You are on page 1of 1

16th March 2014

Ref. No. swa/vg/gy/2014/0406 /


To:

M/S Nasser Bin Faleh Al Thani Group

Attention:

Sheikh Ahmad Bin Nasser Faleh Al Thani

Project:

Hypermarket B+G+M at South Salwa Rd., Al Rayyan

Subject:

No Payment for Interim Payment Application No.25

Dear Sheikh,

Reference to your letter ref.: PLQ/Hyper/SWA/PM/0393/2014 dated 27th February 2014;


(Copy attached). We are unable to process the Interim Payment no. 25 due to the following
reason;

Deduction of Penalty for Delays: M/S Power Line Engineering Delayed by 289 Days
(as of 31st January 2014) and penalty shall be applied for QR 15,000 per Day (As per
the Clause 10.2 of the Contract Agreement)
15% of Bank Loan Recovery from progress month of November 2013, as agree with
the Owner.

Based up on the above mentioned reason, a negative value of payment has resulted (See
attached assessment)
For your Information and attention
Yours faithfully,

Ghassan Al Yacoub

Deputy General Manager

Cc:

Site, File
PLQ