Professional Documents
Culture Documents
Rev. No
: 0
Page No
: 1 of 41
CLIENT
PROJECT NAME
TUBAN IV PROJECT
OUR PO NO
OUR WO NO
0
Rev. No
Doc. No
Status
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
Prepared
by
Reviewed Approved
by
by
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 2 of 41
1
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
REVISIONS
2 3 4
REMARK
5
SHEET
TABLE OF CONTENT
COVERING SHEET
TABULATION OF REVISED PAGES
TABLE OF CONTENT
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
0
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
1
X
X
X
X
X
X
X
X
X
X
X
REVISIONS
2 3 4
REMARK
5
.333
PROCEDURE
1.
Doc. No
Rev. No
: 0
Page No
: 3 of 41
PURPOSE................................................................................................................6
2.
SCOPE...................................................................................................................6
3.
DEFINITION..............................................................................................................7
3.1.
3.2.
3.3.
Project Schedule.................................................................................................................................................
3.4.
Resources...........................................................................................................................................................
3.5.
Project Budget.....................................................................................................................................................
3.6.
Project Cost.........................................................................................................................................................
3.7.
Cost Control........................................................................................................................................................
3.8.
Current Budget....................................................................................................................................................
3.9.
Posted Cost.........................................................................................................................................................
Total Expense.....................................................................................................................................................
4.
REFERENCE............................................................................................................9
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.
Doc. No
Rev. No
: 0
Page No
: 4 of 41
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 5 of 41
1. PURPOSE
This project execution plan prepared for Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban Project. It is intended to enhance communication and
coordination of project activities between Company and Subcontractor.
The Company is PT SEMEN GRESIK (PERSERO)
The contractor is PT. Tuban Steel Work
This procedure serves as a project guideline for all parties to achieve effective and efficient project
implementation. The primary uses of the project plan are to document planning assumptions and decisions, to
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 6 of 41
facilitate communication among stakeholders, and to document approved scope, cost and schedule baseline.
This
procedure
PT. TUBAN
STEEL
WORK describes the basic and method to be used in controlling the cost through out the project
Fabricator&Engineering
period, to Service
detect the variance by identifying potential problem and delay as early as possible. This procedure
describes the basis and method to be used in controlling the schedule throughout the project period, to detect
the variance by identifying potential problem and delay as early as possible.
2. SCOPE
This procedure covers detail of Project Execution Plan based on the latest project information. This document
is developed to enhance communication and coordination between the participants and/or the company. It
establishes project execution plant with the following item:
Project Schedule
Resources Plan
Project Budged
Project Procedure
Data Collection
Varian Analysis
Corrective Action
Budget Revision
Calculate Forecast To Go
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 7 of 41
Initiation is to determine a baseline for controlling the schedule for engineering, procurement,
construction
PT. TUBAN STEEL
WORK and overall activities, including the progress measurement.
Fabricator&Engineering Service
Data collection is to collect progress and/or status report from engineering, procurement and
construction.
Progress Monitoring is to calculate the progress for engineering, procurement, construction and overall
project.
Varian Analysis is to analyze the difference between plan and actual of every discipline and its impact to
project completion date.
Corrective Action is to perform necessary steps attempting to recover any schedule delay by means of
expediting, accelerating, fast tracking, adding resources.
Forecast the final completion date is to estimate the end date of project completion based on the current
progress achievement by means of CPM scheduling technique or bar charting.
Recovery Schedule is to develop a revised project schedule after the fact that the current progress
achievement slipped the project completion date, using CPM scheduling and cost optimation technique.
Resource Forecasting is to calculate the resource requirement needed to accomplish the remaining
activities.
Re-planning is to revise the project schedule in case there is a major change in scope impacting the
project completion date
Reporting is to prepare updates reports by summarizing the project progress into the reporting format
3. DEFINITION
3.1.
3.2.
3.3.
Project Schedule
The detail-planned dates for performing activities and the planned dates for meeting milestone, used
as a project control tool.
3.4.
Resources
The manpower, equipment and material required for project in achieving its objective and
implementation.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
3.5.
Doc. No
Rev. No
: 0
Page No
: 8 of 41
Project Budget
profit, marketing expenses, corporate cost and contingencies, approved by Vice President and
Operation Manager.
3.6.
Project Cost
The cost required for project implementation.
3.7.
Cost Control
A process of keeping cost within the bounds of budget or standard based upon work actually
performed, including monitoring actual versus budget, variance analysis, integrated cost/schedule
reporting, progress analysis and corrective action.
3.8.
Current Budget
A valid budget at a point in time.
3.9.
Posted Cost
Cost of work completed to date.
3.10.
Committed Cost
Cost of work committed to be done.
3.11.
Total Expense
Posted cost plus committed cost.
3.12.
Actual Cost
Actual cost of work committed to be done to date.
3.13.
Total Actual
Posted cost plus actual cost.
3.14.
Forecast to Go
Predicted cost for finishing the remaining work.
3.15.
Estimated at Completion
Total expense cost plus forecasted to go.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
3.16.
Doc. No
Rev. No
: 0
Page No
: 9 of 41
with main key date(s) in monthly basis. The work package could also be treated as a milestone to
achieve the target at a certain time.
3.17.
3.18.
Work Item
Support to level-1 work unit that covers all activities using PERT method, showing the critical path
and floats in daily basis.
3.19.
3.20.
Progress
Actual work completed divided by total scope of work. Physical progress measurement is determined
on monthly basis at the monthly cut off date for all specific work units and for the overall work, the
weight of each specific work unit being proportional to its cost value
3.21.
Baseline
The original plan ( a project work package or an activity ) plus or minus approved changes. Usually
used with a modifier (e.g., cost baseline, schedule baseline, performance measurement baseline).
4. REFERENCE
These procedure developed refer to the following document :
Quality Manual
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 10 of 41
Upon completion of Internal Kick off meeting, Project Manager (PM) and project team coinciding with
the preparation of Client Kick off meeting will review and complete the Project Execution Plan (PEP),
to ensure its completeness and accuracy for field implementation. In case of limited time to prepare
both Client Kick off meeting and PEP, PM should attempt to accelerate the preparation work.
The schedule described in contract document is defined as Master Schedule and become the original
summarized schedule (level 2 or 3). The amount stated in the contract is known as Contract Price.
The real cost for implementing the project named project budget, is the contract price minus
overhead cost, profit, marketing expenses, corporate cost and contingencies.
5.2.
5.2.1.
Liaison with the Company and obtaining necessary information from the owner and
vendors and feeding in the engineering, procurement and construction section
Coordination developing and compiling all project documents as per the agreed documents
list and coordinating with the Company for approval of all relevant documents
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Fabricator&Engineering Service
Doc. No
Rev. No
: 0
Page No
: 11 of 41
Project Control Manager : who is a manager that has almost all of the project information has
responsibility as follows:
Determine the schedule recovery and re-schedule, together with Project Manager
Project Control Engineer : who is the supporting engineer to Project Control Manager has
responsibility as follows:
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Fabricator&Engineering Service
Doc. No
Rev. No
: 0
Page No
: 12 of 41
Input data into monthly cost summary report and project cost status report
Provide variance analysis and recommend necessary corrective action
Calculate forecast to go
Review the contract and determine the Project Control System such as level of activities,
weight value and progress measurement
Collect the data and other reports regarding the progress and schedule control
Calculate the progress percentage for engineering, procurement and all work discipline
Review the difference between plan and actual, analyze constraints and its impact to
project schedule
5.2.2.
Prepare forecast and/or recovery schedule, resource forecast, re-planning and reporting
Project Communications
5.2.2.1.
Introduction
This section is implemented for correspondence between Company and Subcontractor.
5.2.2.2.
Company correspondence
All formal correspondence to Company will be by Subcontractor transmittal letter.
Drawing submittals, design information submittal, and project progress report will be
prepared by all project section.
5.2.2.3.
Internal Correspondence
For correspondence regarding progress and schedule, subcontractor and vendors will
correspond directly with Project Manager and provide carbon copy to Site Manager.
For correspondence regarding technical design matter, quality control and start-up and
performance testing, subcontractor and vendors will correspond directly with the
Engineering Manager and provide carbon copy to Project Manager.
5.2.2.4.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.2.2.5.
PT. TUBAN STEEL WORK
Fabricator&Engineering Service
Doc. No
Rev. No
: 0
Page No
: 13 of 41
Telephone Communications
Others may use telephone communication to transmit information or to further the
consideration of information. Telephone conversations are not conclusive in them and
must be documented by telephone memoranda if the communication has an official or
significant status. It is not necessary to assign log number to telephone memoranda.
Telephone memoranda will be prepared and distributed to the parties involved in the
telephone discussion with copies to other parties, as required.
5.2.3.
5.2.3.1.
Introduction
Project documents to be controlled include official project correspondence, memoranda,
calculations, drawings, design specifications, test records, manufacturer's material
certifications, manufacture's drawing and other such records. Document control
procedures are based on the project file system developed under the supervision of
Project Control.
5.2.3.2.
Administration
Project Control shall serve as the central point of project document control and shall
process or supervise the processing of documents from outside sources as well as
documents generated from consortium internal distribution or transmitted by
Subcontractor to outside sources. The activities include receiving, application of file
numbers, distributing, expediting and releasing all project documents.
5.2.3.3.
Documents Receipt
Documents may be received from outside sources such as Company, subcontractor and
vendors.
5.2.3.4.
Document Identification
All project mail, including faxes telegrams and package shall be delivered to Project
Control as incoming documents. Project Control shall process the original copy of each
incoming document, other than documents submitted in multiple copies (proposal,
instruction manual, etc.) and the transmittal letter or form for documents submitted in
multiple copies.
Processing shall include stamping document with the project routing stamp, dating the
receipt, marking the appropriate file number and indicating action and information
parties in the space provide on the routing stamp, and making required copies for action
and information parties. All documents should use numbering system as per attachment
5.2.3.5.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 14 of 41
particular attention that the proper file numbers are assigned and the correct party is
PT. TUBAN STEEL WORK
Fabricator&Engineering Service
designated. The complete document package shall be returned to Project Control for
transmittal of the action and information copies, and filling of the original documents.
Project Control shall forward the action copy of the technical documents to Engineering
Manager who is assigned and the correct party is designated. The complete document
package shall be returned to Project Control for transmittal of the action and information
copies, and filling of original documents.
5.2.3.6.
5.2.3.7.
5.2.3.8.
Outgoing Documents
Project Control shall process all outgoing correspondence. Processing shall include
verification of file numbers, preparation of documents for mailing, completion of
Subcontractor internal distribution and distribution of copies to the project file, with
appropriate copies to subcontractor, other parties and Subcontractor Site Manager.
5.2.3.9.
5.2.4.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.3.
Doc. No
Rev. No
: 0
Page No
: 15 of 41
QA / QC Management Plan
5.3.1.
QA Management Plan
5.3.1.1.
Introduction
The subcontractor will issue Project Quality Assurance Plan to assure all material,
equipment, fabrication and installation process fulfill the project requirement by referring
to the Quality System requirement. The Document is model of Project Quality Plan that
will be used by subcontractor during perform The Project.
5.3.1.2.
Purpose
This document will describe The Quality System, and subcontractor to assure the
Project requirement will do activities and Quality Standard will be fulfilled. Referring to
The Quality System of subcontractor will develop Project Quality Plan.
5.3.1.3.
Terminology
Vendor : The companies that appointed by subcontractor and approved by
subcontractor/company to supply part of product and perform part of subcontractor
scope of work or services for this project purpose.
5.3.1.4.
Quality Requirement
as Management
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 16 of 41
audit or review and assist of Project Manager in project review meeting that
attended by Department Manager. Project review meeting will evaluate:
Project QA/QC Manager under controlled by Project Manager will report The
Project Quality System implementation to QA/QC Division Manager.
5.3.1.4.2.
Commitment Management
Management of subcontractor has a commitment to produce qualified products
through:
5.3.1.5.
Quality System
Project Quality Assurance Plan will be supported by management procedure and
detailed by relevant procedures, describe regulation of process control of each
department activities. During performed this project, Project Quality Assurance Plan and
Management Procedure will be controlled by Project Quality Assurance/ Quality Control
Manager (Project QA/QC Manager), Project QA/QC Manager and relevant Department
Manager will develop Project Quality Assurance Plan and relevant procedures.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.3.1.6.
PT. TUBAN STEEL WORK
Fabricator&Engineering Service
Doc. No
Rev. No
: 0
Page No
: 17 of 41
Contract Review
During perform this Project, Engineering Manager will be supported by relevant
Department Manager, have responsibilities to review and verify engineering design
changes. The changes related to the construction activities will be reviewed and
clarified by Site Manager. The clarifications of the changes include all aspect, and not
limited to the commercial aspect, schedule of project, and etc. Project Manager should
approve all deviation or the changes item.
5.3.1.7.
Design Control
5.3.1.7.1.
Responsibilities
Engineering Manager has responsible to control all engineering activities.
5.3.1.7.2.
5.3.1.7.3.
Input Design
Engineering Manager will control and develop all design information from
company, vendor, authorize party and assure that only up to date information will
be used and distributed to relevant department. Design criteria will be fixed refer
to contract requirement and specification.
5.3.1.7.4.
Engineering Manager will approve the design out put to make sure the design
procedure have been followed and approved by authorized personnel and
distributed to other related departments.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 18 of 41
Design Verification
Project Engineering Manager has responsibilities to control and develop the
design verification. The important items that should be confirmed during design
verification are:
5.3.1.7.6.
Construction ability
5.3.1.7.7.
5.3.1.8.
Document Control
Each administration department will control correspondence document. Engineering
Manager will control technical document as drawing, procedure, vendor technical
document. All Department Manager should ensure that only latest revision document or
procedure that will be used as work reference, if prior revision document being used as
reference, this document should be marked Void .
5.3.1.9.
5.3.1.9.1.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.3.1.9.2.
Doc. No
Rev. No
: 0
Page No
: 19 of 41
5.3.1.9.3.
5.3.1.9.4.
Bid. Evaluation
Bid evaluation, purchase order and sub subcontractor were controlled by
consider;
5.3.1.10.
5.3.1.11.
5.3.1.11.1.
Organization
Inspection activities will be performed by personnel that have been qualified
and controlled by Quality Assurance / Quality Control Department.
5.3.1.11.2.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 20 of 41
Inspection and Test Plan will be fitted to identify detail items of inspection
PT. TUBAN STEEL WORK
Fabricator&Engineering Service
5.3.1.11.3.
shipping preparation.
5.3.1.11.4.
5.3.1.11.5.
5.3.1.11.6.
Final Inspection
Inspection and Test of each system will be done by refer to the inspection
planning. Result of inspection should be evaluated to the customer
requirement specification. Final Inspection will be performed after equipment
and/or system completely erected and it become document to release precommissioning.
5.3.1.11.7.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 21 of 41
5.3.1.12.
5.3.1.13.
Review Report
Quality Assurance / Quality Control Manager will arrange these activities mentioned
below:
5.3.1.14.
Review and perform the relevant Inspection item of the corrective action.
Corrective Action
Quality Assurance / Quality Control Manager will identify the condition that cause of
deviation to the Project Quality.
Quality Assurance / Quality Control Manager will arrange the meeting to find sources
and fix the plant to avoid this condition will be happened.
5.3.1.15.
5.3.1.16.
Quality Report
Quality Report Document will be given to the company as Project requirement.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.3.1.17.
PT. TUBAN STEEL WORK
Fabricator&Engineering Service
Doc. No
Rev. No
: 0
Page No
: 22 of 41
Quality Audit
Quality audit for internal subcontractor organization or vendor / sub subcontractor, will
be planed and controlled by Quality Assurance / Quality Control Manager. Result of
audit will be documented by Quality Assurance / Quality Control Manager and reported
to Division QA/QC Manager.
5.3.2.
QC Management Plan
5.3.2.1.
Introduction
Quality Assurance / Quality Control Department will prepare Quality Control guidance of
material and equipments inspection that will be used during fabrication and repair work.
5.3.2.2.
Purpose
Project Quality Control Plan describe work methods and inspection activities as
mentioned on Quality Project requirement. Project Quality control Plan, Inspection &
Test Plan and Quality Control procedure will be prepared to provide inspection activities
as mentioned below:
Arrange
inspection
activities
between
Vendor,
Subcontractor,
Contractor,
Government and third party during fabrication, construction phase and certification
process.
Ensure all test equipments, measurement instruments that will be used during
inspection in valid calibration period
5.3.2.3.
Terminology
5.3.2.4.
Responsibility
Responsibility each member described as follows :
Quality Assurance / Quality Control Manager has responsible:
Ensure that Project Quality Control Plan conform to quality project requirement.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 23 of 41
Inspector : Perform Quality Control activities as mentioned on the Inspection and Test
Plan, including internal test and inspection or witnessed by company, prepare and
review inspection and test record.
Document Control : To assist and support Quality Assurance / Quality Control Manager
in the administration and documentation matter.
5.3.2.5.
5.3.2.6.
Inspection Activities
During performed of inspection activities, SUBCONTRACTOR will refer to The
Inspection and Test Plan, Customer Requirement.
5.3.2.6.1.
Ensure welder personal and NDE operator that involved in this project and
were certified.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 24 of 41
5.3.2.6.2.
Use-as-Is
Repair / rework
Repair / rework was need , for pressure vessel that have been
tested on shop.
Subcontractor will propose corrective action to get company
approval.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.3.2.7.
PT. TUBAN STEEL WORK
Fabricator&Engineering Service
5.4.
Doc. No
Rev. No
: 0
Page No
: 25 of 41
Inspection Report
The subcontractor will use inspection / test form as applied procedure during inspection
activities at shop and site project
5.4.1.
Introduction
The aim of emphasize of the Roll and Financial Management plan is to formulate and
recommend steps to be taken by the Project Manager related to the Integrated Tank Repair
Project, particularly to the preparation of planning, implementation and control. The formulation
of financial management plan could be described as follow.
G OAL
5.4.2.
FINANCIAL VISION
To Support Project Execution
FINANCIAL MISSION
To Provide Working Capital / Financing
For Project Execution
FIGURE SCHEME OF
ROLL AND FINANCIAL
MANAGEMENT
S T R AT E G Y
Professionalisme of
Man Power
Efficiently
Organization
Increase of Service
Competences &
Integrity
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
FINANCIAL FUNCTION
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 26 of 41
5.4.3.
Financial Function
FINANCIAL FUNCTION
SINKIND FUND
FUND ALLOCATION
PERFORMANCE MANAGEMENT
TOTAL PROJECT PLANNING
COST CONTROL
PERFORMANCE MANAGEMENT
SYSTEM AND PROCEDURE
Cash Receiving
Cash Disbursement
Material Receiving
SYSTEM ARRANGEMENT PLAN
Sub Contractor Receiving
Investment Receiving
IMPLEMENTATION
BUDGET
Import Price Calculation
Shipment
Maintenance
Material Usage
Overhead Application
Finish Good
PROJECT MASTER BUDGET
Delivery of Good / Project
Progress Delivery Invoicing
Credit Note
Intern Progress
Closing Order
Overhead Cost Breakdown
PROJECT OPERATIONAL BUDGET
Project Site Cost Breakdown
BASED ON SECTION BUDGET
of Adjustment
Pekerjaan Pabrikasi & Ereksi Struktur Baja BeltMemo
Conveyor
649 BC03 / Correction
IMPLEMENTATION
REALIZATION
Q: Master Design
Detail Design
Shop Drawing
C: Matl Cost
Labour Cost
FOH Cost
Progress, Etc
D: (Delivery)
Progress of
Good Delivery
RISKS
CONTROL
Comply
with Spec
of Quality
Comply
with
Project
Budget
Comply
with
Project
Schedule
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 27 of 41
ADJUSTMENT/REPLANNING
OF BUDGET TO MEET THE
QCD TARGET
NO
CONTROL
/ RESULT
QCD =
PLAN
YES
QCD =
PLANNING
5.5.
5.5.1.
Introduction
The successful of project implementation is depend in to how to manage the risk's during project
execution, so this risks project Management plan is to provide a management to take any
necessary action based on some factors such as:
5.5.2.
Damage factor
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.6.
Doc. No
Rev. No
: 0
Page No
: 28 of 41
Surveying Plan
5.6.1.
Introduction
Surveying plan is all activity that will be done at site before design engineering works is started.
The activity in order to get all data that will be used engineering calculation, transportation
planning, choice of type equipment and others civil works planning.
5.6.2.
5.7.
Management Plan
5.7.1.
Engineering Organization
Engineering Manager shall manage all engineering activities within this project
and responsible to Project Manager.
Discipline Engineer
Engineer shall do the design each discipline under the coordination of Lead Discipline
Engineer.
Field Engineer
Field Engineer shall support construction activities, accommodate all modification done on
site and implemented those modifications to marked drawings will informed to Discipline
Engineer through Engineering Manager.
Draftsman
Draftsman shall make the drawing and coordinated by Discipline Engineer.
5.7.2.
Engineering Communication
This section is implemented for communication among engineering sub-sections. All formal
correspondence with company and other will be by Project Manager transmittal letter.
Engineering Manager will conduct daily meeting to solve problem among sub-sections moreover
in interfacing problem. In case of small problem, Engineers may precede a coordination meeting
among and copy carbon shall be forward to engineering manager.
5.7.3.
Document Control
Administration
Document Control officer also shall act as the central point of engineering document as
well as documents generated from internal subcontractor or transmitted by Company.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 29 of 41
The activities include receiving, application of file number, distributing, expediting and
PT. TUBAN STEEL WORK
Fabricator&Engineering Service
releasing all engineering documents to assure that the document will receiving by
related section in same version.
Documents Receipt
Documents may be received from outside sources such as Company and NA or others.
Document Identification
All engineering mail, including e-mail, telecopy, telegrams and package shall be
identified.
The Document Control shall process the original copy of each incoming document, other than
documents submitted in multiple copies (proposal, instruction manual, etc.) and the
transmittal letter or form for documents submitted in multiple copies.
Identifying shall include stamping document with the engineering routing stamp, dating the
receipt, marking the appropriate file number and indicating action and information parties in
the space provide on the routing stamp, and making required copies for action and
information parties. All documents should use numbering system as per attachment
Document Traffic
The copy of documents transmitted to the responsible action party shall be marked with
the word ACTION and route directly to the action party.
The responsible engineer is responsible to review the document and provide the action
as required. The responsible engineer could get additional information from other Lead
engineer under coordination of the engineering manager.
Outgoing Documents
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 30 of 41
Document Control shall record and forward documents include verification of file
numbers, preparation of documents for mailing, completion of Engineering internal
5.8.
5.8.1.
Introduction
In order to achieve the aim of project, the procurement section shall be divided into four
sub sections as on organization chart.
5.8.2.
Job Description
The aim of this written job description is to clarify all jobs and duties to avoid confusion and
overlap among procurement section.
Procurement Manager
Purchasing Officer
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.9.
Doc. No
Rev. No
: 0
Page No
: 31 of 41
5.9.1.
Job Description
Logistic Manager has responsible for inventory control of material, tools, consumable, and
equipment start from receiving materials etc, up to storage at warehouse.
Warehousing of the material etc, could be indoor / outdoor.
5.9.2.
Inventory Control
Inventory control is arrangement of method material, tools, consumable and equipment in
storage to support site activities I e :
5.9.3.
Warehouse
Indoor warehouse is storage place to protect of material, tools and consumables from weather to
prevent material from damage or corrosive.
All material, tools etc should be identified base on its type & size, prior stored on the racks or put
on the floor according to storage system at warehouse as below
Equipment for large size as panels, pumps, generator power, fittings etc should be stored on the
floor indoor and its gave distance from the floor around 15 cm.
Inflammable material as chemical liquid, painting, gas bottles should be stored at special place.
5.9.4.
Outdoor Warehouse
Outdoor warehouse is open storage place which will use for storing large size of raw material as
pipe, fittings, material profile, cable etc.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 32 of 41
Placement of raw material in outdoor warehouse to be prevent contact with ground and its gave
distance around 20 cm from the ground.
PT. TUBAN STEEL WORK
Fabricator&Engineering Service
5.10.
The contract system will be written in the KKWT form according to the Depnaker
regulation.
Releasing Policies
Labor contract duration is depending upon project time schedule and releasing of contract
employment shall follow applicable Depnaker regulations.
All employee have to fill the absence time card when get in or out of the
office/project area.
Using ID Card
Using Uniform
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 33 of 41
Fabricator&Engineering Service
Oral warning
Exactly warning
Less fee
Accommodation
Accommodation
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 34 of 41
Drivers
Security guards
Office Boys
Helpers
Maids
5.11.
5.12.
Security Plan
Security system is planning for all installation area and material including report and
taking over system.
2.
3.
4.
5.
5.12.2. Facility
1.
Handy Talky
2.
Fire Extinguisher
3.
4.
Pick Up Mobile
5.
Etc
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 35 of 41
5.12.3. Location
PT. TUBAN STEEL WORK 1.
Fabricator&Engineering Service
Office
2.
Project Area
3.
Etc
5.13.
1.
Guard
2.
Patrol
3.
Inspection
4.
Investigation
5.
Warning
6.
Report
5.14.
5.14.1. Introduction
This section describes the management and coordination of the construction work for successful
performance. In accordance with the site condition and to achieve goal of the project, the activity
of construction work shall be performed as parallel job depending on the work area. The Time
Schedule for construction work will follow as per confirmed schedule.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 36 of 41
schedule and other relating data. Construction Engineer shall monitor construction activities and
issue the progress of activities to Site Manager. Before commencement of the erection work
PT. TUBAN STEEL WORK
Fabricator&Engineering Service
some checks list must be conducted at least for the following:
Provide the labors, supervisors and engineers who will be in-charge for
construction.
Provide other documents related to erection work for example: Erection Procedure,
Lifting Procedure, Test Procedure, etc.
All the above documents or activity shall be reviewed and checked by each Supervisor, Safety
Officer and Superintendent.
5.15.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
5.16.
Doc. No
Rev. No
: 0
Page No
: 37 of 41
(detail 90 days window), before the overall detail plan has been completed, especially for the multi
year project. It lists all major activities that must be started and or completed within the three month
time period. For the short period project, PM has authority to determine the necessity of front end
schedule, unless Client request to do so.
PM and Project Team Member collect all related information such as:
Contract Document
Project Goal and Objective
Scope of Services
Work Breakdown Structure
Risk assessment
Limitation and information from each discipline
Subcontractor / vendor schedule
Man-hour estimate from each discipline
Manpower information
Fabrication/installation method
Equipment availability
etc
Each project discipline will breakdown the activities in Mater Schedule by top-down approach into a
detail activities , determine dependencies and estimate the duration for each activities (see Work
Breakdown Structure describing the detail activity for , up to level 3 (sub-system)). Project Control
assisted by each project discipline will summarize the detailed activities and check the front end
schedule then compare the summarized duration with the total duration of a given activities in the
master schedule. Project Manager will review the front end schedule and finalize it for approval , see
attachment.
5.17.
Project Schedule
The purpose of this schedule is to describe the overall project detail plan (schedule level 2), ensuring
the work will be carried out according to the allocated project timeframe. The process to prepare the
project schedule is the same as the preparation of front end schedule. Once the Project Manager
approves the project schedule, it defines as a baseline time used for controlling the project see
attachment.
5.18.
Resources Plan
Project Manager and Project Team Member collect the information as follows:
Project Schedule
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 38 of 41
Construction Equipment : Amount and duration needed for each construction activities (see
attachment )
Definite factors such as resources availability, physical constraint or logistic due to project location,
manpower density, productivity, etc.
Resources Plan Form (see attachment )
Base on the above information, each project discipline shall update manpower, material and
equipment plan for each activities in project schedule.
Project Control assisted by each project discipline will summarize the manpower, material and
equipment into Resources Plan Form. Project Manager will review the Resources Plan Form, and
approve.
5.19.
Project Budget
The project budget which has already been defined by management is now used for internal
purposes. PM should detail the project budget according to the following steps.
Project Manager and Project Team Member collect information such as:
project schedule
Engineering
subcontractor
Direct Manpower
Other Charges
Estimate Summary Form which is the total calculation of all cost estimate for each activities
Based on the above information, Project Control assisted by each discipline will detail the project
budget for each activities and prepare the Project Execution Budget Summary Form. The cost code is
always prefixed with the project number followed by project cost account number.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 39 of 41
Project Manager shall review the Project Execution Budget and finalize for approval.
PT. TUBAN STEEL WORK
Fabricator&Engineering
Service Cash Flow
5.20. Projected
The projected cash flow is used for internal purpose in giving the overall figure of the comparison
between account receivable (payment from Client) and account payable (project costs including
payment to vendor) on a monthly basis. PM should prepare the projected cash flow according to the
following steps.
Project Control collect the information as follows:
Project Schedule
Project Budget
Resources Plan
Contract Term of Payment with Client
Contract Term of Payment with subcontractor
Vendor Quotation or CPM Purchase Order
Contract or Proposal from subcontractor
Contract price with Client
Base on the above information, Project Control shall prepare Projected Cash In Flow with the
following step:
In the absence of a cut off date specified in contract document, Project Control shall
determine the Cut off Date for Monthly Report along the project period and propose to the
Client.
Check the contract document regarding the statement of period time between the issuance
of invoice up to the payment from Client, for example, the payment is at least one month
after the received invoice.
Estimate the overall plan progress in every cut off date base on the schedule and budget.
Estimate the total amount of the invoice in every cut off date and when it will be
paid/transferred by the Client.
Estimate the total cash in flow in every month for every project cost account
Project Control shall also prepare Projected Cash Out Flow with the following steps:
Based on the breakdown of project budget, Project Control shall estimate the cost out for
every item of cost account .
For project management, the value of manpower is to multiply the total man-hour/manmonth by weight rate from those manpower, and the value of expenses is base on project
budget that is distributed each monthly accordance to the schedule.
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 40 of 41
For engineering, the value of manpower is same as manpower of project management and
PT. TUBAN STEEL WORK the value of expense is same as expenses of project management.
Fabricator&Engineering Service
For supplies/material, the value is the percentage of payment (term of payment) by budget
for every material. Check also when it will be paid/transferred by the Client.
For transport, the value is based on project budget that is distributed into each month in
accordance with the schedule of material and equipment.
For subcontract, this is the same as material notice the percentage of payment is depend
on the subcontracts progress in each month.
For site expenses, the value of construction equipment is same as subcontractor, the value
of small tools/consumable is same as supplies and the value of expenses is same as
expenses of project management
For commissioning & start up, the value of personnel is same as manpower, the value of
tools/consumables is same as supplies and the value of expenses is same as expenses of
project management.
Estimate the total cash out flow in every month for every project cost account
Project Control shall summarize the total cash in flow and cash out flow into Projected Cash Flow
Form. Project Manager shall review the Projected Cash Flow and finalize for approval.
5.21.
Project Procedures
Upon completion of Internal Project Kick off meeting, the Project Manager assisted by Project Team
Members will prepare project procedures for internal and Client purpose.
PROCEDURE
Doc. No
Rev. No
: 0
Page No
: 41 of 41
Pekerjaan Pabrikasi & Ereksi Struktur Baja Belt Conveyor 649 BC03
Cement Loading Lokasi Pelsus Semen Gresik Di Tuban