Department of Transportation
(MnDOT).
FromMendotaRoadatthesouthendoftheCitytoButlerAvenueonthenorthendoftheCity,Robert
Street exists as a 5lane undivided roadway with no parking on either side and Average Daily Traffic
(ADT)rangingfrom16,000to26,000vehicles(per2009ADTmaps).FromButlerAvenuetothenorth
CitylimitlineatAnnapolisStreet,RobertStreetisa3laneundividedroadwaywithparkingpermittedon
eachsideand16,000vehiclesADT.
Throughoutthecorridor,butespeciallyinthesoutherntwothirds,therearenumerousdrivewaysalong
bothsidesofthestreet.Insomeareasthedrivewaysarespacedjust50feetapart.Becauseofthese
closelyspaceddriveways,thecrashratesalongRobertStreetarehigherthanaveragewhencompared
tootherundividedTrunkHighwaysinthemetroarea.
ThepurposeoftheprojectistoreconstructRobertStreettoimprovesafetyandmobilityandprovide
accommodationstomeettheAmericanswithDisabilitiesAct(ADA)standards.Theprojectwillconvert
twowayleftturnlanesintoamedian,addtravellanesnorthofButlerStreetbyremovingparking,add
turnlanesandimprovesidewalks.

Figure2TypicalSection
RobertStreetImprovements
ValueEngineeringStudyReport

ProjectDescription5
September1013,2013


Theprojectwillalsoreconstructthestormsewernetwork,replacetrafficsignals,replacestreetlighting,
andinstallotherstreetscapeelements.TheprojectisintendedtoimprovetheentirelengthofRobert
StreetinWestSt.Paulinfourcategories:
Infrastructure

Milling/overlayoftheexistingbituminouspavementsurface
Replacementofbroken/deterioratedconcretecurbsections
Stormsewerupgrading/replacement
Improvementstopublicutilities(sanitarysewerandwatermains)asneeded.

Safety

Addingaraisedmediandowntheexistingcenterturnlane
ProvidingadditionalcapacityineachdirectiononthenorthendofRobertStreetbetweenButler
andAnnapolis
Intersectionimprovementsincludingwideningradii,signalupgrades,additionaldedicatedturn
lanestoRobertStreetfromselectsidestreets
Consolidationofdrivewayswhereappropriate.

Aesthetics

Replacingtheexistingstreetlightswithamoreefficientandaestheticlightsystem
Adding a "green element" along Robert Street through the use of boulevard trees and
landscapingelementswithinthecorridor.

Transit

Ensuringthedesigncanaccommodatepossiblefuturestreetcarlinesorbusrapidtransitwithin
theoutertravellane.

ConstraintsandControllingDecisions
Aspartoftheprojectbriefing,theVETeamwasgiventhefollowingprojectconstraintsandcontrolling
decisionsthatneededtobetakenintoaccountwhenconsideringpossiblealternatives:

80feetofrightofway
ProjectneedstobeletbyApril2014
Maintain2lanesinonedirectiononRobertStreetduringconstructionanddetourfortheother
direction
Maintainaccesstobusinessesduringconstruction
Maintainabusinessdetourduringconstruction
Maintainabypassdetourduringconstruction
Maintainabusdetourduringconstruction
Maintainpedestrianpathduringconstruction.

StakeholderConcerns

Workneedstobeginin2014
Driversandpedestrianswillbeguidedinaclearandappropriatemannerthroughtheworkzone
andtobusinesses
Minimize community impacts by completing work efficiently while maintaining quality
constructionrequirements
LatebidopeninginApril2014mayreducenumberofbiddersandincreaseprices.

RobertStreetImprovements
ValueEngineeringStudyReport

ProjectDescription6
September1013,2013

InvestigationObservations
ThefirstdayofthestudyincludedapresentationfromtheProjectTeam.Thefollowingsummarizeskey
projectissues,projectdrivers,andobservationsidentifiedduringthesesessions:

Driversmakingillegalturns
Sidewalksindisrepair
Pavementcracking(duetoconcretepanels)
Pavementfailures/fatigue
Alotofdriveways(businesses)
Transit/pedestrianactivity
The north end (north of Butler Avenue) is different than the rest of project (residential vs.
business)
Pedestrianswithdisabilities
Somedrivewayswentnowhere
Thecontractorwilldig/backfillthetrenchforthewatermainbutSt.PaulWaterServicewilllay
thepipe.

ProjectCostEstimate
The VE Team was provided a design cost estimate (opinion of cost) prior to the study. The VE Team
notedthatthequantitieswithinthecostestimatedidnotnecessarilyreflectthe60%designreviewset
ofplansthatwasalsoprovidedtotheVETeam.ItwastheopinionoftheVETeamthatthedesignhas
progressedto60%andthecurrentestimatehasnotbeenupdatedyettoaccountfortheaddedscope
andquantities.Whereapplicable,theTeamusedtheunitbidpricesprovidedwithinthecostestimate
andobtainedquantitiesfromthe60%plans.
Table1CostEstimateSummary
Category

Subtotal

%ofTotal

Roadway

$4.09M

24.9%

Streetscape

$4.06M

24.6%

TrafficSignals

$1.93M

11.7%

StormSewer

$1.88M

11.4%

WaterMain

$1.31M

7.9%

Contingency

$1.14M

6.9%

Mobilization

$0.75M

4.6%

SanitarySewer

$0.65M

3.9%

Traffic/ErosionControl

$0.45M

2.7%

RetainingWalls

$0.22M

1.3%

$16.47M

100%

ConstructionTotal

ProjectSchedule
The project is scheduled to be advertised in January 2014 with a bid opening in April 2014. The
expectedconstructionstartisJune2014withtheprojectbeingcompletedin2017(3.5yearsduration).
RobertStreetImprovements
ValueEngineeringStudyReport

ProjectDescription7
September1013,2013

InformationProvidedtotheVETeam
ThefollowingprojectdocumentswereprovidedtotheVETeamfortheiruseduringthestudy:
Table2InformationProvidedtoVETeam
Document

Date

PlanView1BLayoutSouthSection

July2013

PlanView1BLayoutNorthSection

July2013

Profile1BLayout

July2013

PreliminaryCostEstimate

August2013

DesignVerificationMeetingMinutes

October2011

ADAMeetingMinutes

April2012

WaterResourcesDesignMeetingminutes

July2012

AttachmentG12014AlternateRoutes

Nodate

AttachmentG22015AlternateRoutes

Nodate

AttachmentG32016AlternateRoutes

Nodate

CONDACMeetingPowerPointPresentation

August2013

ConstructionPlanViewsheets

August2013

ProjectMemorandum

Nodate

RobertStreetIntersectionsPlanViews

July2013

60%AgencyReviewSet

August2013

ConstructionStaging/SequencingReview

August2013

DraftProjectMemorandum

Nodate

RobertStreetImprovements
ValueEngineeringStudyReport

ProjectDescription8
September1013,2013

ProjectAnalysis
SummaryofAnalysis
Thefollowinganalysistoolswereusedtostudytheproject:

CostModel
PerformanceAttributes
PerformanceAttributeMatrix
FunctionalAnalysis
FASTDiagram

CostModel
TheVETeamLeaderpreparedacostmodelfromthecostestimateprovidedtotheteam.
The cost model is organized to identify major construction elements or trade categories, and the
percentoftotalprojectcostforthesignificantcostitems.Figure3demonstratesthatreconstructionof
theroadwayandthestreetscape,whichincludesthelighting,isover50%oftheproject.

Figure3CostModel

PerformanceAttributes
Performance attributes an integral part of the value engineering process. The performance of each
projectmustbeproperlydefinedandagreeduponbytheProjectTeam,VETeamandstakeholdersat
the beginning of the each study. These attributes represent those aspects of a projects scope and
schedulethatpossessarangeofpotentialvalues.
TheVETeam,alongwith theProjectTeam,identifiedand definedtheperformanceattributesforthis
project and then defined the baseline concept as it pertains to these attributes. The following
performanceattributeswereusedthroughoutthestudytoidentify,evaluate,anddocumentideasand
recommendations.
RobertStreetImprovements
ValueEngineeringStudyReport

ProjectAnalysis9
September1013,2013


Table3PerformanceAttributes
Performance
Attribute

Mainline
Operations

Local
Operations

Definition

Baseline

Design/PostedSpeed=40MPHsouth
ofMarieAvenue,35MPHnorthof
MarieAvenue
Anassessmentoftrafficoperationsand
411drivinglanes(doesntinclude
safetyontheTH952A,RobertStreet
gutter)
withintheprojectlimits.
11left&rightturnlanes
Operationalconsiderationsincludelevel
Raisedcentermedianwidthvaries
ofservicerelativetothe20yeartraffic
(415)
projections,aswellasgeometric
considerationssuchasdesignspeed,sight EnhancedUturnstoallowlarger
passengervehicleatthefollowing
distance,andlaneandshoulderwidths.
intersectionsatMendotaRoad,Marie
Avenue,WentworthAvenue&Butler
Avenue.
Anassessmentoftrafficoperationsand
safetyonthelocalroadwayinfrastructure
(crossstreets).
Operationalconsiderationsincludelevel
ofservicerelativetothe20yeartraffic
projections;geometricconsiderations
suchasdesignspeed,sightdistance,lane
andshoulderwidths;bicycleand
pedestrianoperationsandaccess.

Anassessmentofthelongterm
maintainabilityofthetransportation
facility(s).
Maintenanceconsiderationsincludethe
Maintainability
overalldurability,longevityand
maintainabilityofpavements,structures
andsystems;easeofmaintenance;
accessibilityandsafetyconsiderationsfor
maintenancepersonnel.

RobertStreetImprovements
ValueEngineeringStudyReport

5sidewalks(4wideatobstructions)
24pavedboulevardbetween
sidewalkandbackofcurb
MeetallADArequirements
WB50designvehicleforturning
movements
Spaceprovidedforbussheltersin
additiontotheexistingcondition.
4minimummilandoverlay
BituminousSurface
Midblockleftturnsaredifficultto
maintain
Landscapeinmedian(irrigation)
Lackofsnowstorage
Allbutonestormseweroutletison
theoutside

ProjectAnalysis10
September1013,2013


Table3PerformanceAttributes
Performance
Attribute

Construction
Impacts

Definition

Anassessmentofthetemporaryimpacts
tothepublicduringconstructionrelated
totrafficdisruptions,detoursanddelays;
impactstobusinessesandresidents
relativetoaccess,visual,noise,vibration,
dustandconstructiontraffic;
environmentalimpacts.

Anassessmentofthepermanentimpacts
totheenvironmentincludingecological
Environmental (i.e.,flora,fauna,airquality,water
quality,visual,noise);socioeconomic
Impacts
impacts(i.e.,environmentaljustice,
business,residents);impactstocultural,
recreationalandhistoricresources.

Project
Schedule

Anassessmentofthetotalproject
deliveryfromthetimeasmeasuredfrom
thetimeoftheVEStudytocompletionof
construction.

Baseline
Leftturnsatdrivewaysandcross
streetswouldbeallowed
Rightturnsfordeliverytruckswould
beallowed
Twolanesoftrafficinonedirection
duringconstruction.Thetrafficgoing
intheoppositedirectionwouldbe
divertedtoalternateroutes.
Nighttimeworkisallowwitha
variancetothenoiseordinance
Weekendworkispartofthebase
schedule
Multipledetours(business&around)
Temporarypedestrianroutewith
accessiblepedestriansignals
144parcelsneedsomekindof
acquisition:
Permanenteasements
Temporaryeasements
FeeAcquisition
Mediumriskofsomecontaminated
soils
Nonoisewalls
LettingApril2014
BeginConstructionJune2014
3.5yearconstructionduration
2014Constructancillary
improvementsoffRobertStreet,
includingparallelrouteimprovements,
temporarysignalsandsharedaccess.
Inaddition,constructRobertStreet
betweenAnnapolisandButler.
2015ConstructRobertStreetfrom
ButlertoWentworth.
2016ConstructRobertStreetfrom
WentworthtoMendotaRd.
2017Finalcleanup,punchlistitems,
remaininglandscaping.

RobertStreetImprovements
ValueEngineeringStudyReport

ProjectAnalysis11
September1013,2013

PerformanceAttributeMatrix
Amatrixwasusedtodeterminetherelativeimportanceoftheindividualperformanceattributesforthe
project.TheProjectandVETeamsevaluatedtherelativeimportanceoftheperformanceattributesthat
wouldbeusedtoevaluatethecreativeideas.
These attributes were compared in pairs, asking the question: Which one is more important to the
purposeandneedoftheproject?Thelettercode(e.g.,A)wasenteredintothematrixforeachpair.
Afterallpairswerediscussedtheyweretallied(afternormalizingthescoresbyaddingapointtoeach
attribute)andthepercentagescalculated.
Table4PerformanceAttributeMatrix
Whichattributeismoreimportanttotheoutcomeoftheproject?
MainlineOperations

LocalOperations

TOTAL

A/B

5.5

26.2%

5.5

26.2%

3.0

14.3%

3.0

14.3%

1.0

4.8%

3.0

14.3%

21.0

100%

Maintainability
ConstructionImpacts
EnvironmentalImpacts
ProjectSchedule

FunctionalAnalysis
Functionalanalysisresultsinauniqueviewoftheproject.Ittransformsprojectelementsintofunctions,
which moves the VE Team mentally away from the original design and takes it toward a functional
conceptoftheproject.
Functions are defined in verbnoun statements to reduce the needs of the project to their most
elementallevel.Identifyingthefunctionsofthemajordesignelementsoftheprojectallowsabroader
consideration of alternative ways to accomplish the functions. The major functions identified by the
teamwere:

Reduceconflicts
Reducecollisions
Improvecorridorimage
Accommodateusers
Reducecongestion
Improvemobility
Reducemaintenancecosts(lighting/signals)
Improveeconomicvitality.

Table5showsthefunctionsassociatedwiththemajoritemsofworkasdefinedbythecostmodel.The
costsshownaretheoriginalcostfromtheestimateprovidedtotheTeamforcomparisonpurposesonly.
RobertStreetImprovements
ValueEngineeringStudyReport

ProjectAnalysis12
September1013,2013


Table5FunctionalAnalysis
MajorItems

%of
Project

Verb

Noun

Cost

Support
Prepare

Load
Site

$4.09M

24.9%

Provide
Illuminate
Control
Create
Improve

Shelter
Roadway
Erosion
Path
Aesthetics

$4.06M

24.6%

TrafficSignals

Control
Direct

Traffic
Traffic

$1.93M

11.7%

StormSewer

Convey
Control

Water
Flow

$1.88M

11.4%

WaterMain

Supply

Water

$1.31M

7.9%

Contingency

Mitigate

Risk

$1.14M

6.9%

Mobilization

Mobilize

Equipment

$0.75M

4.6%

SanitarySewer

Convey

Wastewater

$0.65M

3.9%

Maintain
Reduce

Traffic
Erosion

$0.45M

2.7%

Retain

Earth

$0.22M

1.3%

Roadway

Streetscape

Traffic/ErosionControl
RetainingWalls

FASTDiagram
The Functional Analysis System Technique or FAST diagram arranges the functions in logical order so
thatwhenreadfromlefttoright;thefunctionsanswerthequestionHow?Ifthediagramisreadfrom
right to left, the functions answer the question Why? Functions connected with a vertical line are
thosethathappenatthesametimeas,orarecausedby,thefunctionatthetopofthecolumn.
TheFASTDiagramforthisprojectshowsImproveMainlineOperationsandImproveLocalOperationsas
the basic functions of this project. Key secondary functions included Maintain Traffic and Relocate
Utilities. This provided the VE Team with an understanding of the project design rationale and which
functionsofferthebestopportunityforcostorperformanceimprovement.

RobertStreetImprovements
ValueEngineeringStudyReport

ProjectAnalysis13
September1013,2013

Figure4aFASTDiagram

Figure4bStageConstructionFASTDiagram

RobertStreetImprovements
ValueEngineeringStudyReport

ProjectAnalysis14
September1013,2013

Speculation
DuringthespeculationorcreativephaseoftheVEJobPlan,theVETeambrainstormedideasonhowto
performthevariousfunctions.Theseideaswerebasedontheavailableinformationgiventothemat
thetimeofthestudy,takingintoconsiderationtheconstraintsandcontrollingdecisionsthatwerealso
giventothem.
Theideaslistedbelowcoincidewitheachfunctionbeingconsidered:
Function:MaintainTraffic(throughthecorridor)

Onelaneeachdirectionwithnosignedbypassdetour,noleftturns
Sameasbaselinebutmovetraffictomiddleandconstructtheoutsidesfirst
Fullclosure(oneblockatatime)
Fullclosure(entiresection)
Movetraffic(2laneseachdirection)tooutsideandconstructcenterofroadwayfirst
Movetraffictomiddle(2laneseachdirection)andconstructalltheutilitiesandsidewalksfirst
Eliminatetemporarybarrierandreduceconstructionspeedto25MPH
Signthebypassrouteonlyonce,coversignsinwinter
AllowA+Bbiddingtoshortentheprojectduration
Allowthecontractortomodifythetrafficcontrol,etc.withapproval
ConstructabilityreviewusingcontractorsASAP
Cut back the details, proposed stages, let the contractor determine the traffic control based
upontheconstraints(performancespecs)
UseATCforthetrafficcontrolwork,givethestagingplanstothecontractorpriortobidding
UseBestValuebiddingprocess
Utilizetheexistingsignalpolesfortemporarysignalsasmuchaspossible
Usetemporaryroundaboutsinsteadoftemporarysignals
Constructcurbtocurbononesideofroadway(eliminateonestage).

Function:MaintainTraffic(tobusinesses)

Maintain2lanesinonedirectionwithnoleftturnsandprovideafrontageagainstthebusiness
toprovideaccess
Contactindividualswithdisabilitiestoidentifytheirneeds
HavethecontractorconductaMondaymorningmeetingwiththebusinesses.

Function:RelocateUtilities

Eliminateundergroundutilityworkaspartoftheproject
Havethewatermainworkstartearly,priortocontract
Useajointutilitytrenchforallthedryutilitiesunderthesidewalk
Utilityworkiscompletedin2014beforeroadwayworkbegin.

Function:ImproveConstructability

Expandtherightofwayto100feet
Usefullroadwayclosures
Closesidestreetsduringconstruction
Useaseparatecontracttorelocateutilities
Streamlinetheapprovalprocesstobeginconstructionearlierin2014
Provideacontractorstagingarea
AllowreclaimforClass5materialorothermaterials(bedding/borrow)
Conductaprebidmeetingtodiscusstheprojectwiththeplanholders.

RobertStreetImprovements
ValueEngineeringStudyReport

Speculation15
September1013,2013


Thispageisleftintentionallyblank

RobertStreetImprovements
ValueEngineeringStudyReport

Speculation16
September1013,2013

Evaluation
Although each project is different, the evaluation process for each VE effort can be thought of in its
simplestformasawayofcombining,evaluating,andnarrowingideasuntiltheVETeamagreesonthe
proposalstobeforwarded.
Taking into consideration the constraints and controlling decisions, the team discussed each idea and
documented the advantages and disadvantages. Each idea was then carefully evaluated with the VE
Teamreachingconsensusontheoverallratingoftheidea(zerothroughfive).Highratedideas(fouror
higher) were developed further; those that were considered to be equivalent to the baseline (rated
three) were documented as design considerations; and lowrated ones (two or lower) were dropped
fromfurtherconsideration;however,theteamprovidedashortdescriptionandjustificationtosupport
thelowrating.Theratingvaluesareshownbelow:
5=GreatOpportunity
4=GoodOpportunity
3=DesignConsideration(comparabletoProjectTeamsapproach)
2=MinorValueDegradation
1=MajorValueDegradation
0=FatalFlaw(unacceptableimpactordoesntmeettheprojectpurposeandneed)
=Advancedasrecommendation
=Forwardedasdesignconsideration
=Droppedfromfutureconsideration
Function:MaintainTraffic(entirecorridor)
#

Description

Advantages

Eliminatesbypassdetour

Onelaneeachdirectionwithno
signedbypassdetour,noleft
turns(alltemporaryaccessis
rightin/rightout)

Disadvantages

Businesscommunitymay
notlike
Busseswillstillneedto
stop
Emergencyresponse
Difficultytoenforce
Increasesigning

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
2

Justification/Comments/Disposition:
Thisideawasdroppedfromfurtherconsideration.

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation17
September1013,2013

Description

Advantages

Disadvantages

Mayeliminateonestageof
construction

Sameasbaselinebutmove
traffictomiddleandconstruct
theoutsidesfirst(sidewalks&
utilities)

Needtomaintainmore
temporaryaccessesatthe
sametime
Increasedneedfor
pedestrianaccessduring
construction
Additionalnighttime
closuresforstormsewer
crossings
Difficultforcontractorto
workbothsidesatsame
time

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
1

Thisideawasdroppedfromfurtherconsideration.

Description

Advantages

Fullclosureoneblockatatime
(Butbusinessstillhaveaccess)

Shouldreduce
constructionduration
Mayreducecost

Disadvantages

Businessesmayobject
Increasestraffic
detours/signingetc.
Increasedcongestion
Localinfrastructuremay
notbeabletosupport
addedvehicles

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
2

Justification/Comments/Disposition:
AblockisconsideredtobefromcrossstreettocrossstreetthatcanaccessOakdaleAvenue.Thisidea
wasdroppedfromfurtherconsideration.

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation18
September1013,2013

Description

Advantages

Shouldreduce
constructionduration
Mayreducecost

Disadvantages

Fullclosure(entiresection)

Businessesmayobject
Increasestraffic
detours/signingetc.
Increasedcongestion
Localinfrastructuremay
notbeabletosupport
addedvehicles

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
1

Thisideawasdroppedfromfurtherconsideration.

Description

Advantages

Movetraffic(2laneseach
direction)tooutsideand
constructcenterofroadway
first

Disadvantages

Lessensneedforbypass

detour
Maintains2laneseach

directionforlongerperiods
oftime

Stormsewercrossingneed
tobeconstructedfirst
Slowerconstructionthan
thebaseline
Mayneedtoreducetoone
laneeachdirectionduring
sanitarysewer
replacement

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:
Stage1constructinside,stage2constructoutside,stage3grindandpaveatnight.
Thisideausesmonolithiccurbinthemedianandthesanitarysewerisreplacedfirst.Thisideawas
droppedfromfurtherconsideration.Incorrectingthecrownoftheroadwaythemedianneedstobe
excavatedandreplacedwhichnegatestheuseofmonolithiccurbandrequiresawiderfootprint.

Rating:
1

Description

Advantages

Movetraffictomiddle(2lanes
eachdirection)andconstructall
theutilitiesandsidewalksfirst

Disadvantages

Lessensneedforbypass

detour
Maintains2laneseach

directionforlongerperiods
oftime

Stormsewercrossingneed
tobeconstructedfirst
Slowerconstructionthan
thebaseline
Mayneedtoreducetoone
laneeachdirectionduring
sanitarysewer
replacement

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
1

Justification/Comments/Disposition:
Sameaspreviousideajustreorderofstages,noleftturnsduringstageone.Thisideawasdropped

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation19
September1013,2013


fromfurtherconsideration.

Description

Advantages

Eliminatetemporarybarrier

Eliminatescostandtime
relocatingbarrier
Provides4ofadditional
width
Eliminatemultiple
snaggingofvehicle
Makesiteasierfor
materialsandequipment
tomovetoandfromthe
workarea

Disadvantages

Mayincreaseconflict
betweenworkersand
traffic

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:

Will still need some barrier adjacent to open trenches if in close proximity to traffic. This idea was
movedtofurtherdevelopment.

Description

Advantages

Signthebypassrouteonlyonce,

coversignsinwinter

Reducescost
CoordinationwithDakota
County

Disadvantages

Stakeholdersmaynotlike
Differentdirections(NBvs.
SB)

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
3

DesignConsideration

Description

Advantages

AllowA+Bbiddingtoshorten
theprojectduration

Reduceconstruction
duration

Disadvantages

Tightbudgetwithcomplex
fundingmechanism

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
4

Justification/Comments/Disposition:
A=costandB=duration.Thisideawasmovedtofurtherdevelopment.Combinewithideas13,14,
32

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation20
September1013,2013

Description

Advantages

Allowthecontractortomodify
thetrafficcontrol,etc.with
approval

10

Disadvantages

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:

Baselineidea

Description

Advantages

Conductaconstructability
reviewusingcontractorsASAP

11

Maylearnimprovedways
tosavecostandtime
Improvethebidabilityof
theplans

Disadvantages

Timetoimplementideas
ifmajorrevisionsare
needed

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
3

Useretiredcontractorsastheteam.DesignConsideration

Description

Advantages

Cutbackthestagingdetails,and
letthecontractordeterminethe
trafficcontrolbaseduponthe

constraints(performancespecs)

12

Allowsforcontractor
innovation
Maysavecost&time

Disadvantages

Difficultforcontractor
(prime&sub)tobid
Mayaddtobidduration

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
3

DesignConsideration

Description

Advantages

UseATCforthetrafficcontrol
work,givethestagingplansto
thecontractorpriortobidding

13

Allowsforcontractor
innovation
Agencygets100%of
savings

Disadvantages

Needtohavetheplans
availabletothebidders
early
Maydelayletting
Newtodesignbidbuild

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
4

Justification/Comments/Disposition:
CombinewithIdeas9,14,32

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation21
September1013,2013

Description

Advantages

UseBestValuebidding
process

14

Disadvantages

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
4

CombinewithIdeas9,13,32

Description

Advantages

Utilizeasmuchaspossiblethe
existingsignalpolesfor
temporarysignals

15

Mayreducecost

Disadvantages

Maynotworkinall
location
Theexistingpolesmaynot
betallenough

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
3

DesignConsideration

Description

Advantages

Usetemporaryroundabouts
insteadoftemporarysignals

16

Mayimprovetrafficflow
duringconstruction
Eliminatesneedfor
temporarysignals

Disadvantages

Makesreconstructionof
intersectionmoredifficult
Willnotworkatmore
intersection

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
2

Justification/Comments/Disposition:
Thisideawasdroppedfromfurtherconsideration.

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation22
September1013,2013

Description

Advantages

Constructoutsidecurbto
mediancurbononesideof
roadway(eliminatesonestage)
theprojectintwostages

eliminatingthe3rdstageand

utilizemonolithiccurbtoreduce
excavation

17

Reducesconstructiontime
Minimizeimpactstousers
Reducesexcavation

Disadvantages

Mayaddcostforcurbing

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
3

DesignConsideration

Function:MaintainTraffic(tobusinesses)
#

Description

Advantages

18

Maintain2lanesinone
directionwithnoleftturnsand
provideafrontageroadagainst
thebusinessestoprovideaccess

Disadvantages

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
1

Addressedwithinpreviousideasandthebaseline.Thisideawasdroppedfromfurtherconsideration.

Description

Advantages

Contactindividualswith
disabilities(pedestrians)to
identifytheirneeds

19

Disadvantages

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:

Justification/Comments/Disposition:
Reasonableaccessforpedestrianswillbemaintainedtoallbusinessesaspartofthebaseline.

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation23
September1013,2013

Description

Advantages

20

Havethecontractorconducta
Mondaymorningmeetingwith
thebusinessesduring
construction

Buildsabetterrelationship
betweenthecontractor
andthebusinesses

Disadvantages

Nonenoted

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
4

Thisideawasmovedtofurtherevaluationanddevelopment.

Function:RelocateUtilities
#

Description

Advantages

Eliminateundergroundutility
workaspartoftheproject

21

Disadvantages

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:

Fatally flawed because the utilities are a part of the current scope of this project. This idea was
droppedfromfurtherconsideration.

Description

Advantages

Havethewatermainworkstart
early(separatecontract),prior
tocontract

22

Utilityworkdoesntaffect
thestaging
Reduceriskforthe2014
work
Temporarywater
connectionsareabigrisk
tothecontractor
Allowsworktobegineven
ifROWisdelayed

Disadvantages

Somebusinessaccesswill
beimpactedmultipletimes
23monthsmoretraffic
control
Coordinationissueswith
twocontractor
Twocontractsto
administer
Additionalpatching
required

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
4

Justification/Comments/Disposition:
Riskmanagementstrategytoinsureworkbeginsin2014.Thisideawasmovedtofurtherevaluation
anddevelopment.

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation24
September1013,2013

Description

Advantages

Useajointutilitytrenchforall

thedryutilitiesunderthe
sidewalk

23

Assistsinmaintainingthe
schedules
Reduceoverall
constructionduration
Lessequipmentwithin
workzone

Disadvantages

Mayaddtocostofproject

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
3

DesignConsideration

Description

Advantages

Utilityworkiscompletedfirst
beforeroadwayworkbegins

24

Utilityworkdoesntaffect
thestaging
Reduceriskforthe2014
work
Temporarywater
connectionsareabigrisk
tothecontractor
Keepsmorelanesoftraffic
openonRobertStreetfor
thefirstyear
Bettercoordination
betweensubcontractor

Disadvantages

Somebusinessaccesswill
beimpactedmultipletimes
Additionalpatching
required
Nothingsappearsfinished
Secondandthirdyear
thereismultiple
operations

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
4

Thisideawasmovedtofurtherevaluationanddevelopment.

Function:ImproveConstructability
#

Description

Advantages

25

Expandtherightofwayto100

Disadvantages

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
0

Justification/Comments/Disposition:
Fatallyflawed.Noadditionalrightofwaywillbeacquiredbeyondwhathasalreadybeenidentified.
Thisideawasdroppedfromfurtherconsideration.

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation25
September1013,2013

Description

26

Advantages

Usefullroadwayclosures

Mainline
Operations

Local
Operations

Disadvantages

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:

Fatallyflawed.Thesurroundinginfrastructure(roadways)cannothandletheadditionalcapacityofa
fullclosureofRobertStreet.Thisideawasdroppedfromfurtherconsideration.

Description

Advantages

Closenonsignalized
intersectionsduring
constructioninthevicinity

27

Canconstructhalfata
timevs.onequarterata
time
Improvedtrafficflowon
mainline
Removesturningconflicts

Disadvantages

Lossofaccess
Additionalvehiclethrough
signalizedintersection
Emergencyresponsetimes
mayincrease

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:

Baselineassumes15dayclosurethisideaassumesclosureuntilmajorityofworkiscompleted(non
bituminousidea).Designconsiderationtoincreasethelengthofclosures.

Description

Advantages

Useaseparatecontractto
relocateutilities

28

Disadvantages

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
4

SameasIdea22

Description

Advantages

Streamlinetheapprovalprocess
tobeginconstructionearlier
within2014

29

Abilitytohaveletting
occurearlierintheyear

Disadvantages

Streamlineapprovalmay
missitemsresultingin
changeorders

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
1

Justification/Comments/Disposition:
Notpossibleunderthecurrentreview/approvalprocess.ThebaselineistocompletetheplansASAP.
Thisideawasdroppedfromfurtherconsideration.

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation26
September1013,2013

Description

Advantages

Provide(secure)contractor
stagingareas

30

Levelsthebidding
environment

Disadvantages

Nonenoted

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
3

DesignConsideration

Description

Advantages

Allowtheuseofreclaimed
materialforClass5materialor
othermaterials
(bedding/borrow)

31

Lowercost
Greenfootprint

Disadvantages

Mayrequirerelaxationof
standardspecs
Mayrequireastockpile
locationwithinclose
proximity

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Justification/Comments/Disposition:

Rating:
3

DesignConsideration

Description

Advantages

Conductaprebidmeetingto

discusstheprojectwiththeplan
holders

32

Buildsabetterrelationship
betweenthecontractor
andtheagency

Disadvantages

Nonenoted

Mainline
Operations

Local
Operations

Maintainability

Construction
Impacts

Environmental
Impacts

Project
Schedule

Rating:
4

Justification/Comments/Disposition:
CombinewithIdeas9,13,14.

RobertStreetImprovements
ValueEngineeringStudyReport

Evaluation27
September1013,2013

Recommendations
TheVERecommendationsarepresentedaswrittenbytheteamduringtheVEStudy.Whiletheyhave
beeneditedfromtheVEreporttocorrecterrorsorbetterclarifytherecommendation,theyrepresent
theVETeamsfindingsduringtheVEStudy.Thefollowingtableisasummaryofallrecommendations
generatedandtheirimpacttotheproject.
Table6SummaryofRecommendations
#

Description

CostSavings

Schedule
Savings

Performance

$0.20M

12weeks

9%

UseTrafficBarrels

Contractor/BusinessWeeklyMeetings

None

None

3%

3a

RelocateUtilitiesFirst

N/Q

6months

11%

3b

RiskMitigationSeparateUtilityContract

N/Q

N/Q

9%

InnovativeContracting

N/Q

6months

11%

Total

$0.20M

NQ=Notquantifiableatthistime
The cost comparisons reflect a difference or delta between the baseline idea and the VE
Recommendation. As the project progresses, these values can be updated to reflect actual
implemented results. These values shown have been adjusted by 10% to reflect the additional
cumulativecostsof:
Table7CostEstimateMarkups
Markup

Percentage

MiscellaneousItemAllowance

5%

Mobilization

5%

TotalMarkup

10%

PerformanceAssessment
As the VE Team developed recommendations, the performance of each is rated against the baseline
concept.Changesinperformancearealwaysbasedupontheoverallimpacttothetotalproject.Once
performance and cost data have been developed by the VE Team, the net change in value of the VE
recommendationscanbecomparedtotheoriginaldesignconcept.
Inordertocompareandcontrastthepotentialforvalueimprovement,individualrecommendationsare
comparedtothebaselineprojectforallattributes.Forthisexercisethebaselinewasgivenascoreof5.
TheresultingvalueimprovementscoresallowawayforMnDOTtoassessthepotentialimpactoftheVE
recommendationsontotalprojectvalue.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations28
September1013,2013


Table8ValueMatrix
TH952A,RobertStreetImprovementsSP190884
Attribute

Attribute
Weight

Concept
Baseline

MainlineOperations

26.2

14.3

10

Total
Performance

131

131

131

3a

131

3b

131

131

131

131

131

3a

131

3b

131

131

71

71

71

3a

71

3b

71

71

71
100

86

3a

100

100

100

Baseline

24

24

24

3a

24

14.3

3b

ProjectSchedule

4.8

3b

EnvironmentalImpacts

Baseline

ConstructionImpacts

Baseline

14.3

Maintainability

Baseline

26.2

LocalOperations

PerformanceRating
1

24

24

Baseline

71

86

71

3a

100

3b

86

100

Understanding the relationship of cost, performance, and value of the project baseline and VE
recommendationsisessentialinevaluatingVErecommendations.Comparingtheperformanceandcost
suggestswhichrecommendationsarepotentiallyasgoodasorbetterthan,theprojectbaselineconcept
intermsofoverallvalue.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations29
September1013,2013


Table9ValueMatrixResults
OVERALLPERFORMANCE

Performance
(P)

%Change
Performance

%
Cost
Change
(C)
Cost

%Value
Improvement

Baseline

500

EliminateTemporaryBarrier

543

9%

$15.1

1%

35.88

10%

Contractor/BusinessWeekly
Meetings

514

3%

$15.3

0%

33.55

3%

557

11%

$15.3

0%

36.34

11%

3a RelocateUtilitiesFirst

$15.3

Value
Index
(P/C)

32.62

3b

RiskMitigationSeparate
UtilityContract

543

9%

$15.3

0%

35.41

9%

InnovativeContracting

557

11%

$15.3

0%

36.34

11%

Recommendations
The results of this study are presented as individual recommendations to the original concept or
baseline.
Eachrecommendationconsistsofasummaryofthebaseline,adescriptionoftherecommendation,a
listing of its advantages and disadvantages, and a brief narrative that includes justification, sketches,
photos,assumptionsandcalculations(whereapplicable)asdevelopedbytheVETeam.
Performancemeasuresarecalculatedbyrating,onascaleof1to10,theoverallprojectagainsteachof
the weighted criteria to arrive at a total score (rating times weight, and totals for all criteria added
together).Thedifferencebetweentherecommendationandthebaselineisexpressedasapercentage.
ThecostcomparisonsreflectacomparablelevelofdetailasintheestimateprovidedtotheVETeam.

DesignConsiderations
In addition to the recommendations above, the VE Team generated a number of ideas that they felt
wereimportantenoughtobedocumentedandshouldbefurtherconsideredbytheProjectTeam.

For the 2014 and 2015 construction seasons, sign the bypass route only once, cover signs in
winter.
Conductaconstructabilityreviewusingretiredcontractors.
Cutbackthestagingdetails,andletthecontractordeterminethetrafficcontrolbaseduponthe
performancespecificationswouldrequirelumpsumtrafficcontrol.
Utilize to the extent possible the existing signal systems for temporary signals. Guys can be
hungbetweenpoles;signalsandotherresourcesmaybereusedinatemporaryconfiguration.
Construct the project in two stages, eliminating the 3rd stage, and utilize monolithic curb to
reduce excavation. Using monolithic curb may reduce some excavation to construct the
median. This idea was moved to further evaluation and development. After evaluation and
reviewofthecrosssections,itwasdeterminedthatexcavationtoconstructthemedianandfix
thecrownormovethepivotpointwillstillbeneeded.Sinceagutterpanisnotneededonthe
high side of the roadway, B6 curb was considered. The cost difference between B6 curb and
B612 is only $1 per linear foot so this idea was lowered to a 3 and moved to a design
consideration.
Useajointutilitytrenchforallthedryutilitiesunderthesidewalk.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations30
September1013,2013

ClosenonsignalizedintersectionsduringconstructioninthevicinityBaselineassumes1to5
day closure. This idea assumes closure until majority of work is completed (non bituminous
idea).Thiswillincreasethedurationoftheclosures.
Identifyandsecurecontractorstagingareas.
AllowtheuseofreclaimedmaterialforClass5materialorothermaterials(bedding/borrow)
Afterinvestigatingthisidea,itwasdiscoveredthatthebaselineconditionleavesthedecisionof
use of reclaimed materials open for the contractor if they can achieve the standard of the
material. The design assumes that some of the reclaim could be used for sidewalk bedding
(embankment)buttheamountofmilledbituminousismuchlargerthanwhatisneededonthe
project.Storageofthematerialsuntilneededisalsoanissue.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations31
September1013,2013


Thispageisleftintentionallyblank

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations32
September1013,2013

VERecommendationNo.1
UseTrafficBarrels

IDEANO.

Baseline
Precast concrete barrier will be placed along the length of the work zone within each stage, to
separatetheworkersfromtraffic.

Recommendation
Replacetheconcretebarrierwithtrafficbarrels.

Advantages

Disadvantages

Reducescost

Reducesconstructionduration
Easiertoshifttraffic
Easiertoadjustaccessthroughtheworkzone
tolocalbusinesses

Nopositiveseparationbetweenworkersand
traffic

CostSummary

Cost

Baseline

$0.18M

Recommendation

$0

CostSavings

$0.18x10%markup=$0.20M
FHWAFunctionalBenefit

Safety

Operations

Environment

Construction

Other

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations33
September1013,2013

VERecommendationNo.1
UseTrafficBarrels

IDEANO.

Discussion/Sketches/Photos

Figure5Workersplacingtrafficbarrier
Withtheremovalofthebarrier,themovementsofbothgeneraltrafficandthoseofthecontractor
are improved by allowing the constraints of the work zone to be adjusted much more easily to
accommodateindividualmovements.Indoingthis,accesstothelocalbusinessaccessismaintained
atahigherlevel.

Figure6Workersmovingtrafficbarrels
Besidesacostsavingsforusingtrafficbarrelsinsteadofconcretebarriertherewillalsobesavingsin
contract duration because barrels can be quickly set up and reset without any specific equipment
needs.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations34
September1013,2013

VERecommendationNo.1
UseTrafficBarrels

IDEANO.

Assumptions/Calculations

Portableconcretebarrier:$14.16/lin.ft.use$15
Relocateportableconcretebarrier:$3.17/lin.ft.use$4
o Relocation of barrier between stages in each construction season for shifting traffic
fromonesideoftheroadtotheother.

traffic
**PricesfromtheAverageBidPricesforAwardedProjects,EnglishUnits,Spec.Year05

FromRSMeanstheaveragepriceforatrafficbarrelis$30eachwiththecosttoresetandremove
fromtheprojectincludedwithinothertrafficcontrollaborcosts.
For a 2530 MPH posted speed barrels are typically placed 40 apart on tangents and 20 apart on
tapers.Halfoftheprojectlengthisapprox.1.25milesor6,600LF.
6,600LF/40=165barrels.
Assumeanother165barrelsforallofthebusinessaccessandcrossstreetsforatotalof330barrels.

Baseline
ItemDescription

Unit

Unit
Cost

Qty

Recommendation
Total

Unit
Cost

Qty

Total

Year2014Barrier

lin.ft.

2715

$15

$40,725

Year2014RelocateBarrier

lin.ft.

3325

$4

$13,300

Year2015Barrier

lin.ft.

3310

$15

$49,650

Year2015RelocateBarrier

lin.ft.

3925

$4

$15,700

Year2016Barrier

lin.ft.

4025

$15

$60,375

Year2016RelocateBarrier

lin.ft.

3345

$4

$13,380

TrafficBarrels

Each

330

$30

$9,900

Baseline

$193,130

Recommendation

$9,900

CostSavings

$183,230

Totals

VERecommendationNo.1
UseTrafficBarrels
RobertStreetImprovements
ValueEngineeringStudyReport

IDEANO.

Recommendations35
September1013,2013


PERFORMANCEMEASURES
Performance

AttributesandRatingRationaleforRecommendation
MainlineOperations

Rating

Nochangetobaseline

LocalOperations

Rating

Nochangetobaseline

Maintainability

Rating

Nochangetobaseline

Reducescost
Reducesconstructionduration
Easiertoshifttraffic
Easiertoadjustaccessthroughtheworkzonetolocalbusinesses
EnvironmentalImpacts

Nochangetobaseline

131

5
26.2

131

131

5
14.3

Contribution

71

70

Rating

7
14.3

Weight

Contribution

71

100

Rating

5
4.8

Weight

ProjectSchedule

131

Weight

ConstructionImpacts

5
26.2

Weight
Contribution

Weight
Contribution

Baseline Recommendation

Thisshouldreducetheoverallconstructionduration

Contribution

24

24

Rating

6
14.3

Weight
Contribution

TotalPerformance:

71

86

500

544

NetChangeinPerformance:

9%

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations36
September1013,2013

VERecommendationNo.2
Contractor/BusinessWeeklyMeetings

IDEANO.

20

Baseline
City/State provides a business liaison to keep businesses informed of schedule and construction
progress.

Recommendation
This recommendation is to have the contractor designated someone, most likely the foreman or
superintendent,whowillgiveweeklyupdatestobusinessownersoftheexpectedworkforthatweek.

Advantages

Disadvantages

Provides an outreach to local businesses


duringconstruction
Allows the businesses to schedule
staff/deliveriesaccordingly
Buildsarelationshipbetweencontractorand
thebusinesses

Schedule changes may cause businesses to


loseconfidenceinContractor

CostSummary

Cost

Baseline

$0

Recommendation

$0

CostSavings

$0(Pricelesstotheinformedbusinessowners!)
FHWAFunctionalBenefit

Safety

Operations

Environment

Construction

Other

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations37
September1013,2013

VERecommendationNo.2
Contractor/BusinessWeeklyMeetings

IDEANO.

20

Discussion/Sketches/Photos
InaMitigationofConstructionImpactsreportdatedFebruary2009preparedbyMnDOT,improving
businessoutreachwasconsideredoneofthemostimportantrecommendations.

Thereportcanbefoundatthefollowinglink:
http://www.dot.state.mn.us/businessimpacts/pdfs/businessimpactsreportfeb2009.pdf

InsteadofamiddlemantheVETeamrecommendsthatthecontractormeetswiththebusinesses
everyMondaymorningtorelaythatweeksscheduleofwheretheconstructionactivitieswillbe.This
canoccuratoneofthebusinesseswithinthatweeksworkarea.
Not all the businesses need to attend every meeting. An email can be sent out to the affected
businessesonFridaylettingthemknowwhereandwhenthemeetingwilltakeplace.Withinthee
mailastreettostreetgenerallocationoftheaffectedbusinessessotheyknowwhetherornottheir
attendancemightbeneeded.
Havingthecontractorconductthesemeetingswillmakethebusinessesfeelliketheyarepartofthe
solution and allow them to make revisions to their business activities (workers, resources and
deliveries)basedupontheinformationobtainedduringtheseweeklymeetings.
Thesemeetingsshouldbekepttoaminimumduration,3045minutesinlength.Thepurposeofthe
meeting is for the contractor to deliver information to the businesses with minimal questions and
answers.Itisnotintendedtobeacomplaintsessionforanyone.
A contract provision would need to be written, it is suggested that the cost of providing these
meetingsisincludedwithintheothercostsoftrafficcontrolitems.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations38
September1013,2013

VERecommendationNo.2
Contractor/BusinessWeeklyMeetings

IDEANO.

20

PERFORMANCEMEASURES
Performance

AttributesandRatingRationaleforRecommendation
MainlineOperations

Rating

Nochangetobaseline

LocalOperations

Rating

Nochangetobaseline

Maintainability

Rating

Nochangetobaseline

Reducedduetocommunication&outreachthroughthesemeetings

EnvironmentalImpacts

Nochangetobaseline

131

5
26.2

131

131

5
14.3

Contribution

71

71

Rating

6
14.3

Weight
Contribution

71

86

Rating

5
4.8

Weight

ProjectSchedule

131

Weight

ConstructionImpacts

5
26.2

Weight
Contribution

Weight
Contribution

Baseline Recommendation

Nochangetobaseline

Contribution

24

71

Rating

5
14.3

Weight
Contribution

TotalPerformance:

71

71

500

514

NetChangeinPerformance:

3%

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations39
September1013,2013


Thispageisleftintentionallyblank

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations40
September1013,2013

VERecommendationNo.3a
RelocateUtilitiesFirst

IDEANO.

24

Baseline
Constructionofthewatermainandsanitarysewerimprovementswillbesplitoverthe2014,2015,
and2016constructionseasons.
Recommendation
Develop an order of work or first order of work contract provision that requires completing the
installation of the water main work along with the proposed sanitary sewer pipe and manhole
replacementspriortostartingworkwithinthatsectionoftheproject.
Advantages

Disadvantages

Water main and sanitary sewer replacement


doesntaffectoverallprojectstaging
Reduces risk for the project stakeholders and
contractor
Above ground temporary water service
connectionsareabigrisktothecontractor
Removes coordination with St. Paul Regional
Water Services from the rest of the prime
contractorsresponsibilities
Eliminates the need for the detour routes
during the first construction season, reducing
thetotalprojectcostsforthedetour
Provides a more palatable project for
contractors and specifically subcontractors
biddingonitemssuchassidewalkandpaving
asthisworkwouldbein2seasonsratherthan
spreadover3
Shouldeliminateanyworkin2017

Some business accesses will be impacted


multipletimes

CostSummary

Cost

Baseline

N/Q

Recommendation

N/Q

CostSavings

N/Q
FHWAFunctionalBenefit

Safety

Operations

Environment

Construction

Other

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations41
September1013,2013

VERecommendationNo.3a
RelocateUtilitiesFirst

IDEANO.

24

Discussion/Sketches/Photos
The 60% design includes construction of the water main and sanitary sewer improvements over 3
yearsduringthe2014,2015,and2016constructionseasons.
2014Season
Watermain andserviceconnectionsatAnnapolis,Hurley,Haskell,Bernard, Stanley,Butler,and
Orme
Replacementofsanitarysewermanholes
2015Season
WatermainSBStation349+20toWentworthAvenue
WatermainLoganAvenuetoOrmeStreet
SanitarySewerSBWentworthAvenuetoThompsonAvenue
2016Season
WatermainSBStation306+00toSBStation321+00
WatermainSBStation328+10toMarieAvenue
WatermainSBStation342+85SBStation349+20
WatermainEastsideofRobertStreetNBStation128+50toMarieAvenue
TheimprovementswillincludeinstallationofnewsanitarymanholesandPVCsanitarypipe,liningof
existing sanitary pipe, and replacement of water main and service connections. The main
constructionactivitiesassociatedwiththiswork(i.e.excavation,backfill,trafficcontrol,etc.)willbe
completedbyacontractorwhiletheactualwaterpipeinstallationandserviceconnectionworkwillbe
completedbyresourcesfromtheSt.PaulRegionalWaterServices.

Figure7BaselineProjectSequencing
This recommendation is to develop an order of work or first order of work contract provision that
wouldrequirecompletingtheinstallationofthenewsanitarysewerpipe,sanitarymanholes,water
main, and service connections prior to starting other work within that section of the project. This
would complete the major utility work in the 2014 season ahead of all other construction activities
andwouldeliminatetheneedforthedetourroutesduringthefirstseasonofconstruction.
Temporary water service will be above ground by connecting users to hydrants and water
connections. Having this many pipes and/or hoses lying on the ground adjacent to and within the
work area will be problematic to the contractor. By removing the water main from the rest of the
workthisreducestheriskofmaintainingtemporarywaterservicetobusinessesandresidents.
Completingthisworkpriortobeginningotheractivitieswillreducesomerisktoprojectbymakingthis
projectmoreappealingtocontractorsbymovingthemainconstructionactivities(i.e.curb,sidewalk,
paving, signals) to two seasons rather than having them spread out over three seasons. Some
RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations42
September1013,2013

VERecommendationNo.3a
RelocateUtilitiesFirst

IDEANO.

24

contractorsmayelecttonotbidontheprojectastheymaynotwanttocommitresourcestoathree
yearprojectandaffecttheirabilitytobidonotherprojectsduringthistimeframe.
Becauseofthedelayedstartofconstruction(June2014)thereisariskthattheworkscheduledfor
2014betweenArlingtontoButlerwontbecompletedpriortowinter,resultinginsomeworksuchas
thebituminouswearingcoursetobecompletedin2015.Thismaycausesomedifficultieswithsnow
removalandotherwintermaintenanceoperations.

Figure8RecommendedProjectSequencing
Thisrecommendationwilllikelybeappealingtolocalbusinesses,eventhoughitwillincludemultiple
timeswhenconstructionactivityinfrontoftheirbusinesses,itwillmaintaincurrenttrafficoperations
along Robert Street through the first year of construction. This recommendation will also likely be
appealingtothetransitauthority.
Construction on sidewalks and other items could begin once the work zone for the water main has
movedfarenoughdownRobertStreet.Thereshouldbeasufficientdistancebetweenworkzoneso
thatthereisnooverlapofsigningandothertrafficcontrolitems.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations43
September1013,2013

VERecommendationNo.3a
RelocateUtilitiesFirst

IDEANO.

24

Assumptions

Dailyproductionrateforwatermaininstallationincludesexcavation,pipeinstall,andbackfilling
ofthetrench(asprovidedbyProjectTeam).Thisworkonthemainlinescouldbeinexcessof200
linear feet per day depending on conflicts with other utilities (per discussions with St Paul
RegionalWaterServices).
Dailyproductionrateforserviceconnectionsincludesexcavationandinstallationofthepipefrom
themaintothelocationofthenewserviceconnectionandinstallationofthemeter/valves/etc.
associatedwiththenewconnection(basedevelopedusingRSMeans,reducedbasedonspecific
projectworkandpreviousconstructionexperience)
Dailyproductionrateforfirehydrantsinstallationincludesexcavationandinstallationofthepipe
fromthemaintothenewhydrantlocationandplacementofthenewhydrant(basedeveloped
usingRSMeans,reducedbasedonspecificprojectworkandpreviousconstructionexperience)
Daily production rate for sanitary sewer installation includes excavation, pipe install, and
backfillingofthetrench.
Daily production rates assume installation of new sanitary manholes will be approximately two
days, including all excavation, installation, backfilling and compaction, and paving. The daily
production for replacing existing manholes will be approximately 2 to 3 days, including
excavation,removalanddisposaloftheexistingmanholes,installationandconnectionofthenew
manhole, backfilling and compacting, and paving. Additional time was incorporated in the
productionrateduetotheexcavationdepthsrequired.
Testingofthenewpipecanbecompletedwithinthecontractworkingdays.
Trenches can be covered temporarily with steel plates for any new excavations within the
roadwaytoaccommodateinstallationandtestingactivities.
Waterservicecanbemaintainedtoallcurrentcustomerswiththeproposedlocationofthenew
watermain.
Water main piping and service connections will be installed and tested by the St. Paul Regional
WaterServices.
Installationofthesanitarysewerandwatercomponentsoftheprojectasthefirstorderofwork
will allow this work to be completed in the short 2014 season and will allow the contractor to
complete the remaining hardscaping, stormwater, and roadway improvements in the 2015 and
2016seasons,eliminatingworkinthe2017season.
Identifyingthisworkasfirstorderwillmakethejobmoreappealingtosubcontractorsasthework
willbeconfinedtoseasonsratherthan3plus.Theoverallprojectcostisapproximately$20M,
withtheworkspreadover3to3.5years;thismaymaketheprojectunappealingtocontractors
resultinginaminimalnumberofbidders.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations44
September1013,2013

VERecommendationNo.3a
RelocateUtilitiesFirst

IDEANO.

24

Calculations
The following tables were developed based on the information contained in the 60% Contract
Drawings and includes approximate lengths of piping derived from scaling the pipe locations as
identifiedinthedrawings.
Table10WaterMainConstruction
Location
Beginning
End
MendotatoCarol
306+02

320+89

Carol
CaroltoEmerson
328+14

382+93

128+65
130+73
Marie
EmersontoWyoming
389+35

Fire
Hydrants
(each)

WaterMain

402+41

Stanley
Bernard
Haskell
Hurley
Annapolis
ProjectLimits
103+86
238+03

(linearfeet)

1487

105

5479

208
160

1306

60
60
60
60
120

Service
Connections
(each)

58

17

Production
Rate

Time

100LF/DAY
4EA/DAY
100LF/DAY
100LF/DAY
100LF/DAY
100LF/DAY
100LF/DAY

(workingdays)

15
2
1

55
15
2
2

13
4
1
1
1
1
1

1EA/DAY
Total

45
157

100LF/DAY
4EA/DAY
100LF/DAY
100LF/DAY
4EA/DAY
100LF/DAY
100LF/DAY

45

Table11SanitarySewerConstruction
Location
Beginning

End

Sanitary
Sewer

New
Manholes

Replace
Manholes

Production
Rate

Time

(linearfeet)

(each)

(each)

(workingdays)

WentworthAvenuetoThompsonAvenue
157+30

169+22

2380

100LF/DAY

24

19

1EA/3DAYS

38

11

1EA/2DAYS

11

Total

73

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations45
September1013,2013

VERecommendationNo.3a
RelocateUtilitiesFirst

IDEANO.

24

Total working days based on installation activities as indicated above is 230 based on a linear
installation approach and does not account for concurrent work activities. The total working days
requiredtocompletethisworkwillbelessasthewatermainandsanitarysewerpipeinstallationscan
occur concurrently; however, the work will have to be scheduled so there is not conflicting traffic
controlorworkzoneareas.

Totalpotentialworkingdaysforwatermainandsanitarysewerinstallation:
Mobilization~5days
Watermain,Hydrant,&ServiceConnection~155days
SanitarySewerandManholes~73
RoadwayCleanupandRestoration~10days

TotalWorkingDays=5+155+73+10=243days

Totalconstructiondurationinmonths:
Assumesalldays,exceptSundaysarecountedasworkingdays
(243days)(26days/month)=9.3Months

Assumesalldayseachmontharecountedasworkingdays
(243days)(30days/month)=8.1Months

There would be other minor work activities included in this work to repair sidewalk and driveways
where installation of the new main impacts these, but this work can be completed within the
durationsandwillbetemporaryuntiltheRobert StreetImprovement projectcomesthroughinthe
followingyear.

*The number of working days for the water main installation could be reduced by 50% based on a
conversation regarding the daily production rate and installation methods with St Paul Regional
WaterServices.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations46
September1013,2013

VERecommendationNo.3a
RelocateUtilitiesFirst

IDEANO.

24

PERFORMANCEMEASURES
Performance

AttributesandRatingRationaleforRecommendation
MainlineOperations

Rating

Nochangetobaseline

LocalOperations

Rating

Nochangetobaseline

Maintainability

Rating

Nochangetobaseline

Water main and sanitary sewer replacement doesnt affect overall


projectstaging
Reducesriskfortheprojectstakeholdersandcontractor
Abovegroundtemporarywaterserviceconnectionsareabigriskto
thecontractor
RemovescoordinationwithSt.PaulRegionalWaterServicesfromthe
restoftheprimecontractorsresponsibilities
Eliminates the need for the detour routes during the first
constructionseason,reducingthetotalprojectcostsforthedetour
EnvironmentalImpacts

Nochangetobaseline

131

5
26.2

131

131

5
14.3

Contribution

71

71

Rating

7
14.3

Weight

Contribution

71

100

Rating

5
4.8

Weight

ProjectSchedule

131

Weight

ConstructionImpacts

5
26.2

Weight
Contribution

Weight
Contribution

Baseline Recommendation

Couldeliminateanyworkin2017
Provides a more palatable project for contractors and specifically
subcontractorsbiddingonitemssuchassidewalkandpavingasthis
workwouldbein2seasonsratherthanspreadover3

Contribution

24

71

Rating

Contribution

TotalPerformance:

14.3

Weight

71

100

500

544

NetChangeinPerformance:

14%

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations47
September1013,2013


Thispageisleftintentionallyblank

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations48
September1013,2013

VERecommendationNo.3b
RiskMitigationSeparateWaterMainContract

IDEANO.

22

Baseline
Constructionofthewatermainimprovementswillbesplitoverthe2014,2015,and2016construction
seasons.

Recommendation
Develop,advertiseandletaseparateconstructionprojectspecificallyfortheinstallationofthewater
mainassociatedwiththeRobertStreetImprovementProjects.Thisisaresponsestrategytotherisk
thattherightofwaywillnotbeacquiredbytheprojectlettinginApril2014andthattheprojectwill
bedelayeduntiltherightofwaycertificationisapprovedbyFHWA.
Advantages

Disadvantages

Water main installation doesnt affect overall


projectstaging
Reducesriskfortheprojectstakeholdersandthe
Contractor
Temporary service connections are a big risk to
thecontractorandothercontractwork

Separate contract allows work to begin on


Robert Street prior to the rightofway
certificationbeingcomplete
Removes coordination with St Paul Regional
Water Services from the rest of the prime
contractorsresponsibilities

Some business access locations will be


impactedmultipletimes
Coordination with two contractors when
the rest of the Roberts Street
Improvementprojectbegins
Twocontractstoadminister

CostSummary

Cost

Baseline

N/Q

Recommendation

N/Q

CostSavings

N/Q
FHWAFunctionalBenefit

Safety

Operations

Environment

Construction

Other

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations49
September1013,2013

VERecommendationNo.3b
RiskMitigationSeparateWaterMainContract

IDEANO.

22

Discussion/Sketches/Photos
The 60% design includes construction of the water main replacement over 3 years during the 2014,
2015,and2016constructionseasons.
2014Season
ConnectionsatAnnapolis,Hurley,Haskell,Bernard,Stanley,Butler,andOrme
2015Season
SBStation349+20toWentworthAvenue
LoganAvenuetoOrmeStreet
2016Season
SBStation306+00toSBStation321+00
SBStation328+10toMarieAvenue
SBStation342+85SBStation349+20
EastsideofRobertStreetNBStation128+50toMarieAvenue
Theimprovementswillincludereplacementofreplacementofthewatermainandserviceconnections
in various locations along the project corridor; the main construction activities associated with this
work(i.e.excavation,backfill,trafficcontrol,etc.)willbecompletedbyacontractorwhiletheactual
pipe installation and service connections will be completed by resources from the St. Paul Regional
WaterServices.ThiswillrequireclosecoordinationbetweentheprimecontractorandSPRWS.

Figure9BaselineProjectSequencing
This recommendation is to remove the water main construction element from the Robert Street
Improvement project and develop and bid a separate construction project specifically for the
installation of the water main and new service connections. This recommendation is a response
strategyfortheriskthattherightofwaycertificationwillnotbeapprovedbyFHWAintimetobegin
work on the corridor by June 2014. Because of funding requirements and the need to show the
businesscommunitythatworkasstartedtheprojectneedstobeginin2014.
Thiscontractcouldbedevelopedandbidinearly2014,allowingworktobeginonthecorridorpriorto
havingRightofWaycertificationforthefullRobertStreetImprovementProject.Thiscontractcouldbe
managedbytheCityofSt.Paulifthatwouldfacilitatemoreefficientcoordination.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations50
September1013,2013

VERecommendationNo.3b
RiskMitigationSeparateWaterMainContract

IDEANO.

22

Assumptions

Dailyproductionrateforwatermaininstallationincludesexcavation,pipeinstall,andbackfillingof
thetrench(asprovidedbyProjectTeam).Thisworkonthemainlinescouldbeinexcessof200
linearfeetperdaydependingonconflictswithotherutilities(perdiscussionswithStPaulRegional
WaterServices).
Dailyproductionrateforserviceconnectionsincludesexcavationandinstallationofthepipefrom
the main to the location of the new service connection and installation of the meter/valves/etc.
associatedwiththenewconnection(basedevelopedusingRSMeans,reducedbasedonspecific
projectworkandpreviousconstructionexperience)
Dailyproductionrateforfirehydrantsinstallationincludesexcavationandinstallationofthepipe
from the main to the new hydrant location and placement of the new hydrant (base developed
usingRSMeans,reducedbasedonspecificprojectworkandpreviousconstructionexperience)
Awardingaseparatecontracttocompletethewatermainreplacement/installationworkwillallow
theprimecontractortofocusoncompletingthisworkandcoordinationwiththeSt.PaulRegion
WaterServiceswillbecompletedinoneseasonratherthanstretchedover3seasons.
Testingofthenewpipecanbecompletedwithinthecontractworkingdays.
Trenchescanbecoveredtemporarilywithsteelplatesforanynewexcavationswithintheroadway
toaccommodateinstallationandtestingactivities.
Servicecanbemaintainedtoallcurrentcustomerswiththeproposedlocationofthenewwater
main.
Water main piping and service connections will be installed and tested by the St. Paul Regional
WaterServices.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations51
September1013,2013

VERecommendationNo.3b
RiskMitigationSeparateWaterMainContract

IDEANO.

22

Calculations
Thefollowingtablewasdevelopedbasedontheinformationcontainedinthe60%ContractDrawings
andincludesapproximatelengthsofpipingderivedfromscalingthepipelocationsasidentifiedinthe
drawings.
Table12WaterMainConstruction
Location
Beginning

End

Watermain

Fire
Hydrants

Service
Connections

Production
Rate

Time

(linearfeet)

(each)

(each)

(workingdays)

1487

100LF/DAY

15

4EA/DAY

105

100LF/DAY

MendotatoCarol
306+02

320+89

Carol
CaroltoEmerson
328+14

382+93

128+65

130+73

Marie
EmersontoWyoming
389+35

402+41

Stanley

5479

100LF/DAY

55

58

4EA/DAY

15

208

100LF/DAY

160

100LF/DAY

1306

100LF/DAY

13

17

4EA/DAY

60

100LF/DAY

Bernard

60

100LF/DAY

Haskell

60

100LF/DAY

Hurley

60

100LF/DAY

Annapolis

120

100LF/DAY

45

1EA/DAY

45

ProjectLimits
103+86

238+03

Total working days based on installation activities as indicated above is 157 based on a linear
installation approach and does not account for concurrent work activities. The total working days
required to complete this work will vary slightly as some of the service installation and hydrant
installationworkcouldhappenconcurrentlywiththeinstallationofthewatermain.
Totalpotentialworkingdaysforwatermaininstallation:
Mobilization~5days
*Watermain,Hydrant,&ServiceConnection~155days
RoadwayCleanupandRestoration~10days
TotalWorkingDays=5+155+10=170days

Totalconstructiondurationinmonths:
RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations52
September1013,2013

VERecommendationNo.3b
RiskMitigationSeparateWaterMainContract

IDEANO.

22

Assumesalldays,exceptSundaysarecountedasworkingdays
(170days)(26days/month)=6.5Months

Assumesalldayseachmontharecountedasworkingdays
(170days)(30days/month)=5.7Months

There would be other minor work activities included in this work to repair sidewalk and driveways
whereinstallationofthenewmainimpactsthese,butthisworkcanbecompletedwithinthedurations
and will be temporary until the Robert Street Improvement project comes through during the
followingyear.

*The number of working days for the water main installation could be reduced by 50% based on a
conversationregardingthedailyproductionrateandinstallationmethodswithStPaulRegionalWater
Services.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations53
September1013,2013

VERecommendationNo.3b
RiskMitigationSeparateWaterMainContract

IDEANO.

22

PERFORMANCEMEASURES
Performance

AttributesandRatingRationaleforRecommendation
MainlineOperations

Rating

Nochangetobaseline

LocalOperations

Rating

Nochangetobaseline

Maintainability

Rating

Nochangetobaseline

Reduces the total amount of time that construction activities are


goingoninfrontofabusiness

EnvironmentalImpacts

Nochangetobaseline

131

5
26.2

131

131

5
14.3

Contribution

71

71

Rating

7
14.3

Weight
Contribution

71

100

Rating

5
4.8

Weight

ProjectSchedule

131

Weight

ConstructionImpacts

5
26.2

Weight
Contribution

Weight
Contribution

Baseline Recommendation

Thiswillmitigateariskthattheprojectstartisdelayed

Contribution

24

71

Rating

Contribution

TotalPerformance:

14.3

Weight

71

86

500

544

NetChangeinPerformance:

9%

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations54
September1013,2013

VERecommendationNo.4
InnovativeContracting

IDEANO.

9,13,14,32

Baseline
Theprojectwillbeadvertisedusingdesignbidbuildcontractingmethod.

Recommendation
Toreceivethebestvaluefortheprojectincorporateinnovativecontractingmethodswithinthe
designbidbuildprojectdeliverytoreducetheoveralldurationoftheproject.

Advantages

Disadvantages

Innovativecontractingmethods(seenextsection)
Prebidmeeting
o Builds a better relationship between the
contractorandtheagency
o Highlights project/contract requirements that the
Contractor must plan for and consider in bid (i.e.
MOTandTPAR)

CostSummary

Innovative contracting methods


(seenextsection)
Prebidmeeting
o Notamandatorymeeting,soall
Contractorsmightnotattend

Cost

Baseline

N/Q

Recommendation

N/Q

CostSavings

N/Q
FHWAFunctionalBenefit

Safety

Operations

Environment

Construction

Other

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations55
September1013,2013

VERecommendationNo.4
InnovativeContracting

IDEANO.

9,13,14,32

Discussion/Sketches/Photos
State and local transportation agencies (DOTs) are increasingly exploring ways to complete
highway projects faster while meeting stringent cost, quality, and safety performance measures.
DOTsmusttakeintoaccountprojectcharacteristicssuchasprojectsize(cost),type(preservation,
rehabilitation,orreconstruction),andcomplexity(urbanorrural,significanttrafficimpact,number
of project elements) when evaluating innovative contracting options that promote accelerated
projectcompletionorfacilitateachievementofotherperformanceobjectives.
Mostinnovativecontractingmethods changehow DOTsprocureanddeliveraproject,usingthe
traditional designbidbuild delivery approach as the benchmark. Contracting alternatives that
shouldbeconsideredforuseonthisprojectinclude:

Costplustime bidding (A+B) aims to expedite project completion through competitive


bidding on the construction time (days). A+B bidding is used on projects with significant
impacts to motorists, businesses, emergency services or other groups that will be directly
impactedbytheproject.
AlternativeTechnicalConcept(ATC)providesamechanismthatallowsContractorstopropose
changestotheplansduringthebiddingphase.TheATCapproachpromotescompetitionand
theexchangeinnovativeapproachesearlyinthedesignprocess,givingDOTstheopportunity
toselectprovendesignandconstructionsolutionsthatofferthebestvalue.
BestValueContractingallowstheownertoconsiderotherfactorsinadditiontopriceinthe
awardandexecutionofconstructioncontracts.Bestvalueprocurementismostusefulwhen
a project has unique objectives or challenges that may be difficult to meet using traditional
lowbidprocurement.
Lane rental encourages contractors to minimize road user impacts during construction by
restrictinglaneuse.

Becauseofthesignificanceofthebusinessandpedestrianimpacts,itisrecommendedthatapre
bidmeetingbeheldforplanholders.Thefocusofthemeetingwouldbeonconstructionstaging,
maintenanceoftraffic,businessimpactmanagement,TemporaryPedestrianAccessRoutes(TPAR)
andtodiscussinnovativecontractingifamethodisselectedforuseonthisproject.
Information presented will be highlighted areas of the plans/specs regarding these items. It is
important to stress the significance of these items, and to communicate to the Contractor that
communicationwiththebusinesses,aswellasaccessforbusinessesandpedestrians,issomething
theyneedtoincorporateintotheirworkandintheirestimatefortheproject.
Attendance at the prebid meeting should include the Project Engineer, MnDOT Traffic
representative, City of West St. Paul representative, Project Manager, and MnDOT Area
representative.

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations56
September1013,2013

VERecommendationNo.4
InnovativeContracting
Innovative
Contracting
Method
A+B

Description

9,13,14,32

Pros

A+Bbiddingfactorstimepluscosttodetermine
the low bid. Under the A+B method, each
submittedbidhastwocomponents:

Earlier
completionof
project

Adollaramountforcontractitems

Contractor's
schedulemust
minimize
construction
timeanddelays

Bcalendardaysrequiredtocompleteproject
Calendardaysaremultipliedbyaroadusercost,
furnished by the owner, and added to the A
componenttoobtainthetotalbid:
A+(Bxroadusercostperday)=totalbid
Theformulaonlydeterminesthelowestbidfor
award and not the payment to the
contractor. A+B can be an effective technique
to reduce delays for critical projects with high
road use. Contracts incorporate a disincentive
provision assessing road user costs to
discouragecontractorsfromexceedingthetime
bid. Contracts may include an incentive
provision to reward contractors if work is
completed in fewer days than bid. Generally,
MnDOTspecifiesamaximumincentive.
Alternative
Technical
Concept

IDEANO.

The effective use of this concept can align


incentives for both the contractor and the
owner to develop ideas which remove
inefficienciesorconstructabilityproblemsinthe
design, and improve the project by reducing
costs,time,andrisksofadverseoutcomesforall
concerned.
The incentive for an owner to include the
provision for ATC proposals is to encourage
contractor to develop innovations to help
reducecostorscheduleandimprovevalue.The
owner benefits from reduced costs and/or
constructionimpactduration.
Forthisproject,ATCswouldonlybeallowedfor
stagingandmaintenanceoftraffic.MnDOTand
the City would review the proposed ATCs and
respond with: Approved, Not Approved,
ConditionallyApproved,orNotanATC(allowed
bycontract)

RobertStreetImprovements
ValueEngineeringStudyReport

Cons
Contractormust
taketimeto
developa
reliableschedule

Contractchanges
are
magnified;too
manychanges
nullify
Contractormust
advantagesof
coordinatewith
A+B
subcontractorsto
meettime
Moreresources
constraints
mayberequired
forcontract
administration
Moreintense
negotiationsfor
additionalwork
because
timelinessis
critical

Encourage
Contractor
innovationwhich
cansavetime
andcost

ATCapproval
processmightbe
difficultduetoall
thestakeholders
thatmaybe
involved
(MnDOT,City,
SPRWS)
MnDOThasnot
beenableto
implementATCs
onDBBprojects
inthepast
Requires
additional
advertisingtime
Alltrafficcontrol
itemsmustbe
lumpsum

Recommendations57
September1013,2013

VERecommendationNo.4
InnovativeContracting
Innovative
Contracting
Method
A+BandATC

Description
AcombinationofA+BandATCs

IDEANO.

9,13,14,32

Pros

Cons

Encourage
Contractor
innovationwhich
cansavetime
andcost.

Maybetoolate
intheprocessfor
thiscontracting
method.

Potentialforbest
qualified
Contractors
wouldbe
evaluatedhigher
AddingATCs
mayeliminate
someconsofthe
A+Balone.

Involvementwith
Officeof
Innovative
Contractingand
FHWAtypically
beginsat30%
plancompletion

AddingA+Bto
ATCwould
provideincentive
forContractorto
developtime
saving(evenif
notcostsaving)
improvements
BestValue

BestValue is a procurementprocess where price Encourage


and other key factors can be considered in the
Contractor
evaluation and selection process to minimize
innovationwhich
impacts and enhance the longterm performance
cansavetime
andvalueofconstruction.
andcost.
Evaluation criteria must include price and may Potentialforbest
qualified
includetime,staging,andqualifications.
Contractors
wouldbe
evaluatedhigher

Maybetoolate
intheprocessfor
thiscontracting
method.
Involvementwith
Officeof
Innovative
Contractingand
FHWAtypically
beginsat30%
plancompletion

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations58
September1013,2013

VERecommendationNo.4
InnovativeContracting

IDEANO.

9,13,14,32

PERFORMANCEMEASURES
Performance

AttributesandRatingRationaleforRecommendation
MainlineOperations

Rating

Nochangetobaseline

LocalOperations

Rating

Nochangetobaseline

Maintainability

Rating

Nochangetobaseline

Innovativecontractingshouldminimizeconstructionimpacts

Nochangetobaseline

5
26.2

131

131

5
14.3

Contribution

71

71

Rating

7
14.3

Contribution

71

100

Rating

5
4.8

Weight

ProjectSchedule

131

Weight

EnvironmentalImpacts

131

Weight

ConstructionImpacts

5
26.2

Weight
Contribution

Weight
Contribution

Baseline Recommendation

Innovativecontractingshoulddecreasetheconstructionduration

Contribution

24

24

Rating

Contribution

TotalPerformance:

14.3

Weight

71

100

500

557

NetChangeinPerformance:

11%

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations59
September1013,2013


Thispageisleftintentionallyblank

RobertStreetImprovements
ValueEngineeringStudyReport

Recommendations60
September1013,2013

AppendixA
ValueEngineeringRecommendationApprovalForm
Project:
VEStudyDate:

TH952A,RobertStreetImprovementProjectSP190884
September1013,2013

Accept
Reject
Acceptforfurther
review

FHWAFunctionalBenefit

Environment

Construction

Other

Added
Cost
($million)

Operations

Estimated
Savings
($million)

Safety

Reason
(Orusethepagesattheendofthismemo)

UseTrafficBarrels

$0.20

Contractor/BusinessWeeklyMeetings

3a

RelocateUtilitiesFirst
RiskMitigationSeparateUtility
Contract
InnovativeContracting

Totalfor4recommendations

0 $0.20

$0

Totalfor4acceptedrecommendations

0 $0.20

$0

Recommendation

3b
4

Pleaseprovidejustificationifthevalueengineeringstudyrecommendationsarenotapprovedorareimplementedinamodifiedform.
MnDOTisrequiredtoreportValueEngineeringresultsannuallytoFHWA.Tofacilitatethisreportingrequirement,aValueEngineeringRecommendationApprovalFormis
includedintheAppendixofthisreport.Iftheregionelectstorejectormodifyarecommendation,pleaseincludeabriefexplanationofwhy.Pleasecompletetheformand
returnittoMinnieMilkert,MnDOTStateValueEngineer,MS696

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixA61
September1013,2013

SignatureProjectManager

7October2013
Date

JonP.Solberg
Name(pleaseprint)

ReasonforAcceptanceorRejectionofRecommendation
1. Usetrafficbarrels.
Thisrecommendationisacceptableandcanbeeasilyimplementedinthefinaldesignplans.
2. Weeklycontractor/businessownermeetings.
Thisrecommendationisacceptableandwillbemadepartoftheprojectrequirements/specifications.
3. Utilities:
a.
Relocatetheutilitiesfirst(underprojectspecificationsschedule)
b.
RiskMitigationLetaSeparateUtilityContract
TheCityissomewhatconcernedaboutimplementingeitheroftheserecommendationsduetothefollowingfactors:
o

Additionaltemporarypavement,curbandsidewalkrestorationwillbenecessarytoallowtheroadwaytobeopenedastheyfinisheachsection.
Thesecostsarenotbudgetedandwouldnotoccuriftheutilitiesweredoneatthesametimeastheroadway.Itisestimatedtoadd
approximately$500,000totheprojectcosts.
StPaulRegionalWaterServiceshaveindicatedthattheirwatermaincrewsandtemporarywaterservicematerialsmaynotbeavailabledueto
thesheeramountofwatermainworkproposedalreadyin2014.Therearenearly10milesofwatermainreplacementinotherprogrammed
city,county,andstateprojectsin2014.Theabilitytodedicatethetwofulltimecrewsthatwouldbeneededforthiseffortwillbechallenging.
(Note:Theirpolicyisthattheagencycontractorexcavatesthetrenchandbackfills,butSt.PaulWatercrewsactuallyinstallthepipe.)
Businessownerswillbesubjecttomultipleyearsofconstructioninareasthatsewerandwaterarebeingreplaced.Theyhavebeeninformed
previouslythattheywouldonlybeimpactedforoneyear.

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixA62
September1013,2013

Certaintemporaryitemssuchasbituminouscurbandsidewalksaremoresusceptibletowinterdamageduetosnowremovaloperationsand
equipment.
o Iftheadvancebidpackageisdonebyadifferentcontractorthantheroadway,warrantydeficienciescanbecomeanissuebetweencontractors
(i.e.,settlementsoverutilitytrenches,etc.).Often,theretendstobealotoffingerpointingastoifthewarrantyrelateddamageswerecaused
bytheutilitycontractororpavingcontractor.
o Privateutilityrelocationswillbedifficult,astheygenerallyprefertocompletethisworkwhentheroadwayisunderconstructiontoreducetheir
overallconstructioncostsforrestoringpavement,sidewalk,etc.
o Temporarywaterservice(abovegroundhoseconnections)ishighlyweatherdependent.Temporaryservicecanonlybeplacedreliablybetween
May15andNovember1.Anythingpastthosedatesisahigherrisk.Ithasbeendonesuccessfullyoutsideofthesedatesinthepast,butithas
alsofailed(i.e.,frozen/crackedtemporarymainsthatputcustomersoutofwaterfortwoplusdays).Whiletemporarywaterserviceswillbe
neededanyway,duetothelargevolumeofworktobedoneiftheutilitiesareconstructedseparately,itmaynotgetfinisheddueto
temperatureconcernsinthelatefall.
o StPaulWaterisconcernedaboutthewillingnessofthecontractortoplaceanemphasisonthecompletingthewaterinatimelyfashion..
Frequently,St.Paulwatercrewsaresidelinedonaprojectduetotheexcavationcontractorpullingoffofthewaterexcavationtodootherwork,
suchassewerorstorm.Ifone,possiblytwo,fulltimewatermaincrewsaregoingtobededicatedtotheadvanceutilitywork,thenthe
understandingthatthosecrewsshouldworkstraightthroughtheprojectmustbeaddressedintheprojectspecificationsandcontract
management.Theirexperiencehasshownthatthisdoesnothappenaswellasplanned.
o Basedontheaboveconcerns,thisrecommendationisrejected.St.PaulWaterServicesdoesnothavesufficientcrewstoconstructallthewater
mainin2014,additionallytheamountoftemporaryworkmayresultinmorecoststhantimesavingstotheproject.Theonlybenefitthatthe
Cityseesindoingthisistoallowworktoproceedin2014ifthereareanydelaysingettingtheroadwayplanscompletedorapprovedbyMnDot
oriftherearedelaysintherightofwayacquisitionschedule.TheCitywillcontinuetomonitortheprogressoftheplansandapprovalsandif
scheduleslippagebecomesaconcern,theywillreevaluatethisoption.
4. Innovativecontracting
o

TheCitywouldbeagreeabletoexploringalternativebiddingmethods(i.e.,A+BBidding,AlternativeTechnicalConcepts,Incentives/Disincentives,etc.).
TheywouldlookfordirectionfromMnDOTonguidanceonthisitemandforthestandardcontractlanguagethatshouldbeputintothebidding
documentsforthemethodofcontractingselected.TheCitysuggeststhatameetingbescheduledwithMnDotConstructionServicestofurtherexplore
thebenefitsofimplementingalternativebidingoptions.

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixA63
September1013,2013

FHWAFunctionalBenefitCriteria

Eachyear,StateDOTsarerequiredtoreportonVErecommendationstoFHWA.Inadditiontocostimplications,FHWArequirestheDOTstoevaluateeach
approvedrecommendationintermsoftheprojectfeatureorfeaturesthatrecommendationbenefits.Ifaspecificrecommendationcanbeshowntoprovide
benefittomorethanonefeaturedescribedbelow,counttherecommendationineachcategorythatisapplicable.

Safety:Recommendationsthatmitigateorreducehazardsonthefacility

Operations:Recommendationsthatimproverealtimeserviceand/orlocal,corridor,orregionallevelsofserviceofthefacility.


Environment:Recommendationsthatsuccessfullyavoidormitigateimpactstonaturalandorculturalresources.

Construction:Recommendationsthatimproveworkzoneconditions,orexpeditetheprojectdelivery.

Other:Recommendationsnotreadilycategorizedbytheaboveperformanceindicators.

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixA64
September1013,2013

AppendixB
VEStudyAgenda

TuesThurs.:

Fri.:

SP190884ValueEngineeringStudy
TH952A,RobertSt.(fromMendotaRdtoAnnapolisSt.)
TuesdaySeptember10FridaySeptember13,2013

MarylandAve.TruckStation;244EastMarylandAve.;St.Paul,MN55117
WatersEdgeBuilding;1500W.CountyRoadB2;Roseville,MN551133174

ValueEngineeringStudyAgenda
Tuesday,Sept.10:MnDOTMarylandAve.TruckStation
8:00am

WelcomeandIntroductions
OverviewandtrainingofVEProcess
InformationPhase

8:45am

DesignTeamspresentationoftheproject

9:45am

Virtualsitevisit(GoogleEarth)
Whatarethegoalsandobjectives?
Whataretheconstraintsandcontrollingdecisions?
Whataretheassumptions?
Whataretheriskhavebeenidentified?

DefineandWeighPerformanceAttributes
FunctionalAnalysisPhase

10:15am

FunctionalAnalysisdevelopmentandtraining
CreativePhase

10:45am

BegintoBrainstormideastoimprovethevalueoftheproject

Noon

SiteVisitLunchalongtheway

about3:30pm

SiteVisitObservations

4:00am

ContinueSpeculation

5:00pm

Adjournfortheday

Wednesday,Sept.11

(BringLaptopsifyouhavethem)

8:00am

ContinueSpeculationandmoveintoEvaluationPhase
EvaluationPhase

10:00am
Noon

Definetheadvantagesanddisadvantagesoftheideas
Lunch

1:00pm

CompletetheEvaluationPhase

4:30pm

Assignrecommendationstoteammembersfordevelopment

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixB65
September1013,2013


5:00pm

Adjournfortheday

Thursday,Sept.12

(BringLaptopsifyouhavethem)
DevelopmentPhase

8:00am
Noon

Developtheideasthatevaluatedthebestintorecommendations
Lunch

1:00pm

ContinueDevelopmentPhase

4:00pm

Defineandevaluatetheperformanceofrecommendations

5:00pm

Adjournfortheday

Friday,Sept.13:MnDOTWatersEdge
8:00am

VETeamReviewofRecommendations(iftimepermits)
PresentationPhase

9:15am
10:00am
Noon

VETeampracticewalkthroughpresentation
PresentationofVEFindings
Adjourn

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixB66
September1013,2013

AppendixC

VEStudyAttendees
TH952A,RobertStreetImprovements
SP190884
TELEPHONE

2013
September

NAME

10

11

12

13

ORGANIZATION

POSITION/DISCIPLINE

Office

Cell
E-MAIL

Michael Arseneau

MnDOT

Design

Liz Benjamin

MnDOT

Construction

Lynne Bly

MnDOT

Multi-Model Planning

Tiffany Dagon

MnDOT

Traffic

David Juliff

SRF Consulting

Project Manager

(651) 234-7652
michael.arseneau@state.mn.us

elizabeth.benjamin@state.mn.us

RobertStreetImprovements
ValueEngineeringStudyReport

lynne.bly@state.mn.us

tiffany.dagon@state.mn.us
(763) 249-6718
djuliff@srfconsulting.com
(763) 249-6748

Jim Gersema

SRF Consulting

Curtiss Kallio

MnDOT

Construction

Molly Kline

MnDOT

Maintenance

jgersema@srfconsulting.com

curt.kallio@state.mn.us
(651) 234-7909
molly.kline@state.mn.us
AppendixC67
September1013,2013

VEStudyAttendees
TH952A,RobertStreetImprovements
SP190884
TELEPHONE

2013
September

NAME

ORGANIZATION

POSITION/DISCIPLINE

Office

Cell
E-MAIL

10

11

12

13

Blane Long

Josh Metcalf

HDR Engineering

Design/Construction

Minnie Milkert

MnDOT

State Value Engineer

Gina Mitteco

MnDOT

Bikes and Pedestrians

Jenny Morris

MnDOT

Project Management

Almin Ramic

MnDOT

Geometrics

James Rosenow

MnDOT

Flexible Design

HDR Engineering

VE Team Leader

(360) 570-4411

(360) 742-7682

Blane.Long@hdrinc.com
(360) 570-4417

(360) 239-9516

Josh.Metcalf@hdrinc.com
(651) 366-4648

(651) 336-3657

minnie.milkert@state.mn.us

gina.mitteco@state.mn.us

jenny.morris@state.mn.us
(651) 366-4673
almin.ramic@state.mn.us
(651) 366-4673
james.rosenow@state.mn.us

RobertStreetImprovements
ValueEngineeringStudyReport

Matt Saam

City of West St. Paul

Mike Salmanowicz

City of West St. Paul

(651) 552-4130
msaam@cityofwsp.org
Public Works Superintendent

(651) 552-4160

(651) 755-9234

msalmanowicz@cityofwsp.org
AppendixC68
September1013,2013

VEStudyAttendees
TH952A,RobertStreetImprovements
SP190884
TELEPHONE

2013
September
10

11

12

NAME

ORGANIZATION

POSITION/DISCIPLINE

Office

Cell
E-MAIL

13
David Sheen

MnDOT

Traffic

(651) 234-7824
David.sheen@state.mn.us

Jon P Solberg

MnDOT

Project Manager

Darwin Yasis

MnDOT

Geometrics

(651) 234-7729
jon.solberg@state.mn.us
(651) 366-4623
Darwin.yasis@state.mn.us

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixC69
September1013,2013

Thispageisleftintentionallyblank

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixC70
September1013,2013

AppendixD
VEStudyReportOutPresentation

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD71
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD72
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD73
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD74
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD75
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD76
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD77
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD78
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD79
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD80
September1013,2013

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD81
September1013,2013

Thispageisleftintentionallyblank

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixD82
September1013,2013

AppendixE
ValueEngineeringProcess
ValueEngineering(VE)isasystematicprocessusingamultidisciplinaryteamtoimprovethevalueofa
project through the analysis of its functions. The VE process incorporates, to the extent possible, the
values of design; construction; maintenance; contractor; state, local and federal approval agencies;
otherstakeholders;andthepublic.
The primary objective of a VE Study is value improvement. The value improvements might relate to
scope definition, functional design, constructability, coordination (both internal and external), or the
schedule for project development. Other possible value improvements are reduced environmental
impacts,reducedpublicinconvenience,orreducedprojectcost.

PreVEStudy
PriortothestartofaVEStudy,theProjectManager,VETeamLeader,andtheStateValueEngineering
Coordinatorcarryoutthefollowingthreeactivities:

InitiateStudy
o PrepareVEStudyrequest
o Definescope,objectiveandgoalsofthestudy
o Definestudytiming
OrganizeStudy
o ConductPreStudymeeting
o Selectteammembers
o Preelicitrisks(ifapplicable)
o Identifyperformanceattributes(ifapplicable)
PrepareData
o Collectanddistributedata
o Preparecostmodels
o Prepforstudy.

AlloftheinformationgatheredpriortotheVEStudyisgiventotheteammembersfortheiruse.

ValueEngineeringJobPlan
TheValueEngineeringJobPlanwasemployedinanalyzingtheproject.Thisprocessisrecommendedby
SAVEInternationalandiscomposedofthefollowingphases:
InformationTheobjectiveofthisphasewastoobtainathoroughunderstandingoftheprojectsdesign
criteria and objectives by reviewing the projects documents and drawings, cost estimates, and
schedules.
FunctionalAnalysisThepurposeofthisphasewastoidentifyanddefinetheprimaryandsecondary
functionsoftheproject.AFunctionalAnalysisSystemTechnique(FAST)wasusedtoquicklydefinethe
functionsoftheproject.

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixE83
September1013,2013

Creative/Speculation During this phase the team employed creative techniques such as team
brainstormingtodevelopanumberofalternativeconceptsthatsatisfytheprojectsprimaryfunctions.
Evaluation The purpose of this phase was to evaluate the alternative concepts developed by the VE
Teamduringthebrainstormingsessions.Theteamusedanumberoftoolstodeterminethequalitative
andquantitativemeritsofeachconcept.
Development Those concepts that ranked highest in the evaluation were further developed into VE
recommendations. Narratives, drawings, calculations, and cost estimates were prepared for each
recommendation.
PresentationTheVETeampresentedtheirfindingintheformofawrittenreport.Inaddition,anoral
presentationwasmadetotheownerandthedesignteamtodiscusstheVErecommendations.
Implementation/Resolution Evaluate, resolve, document and implement all approved
recommendations.

Figure10ValueEngineeringJobPlan

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixE84
September1013,2013

PerformanceBasedResults
Usingperformanceattributesprocessisanintegralpartofthevalueengineeringprocess.Thisprocess
provides the cornerstone of the VE process by providing a systematic and structured means of
considering the relationship of a projects performance and cost as they relate to value. Project
performance must be properly defined and agreed upon by the stakeholders at the beginning of the
value study. The performance attributes and requirements developed are then used throughout the
studytoidentify,evaluate,anddocumentalternatives.
Introduction
The methodology described herein measures project value by correlating the performance of project
scopeandscheduletotheprojectcosts.Theobjectiveofthismethodologyistoprescribeasystematic,
structuredapproachtostudyandoptimizeaprojectsscope,schedule,andcost.
Value engineering has traditionally been perceived as an effective means for reducing project costs.
Thisparadigmonlyaddressesonepartofthevalueequation,oftentimesattheexpenseofoverlooking
therolethatVEcanplaywithregardtoimprovingprojectperformance.Projectcostsarefairlyeasyto
quantify and compare through traditional estimating techniques. Performance is not so easily
quantifiable.
TheVETeamLeaderwillleadtheteamandexternalstakeholdersthroughthemethodology,usingthe
poweroftheprocesstodistillsubjectivethoughtintoanobjectivelanguagethateveryonecanrelateto
and understand. The dialog that develops forms the basis for the VE Team understanding of the
performance requirements of the project and to what degree the current design concept is meeting
thoserequirements.Fromthisbaseline,theVETeamcanfocusondevelopingalternativeconceptsthat
willquantifybothperformanceandcostandcontributetooverallprojectvalue.
Performancebasedvalueengineeringyieldsthefollowingbenefits:

Buildsconsensusamongprojectstakeholders(especiallythoseholdingconflictingviews)
Developsabetterunderstandingofaprojectsgoalsandobjectives
Develops a baseline understanding of how the project is meeting performance goals and
objectives
IdentifiesareaswhereprojectperformancecanbeimprovedthroughtheVEprocess
DevelopsabetterunderstandingofaVErecommendationseffectonprojectperformance
Develops an understanding of the relationship between performance and cost in determining
value
Uses value as the true measurement for the basis of selecting the right project or design
concept
Provides decision makers with a means of comparing costs and performance (i.e., costs vs.
benefits)inawaythatcanassisttheminmakingbetterdecisions.

Methodology
Theapplicationofperformancebasedvalueengineeringconsistsofthefollowingsteps:
1.

Identify key project (scope and delivery) performance attributes and requirements for the
project

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixE85
September1013,2013


2.
3.
4.
5.

Establishthehierarchyandimpactoftheseattributesupontheproject
Establish the baseline of the current project performance by evaluating and rating the
effectivenessofthecurrentdesignconcepts
Identifythechangeinperformanceofalternativeprojectconceptsgeneratedbythestudy
Measure the aggregate effect of alternative concepts relative to the baseline projects
performanceasameasureofoverallvalueimprovement

The primary goal of value engineering is to improve project value. A simple way to think of value in
termsofanequationisasfollows:

Value

Performance

Cost

Assumptions
Before embarking on the details of this methodology some assumptions need to be identified. The
methodology described in the following steps assumes the project functions are well established.
Projectfunctionsarethewhattheprojectdeliverstoitsusersandstakeholders;agoodreferencefor
the project functions can be found in the environmental documents purpose and need statement.
Project functions are generally well defined prior to the start of the value study. In the event that
project functions have been substantially modified, the methodology must begin a new from the
beginning(Step1).
Step1DeterminetheMajorPerformanceAttributes
Performance attributes can generally be divided between Project Scope components (Highway
Operations,EnvironmentalImpacts,andSystemPreservation)andProjectDeliverycomponents.
It is important to make a distinction between performance attributes and performance requirements.
Performance requirements are mandatory. All performance requirements MUST be met by any idea
beingconsidered.
Performanceattributespossessarangeofacceptablelevelsofperformance.Forexample,iftheproject
wasthedesignandconstructionofanewbridge,aperformancerequirementmightbethatthebridge
must meet all current seismic design criteria. In contrast, a performance attribute might be Project
Schedule which means that a wide range of alternatives could be acceptable that had different
durations.
The VE Team Leader will initially request that representatives from Project Team and external
stakeholders identify performance attributes that they feel are essential to meeting the overall need
and purpose of the project. Usually four to seven attributes are selected. It is important that all
potentialattributesbethoroughlydiscussed.
TheinformationthatcomesoutofthisdiscussionwillbevaluabletoboththeVETeamandtheProject
Owner.Itisimportantthattheattributebediscretelydefined,andtheymustbequantifiableinsome
form.Byquantifiable,itismeantthatauseablescalemustbedelineatedwithvaluesgivenonascaleof
0to10.A0indicatesunacceptableperformance,whilea10indicatesoptimaloridealperformance.
The vast majority of performance attributes that typically appear in transportation value studies have
RobertStreetImprovements
ValueEngineeringStudyReport

AppendixE86
September1013,2013

been standardized. This standardized list can be used as is or adopted with minor adjustments as
required.Everyeffortshouldbemadetomaketheratingsasobjectiveaspossible.
Step2DeterminetheRelativeImportanceoftheAttributes
Once the group has agreed upon the projects performance attributes, the next step is to determine
their relative importance in relation to each other. This is accomplished through the use of an
evaluativetooltermedinthisreportasthePerformanceAttributeMatrix.
This matrix compares the performance attributes in pairs, asking the question: An improvement in
whichattributewillprovidethegreatestbenefittotheprojectrelativetopurposeandneed?Aletter
code(e.g.,a)isenteredintothematrixforeachpair,identifyingwhichofthetwoismoreimportant.
Ifapairofattributesisconsideredtobeofessentiallyequalimportance,bothletters(e.g.,a/b)are
enteredintotheappropriatebox.This,however,shouldbediscouraged,asithasbeenfoundthatin
practiceatieusuallyindicatesthatthepairshavenotbeenadequatelydiscussed.
Whenallpairshavebeendiscussed,thenumberofvotesforeachistalliedandpercentages(which
will be used as weighted multipliers later in the process) are calculated. It is not uncommon for one
attributetonotreceiveanyvotes.Ifthisoccurs,theattributeisgivenatokenvote,asitmadethe
listinthefirstplaceandshouldbegivensomedegreeofimportance.
Step3EstablishthePerformanceBaselinefortheOriginalDesign
Thenextstepistodefinethebaselineasitpertainstoeachperformanceattribute.Thebaselineisthen
givenascoreof5onascaleof0to10foreachattribute.
Step4EvaluatethePerformanceoftheVERecommendations
Once the performance of the baseline has been established for the original design concept, it can be
usedtohelptheVETeamdevelopperformanceratingsforindividualVErecommendationsastheyare
developedduringthecourseofthevaluestudy.ThePerformanceMeasuresformatthebackofeach
recommendationisusedtocapturethisinformation.
Itisimportanttoconsidertherecommendationsimpactontheentireproject,ratherthanondiscrete
components.
Step5ComparethePerformanceRatingsofRecommendationstotheBaselineProject
Thelaststepintheprocessistodeveloptheperformanceratingsfortheoriginaldesignconcept.The
VE Team groups the recommendation into a scenario (or scenarios) to provide the decision makers a
clearpictureofhowtherecommendationsfittogetherintopossiblesolutions.Atleastonescenariois
developedtopresenttheVETeamsconsensusofwhatshouldbeimplemented.Additionalscenarios
are developed as necessary to present other combinations to the decision makers that should be
considered. The scenario(s) of VE recommendations are rated and compared against the original
concept.TheperformanceratingsdevelopedfortheVEScenariosareenteredintothematrix,andthe
summaryportionofiscompleted.Thesummaryprovidesdetailsonnetchangestocost,performance,
andvalue,usingthefollowingcalculations.

% Performance Improvement = Performance VE Strategy / Total Performance Original


Concept
ValueIndex=TotalPerformance/TotalCost(inMillions)
%ValueImprovement=ValueIndexVEStrategy/ValueIndexOriginalConcept

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixE87
September1013,2013

Reporting
FollowingtheVEStudy,theTeamLeaderassemblesallstudydocumentationintothedraft/finalreports:

PublishResultsPrepareadraftandafinalVEStudyReport;distributeprintedandelectronic
copiesasneeded.

The VE Study is complete when the report is issued as a record of the VE Teams analysis and
development work, as well as the Project Teams implementation dispositions for the
recommendations.

RobertStreetImprovements
ValueEngineeringStudyReport

AppendixE88
September1013,2013

You might also like