You are on page 1of 158

SSPC Protective Coatings Inspector Training

and Certification (PCI)


Study Guide

PCI Study Guide- October 2007


Table of Contents
Module One: Protecting Steel from Corrosion: The Role of Protective
Coatings2
Module Two: The Roles of Quality Assurance (QA) and Quality Control (QC)
Inspection Personnel on a Coating Project...7
Module Three: Surface Preparation Methods, Industry Standards, and
Inspection..15
Module Four: Practical Arithmetic for the Coatings Inspector.31
Module Five: Coating Mixing, Thinning, and Application: Equipment Overview and
Inspection Techniques...43
Module Six: Industrial and Marine Protective Coatings and Coating
Systems..62
Module Seven: Specialty Inspection Projects...69
Module Eight: Coating Failures: Investigation Procedures and Case
Studies74
Module Nine: Inspector Safety..77
Module Ten: Navigating Coatings Specification.. 82
Module Eleven: Specification Review and Pre-Construction Conference; Inspection Plan
Development for the Inspection of Fuel Tank Lining Installation..84
Module Twelve: Project Inspection Workshop...85
Appendix A
Quiz Answer Keys....A-1
Appendix B
GlossaryB-1
Appendix C
Arithmetic.C-1

PCI Study Guide- October 2007


Module One: Protecting Steel from Corrosion: The Role of Protective Coatings
Module one explains how coatings protect metals from corroding. Corrosion is a process
where man-made metals give up energy and return to their natural state. Some manmade metals have a stronger propensity to corrode than others, but all man-made metals
corrode eventually. Only four elements need to be present for corrosion to occur: an
anode, a cathode, a metallic pathway, and an electrolyte. While the corrosion of manmade metals cannot be completely halted, it can be controlled. The most widely used
method to prevent/slow corrosion today, particularly on carbon steel, is the application of
high performance coatings. Module One explains how todays high performance
coatings use barrier protection, sacrificial or cathodic protection, and inhibitive protection
to protect modern day steel structures from the inevitable process of deterioration and
decay.
Learning Outcomes
At the completion of this module you should be able to:
- Identify the elements of a corrosion cell
- Describe the corrosion of man-made metals
- Explain how industrial coatings control corrosion
- Describe alternative methods used to protect carbon steel from corrosion
Identify the Elements of a Corrosion Cell
Corrosion will occur when four required elements are present. If any one of the elements
is missing, the corrosion process will not proceed. The required elements, which
compose a corrosion cell are:
1. Anode
2. Cathode
3. Metallic Pathway (connecting the anode and cathode)
4. Electrolyte
Corrosion of Man-made Metals
A metal in its pure form will begin to corrode and revert to its natural state when all of
the elements of a corrosion cell are present. Exposure to air and water are usually enough
to get the process started and the metal surface begins to corrode and oxidize (oxidation
is another term that is sometimes used along with corrosion and simply refers to reaction
with oxygen.)
Explain How Industrial Coatings Control Corrosion
Corrosion of metals really cannot be completely stopped. Slowing down the process as
much as possible is the only option to preserve the metal and this is where protective
coatings play a crucial role. Coatings are considered to function as a protective layer in
three different ways: by providing barrier, sacrificial or inhibitive protection.

PCI Study Guide- October 2007


Describe Alternative Methods Used to Protect Carbon Steel from Corrosion
Cathodic protection can be provided by passive or active means. Passive cathodic
protection can be accomplished by attaching a dissimilar metal directly to a metal
substrate to act as a sacrificial anode to corrode preferentially.
Active cathodic protection can be provided by applying or impressing an electrical
current to the structure.

PCI Study Guide- October 2007


Module One: Protecting Steel from Corrosion: The Role of Protective Coatings
Quiz 1
1. Corrosion is defined as the ________________ of _________________________.
2. Carbon steel _____________________ energy during the corrosion process.
3. The use of ________________ __________________ is the most widely used
method of corrosion control.
4. List four elements of a corrosion cell:
_____________________________
_____________________________
_____________________________
_____________________________
5. Which of the four elements in question 4 does a protective coating prevent from
contacting the steel? __________________________________________________
6. When corrosion occurs, the _____________________ depletes or decays.
7. If a copper pipe is combined to an aluminum pipe without an insulator, which metal
represents the anode?
_____________________________________________________
8. List two dissimilar metals that are intentionally coupled in the protective coatings
industry as a method of corrosion prevention?
________________________ and ____________________________
9. What type of chemical will deteriorate uncoated weathering steel?
_________________________
10. ___________________ pigments form plate-like layers and provide barrier
protection to steel surfaces.
11. What two elements are prevented from contacting steel when a barrier-type coating
is employed? _____________________ and ___________________________
12. Zinc-rich primers protect the steel by _______________ and ________________
protection.
13. Thermal spray metallizing and galvanizing protect the steel by _______________
and ________________ protection.

PCI Study Guide- October 2007


14. Borates, chromates, phosphates and other pigments protect the steel by
_________________.
15. Cathodic protection can be in the form of ______________________
_______________ or __________________ current.
16. ___________________ is considered passive cathodic protection.
17. ___________________ is considered active cathodic protection.
18. Cathodic protection is used in conjunction with ___________________
_________________.
19. _________________ and __________________ are metals that form a protective
oxidation layer.
20. When corrosion occurs, the steel is __________________ energy.

PCI Study Guide- October 2007


Module One: Protecting Steel from Corrosion: The Role of Protective Coatings
Supplemental Reading
-

Corrosion and Coatings: An Introduction to Corrosion for Coatings Personnel


(SSPC Item #98-08)
Corrosion Prevention by Protective Coatings (SSPC Item #00-16)
Value of Coatings (SSPC Item VT-VOC)

PCI Study Guide- October 2007


Module Two: The Roles of Quality Assurance (QA) and Quality Control (QC)
Inspection Personnel on a Coating Project
Module Two compares the roles of QA and QC inspectors on coatings projects. All too
often, the lines between the QC and the QA on a coatings project get blurred. When that
happens, the scope of work and responsibility for that work can get blurred in the
process. This module is designed to clarify the common roles and responsibilities of both
the contractors QC inspector and the Owners QA inspector. This is a textbook: the
way it would work in a perfect world, but it is helpful to know how things could/should
work before getting caught up in the day to day rush of a real world coatings project.
Module Two compares and contrasts the role of the QA and QC inspector on a typical
coatings project. The commonalities will be explored, including understanding the
specification, reviewing the product data sheets (the PDS) and the material safety data
sheet (the MSDS), comprehending the industry standard relevant to the specific project,
documenting hold or checkpoints, understanding paper trails, and taking responsibility
for ethics on the job. Module Two also explores the critical differences in the two roles,
including issues of authority, reporting, testing, and documentation (which again,
depends on the scope of work and the specification). Another issue explored by this
module is the management of nonconformities.
Learning Outcomes
At the completion of this module you should be able to:
- Describe the differences between quality assurance and quality control
- Describe the common duties of quality assurance and quality control personnel
- Describe the purpose and content of a pre-job conference
- Explain the purpose of an inspection procedure/plan
- Explain the importance of ethics of inspection personnel
Describe the Differences Between Quality Assurance and Control
Quality control (QC) is performing necessary observations, testing and documentation
that verifies the work performed meets or exceeds some minimum standard as required
by the project specification. Quality control is the contractors responsibility. Quality
control involves the routine and systematic inspection and tests that are conducted to
verify that each phase of the work (hold point) is in compliance with the specification.
Quality Assurance (QA) is defined as the process to verify that the quality of work
performed is actually what was reported by quality control. Quality assurance is typically
performed by the owner (e.g. facility project engineer) or a third party on behalf of the
Owner.
Describe the Common Duties of Quality Assurance and Control Personnel
Hold point inspections are typically done at:
1. Pre-cleaning
2. Surface Preparation
3. Primer Application
4. Intermediate Coat Application
7

PCI Study Guide- October 2007


5. Top Coat Application
6. Cure
QC inspection should occur first and any non-conforming items identified by QC should
be corrected, re-inspected and accepted by the QC. The QA observations should only
occur after the work (hold point) has been accepted by the QC. The QA should then
verify that the work that the QC accepted meets the requirements of the specification.
Describe the Purpose and Content of a Pre-job Conference
The pre-job conference should provide a review for all parties on the organizational
structure and representatives of each stakeholder. This should include the title and
responsibilities of each person as well as their reporting relationship within the company
or organization.
The pre-job conference should summarize the contractors approach to the project
including: schedule, location(s) of equipment, and manpower estimates.
The pre-job conference should review the specification and sequence of work, address
specification discrepancies, and discuss how QC and QA inspections will be coordinated
and implemented. It should include discussion of preparation of test sections, if required;
adequate lighting; inspector safe access; inaccessible areas; and other project-specific
considerations.
The final phase of the pre-job conference should include a discussion of all required QC
and QA documentation and submission schedules. The Owner should also address the
procedure that should be followed if there are discrepancies in the QC and QA
documentation.
Explain the Purpose of an Inspection Procedure/Plan
Project specifications can often be complex and contain many details unrelated to surface
preparation and painting. As a result, locating the inspection check points can be
cumbersome and time consuming. More consequential, key inspection checkpoints may
be overlooked. The development of an inspection procedure before the project begins
can aid the inspector in identifying the inspection checkpoints and the associated
acceptance criteria.
Explain the Importance of Ethics of Inspection Personnel
Ethics is defined as motivation defined by the ideas of right and wrong. The legal
definition of ethics is of or relating to moral action and conduct; professionally right;
conforming to professional standards.
Regardless of whether the coating inspector is functioning as QC or QA, the inspector
must have a high level of personal integrity and a strong work ethic to provide quality
monitoring of the project and a fair accounting to all involved parties. The inspector
should not impose personal standards of quality or work, and must remain constantly
aware that the criteria for work acceptance are the specification requirements.
8

PCI Study Guide- October 2007


Module Two: The Role of Quality Assurance (QA) and Quality Control (QC)
Inspection Personnel on a Coating Project
Workshop: Ethics
As a group, review each of the scenarios below and discuss and answer the questions.
Have a group spokesperson prepared to discuss your groups answers at the end of the
session.
SCENARIO 1:
You are performing part-time third party Quality Assurance services for the Owner. The
contractor blast cleaned and painted while you were not on-site. When you arrive on-site,
the Owner hands you a piece of paper that says Tuesday, surface preparation OK.
Ambient OK 100 gallons primer applied, OK. He asks you to record this information
on a dated inspection report and to sign it.
Question 1: Do you record the information?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Question 2: If yes, how do record it ethically?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Question 3: If no, what action(s) should you take?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
SCENARIO 2:
You are hired by a Facility Owner to provide third party QA. Youve been assigned to
go out-of-town and are living in the same hotel as the contractors workers. You often see
them in the hotel bar. Every time you are at the bar, the contractor pays for your drinks.
Question 1: Is it okay to accept the free drinks?
_________________________________________________________________________________
_________________________________________________________________________________
9

PCI Study Guide- October 2007


_________________________________________________________________________________
Question 2: If no, how might you prevent this from occurring or handle it ethically?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
SCENARIO 3:
The coating manufacturer is on-site passing out free hats.
Question 1: Is it okay to accept the free hat?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
SCENARIO 4:
Youve been working as the Facility Owners QA on the same out-of-town project with
the same contractor for over a year. You have a good working relationship. Your vehicle
breaks down and you cannot replace it. The contractor allows you to use the company
pick-up truck. He also gives you his credit card to use for gas.
Question 1: What are the potential risks to this arrangement?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Question 2: List 3 potential ethical breaches related to this scenario:
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
SCENARIO 5:
You are the contractors QC. You measure the ambient conditions prior to the start of
painting with an epoxy primer and they comply with the specification. However, during
painting you notice that the weather is changing and obtain additional ambient
measurements that indicate the dew point temperature has now fallen below the surface
10

PCI Study Guide- October 2007


temperature. You advise the foreman, who tells you that his application is underway and
that hes going to finish painting, regardless of the conditions. He tells you to ignore it, to
not record the additional measurements, and just let him finish the job.
Question 1: Should you record the conditions?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Question 2: If yes, what then?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Question 3: If no, why?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Question 4: What other actions should be taken by the QC?
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________

11

PCI Study Guide- October 2007


Module Two: The Role of Quality Assurance (QA) and Quality Control (QC)
Inspection Personnel on a Coating Project
Quiz 2
1. _________________ ___________________ is performing observations and tests, and
documenting that the work meets/exceeds the specification requirements.
2. ________________ ____________________ is the contractors responsibility.
3. ________________ ____________________ is the process to verify the quality of
work performed as reported by quality control personnel.
4. ________________ ____________________ is performed by the ______________ or
a ________________ _____________________ on behalf of the __________________.
5. When an _______________ performs QA with his direct staff, he has a
______________________ _________________________ with the contractor and can
exert control.
6. When an _____________ __________ performs QA for the owner, he does not have
______________________ _________________________ with the contractor and can
only _________________ and document, and advise the __________________ QC.
7. Independent of whether _________________ ______________ personnel are on-site,
the contractor remains responsible for __________________ _____________________.
8. When work is halted for an inspection, it is known as a __________ _____________
inspection.
9. List six common hold point inspections:
_________________________________ _________________________________
_________________________________ _________________________________
_________________________________ _________________________________
10. Which party should inspect the completed work first, QA or QC? ______________
11. If the inspected area is deficient, which party should inspect the surface first after the
rework is completed, QA or QC? _____________________
12. ________ observations and test results typically supersede those of __________.
13. Prior to a pre-construction conference an inspector should ______________ the
______________________________.

12

PCI Study Guide- October 2007


14. List seven topics that should be discussed at a pre-construction conference:
_________________________________ _________________________________
_________________________________ _________________________________
_________________________________ _________________________________
_________________________________
15. An inspection plan can contain three columns, titled as:
_________________________________
_________________________________
_________________________________
16. The content of the acceptance criteria section for an inspection plan comes from the
_________________________________
17. A Work Plan should cover the individual _________________ of a project, including
both _________________________ and ___________________________.
18. A Work Plan is also known as a ____________________ ____________________
_____________________________.
19. One of the most important responsibilities of a coatings inspector is to
______________ the results of _______________________.
20. Fraudulent documentation, falsification of time/expense reports and acceptance of
gifts in exchange for lenient inspection are ________________ ________________.

13

PCI Study Guide- October 2007


Module Two: The Role of Quality Assurance (QA) and Quality Control (QC)
Inspection Personnel on a Coating Project
Supplemental Reading
- Planning and Specifying Industrial Protective Coating Projects (SSPC Item #04-10)
- The Inspection of Coatings and Linings: A Handbook of Basic Practice for Inspectors,
Owners, and Specifiers, 2nd Edition (SSPC Item #03-14)
- Coating and Lining Inspection Manual (SSPC Item #91-12)

14

PCI Study Guide- October 2007


Module Three: Surface Preparation- Methods, Industry Standards and Inspection
Module three explains the inspection of surface preparation. Inadequate surface
preparation may be the most costly phase of a coating operation, and it is always critical
to the projects success. Surface preparation has a major focus in this training program,
which covers in detail common standards used throughout the industry. The initial phase
of pre-surface preparation and the inspection hold points are covered first, detailing the
problems of weld spatter, edges, and repair areas. SSPC: The Society for Protective
Coatings has developed a series of consensus standards to govern the surface cleanliness
requirements. Currently, there are thirteen consensus standards for surface preparation.
Each of these standards will be explored, including descriptions of what must be removed
from the surface and what may remain on the surface for each standard. In addition to
the surface preparation standards, the training will also focus on means and methods,
including: blast cleaning equipment, a variety of abrasives, wet and dry abrasive blast
cleaning, centrifugal blast cleaning, vacuum blast cleaning, hand and power tools, and
waterjetting. The final focal points for Module Three are the common inspection
checkpoints for surface preparation and the methods used to verify adherence to the
specification.
Learning Outcomes
At the completion of this module you should be able to:
- Describe the importance and dual objective of proper surface preparation
- Define the SSPC, NACE, and ISO standards for surface preparation
- Describe common methods used to prepare surfaces for coating
- Describe methods used to control an environment during surface preparation
activities
- Measure and record surface profile
- Evaluate surface cleanliness
Describe the Importance and Dual Objective of Proper Surface Preparation
The purpose of surface preparation is two-fold: to clean and to roughen the substrate
according to the requirements of the specification. Sometimes the methods used to
prepare surfaces for coating application achieve these criteria simultaneously (as with
abrasive blast cleaning), while other times these steps must be performed separately (as
with chemical stripping). In either case, the inspector must treat these as two distinct
acceptance criteria, as the level of cleaning may be adequate, but the roughness may be
insufficient or excessive. Alternatively, the surface roughness may be on target, but the
level of cleaning may be inadequate.
Define the SSPC, NACE, and ISO Standards for Surface Preparation
The SSPC, NACE and ISO surface cleanliness standards prescribe a minimum acceptable
level of cleaning, depending upon the specified degree of cleanliness required. The
standards are known as consensus documents that are created by industry experts for
inclusion in coatings specifications. They are not laws or regulations, but they become
contract law once they are invoked in a specification for a coatings project. There are
currently thirteen SSPC surface cleanliness standards. SSPC and NACE have jointly
15

PCI Study Guide- October 2007


published seven of them; SSPC is the sole publisher of the remaining six. The written
standards for surface cleanliness are contained in Volume 2 of the SSPC Painting
Manual, Systems and Specifications and are available for individual download from
www.sspc.org. ISO currently has seven surface cleanliness standards. These standards
define the level of cleaning required, and many of them are accompanied by visual guides
that an inspector can use to verify that the minimum level of cleaning has been achieved.
Describe Common Methods used to Prepare Surfaces for Coating
Surface preparation methods employed by a painting contractor or facility owner can
range from simple solvent cleaning to hand and power tool cleaning, dry and wet
abrasive blast cleaning, chemical stripping, waterjetting and other more non-traditional
methods such as sponge jetting and cryogenic blast cleaning using dry ice pellets. The
degree of cleaning required by a given project specification is dependent on the service
environment (the environment the coating must perform in), the coating system and the
intended service life of the coating once installed.
Describe Methods used to Control an Environment During Surface Preparation
Activities
The measurement of air temperature, relative humidity, dew point temperature, and
surface temperature is usually associated with coating application. However, if the air
temperature and relative humidity are such that moisture from the air condenses on the
surface during final surface preparation, the surface may flash rust. Therefore, it is
important to verify that the temperature of the surface is at least 3C (5F) higher than the
temperature of the dew point, to preclude airborne moisture from condensing on the
surfaces.
These values (surface temperature and dew-point temperature) can be obtained using
sling or battery-powered psychrometers in conjunction with US Weather Bureau
Psychrometric Tables and surface temperature thermometers, or can be obtained using
direct read-out electronic psychrometers equipped with surface temperature probes. The
step-by-step use of this instrumentation is described below. It is important that the
inspector not rely on prevailing weather conditions from a local service (e.g., airport
weather station) as conditions at the project site and the specific work area can vary
considerably. Ambient conditions should be measured and recorded prior to initiating
final surface preparation and at 4-hour intervals thereafter, unless conditions appear to be
declining. In this case, more frequent checks may be required. If surface preparation
work will be done inside a facility, tank or inside of a containment, then the prevailing
ambient conditions inside of the areas (at the actual location of the work) should be
assessed. The location, date, time of day and the condition of air temperature, relative
humidity, dew-point temperature and surface temperature should be recorded. However,
since the only operation being monitored is surface preparation, the dew point/surface
temperature relationship is most critical. Typically, there is no specified range for air
temperature and relative humidity during surface preparation operations.

16

PCI Study Guide- October 2007

Measure and Record Surface Profile


Surface profile is defined as the average peak-to-valley depth that is generated by
abrasive impacting the surface at high speed and by the impact created using certain
power tools. By imparting a profile, the surface area is increased, enhancing the adhesion
of the coating system to the surface. While an insufficient surface profile depth may
result in poor coating system adhesion, excessive surface profile may cause pinpoint
rusting and will require significantly more coating to fill all of the valleys of the
surface profile and provide the specified thickness of coating above the peaks of the
surface profile. Therefore, compliance with the minimum and maximum specified
surface profile depth is critical to the success of a coating system.
Factors affecting the depth of the surface profile include (for abrasive blasting) the type,
hardness and size of the abrasive media employed, as well as the hardness of the surface
being prepared. Lesser factors include the distance from the blast nozzle to the surface.
For power tool cleaning, the type of tool and the configuration of the impactors will
oftentimes dictate the depth of the surface profile. Adjusting to changes in profile depth
requirements in specifications is best achieved by selecting a different sized abrasive.
For projects requiring a relatively shallow surface profile depth, a smaller abrasive should
be selected. For projects requiring a relatively deep surface profile, a larger abrasive
should be selected, but may be blended with a smaller abrasive to increase productivity.
Because of the industrys recognition of the importance of surface roughness
characteristics (beyond average surface profile depth), ASTM D7127, Standard Test
Method for Measurement of Surface Roughness of Abrasive Blast Cleaned Metal
Surfaces Using a Portable Stylus Instrument was published in 2005. The standard
describes the procedures for verifying accuracy and using portable stylus-type
instruments to obtain surface characterization data. An inspector may be required to
perform peak count measurements in addition to peak-to-valley depth measurements (if
required by the project specification).
There are four industry-recognized standards for measuring surface profile, including
ASTM D4417, Test Methods for Field Measurement of Surface Profile of Blast Cleaned
Steel; NACE RP0287, Field Measurement of Surface Profile of Abrasive Blast Cleaned
Steel Surfaces Using a Replica Tape; ASTM D7127 Standard Test Method for
Measurement of Surface Roughness of Abrasive Blast Cleaned Metal Surface Using a
Replica Tape; ASTM D7127 Standard Test Method for Measurement of Surface
Roughness of Abrasive Blast Cleaned Metal Surfaces Using a Portable Stylus
Instrument. These methods prescribe how to obtain measurements of surface profile
depth and peak count, but do not provide an acceptance criterion (e.g., the surface
profile shall be 50-88 m [2-3.5 mils]. Therefore, the project specification must
indicate the desired surface profile depth and the minimum peak count (as required).

17

PCI Study Guide- October 2007

Evaluate Surface Cleanliness


There are four visual standards that have been developed for industry use by SSPC. To
select the correct visual standard, simply ask yourself, What does the project
specification require regarding the method of surface preparation? Then select from one
of the four visual standards currently available:
-

SSPC-VIS 1, Guide and Reference Photographs for Steel Surfaces Prepared by


Dry Abrasive Blast Cleaning,
SSPC-VIS 3, Guide and Reference Photographs for Steel Surfaces Prepared by
Power and Hand Tool Cleaning,
SSPC-VIS 4/NACE VIS 7, Guide and Reference Photographs for Steel Surfaces
Prepared by Waterjetting, or
SSPC-VIS 5/NACE VIS 9, Guide and Reference Photographs for Steel Surfaces
Prepared by Wet Abrasive Blast Cleaning.

These visual standards are designed for use as guides. In the event of a dispute, it is the
written surface cleanliness definitions that prevail. Also, the photographs in the standard
will likely not provide an exact match to the surfaces prepared on your project, because
the initial condition of the surface, the abrasive or tool employed, the surface profile,
lighting and other factors can affect the appearance of the surface. Therefore the visual
standards are truly designed as guides. In fact, many specifications now require the
contractor to prepare a project specific cleanliness standard on the actual structure to be
cleaned and coated. The project-specific standard represents the actual initial condition,
the actual abrasive or tool employed, the surface profile depth and other jobsite
conditions. The SSPC visual standards can be used during this process to establish the
minimum acceptable cleanliness level for the specific project. Once established, this area
can be preserved until the surface preparation portion of the project is completed.

18

PCI Study Guide- October 2007

Module Three: Surface Preparation- Methods, Industry Standards and Inspection


Workshop: Case Study

Surface Preparation of the Interior and Exterior of the Sun


Spree Township Elevated Potable Water Storage Tank
Project Description
The Sun Spree Township Municipal Authority (a suburb of Ft. Lauderdale, FL)
commissioned a coating condition survey of their 50 year old elevated potable water
storage tank. The engineering firms report recommended total removal and replacement
of the lining on the interior of the tank, as well as removal of the coating on the exterior of
the tank, which contains both lead and chromium pigmentation in the existing coating. The
exterior surfaces (underside of the bowl) also contain high levels of chloride (range of 50
to 100 g/cm2), which is likely due to the proximity of the tank to the beach front.
Sun Spree Township awarded the surface preparation and coating application work to
Smith Bros. Contracting, a local QP1 certified firm that specializes in industrial surface
preparation and painting. Smith Bros. is responsible for providing a trained specialist to
perform quality control throughout the project. You are employed by Sun Spree
Township as the resident corrosion specialist, and will be performing quality assurance
oversight on the project.
The information provided below was excerpted from the project specification and only
pertains to surface preparation activities:
Abrasive

Recyclable steel grit (conforming to SSPCAB 2 and AB 3)

Surface Cleanliness of Interior Surfaces

SSPC-SP 10/NACE No. 2

Surface Cleanliness of Exterior Surfaces

SSPC-SP 6/NACE No. 3

Cleanliness of Compressed Air

Per ASTM D 4285 (once/shift)

19

PCI Study Guide- October 2007

Minimum Blast Nozzle Pressure

758 KPa (110 psi)

Surface Profile of Interior and Exterior Surfaces

Angular; 50-87.5 microns (2-3.5 mils);


Minimum peak count: 34/cm

Minimum Lighting for Surface Preparation

500 Lux (47 foot-candles)

Minimum Lighting for Inspection

2000 Lux (186 foot-candles)

Environmental Conditions

Surface temperature a minimum of 3C


(5F) above dew point

Maximum Surface Contamination Levels-Interior

Per SSPC-SP12; Level NV-1

Maximum Surface Contamination Levels-Exterior

Per SSPC-SP12; Level NV-2

Surface Dust Quantity Rating

Surface Dust Size Rating

Maximum Time Between Surface Preparation and


Primer Application

8 hours

Work together in your teams to address each of the quality-related issues described
below. Elect a team spokesperson to present your answers to the class and be prepared
to defend them if questioned.

1. As the quality assurance inspector, how would you determine whether the abrasive
the contractor has mobilized on the project site conforms to SSPC-AB3?
20

PCI Study Guide- October 2007

2. The contractor spent extra time preparing the exterior surfaces, and even exceeded
the specified level of cleanliness (approached level SSPC-SP 10). However, the
surface began to rust bloom before the primer could be applied. By coincidence, the
amount of rust bloom did not exceed 33% of the surface. The contractor is claiming
that the surface meets the minimum level of cleanliness required by the specification
and wants to proceed with primer application. The surface preparation-to-primer
application time is within the 8-hour window. Explain how you would respond.

3. The cleanliness of the compressed air was assessed by the quality control specialist
upstream of the moisture and oil extractor. Comment as to whether this test was
performed properly.

4. The blast nozzle pressure was reportedly measured by the quality control specialist
before production blast cleaning was initiated and was recorded as 862 KPa (125
psi). During production abrasive blast cleaning, you ask the quality control
specialist to re-measure the blast nozzle pressure, and the gage read 620 KPa (90
psi). Based on this information, answer the following:
Does the during production pressure reading conform to the specification?

What may be causing the difference in the two pressures?


5. The interior steel surfaces of the tank contain pitting of the steel. Inspection of the
surfaces after abrasive blast cleaning revealed trace amounts of paint residue in the
bottom of the pits. However, the residue is only visible using a 10X illuminated
magnifier. Is the presence of this residue cause for re-blasting of the surfaces?

6. The quality control specialist tested the condition of the recycled abrasive and
recorded that the abrasive samples collected contained 2% of non-abrasive residue.
Does the abrasive meet the requirement for non-abrasive residue under SSPC-AB2?

7. After 5 hours of production blast cleaning on the interior of the tank, the surface
profile depth was measured by the quality control specialist and recorded as 107
m (4.2 mils), with a peak count of 40/cm.
21

PCI Study Guide- October 2007

Does the surface roughness meet the requirements of the project specification?

If no, describe what steps the contractor may take to correct the non-conformity.

If no, describe what the contractor could have done to avoid the non-conformity.

8. The quality control specialist assessed the amount of light inside the tank prior to
surface preparation operations. The amount of light was measured and recorded as
600 Lux (56 foot-candles).

Does this conform to the project specification?

The same amount of light was available when he assessed the surface cleanliness. Is
this acceptable? Explain.

9. The quality control specialist measured the ambient conditions and surface
temperature prior to abrasive blast cleaning. The surface temperature was 2C (3F)
above the dew point, but the conditions appeared to be improving, so the quality
control specialist allowed the contractor to proceed. Was this acceptable? Explain.

22

PCI Study Guide- October 2007

10. The quality control specialist reported the following levels after assessing the
cleanliness of the exterior surfaces. Do the surfaces meet the requirements of the
project specification?

Meets Specification
CHEMICALChemi LLEVEL
cal

Chloride

12 g/cm2

Ferrous Ion

3 g/cm2

Sulfate

None Detected

Yes

No

23

PCI Study Guide- October 2007


Module Three: Surface Preparation- Methods, Industry Standards and Inspection
Quiz 3
1. Preparing a surface for coating application is the most _________ and typically
the most ____________________ step.
2. List five common responsibilities of a coatings inspector relating to surface
preparation:
______________________________
______________________________
______________________________

___________________________
___________________________

3. The two-fold purpose of surface preparation is to _________________ and


____________________the substrate.
4. ____________________and ____________________have prepared a standard
and a recommended practice for measurement of ____________________.
5. ____________________dictates the required surface profile depth.
6. The surface profile or anchor pattern must be ____________________ with the
entire ____________________.
7. List two fabrication defects that may be addressed in a coating specification.
____________________
____________________
8. List three methods that can be used to inspect surfaces for the presence of
grease/oil:
____________________
________________ ____________________
9. ____________________occurs between mating surfaces, while
____________________forms on the surface of the steel.
10. Chemical contaminants like chloride trapped beneath a coating film can cause
____________________blistering, ____________________and
____________________failure.
11. Testing for chemical contamination involves two steps: ____________________
and ____________________.
12. ____________________environments are more conducive to coating
deterioration caused by chemical contamination beneath the coating film than
____________________ environments.

24

PCI Study Guide- October 2007


13. Suggested thresholds for soluble salt concentrations are found in the appendix to
_____________________________________________.
14. The depth and shape of the surface profile generated by abrasive blast cleaning is
determined by the ____________________and the ____________________ of
the surface.
15. Abrasives fall into two general categories, ____________________ and
____________________.
16. SSPC AB 1 categorizes abrasives according to ____________________,
____________________and ____________________.
17. The abrasive cleanliness requirements in SSPC abrasive specifications AB1, AB2
and AB3 are ____________________requirements of the SSPC abrasive blast
cleaning surface cleanliness standards.
18. List four tests that an inspector can perform in the field to verify conformance to
SSPC AB1:
______________________________
___________________________
______________________________
___________________________
19. SSPC AB2 governs the quality of ____________________.
20. Steel grit produces an ____________________-shaped surface profile.
21. Steel shot produces a ____________________-shaped surface profile.
22. List three tests that an inspector can perform in the field to verify conformance to
SSPC AB3:
______________________________
___________________________
______________________________
23. List one test that an inspector cannot perform in the field to verify conformance to
SSPC AB2: ____________________.
24. The diameter of an S330 steel shot abrasive is ____________________.
25. Which abrasive is larger, G25 or G50? ____________________.
26. Centrifugal blast machines often incorporate a blend of
____________________and ____________________abrasives.
27. Wet abrasive blast cleaning is used when ____________________must be
controlled.

25

PCI Study Guide- October 2007


28. High pressure water jetting incorporates pressures from _______ to _____ MPa.
29. Chemical strippers do not remove ____________________or
____________________and will not generate a ____________________.
30. Three methods used to prepare concrete for coating include:
______________________________
___________________________
______________________________
31. SSPC surface cleanliness standards become contract law once they are invoked by
the ___________________.
32. SSPC-SP1, ___________________ is an ___________________requirement of
the SSPC surface cleanliness standards.
33. SSPC-SP2 ___________________ requires the removal of all
___________________& ___________________.
34. SSPC-SP2 requires the use of a ___________________as the inspection tool.
35. SSPC-SP3 ___________________ requires the removal of all
___________________mill scale, rust & ___________________.
36. What is the primary difference between SSPC-SP15, ___________________
and SSPC-SP11, ___________________?
_____________________________________________________.
37. In addition to solvent cleaning ___________________is an indirect requirement
of SSPC-SP3, SP15 and SP11.
38. Which two SSPC surface cleanliness standards invoke a minimum surface profile
requirement? ___________________and ___________________
What is the minimum requirement? ___________________
39. List three possible indirect requirements of the SSPC abrasive blast cleaning
standards:
______________________________
___________________________
______________________________
40. The amount of staining allowed by the SSPC abrasive blast cleaning standards is
based on what area? __________________

26

PCI Study Guide- October 2007


41. SSPC-SP___/NACE No. 4, __________________ requires the removal of all
__________________rust, paint & mill scale.
42. SSPC-SP14/NACE No. ___, ___________________Cleaning allows up to
___% ___________________ rust, paint or mill scale to remain. The amount of
staining is ___________________.
43. The only difference between SSPC-SP ___/NACE No. 3,
___________________ and SSPC-SP10/NACE No. ___,
___________________ is ____________________________.
44. SSPC-SP___/NACE No. 3 allows up to ___% staining to remain on each ___
square inch area.
45. SSPC-SP10/NACE No. ___ allows up to ___% staining to remain on each
___square inch area.
46. SSPC-SP___/NACE No. ___allows no paint, rust, mill scale or straining to
remain.
47. SSPC-SP___/NACE No. ___, level WJ-2 allows up to ___% of the surface to
contain straining or tightly adhering matter.
48. The L in SSPC SP12-WJ-3-L indicates ______is permitted by the
specification.
49. ISO St2, ___________________ requires removal of all
___________________materials.
50. ISO ___, ___________________ allows only stains to remain on the surface.
51. The SSPC/NACE and ISO cleanliness standards prohibit the use of
___________________ when inspecting surface cleanliness.
52. Prior to final surface preparation, it is recommended that the inspector verify that
the ___________________ temperature is at least ___oF (___oC) higher than the
___________________ temperature.
53. Dehumidification equipment ___________________ moisture from the air.
54. List three methods of dehumidification: ___________________,
___________________, ___________________.

27

PCI Study Guide- October 2007


55. Cooling air below the dew point for dehumidification of the air is the
___________________ method.
56. Products that absorb moisture from the air as a means of dehumidification use the
___________________ method.
57. Indicate the procedure for conducting a compressed air cleanliness test, below:
Conduct the test ___________________ stream of ___________________ and
oil separation. Position the air outlet ___ from the collector
Exhaust the compressed air onto the collector for approximately ______.
58. To conduct a vial test, fill a clear container with ___abrasive and an equal
amount of ___________________. Allow the shaken blend to settle for
___________________.
59. The maximum abrasive conductivity according to the SSPC abrasive
specifications is ___ S.
60. The minimum level of lighting for inspection is ___ Lux.
61. The recommended level of lighting for inspection is ___ ft/candles.
62. The visual standard reference G2 SP14 in SSPC VIS 1 indicates:
___________________________________________________.
63. The visual standard reference F SP3 PWB in SSPC VIS 3 indicates:
______________________________________________________
64. The visual standard reference D WJ3 M in SSPC VIS 4/NACE VIS 7 indicates:
__________________________________________________________
65. The visual standard reference C WAB 6 H in SSPC VIS 5/NACE VIS 9
indicates: _______________________________________________
66. The visual standard reference A Sa3 in ISO 8501-1:1988 indicates:
__________________________________________________
67. Surface profile is defined as the maximum ___________________depth.
68. Profile generation ___________________ the surface area of the steel.
69. An increase in peak count reportedly enhances ___________________and a
greater resistance to ___________________.
70. The ___comparator disc is selected for inspection of surface profile when garnet
abrasive is used to perform abrasive blast cleaning.
28

PCI Study Guide- October 2007

71. 3.0SH76 on a comparator disc segment indicates: ___________________.


72. Verify zero-set on a surface profile depth micrometer using a
___________________.
73. The measuring range of X-Coarse replica tape is ___mils.
74. The thickness of the Mylar film on replica tape is ___ mils.
75. Each grade of replica tape is most accurate in the ___ of the range.
76. Complete the following chart:
Parts Per Million Chloride
Amount of Extraction Liquid
Micrograms of Chloride
Area Extracted
Micrograms per cm2 chloride

176
2 mL
___
12.25 cm2
___

77. Complete the following chart:


Conductivity of sample
Conductivity of blank
Net Conductivity of sample

120 S/cm
8.7 S/cm
___

78. Convert 35 S/cm to surface chloride concentration using the formula on Page
3-147.
___________________
79. A pH of 10 is considered ___________________.
80. A pH of 3 is considered ___________________.

29

PCI Study Guide- October 2007

Module Three: Surface Preparation- Methods, Industry Standards and Inspection


Supplemental Reading List
-

Good Painting Practice: SSPC Painting Manual, Volume 1, 4th Edition (SSPC Item
#02-14)

Systems and Specifications: SSPC Painting Manual, Volume 2, 2005 Edition (SSPC
Item #04-13)

Surface Preparation Specifications and Practices (SSPC Item #05-03)

SSPC-VIS 1 Guide and Reference Photographs for Steel Surfaces Prepared by Dry
Abrasive Blast Cleaning (SSPC Item #02-12)

SSPC-VIS 3 Guide and Reference Photographs for Steel Surfaces Prepared by Hand
and Power Tool Cleaning (SSPC Item #04-07)

SSPC-VIS 4 Guide and Reference Photographs for Steel Surfaces Prepared by


Waterjetting (SSPC Item #01-05)

SSPC-VIS 5 Guide and Reference Photographs for Steel Surfaces Prepared by Wet
Abrasive Blast Cleaning (SSPC Item #01-06)

30

PCI Study Guide- October 2007

Module Four: Practical Arithmetic for the Coatings Inspector


Module Four reviews practical math skills used by the coatings inspector. Coating
inspectors frequently need to apply basic math skills to everyday inspections. This
module provides a review of common arithmetic associated with coatings inspection,
including: converting percentages to decimal format; calculating square footages;
calculating volume and converting ounces/gallon to percentage of thinner addition;
converting VOC values; converting temperatures; and converting units of measurement
for surface profile depth and paint thickness (mils to microns and back). A special
session on calculating coating material quantities based on theoretical and practical
coverage rates is included in this module.
Learning Outcomes
At the completion of this module you should be able to:
- Apply practical arithmetic to calculations relating to everyday jobs
Apply Practical Arithmetic to Calculations Relating to Everyday Jobs
Arithmetic can be one of the more challenging aspects of coatings inspection that an
inspector must employ on a project. Those challenged by mathematics simply throw up
their hands and give up, rather than working through the formulas to generate the correct
value(s), or they may rely on others to perform calculations for them. This module
helps inspectors to become more comfortable with mathematics and describes the steps
necessary to perform basic calculations.
An inspector should always be equipped with a working calculator to make the
calculations easier and faster, and to avoid making simple mathematical errors.
Recognize however, that if an incorrect value (or the incorrect form of a value) is
inadvertently entered into the calculator, the answer will be wrong despite using the
correct formula. So take your time and double check all entries. The old phrase says
practice makes perfect and replication helps. If you are unfamiliar with any of the
mathematics described in this module, practice the examples over and over. You can
even substitute your own numbers in the examples to help gain confidence in application
of the formulas. Finally, recognize that there is always more than one way to arrive at the
correct answer. This module describes commonly used methods, but other methods or
procedures may be used, as long as the final answer is the same.

31

PCI Study Guide- October 2007

Module Four: Practical Arithmetic for the Coatings Inspector


Workshop: Arithmetic for Protective Coatings Inspector

Instructions
Using the basic arithmetic skills taught in Module 4, solve each of the Problem Sets
below. Remember to use your calculator to avoid making simple math errors. You may
select the US standard or the metric exercises, depending on the prevailing system used.
Problem Set 1: Averaging Values
You have collected the following surface profile measurements. Calculate the average of
each area, then average all of the areas together.
Area 1
50 microns
75 microns
62 microns

Area 2
40 microns
43 microns
49 microns

Area 3
76 microns
80 microns
57 microns

Area 4
42 microns
58 microns
55 microns

Area 5
44 microns
71 microns
56 microns

Area 1
2 mils
3 mils
2.4 mils

Area 2
1.6 mils
1.7 mils
2 mils

Area 3
3 mils
3.1 mils
2.2 mils

Area 4
1.7 mils
2.3 mils
2.2 mils

Area 5
1.7 mils
2.8 mils
2.2 mils

Average of Area 1
Average of Area 2
Average of Area 3
Average of Area 4
Average of Area 5

______________
______________
______________
______________
______________

Average of all Areas _______________

32

PCI Study Guide- October 2007

Problem Set 2: Averaging Values


You have collected the following coating thickness measurements. Calculate the average of
each area, then average all of the areas together.
Area 1
205 microns
312 microns
199 microns

Area 2
181 microns
233 microns
241 microns

Area 3
305 microns
295 microns
287 microns

Area 4
256 microns
214 microns
277 microns

Area 5
311 microns
298 microns
283 microns

Area 1
8 mils
12.3 mils
7.8 mils

Area 2
7.1 mils
9.2 mils
9.5 mils

Area 3
12 mils
11.6 mils
11.3 mils

Area 4
10.1 mils
8.4 mils
10.9 mils

Area 5
12.2 mils
11.7 mils
11.1 mils

Average of Area 1
Average of Area 2
Average of Area 3
Average of Area 4
Average of Area 5

______________
______________
______________
______________
______________

Average of all Areas _______________

Problem Set 3: Converting Percentages to Decimal Format


A two-coat exterior coating system has been specified and the products have been
delivered to the project site. You have elected to calculate target wet film thickness and
the maximum amount of thinner that can be added to each. The coating manufacturer lists
the volume solids content and the allowable thinner as a percentage. You will need to
convert each of the percentages to decimal.

Allowable percentage of thinner for the primer:


Volume solids content of primer:
Allowable percentage of thinner for the topcoat:
Volume solids content of topcoat:

15%
65%
5%
52%

Decimal Format
_____________
_____________
_____________
_____________

33

PCI Study Guide- October 2007


Problem Set 4: Calculating Area
A cylindrical ground storage tank contains four (4) shell rings. Each shell ring is made
from eight (8) steel plates measuring 3 meters (10 feet) by 7 meters (23 feet). The interior
and exterior of the tank is to be coated (excluding the interior floor and interior ceiling, and
the exterior roof, which all appear to be in good condition). The tank owner has asked you
to verify that the contractor has ordered enough coating, so you will need to first calculate
the total area of the shell rings to be coated. Use the space below to show the steps you
took to arrive at the final answer.
Total area of shell rings to be coated:

________________

Show steps here:

Problem Set 5: Calculating Area


The project specification for surface preparation of steel I beams in the fabrication shop
requires three (3) surface profile measurements every 30 square meters (100 square feet)
of prepared surface. There are two sizes of I beams on the project:
Beam Size A: 0.5 meter (18 inch) flanges (2.54 cm [1 inch] thick)
2 meter (6 foot) web
18 meters (60 foot) beam length
12 stiffeners, each 2 meters (6 foot) x 10 cm (4 inches) wide
Beam Size B: 0.5 meter (18 inch) flanges (2.54 cm [1 inch] thick)
2.5 meter (8 foot) web
24 meters (80 foot) beam length
16 stiffeners, each 2 meters (6 foot) x 10 cm (4 inches) wide
Total square meters (square feet) for Beam Size A: ______________
Total square meters (square feet) for Beam Size B: ______________
If the total project involves 12 beams of Size A and 15 beams of Size B, now many
surface profile measurements are required for the project? ___________________
34

PCI Study Guide- October 2007

Use the space below to show the steps you took to arrive at the answers. You may also
want to draw and label the two beams with the dimensions for each to help visualize the
sizes.

Problem Set 6: Calculating Volume of Coating


A three-component product has been selected for use on a project. Component A is 11
liters (3 gallons) in a 19 liter (5 gallon) container. Component B is 3.8 liters (1 gallon) in a
3.8 liter (1 gallon) container. Component C is 0.5 liter (1 pint) in a 1 liter (1 quart)
container. What is the total volume of coating once all components are combined together?

Problem Set 7: Calculating Volume of Thinner


According to the manufacturers product data sheet for the three-component coating in
Problem Set 6, the coating must be thinned 15%. What is the total volume of thinner that
must be added to the coating?

Problem Set 8: Converting Milliliters/Liter to Percentage


According to the manufacturers product data sheet, the recommended amount of thinner
to add to a coating is 50 milliliters per liter of coating. If the mixed volume of coating is 5
liters, how many milliliters of thinner will be added?
What percentage of thinner will be added to the coating?

35

PCI Study Guide- October 2007


Problem Set 9: Converting Ounces/Gallon to Percentage

According to the manufacturers product data sheet, the recommended amount of thinner
to add to a coating is 13 ounces per gallon of coating. If the mixed volume of coating is 5
gallons, how many ounces of thinner will be added?
What percentage of thinner will be added to the coating?
Problem Set 10: Converting VOC Content
The local air quality regulations for a recoating project do not allow coatings containing
VOC in excess of 2.1 lbs./gallon. The product data sheet that the coating manufacturer
provided for the solvent-borne primer only reports the VOC content in grams per liter,
which is 250 grams/liter. Can the coating be used on the project?

Based on the VOC content reported on the product data sheet, will the contractor be able
to thin the coating?

Problem Set 11: Converting VOC Content


A steel fabrication shop that also performs surface preparation and primer application
work is located in an area with very strict air pollution regulations. Coatings used by the
fabrication shop cannot exceed 375 grams/liter VOC. The shop wants to use a primer that
contains 3.9 lbs./gal. VOC. Can the primer be used by the shop?

36

PCI Study Guide- October 2007


Problem Set 12: Converting Temperature
According to the coating manufacturers product data sheet, the air temperature must be
maintained between 40F and 100F during application. The air temperature is 34C. Can
coating application work continue? After answering yes/no, indicate the actual
temperature in F.

Problem Set 13: Converting Temperature


According to the coating manufacturers product data sheet, the coating storage area must
be maintained between 10C and 49C. The air temperature in the storage area is 125F.
Does the storage temperature conform to the manufacturers requirements? After
answering yes/no, indicate the actual temperature in C.

Problem Set 14: Converting Units Used to Express Coating Thickness and
Surface Profile Depth
The coating specification requires a 2.0-3.5 mil surface profile depth. The actual surface
profile depth ranges from 63.5 to 83.8 microns. Does the area meet the specification?
After answering yes/no, indicate the actual surface profile range in mils.

37

PCI Study Guide- October 2007


Problem Set 15: Converting Units Used to Express Coating Thickness and
Surface Profile Depth
The coating specification requires the primer and intermediate coats to be a combined
thickness of 203-305 microns. The thickness of the combined coats ranges from 6 to 10
mils. Does the area meet the specification? After answering yes/no, indicate the actual
coating thickness range in microns.

38

PCI Study Guide- October 2007


Problem Set 16: Calculating Coating Material and Thinner Requirements
A three-coat system has been specified for protecting a structure estimated to be 2,323
square meters in area. The volume solids content is 75% for the primer, 56% for the
intermediate coat and 46% for the topcoat. The specified thickness is 75-100 microns for
the primer, 125-178 microns for the intermediate coat and 50-75 microns for the topcoat.
The contractor will need to reduce the primer and intermediate coatings by 10% with
Thinner No. 2 and will need to thin the topcoat by 5% using Thinner No. 4. Mixing and
application losses are estimated to be 20% for each coating, and the surface profile is
expected to consume 15% of the primer. Based on this scenario, complete the chart
below:
Inquiry

Enter Answer Here

Quantity of primer required (in liters)


Quantity of intermediate coating required (in liters)
Quantity of topcoat required (in liters)
Quantity of thinner required for primer &
intermediate coatings (in liters)
Quantity of thinner required for topcoat (in liters)

Show the metric version of the formula for calculating coating coverage here:

Show the values/equations you used to arrive at each answer below.

39

PCI Study Guide- October 2007


Problem Set 17: Calculating Coating Material and Thinner Requirements
A three-coat system has been specified for protecting a structure estimated to be 25,000
square feet in area. The volume solids content is 75% for the primer, 56% for the
intermediate coat and 46% for the topcoat. The specified thickness is 3-4 mils for the
primer, 5-7 mils for the intermediate coat and 2-3 mils for the topcoat. The contractor will
need to reduce the primer and intermediate coatings by 10% with Thinner No. 2 and will
need to thin the topcoat by 5% using Thinner No. 4. Mixing and application losses are
estimated to be 20% for each coating, and the surface profile is expected to consume 15%
of the primer. Based on this scenario, answer the questions below:
Inquiry

Enter Answer Here

Quantity of primer required (in gallons)


Quantity of intermediate coating required (in
gallons)
Quantity of topcoat required (in gallons)
Quantity of thinner required for primer &
intermediate coatings (in gallons)
Quantity of thinner required for topcoat (in gallons)

Show the US Standard version of the formula for calculating coating coverage here:

Show the values/equations you used to arrive at each answer below.

40

PCI Study Guide- October 2007


Module Four: Practical Arithmetic for the Coatings Inspector
Quiz 4
1. Average the following set of surface profile measurements: 3.5, 3.7, 2.9, 3.1, 4.0
_____________
2. Convert 39% to decimal format.

_____________

3. Calculate the amount of thinner to add to 10 gallons of mixed coating to be


reduced 20%. _____________
4. Calculate the area of a square that is 4.5 feet x 13.6 feet. _____________
5. Calculate the area of an I-beam that is 40 feet in length, has 12 wide flanges, a
48 web, and 8 stiffeners (4 wide x 48 long). _____________
6. Calculate the exterior surface area of a tank that is 45 feet in height and 90 feet in
diameter.
_________________________________________________________
Calculate the volume of water the tank in Question 6 will hold.
_________________________________________________________
7. Convert 2.4 pounds/gallon VOC to grams/Liter.
_____________________________________
8. Convert 64oF to oC. ______________
9. Convert 275 micrometers to mils _______________
10. Calculate the quantity of primer required to coat 15,000 square feet of blast
cleaned steel, based on the following data:
Specified Dry Film Thickness:
Volume Solids Content:
Mixing/Application Loss Estimate:
Surface Roughness Loss Estimate:
Recommended Thinner Addition:

3-5 mils
84%
25%
20%
One pint per gallon

_________________________________________________________

41

PCI Study Guide- October 2007


Module Four: Practical Arithmetic for the Coatings Inspector
Supplemental Reading List
- Practical Math for the Protective Coatings Industry (SSPC Item #03-05)

42

PCI Study Guide- October 2007


Module Five: Coating, Mixing, Thinning and Application: Equipment Overview
and Inspection Techniques
Module Five explains the inspection of coating mixing, thinning, and application.
Experts claim that poor application, along with inadequate surface preparation, cause the
majority of all industrial coating failures. This module provides an overview of the
various methods used to apply coatings, including conventional (air) spray, airless spray,
HVLP, air-assisted airless spray, and brush & roller. The advantages and limitations of
each method, along with proper technique will be emphasized. Module Five will
continue with the inspection of mixing, thinning, and coating application processes,
including measuring ambient conditions, witnessing and documenting mixing and
thinning procedures, wet and dry film measurements, use of the Tooke Gage (destructive
testing) to determine the thickness of individual layers in a coating system,
pinhole/holiday detection, adhesion, and coating hardness and curing tests.
Learning Outcomes
At the completion of this module you should be able to:
- Describe the procedures associated with proper mixing, thinning, and
application of industrial coatings
- Define the SSPC standards for coating application
- Describe the role of the coating inspector on a coatings project
- Use MSDS and product data sheets to verify safe and proper mixing, thinning,
and application of coatings
- Describe the inspectors role regarding coating material receipt and storage
- Measure and record ambient conditions and surface temperature
- Calculate Wet Film Thickness
- Measure Wet Film Thickness
- Verify accuracy of nondestructive coating thickness gages
- Measure coating thickness using nondestructive gages
- Describe the SSPC standard for measurement of coating thickness
- Measure coating thickness using destructive methods
- Detect pinholes and holidays
- Measure coating adhesion
- Evaluate coating cure
- Measure coating hardness
- Describe methods used to verify intercoat cleanliness
Describe the Procedures Associated with Proper Mixing, Thinning, and Application
of Industrial Coatings
Proper coating mixing procedures are one of the most important steps in the successful
installation of a protective coating system. The procedures for blending single
component materials is straightforward and needs little instruction other than ensuring the
material is homogeneous by mixing all of the settled pigment and solids materials into the
liquid. Conversely, the mixing procedures for multiple component materials can be more
complex, and often requires the individual responsible for mixing the coatings and the
inspector to read and comprehend the product data sheets.
43

PCI Study Guide- October 2007

Similar to mixing, thinning of a coating material is perceived to be rather straightforward


and requires little explanation. However, the type and amount of thinner added to the
coating impacts the volatile organic compound (VOC) content, the target wet film
thickness of the coating, and over thinning or under thinning a coating can adversely
affect the application and performance characteristics. Therefore, thinning of a coating is
an important area to discuss and is equally important to verify that it is done properly.
Transferring the coating materials from the can to the surface can be accomplished in a
number of ways. Factors that should be considered when deciding on an application
method include the size and configuration of the surfaces to be coated, the desired or
required transfer efficiency, the type of coating, environmental regulations, the proximity
to other operations/conditions, the specification and the coating manufacturers
recommendations.
The seven methods of coating application that we will describe in this module include:
1. Brushes, rollers, and daubers
2. Airless spray
3. Conventional (air) spray
4. High Volume Low Pressure (HVLP) spray
5. Air-assisted airless spray
6. Metallized spray
7. Plural component spray
Define the SSPC Standards for Coating Application
SSPC has two main standards that pertain to coating application, including SSPC PA 1
(Shop, Field and Maintenance Painting of Steel) and SSPC PA 2 (Measurement of Dry
Coating Thickness with Magnetic Gages).
Describe the Role of the Coating Inspector on a Coatings Project
The inspectors role in a coating project varies, depending on the requirements of the
specification. The more common checkpoints include:
1. performing materials receipt inspection and documentation
2. witnessing and verifying (documenting) coating mixing and thinning procedures
3. measuring and documenting ambient conditions and surface temperature
4. calculating and measuring wet film thickness
5. measuring dry film thickness nondestructively
6. verifying re-coat times
7. assessing intercoat cleanliness
8. assessing cure
9. assessing coating hardness
10. performing pinhole or holiday detection
11. adhesion testing

44

PCI Study Guide- October 2007


Use MSDS and Product Data Sheets to Verify Safe and Proper Mixing, Thinning,
and Application of Coatings
Coating manufacturers technical bulletins or product data sheets (PDS) contain very
useful information about the products being used on the project. However, the
manufacturer is not limited to which product information they may or may not reveal.
While the PDS typically contains critical information about the content and use of the
coating products, in cases where the PDS and the specification differ (say on the
maximum humidity during application), the specification is the governing document,
except when the owner incorporates the manufacturers recommendations on the PDS
into the specification. When that occurs, the PDS becomes part of the project
specification.
Describe the Inspectors Role Regarding Coating Material Receipt and Storage
Verifying that what was ordered (coating products, coating components, and thinners, if
permitted) was received at the project site in good condition and in the correct amounts is
called a material receipt inspection. This is typically a job for the contractors QC and
although it is not a difficult process, it can prevent a multitude of problems as the job
moves forward. The contractor should also verify that the coating products are properly
stored on the project site prior to use, and should record batch nos. for each component
and thinner.
Measure and Record Ambient Conditions and Surface Temperature
Prior to the mix and throughout the application process, the measurement of ambient
conditions (relative humidity, dew point, air temperature, wind conditions) helps
determine whether the application of the coating can move forward. Often, both the
specification and the PDS will contain information on the conditions required to apply
each specific coating product. If the requirements listed in the project specification differ
from that listed on the PDS, the specification is the governing document. The right
weather conditions for the coating products open the way to a successful application of
the coating. If a coating must have moisture to cure, too little moisture in the air becomes
a problem. Conversely, for some coatings, too much moisture in the air creates a
problem. Warm versus cold air temperature ranges are also important issues. And wind
conditions are important, especially in areas where strong winds are frequently a
problem.
Ambient conditions should be measured at regular intervals both before and throughout
the application process, and anytime the weather conditions appear to be changing.
Perhaps the single most important temperature relationship is the relationship between
the dew point and the surface temperature. To prevent applicators from coating a wet
surface, the surface temperature should be at least 3C (5F) higher than the dew point
temperature. An inspector should not depend on national or regional weather service
information for weather conditions. Conditions must be measured at the correct time at
the exact location where the coating application will take/ is taking place.

45

PCI Study Guide- October 2007


Calculate Wet Film Thickness
Some coating manufacturers list the target wet film thickness, while others do not. But
even when the targeted wet film thickness is listed on the PDS, this thickness will change
if the thinner is added to the product, or when the specified dry film thickness differs
from that on the PDS. It is important for contractors and inspectors to know how to
calculate the target wet film thickness, in order to arrive at the desired dry film thickness.
There are two formulas that can be used to calculate wet film thickness; one for
unthinned coatings and one for coatings that is reduced. The volume solids content of the
coating and the percentage of thinner added to the coating must be known in order to
calculate a wet film thickness.
Measure Wet Film Thickness
Measurement of wet film thickness is typically performed by the applicator, although an
inspector should spot-check and record the measured wet film thickness. A notch-type
wet film thickness gage can be used for this purpose.
Verify Accuracy of Nondestructive Coating Thickness Gages
All coating thickness gages, whether Type 1 (magnetic pull-off) or Type 2 (electronic),
must be verified for accuracy before and after each period of use. Typically, calibration
blocks are used to verify the accuracy of magnetic pull-off gages, while plastic shims are
used to verify electronic gages. However, the inspector should always check the
specification to determine which type of gage to use and the method to verify the gages
accuracy.
Surface profile or roughness affects dry film thickness gages. If a gage is verified for
accuracy on smooth steel blocks (and the coating will be applied to roughened steel) the
amount the gage is affected (called the Base Metal Reading or BMR) must be measured
and deducted from each cumulative coating layer. If a gage is verified for accuracy by
placing shims of known thickness on top of the peaks of the roughened steel (the same
surface the coating will be applied to), then there is no BMR to measure or deduct.
Measure Coating Thickness Using Nondestructive Gages
While the applicator is concerned with the wet film thickness of the applied coating,
inspection personnel are much more concerned with the end result, or the dry film
thickness. The measurement of wet film thickness is simply a means to an end on most
metal surfaces where measurement of the dry film is feasible. Currently there are three
standards that address the nondestructive measurement of coating thickness: SSPC PA 2
(2004), Measurement of Dry Coating Thickness with Magnetic Gages; ASTM D 709105, Standard Practice for Nondestructive Measurement of Dry Film Thickness of
Nonmagnetic Coatings Applied to Ferrous Metals and Nonmagnetic, Nonconductive
Coatings Applied to Non-Ferrous Metals; and ASTM D 6132, Standard Test Method
for Nondestructive Measurement of Dry Film Thickness of Applied Organic Coatings
over Concrete Using and Ultrasonic Gage. Each of these standards prescribes methods
for verifying the accuracy of the measuring devices and for obtaining coating thickness
measurements.

46

PCI Study Guide- October 2007


Aside from the industry standards, coating thickness measurements should be obtained
after the application of each coat in a multiple coat system, not just after the final coat.
The vast majority of nondestructive coating thickness gages described in SSPC-PA 2 and
ASTM D7091 cannot distinguish individual coating layers, but rather measure the total
gap between the substrate and the gage probe.
Describe the SSPC Standard for Measurement of Coating Thickness
Frequency of dry film thickness measurements is another inspection concern. Both
ASTM D 7091 and SSPC PA 2 have specific requirements for the number of readings
that are taken and the number of areas measured according to the size of the structure.
SSPC PA 2 requires obtaining a minimum of three gage readings at each spot. These
gage readings are averaged to create a spot measurement and there is no restriction placed
on the individual gage readings (relating to thickness tolerance). SSPC PA 2 places a
tolerance on the five spot measurements that comprise an area measurement. The spot
measurements must be within 80% of the minimum specified thickness and 120% of the
maximum specified thickness. The average of the five spot measurements (the area
measurement) must fall within the specified thickness range established by the project
specification.
Measure Coating Thickness Using Destructive Methods
Once all the coatings of a multi-coat system have been applied, the only way to assess the
thickness of each coat is through the use of a Tooke Gage. The Tooke Gage cuts a
groove through the coating layers all the way down to the substrate using one of three
precision cutting tips. By using the microscope on the gage, an inspector can examine
the coating to determine the thickness of each layer. The Tooke Gage can be used to
examine different or alternating colored layers in a multi-coat system up to 50 mils thick.
Detect Pinholes and Holidays
Some coatings must perform in very challenging service environments: for example, the
coatings applied to the interior of storage tanks, railcars, and liquid and gas pipelines.
Visual inspection of these coatings for pinholes, skips, or missed areas would not be
adequate, therefore holiday or pinhole detectors are used to determine the location of
skips, misses, and pinholes. This testing is performed so coating or lining can be repaired
before the vessel is put into service. Holidays are skips or misses in the coating system.
Pinholes are tiny voids in the coating that penetrate all the way to the substrate. The type
of pinhole detection employed (low or high voltage) is based on the coating system
thickness. This type of inspection can only be performed on nonconductive coatings
applied to electronically conductive substrates. In general, the test voltage for high
voltage holiday detection is 100-125 volts/25m (1 mil); however, the manufacturer of
the coating system should provide the proper test voltage.
Measure Coating Adhesion
Some specifications require the measurement of the adhesion of the applied coating
system after it has cured. Adhesion assessments may include: the adhesion of the
coating to the substrate, the adhesion or the bond of one layer of the coating to another, or
the inner-strength of the coating, also known as cohesive strength.
47

PCI Study Guide- October 2007


Different adhesion tests measure different coating adhesion mechanisms (peel back
versus pull-off). Two tests that are common for the field are the Adhesion by Tape
Test (ASTM D3359) and the Knife Adhesion Test (ASTM D6677). These two tests
are used to evaluate the coatings shear or peel strength. The third test measures
tensile strength and is governed by ASTM D 4541, Pull-off Strength of Coatings Using
Portable Adhesion Testers, This test is used to evaluate the coatings resistance to a
perpendicular force on a pre-attached pull stub. All adhesion testing is destructive to the
coating film and should not be conducted unless required by the specification. The
specification should include repair procedures for the affected areas.
Evaluate Coating Cure
The inspector may be required to verify that a coating has adequately dried or cured prior
to application of subsequent coats, or prior to placing the coating system into service (i.e.,
filling up the tank/vessel). ASTM has three test methods for evaluating or assessing the
degree of coating drying or curing. These methods include drying tests (set-to-touch,
tack-free, dry-to-touch, dry-to-handle, dry-to-recoat, etc.) per ASTM D 1640 and two
solvent rub tests (one for organic coatings [ASTM D 5402] and one for ethyl silicate type
inorganic zinc-rich primers [ASTM D 4752]).
Measure Coating Hardness
The hardness of a coating can also be an indicator of the degree of cure, and an inspector
may be required to test the hardness of the coating film using the pencil hardness test
(ASTM D 3363), or an impressor/indenter test (Barcol hardness [ASTM D 2583] or
Durometer hardness [ASTM D 2240]).
Describe Methods Used to Verify Intercoat Cleanliness
Airborne dirt and dust is common on industrial painting sites and may become deposited
onto the coated surface. This poses no particular problem unless the surface is scheduled
to be recoated. In this case, a visual or tactical (touch) examination of the surface is
required to detect the presence of dust and to help prevent intercoat contamination.
Alternatively, the pressure-sensitive tape procedure (ISO 8502, Part 3) can be used to
assess the presence of dust on coated surfaces, in the same manner used for evaluating
dust on prepared surfaces. Surface dust/debris can cause subsequent applied coatings to
fisheye (inability to wet the surface) and, in sufficient quantities, can cause intercoat
delamination.

48

PCI Study Guide- October 2007


Module Five: Coating, Mixing, Thinning and Application: Equipment Overview
and Inspection Techniques
Workshop: Case Study

Project Description

The Sun Spree Township Municipal Authority (a suburb of Ft. Lauderdale, FL)
commissioned a coating condition survey of their 50-year-old elevated potable water
storage tank. The engineering firms report recommended total removal and replacement
of the lining on the interior of the tank, as well as removal of the coating on the exterior of
the tank, which contains both lead and chromium pigmentation in the existing coating.
Sun Spree Township awarded the surface preparation and coating application work to
Smith Bros. Contracting, a local firm that specializes in industrial surface preparation and
painting. Smith Bros. is responsible for providing a trained specialist to perform quality
control throughout the project. You are employed by Sun Spree Township as the resident
corrosion specialist, and will be performing quality assurance oversight on the project.
The interior of the tank has been prepared to achieve a Near-White Metal blast; the
exterior has been blast cleaned to conform to SSPC-SP 6, Commercial Blast. Both
surfaces are ready to be coated. The interior will be lined with a 3-coat NSF-approved
epoxy system. The three coats will be tinted different colors, but the manufacturer and
product no. are the same for each coat. The exterior will be coated with one coat of epoxy
and two coats of polyurethane (color coat and clear coat with dissipative dye).
The information provided below was excerpted from the project specification and only
pertains to coating/lining system installation activities:

49

PCI Study Guide- October 2007


Interior Lining
Minimum Lighting for Coating Application

500 Lux (47 foot-candles)

Minimum Lighting for Inspection

2000 Lux (186 foot-candles)

Environmental Conditions

Air Temperature: 50-120F


Relative Humidity: Maximum 85%
Surface Temperature: 50-120F
Surface Temperature a Minimum of 3C
(5F) Above Dew Point

Mixing Requirements

Complete kits as supplied using a shear mixing


blade

Thinning Requirements

Per manufacturers instructions

Coating Application Equipment

Airless Spray, per manufacturers instructions

Coating Thickness

SSPC-PA2

Primer Thickness

125-175 m (5-7 mils)

Intermediate Coat Thickness

125-175 m (5-7 mils)

Topcoat Thickness

125-175 m (5-7 mils)

Stripe Coats

After primer application (using primer)


After intermediate coat application (using
intermediate coat)

Maximum Time Between Coats

30 Days

50

PCI Study Guide- October 2007


Exterior Coating
Minimum Lighting for Coating Application

500 Lux (47 foot-candles)

Minimum Lighting for Inspection

2000 Lux (186 foot-candles)

Environmental Conditions

Air Temperature: 50-120F


Relative Humidity: Maximum 85%
Surface Temperature: 50-120F
Surface Temperature a Minimum of 3C
(5F) Above Dew Point

Mixing Requirements

Complete kits as supplied using a shear mixing


blade

Thinning Requirements

Per manufacturers instructions

Coating Application Equipment

Airless Spray, per manufacturers instructions

Coating Thickness

SSPC-PA2

Primer Thickness

125-175 m (5-7 mils)

Intermediate Coat Thickness

75-100 m (3-4 mils)

Topcoat Thickness

37-50 m (1.5-2 mils)

Maximum Time Between Coats

30 Days

Work together in your teams to address each of the quality-related issues described
below. Elect a team spokesperson to present your answers to the class and be prepared
to defend them if questioned.

51

PCI Study Guide- October 2007

1.

You arrive onto the project site and the contractor has already begun exterior
coating application. You measure the prevailing ambient conditions and the surface
temperature is within 3C (5F) of the dew point temperature, but the surface
temperature is higher than the dew point temperature. Based on this scenario,
answer the following:
Do you allow the contractor to proceed? _________________________________________
If no, why not?

What could have been done to prevent this occurrence?

2.

You measure the thickness of the primer and it is less than the specified minimum
by 1 mil. The contractor also measures the thickness of the primer and states that
it is within the specified range. How would you resolve this discrepancy?

3.

You were inside the tank obtaining dry film thickness measurements of the primer.
Meanwhile, the contractor proceeded with mixing and thinning 10 gallons of the
intermediate coat, which you were unable to witness. You inquired as to how
much thinner was added to the coating and the mixing crew responded, We didnt
52

PCI Study Guide- October 2007


measure, but we estimate probably about a gallon or so The product data sheet
allows up to 10% thinner addition. Based on this scenario, answer the following:
Do you allow the contractor to apply the coating __________________________________
If yes, what do you record on your documentation regarding the amount of thinner
added?

If no, what explanation do you provide to the contractor?

4.

The quality control specialist assessed the amount of light inside the tank prior to
inspecting the primer for dry film thickness. The amount of light was measured
and recorded as 600 Lux (56 foot-candles).
Does this conform to the project specification? __________________________________
The same amount of light was available when the contractor applied the primer to
the interior surfaces. Is this acceptable? Explain.

5.

The total square footage on the exterior of the tank was estimated to be 1,100
square meters (26,000 square feet).
53

PCI Study Guide- October 2007

6.

5A:

How many 9 square meter (100 square foot) areas must be measured for
coating thickness? ____________________________________________________

5B:

What is the minimum number of individual gage readings that must be


obtained?
____________________________________________________________________

5C:

How many spot measurements will be obtained? ____________________________

5D:

What is the range of thickness for the spot measurements of the primer? _________

5E:

What is the range of thickness for the spot measurements of the primer +
intermediate coats? ___________________________________________________

5F:

What is the range of thickness for the spot measurements of the primer +
intermediate + finish coats?______________________________________________

The contractor begins to apply the clear coat to the exterior surfaces and you
notice that there is no dissipative dye in the coating as it is being applied. You
inquire, and the contractor responds that previous experience with another
product resulted in rework because the dye did not fully dissipate, so he refuses
to use it.
Do you allow the contractor to proceed? ________________________________________
If no, why not?

54

PCI Study Guide- October 2007


What could have been done to prevent this occurrence?

7.

Application of the white primer to a portion of the exterior surfaces was done in
the early evening around 6:00 PM or so. The next day, you observe a yellowish
haze on portions of the surface, which is slightly tacky.
As an inspector, what do you suspect occurred? _________________________________
_________________________________________________________________________
Does the presence of this substance put the project at risk? _________________________
_________________________________________________________________________
How would you determine the nature of this substance? ___________________________

55

PCI Study Guide- October 2007


Module Five: Coating, Mixing, Thinning and Application: Equipment Overview
and Inspection Techniques
Quiz 5
1. A product data sheet is considered an __________________for a coating.
2. Calculate a target wet film thickness based on the following data:
Dry film thickness:
Volume solids content:
Thinner addition:

5-7 mils
72%
12.5%

__________________

3. During a material receipt inspection, the inspector should record the following
seven items:
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
4. Most coating manufacturers prohibit mixing of __________________ kits.
5. Most industrial coatings must be mixed using a __________________-type
mixing blade.
6. Boxing a coating is not recommended for which two generic types of coatings?
__________________
__________________
7. When inspecting mixing of zinc-rich primers, the
__________________component should be slowly sifted into the
__________________component while under __________________.
8. Straining of a __________________primer is typically required by the
specification or coating manufacturers PDS.
9. Pot agitation is typically required for __________________primers, except
moisture-cured __________________zinc-rich primers.
10. What is the first step when considering adding thinner to a coating?
_____________________________________
11. What is the second step when considering adding thinner to a coating?
_______________________________
12. List three consequences of adding an unknown quantity of thinner to a coating.
_________________________________________________________________

56

PCI Study Guide- October 2007


13. Application of coating to welds, edges, bolt/nuts, and rivets prior to full scale
application is known as __________________.
14. __________________ are used to coat crevices and between back-to-back angles.
15. __________________ spray is the most common method used to apply
industrial/marine coatings.
16. What is the paint pressure when the regulator on 45:1 airless spray pump is set to
60 psi? __________________
17. What does the marking 723 indicate on an airless spray tip?
__________________
18. Proper distance of an airless spray gun from the surface is __________________
inches.
19. The upper control on a conventional spray gun controls the
__________________.
20. The lower control on a conventional spray gun controls the
__________________.
21. Proper distance of a conventional spray gun from the surface is
__________________inches.
22. The diameter of the holes in an HVLP spray air cap are __________________
than the holes in a conventional spray air cap.
23. Plural component spray is used to apply coatings with what characteristics?
__________________and __________________.
24. For plural component spray, what method is typically used to reduce viscosity of
the components? __________________
25. An applicator should overlap spray passes __________________% to build a
consistent thickness.
26. List ten common inspection checkpoints that are performed on nearly every
industrial coatings project:
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________

57

PCI Study Guide- October 2007


27. What two values are used to determine the relative humidity and dew point
temperature when using a sling or battery powered psychrometer in conjunction
with the US Weather Bureau Psychrometric Charts?
__________________
__________________
28. Ambient conditions should be measured where __________________.
29. The temperature of the surface to be coated must be at least
__________________above the __________________.
30. The wet bulb temperature is considered to be stabilized when two readings taken
within __________________seconds are within __________________of one
another.
31. A coating material with a six hour pot life and a 45 minute induction has a useable
pot life of __________________.
32. The wet film thickness reading on a wet film thickness gage is considered the
__________________numbered tooth (step) on the gage.
33. According to SSPC PA2, the accuracy of a coating thickness gage should be
verified __________________and __________________ each period of use.
34. A Type 1 gage is known as a __________________gage.
35. A Type 2 gage is known as an __________________ gage.
36. The accuracy of Type 1 gages is verified using __________________.
37. The accuracy of Type 2 gages is verified using __________________.
38. The effect of surface roughness on a coating thickness gage measurement is
known as a __________________.
39. The BMR is __________________ from the coating thickness to determine the
thickness of the coating above the __________________of the surface profile.
40. If the tolerance of a coating thickness gage is +/- 5% and the tolerance of the
standard used to verify gage accuracy is +/- 3%, what is the tolerance of the
reading on a 6.4 mil test block? __________________.
41. 41.
The BMR is not necessary to measure when a Type 2 gage is verified for
accuracy using __________________placed onto the __________________,
uncoated steel.

58

PCI Study Guide- October 2007


42. How many spot measurements are obtained within an area?
__________________
43. How many individual readings comprise a spot measurement?
__________________
44. The surface to be assessed for DFT represents 600 square feet
No. of areas to measure: __________________
Total No. of spots: __________________
Minimum no. of individual gage readings: __________________
45. The surface to be assessed for DFT represents 24,000 square feet
No. of areas to measure: __________________
Total no. of spots: __________________
Minimum no. of individual gage readings: __________________
46. The surface to be assessed for DFT represents an I-beam that is 40 feet in length,
has 12 wide flanges, a 48 web.
No. of areas to measure: __________________
Total no. of spots: __________________
Minimum no. of individual gage readings: __________________
47. According to SSPC PA2, what is the tolerance of a spot measurement for a
project specification that specifies 2-4 mils of primer? __________________
48. When spot or area DFT measurements do conform to the specification
requirements, then each __________________ square foot area coated during the
same __________________must be inspected.
49. What is the cumulative thickness range of the primer and intermediate coats for a
project specification that requires 4-6 mils of primer and 8-10 mils of intermediate
coat? __________________
50. If the coating thickness is 12-15 mils, what Tooke gage tip should be used to
make an incision through the coating film to assess layer thicknesses?
__________________
51. The following data was acquired when viewing an incision (made with a 10X
cutting tip) through a Tooke Gage lens. What is the thickness of each layer?
Primer: 10 divisions: __________________ mils
Intermediate: 12 divisions: __________________mils
52. Amine exudate or blush can occur on __________________ coatings that are
applied and/or cured during __________________conditions.

59

PCI Study Guide- October 2007


53. Application of coatings over an amine exudate may result in what type of coating
failure?
__________________
54. A pinhole is a __________________in the coating that penetrates to the substrate.
55. A holiday is a __________________ or __________________ in the lining
system application.
56. Low voltage, wet sponge pinhole detection is can be used on nonconductive
__________________ (up to __________________ mils) applied to a
__________________substrate.
57. High voltage, spark testing is can be used on nonconductive
__________________ applied to a __________________ substrate.
58. According to NACE RP0188-99, the suggested voltage for testing a coating
system that is 41-55 mils thick is __________________.
59. The most reliable method for determining the cure of an ethyl silicate inorganic
zinc-rich primer is the __________________test.
60. If a 3H pencil will not scratch or gouge the coating film, but a 4H pencil will,
what is the pencil hardness of the coating? __________________
61. Tensile adhesion testers assess the __________________strength of coatings;
while tape adhesion assesses the coatings resistance to __________________.
62. The cross-cut method (Method B) of the tape adhesion test is used for coatings
that are less than __________________ mils thick.
63. When a coating breaks cleanly from the substrate, the location of break is
__________________.
64. What is the primary difference between conducting an adhesion test per ASTM
D3359 (method A) and ASTM D6677? __________________
65. The gage for measuring the thickness of coatings on concrete (nondestructively)
employs an __________________principle of measurement.

60

PCI Study Guide- October 2007

Module Five: Coating, Mixing, Thinning and Application: Equipment Overview


and Inspection Techniques
Supplemental Reading List
- Using Coatings Inspection Instruments (SSPC Item #03-08)
- Shop Painting of Steel (SSPC Item #02-01)
- SSPC Basic Spray Application Manual (SSPC Item #04-05)
- Industrial Painters Training (SSPC Item #94-09)

61

PCI Study Guide- October 2007

Module Six: Industrial and Marine Protective Coatings and Coating Systems
Module six introduces the basic components in an industrial coating: non-volatile and
volatiles. Subsequently, VOC (volatile organic compound) regulations will be explored
in the context of what a QC or QA inspector should know about monitoring and reporting
the addition of thinner to coating products and the actual quantity of VOC emitted into
the atmosphere during application. In Module Six, participants will also learn how
coatings cure. An overview of coating types and coating characteristics will be followed
by key inspection concerns by specific coating type. Module Six will conclude with an
overview of common coating systems used in a number of industries including: water
storage/tanks; power generation (both coal and nuclear); waste water treatment; pulp and
paper; lock and dam; chemical plants; buried pipeline; ships/marine vessels and
highway/bridges.
Learning Outcomes
At the completion of this module you should be able to:
- Identify basic differences between house paint and industrial/marine protective
coatings
- List volatile and non-volatile components of a coating
- Describe the functions of the resin, additives, pigments, and solvents in a coating
- Describe the methods by which coatings cure
- Describe the procedures used to identify service environments
- List advantages and limitations of various generic types of industrial/marine
coatings
- Describe functions of the primer, mid-coat and finish coat
- Identify common coating systems used by various industries
- Describe proper methods used to evaluate coating performance prior to full scale
installation
Identify Basic Differences Between House Paint and Industrial/Marine Protective
Coatings
Module Six begins by describing the differences between ordinary household paints and
industrial/marine protective coatings. One notable difference is the increased cost of
protective coatings, another is the reason behind the higher costs. The performance
requirements of industrial/marine coatings are much higher than those of house paints,
which are used primarily to improve aesthetics. Protective coatings, on the other hand,
may have to withstand immersion in water, chemical exposure, impact and abrasion, as
well as provide aesthetics.
List Volatile and Non-Volatile Components of a Coating
There are many different ingredients or raw materials that are used to formulate an
industrial/marine coating. This curriculum divides them into two categories:
1. Volatiles and non-volatiles
2. Pigmentation and vehicle

62

PCI Study Guide- October 2007


In the first category, volatiles are part of the wet film, but evaporate into the air once the
coating is applied to the surface, while non-volatiles are part of the wet and dry film and
remain on the surface once the coating is applied.
Describe the Functions of the Resin, Additives, Pigments, and Solvents in a Coating
In the second category for coating components, pigmentation and vehicle, the vehicle
carries the pigmentation to the surface and binds it into the coating film. The vehicle
typically consists of the resin or binder, solvents, and any additives that may be included
in the formulation. While part of the vehicle evaporates (the solvents) once the coating is
applied, other components, like the resin, remain behind as part of the dry film. The resin
system cohesively bonds the pigmentation together and adhesively bonds the coating to
the underlying substrate or coating layer. In fact, the resin is so significant that the type
of resin in the formulation is often used to generically identify the coating. In many
cases, the resin system dictates the performance properties of a coating.
Additives are also a part of the vehicle that remains on the surface. Additives are added
to coating formulations to improve flow-out, surface wetting, and flexibility. Additives
can also be used to adjust the consistency of a coating, to resist ultraviolet light, and to
prevent settling in the can.
In the category of pigmentation and vehicle, the pigment gives the coating the ability to
hide the underlying surface. Pigments also give coatings their color and gloss, but
pigments may also provide corrosion protection. Pigments like iron oxide or barium can
be formulated into a primer to inhibit the corrosion process. Pigments like zinc powder
can be added to the primer in sufficient quantities to galvanically protect the underlying
carbon steel. Still other pigments, like micaceous iron oxide and leafing aluminum
pigments, provide barrier protection. These pigments are plate-like, and the way they
position themselves in the coating film forces any moisture that penetrates the coating
film to take a longer path to reach the substrate.
Extenders are pigments like clay, silica, and mica, which can be incorporated into the
formulation to improve film build. Extenders also increase the solids content of a coating
and provide added barrier protection. Remember that all pigments, regardless of their
individual functions in the coating, remain on the surface and become part of the dry
film.
When coating components are divided into volatiles and non-volatiles, the solvent system
is the volatile component. White it is part of the wet film during application, it is not
intended to be part of the dry film once the coating dries or cures. Typically, a blend of
solvents is used in the formulation of a coating and each type of solvent in the blend
performs a different function. As a general rule, primary solvents reduce the viscosity of
the resin, pigments and additives, so the coating can be properly atomized through a
spray gun or applied by brush or roller. Primary solvents evaporate from the coating film
first, while secondary or coalescing solvents typically remain in the wet film a little
longer to help the coating flow-out and knit together to form a uniform, continuous film.

63

PCI Study Guide- October 2007


Many solvent systems (and thinners) are categorized as volatile organic compounds of
VOCs by the U.S. Environmental Protection Agency (EPA). The amount of VOCs that
can be legally emitted into the atmosphere varies from location to location. Some
densely populated areas have very strict regulations, while less populated areas typically
comply with the Federal limit, which is less restrictive. In the field, the VOC limit is
usually dictated by the specification or the local air pollution agency for that project.
Fixed facilities like paint shops, however, are sometimes required to log the number of
gallons of paint used over a specific period, as well as the VOC content of each type.
The local environmental agency regulates the maximum quantity of VOCs produced by
fixed facilities.
Coating manufacturers can formulate coatings to comply with VOC regulations by using
non-regulated solvents, like water and acetone, or by increasing the non-volatile content
of the coating. Since adding thinner in the field may increase VOC levels, the amount of
thinner added must be carefully monitored.
Describe the Methods by Which Coatings Cure
The method in which a coating converts from a liquid to a solid state is known as the
curing mechanism. In this module, five basic curing mechanisms are discussed: solvent
evaporation, coalescence, oxidation, polymerization and moisture cure.
Solvent evaporation is perhaps the most commonly understood coating cure. In this
process, the solvent in the coating evaporates into the air after application, while the
resin, pigment, and additives remain on the surface to form a dry film. There is no
second step or subsequent curing reaction, so the resin can be redissolved by the same
solvent system that was used in the blended coating. Coatings that cure by solvent
evaporation should not be overcoated with a coating that contains strong solvents.
Coalescence also involves evaporation of solvents from the coating film, but in this case
there are primary solvents which evaporate first and coalescing solvents (secondary
solvents) which remain in the film a little longer (to help fuse the molecules together to
form a solid film). After the film has been formed, the secondary solvents also evaporate
from the film. This type of cure typically requires a minimum air temperature of 50F.
Oxidation is a third method of coating cure. Components in the coating (drying oils)
react with oxygen (from the surrounding air) to form a film. One problem with this
method of cure is that the process of oxidation never really stops as long as the coating is
exposed to oxygen. Alkyds, which cure by this method, can become very brittle after
many years of service, since the resin continues to oxidize long after the coating is fully
cured.
A fourth method of cure or polymerization is more complex than the first three. Different
resin components are carefully measured by the manufacturer and packaged separately,
so that when these components are properly blended a chemical reaction occurs,
generating a new, resilient coating. The components must be blended in the correct
ratios (complete kits) for the chemical reaction (or polymerization) to produce the correct
64

PCI Study Guide- October 2007


blend. Coatings that cure by this method are multi-component, and once they are blended
together, the pot life begins. The pot life may vary from a few minutes to several hours.
A few of the more common coatings that cure by polymerization are epoxies, aliphatic
acrylics, and polyester polyurethanes.
Moisture-cure is the fifth method of coating cure discussed. The coating components
react with moisture and require a minimum amount of moisture to cure. Moisture-cure
urethanes cure this way and release carbon dioxide (CO2) during the process, while
inorganic zinc-rich primers also cure by moisture cure, but release ethyl alcohol during
the process. The result is a very resilient coating layer, similar to that produced by
polymerization.
Describe the Procedures Used to Identify Service Environments
Properly identifying the service environments is another challenge to the specifier. As
the curriculum has pointed out, even when the substrate is prepared according to the
specification and the coating is applied properly, the substrate will not be protected if the
coating cannot stand up to the service environment. Therefore understanding what the
coating system will be subjected to, once applied, is critical. The problem is that service
environments arent always predictable. For example, when an exhaust stack that was
designed to operate at 500F, undergoes a 1000F spike, will the coating system fail?
There are a number of questions to answer about a service environment before a coating
system is selected. Will the coating be subjected to immersion service? If so, will the
immersion be constant or intermittent (i.e., splash)? Will the immersion be in potable
water, waste water, salt water, solvent, acids, etc.? What is the likelihood and type of
physical damage that the coated substrate might sustain (i.e., the impact damage from
river debris on a set of dam gates)?
Questions on service environments must be answered prior to selecting a coating system.
And it should be noted that there may be multiple service environments for a given
structure, for example the interior of a chemical plant.
Once all the background questions are asked and answered, specifiers can look at the
history and performance records of coating systems that have been commonly used in
specific industries and service environments.
Describe Functions of the Primer, Mid-Coat and Finish Coat
Coatings are typically specified in systems which consists of the specified surface
preparation and the application of one or more coats. Specifiers may recommend
multiple layers of the same product, or specify one coating to be used as the primer,
another to be used as the midcoat and still another to be used as the topcoat. If the
coatings applied are different formulations, they must be compatible with each other.
In addition, each layer must be able to perform the function intended for that layer. For
example, the function of the primer is to bond the coating system to the substrate. The
primer may also be selected to provide corrosion protection to the substrate. The primer
65

PCI Study Guide- October 2007


must be equally compatible with the level of surface preparation beneath it and the
coating directly above it.
The intermediate coat is typically part of the coating system for the purpose of adding
barrier protection. It must also be compatible with the primer and the topcoat.
The topcoat is the first line of defense against corrosion and must be resistant to the
service environment. Typically, the topcoat must also be aesthetically pleasing (good
color and gloss) and be compatible with the underlying coating layer.
Identify Common Coating Systems Used by Various Industries
Selecting a coating system is based on the prevailing service environment, the intended
service life of the structure, the level of surface preparation possible, the intended service
life of the coating, access to the structure to be coated, and economical restraints and
considerations.
Describe Proper Methods Used to Evaluate Coating Performance Prior to Full Scale
Installation
Another consideration for the specifier when selecting a coating system for an industry is
past performance and testing. There are industry specific coating performance
evaluations that generate data based on testing that represents the service environment.
Once this data is generated, coating manufacturers can access the information and
establish their own qualified products lists. The advantage of this type of performance
evaluation is that many agencies within a given industry can access performance data
with little or no associated costs.
An additional method to evaluate the performance of a protective coating or lining
system is to employ an industry standard testing procedure designed specifically for a
type of coating. The focus of this type of testing is on the performance of the formulated
product, not the individual ingredients of the coating. Therefore, the specification/testing
includes functions like package stability, application properties, weathering properties,
and color and gloss retention.
And a final method to evaluate a coating system prior to specifying that system is to
employ a combination of the performance evaluations described above. A bridge owner,
for example, may refer to industry specific coating performance evaluations, while they
simultaneously conduct their own testing for a variety of coating systems on panels of the
substrate at the actual site of a future project.

66

PCI Study Guide- October 2007


Module Six: Industrial Marine Protective Coatings and Coating Systems
Quiz 6
1. The resin, solvent, and additives are known as the ________________ of a
coating that carries the _____________________ to the surface and binds it into
the film.
2. List five functions of pigmentation in an industrial/marine coating:
_____________________________ _______________________________
_____________________________ _______________________________
_____________________________
3. Solvents are part of the _______ film, but are not part of the ____ film.
4. Primary solvents are used to _______________ __________________; secondary
solvents are used to help the coating _____________________.
5. Coatings that dry rather than cure form a solid film by a process known as
_____________________ ____________________.
6. Waterborne coatings cure by a process known as _________________________.
7. Coatings that cure by a reaction with oxygen cure by ______________________.
8. Multi-component epoxy and polyurethane coating cure by __________________.
9. Coatings that hydrolyze are said to ___________________ cure.
10. What is the primary function of an intermediate coat? _____________________
11. Which coating system is recommended for use on surfaces with an elevated
temperature in a waste water treatment plant?
________________________________________________________________
12. Mounting test panels containing candidate coating systems in the actual
environment where the new coating will be installed is known as a
________________-________________ performance evaluation.
13. Coatings contain two categories of ingredients: _________________ and
____________________________.
14. Thinner addition ______________________ the VOC content of a coating.
15. Prior to selecting a coating system, the facility owner must properly identify the
prevailing _______________________ ______________________________.
67

PCI Study Guide- October 2007

Module Six: Industrial Marine Protective Coatings and Coating Systems


Supplemental Reading List
- Protective Coating for Water and Wastewater Facilities (SSPC Item #06-01)
- Fundamentals of Chemistry and Composition (SSPC Item #94-17)

68

PCI Study Guide- October 2007

Module Seven: Specialty Inspection Projects


Module Seven describes non-routine inspection projects that can pose special challenges
to the coatings inspector. Inspecting the surface preparation and coating application in a
steel fabrication shop presents a different set of challenges for a coatings inspector, as
does maintenance painting in the field when overcoating becomes the maintenance
strategy. Additionally, many existing industrial structures contain coatings with toxic
metal ingredients. The hazards associated with removal, handling and disposal when
these coatings are disturbed during maintenance painting operations must be
controlled. The inspector may have responsibility for verifying proper set-up and
maintenance of containment and ventilation systems, assuring proper worker protection,
monitoring air, soil and water quality, and assuring proper handling and disposal of
hazardous waste streams.
Learning Outcomes
At the completion of this module you should be able to:
- Describe the unique aspects of performing coatings inspection in a steel
fabrication or blast & paint shop
- Describe the unique aspects of performing coatings inspection on an overcoating
project
- Describe what the inspectors role might include on projects involving
disturbance of coatings containing toxic metals
Describe the Unique Aspects of Performing Coatings Inspection in a Steel
Fabrication or Blast & Paint Shop
Surface preparation and coating application inspection in a steel fabrication shop or a
blast & paint shop is similar to field inspection. SSPC QP 3 and AISC SPE categorize
shops into three types: Covered Shop, Enclosed Shop, Open Shop and Field and both
qualification and certification programs require implementation of quality control
procedures and documentation. Inspection in the shop includes pre-surface preparation
inspection (weld spatter removal; edge preparation; sliver and lamination removal; oil
and lubricant removal), surface preparation inspection (abrasive type, size and
cleanliness; compressed air cleanliness, surface profile and cleanliness), coating
application inspection (ambient conditions monitoring, witnessing mixing and thinning
procedures, verifying minimum and maximum recoat intervals, pot life monitoring and
application technique; measurement of wet and dry film thickness; assessing intercoat
cleanliness and cure; pinhole/holiday detection; and adhesion testing).
Describe the Unique Aspects of Performing Coatings Inspection on an Overcoating
Project
Overcoating is a maintenance strategy that can be employed by a facility owner to reduce
costs by extending the life of the existing coating system, verses the cost of totally
removing and replacing the coating. There is risk associated with overcoating, so the
existing coating system must be carefully evaluated to assess whether it is a candidate for
overcoating. The assessment includes tests for substrate condition, amount of corrosion
69

PCI Study Guide- October 2007


and deterioration present, the thickness and adhesion of the existing coating, and the
generic type of the existing coating. Test patches can be applied and evaluated prior to
full scale overcoating when the condition of the existing coating is marginal. Surface
preparation inspection includes verification of oil/grease removal per SSPC-SP 1, and
inspection of spot touch-up areas for cleanliness, roughness (if required) and proper
feathering of the existing coating for a smooth transition. The remaining surfaces may be
brush blasted or pressure washed. These surfaces must be inspected to ensure the
existing coating was not severely fractured, and that surface dirt, chalk and other debris
has been adequately removed. Testing for chemical contamination may also be required,
if soluble salts were deposited onto the surfaces while in service. The inspector may be
required to measure and map the thickness of the existing coating, and may be required to
measure the wet film thickness of the overcoat material during application. The final dry
film thickness can be measured either nondestructively or using a destructive gage. If a
nondestructive gage is used, the thickness of the existing system must be deducted from
the measurements in order to isolate and document the thickness of the overcoat, or the
readings taken in spots where the existing had been totally removed. Adhesion of the
overcoat to the existing system may be assessed to ensure that the overcoat is properly
bonded, and is similar to the adhesion characteristics of the coating system on a test
patch, if one was prepared. Areas where destructive coating thickness and/or adhesion
testing were preformed should be touched up by the contractor to prevent premature
rusting in these areas.
Describe What the Inspectors Role Might Include on Projects Involving
Disturbance of Coatings Containing Toxic Metals
The inspectors role on projects involving removal of coatings containing toxic metals
(primarily lead, chromium and hexavalent chromium ) can include inspecting the
effectiveness of the containment system by monitoring the air, soils and water around the
project site, and by performing visible emissions (VE) monitoring during surface
preparation activities. Air quality is monitored by VE observation, or by employing high
volume air sampling for total suspended particulate or respirable particulate. Soil and
water quality is monitored by collecting and analyzing pre- and post-job samples, or
visually. The inspector may also be responsible for verifying that the contractor and his
personnel are conforming to their site plan for complying with OSHAs comprehensive
health standard(s) for the toxic metal(s) in the coating, including the implementation of
engineering controls, work practices and respiratory protection to control the hazard. The
inspector may also evaluate the effectiveness of the ventilation system by measuring air
movement inside the containment. Likewise, the inspector should follow the same rules
as the contractors personnel regarding protective clothing, respiratory protection and use
of hygiene facilities on the project site.
Finally, the inspector may be responsible for verifying that the contractor is handling and
storing all of the waste (hazardous and non-hazardous) properly, and that the waste is
tested by an approved laboratory and hauled from the site by a licensed transporter. The
inspector may be asked to review the contractors site-specific, written worker protection,
environmental protection and waste management compliance plans prior to production

70

PCI Study Guide- October 2007


work, and may be required to verify conformance to the written plans during production
work.
Module Seven: Specialty Inspection Projects
Quiz 7
1. The primer used on connection points of I beams must often have a Class A or
Class B _________________ ___________ if the connection is ________ critical.
2. List four inspection concerns relating to application of primers on slip-critical
connections.
_____________________________ _________________________________
_____________________________ _________________________________
3. List three forms of metallized spray: __________________________________
____________________________ __________________________________
4. What is the minimum surface cleanliness and surface profile depth for metallizing
applied to structures for marine or immersion service? ______________________
5. Which form of metallizing feeds two wires to a spray gun? __________________
6. When measuring the thickness of thermal spray coatings on flat surfaces, a
minimum of _____ readings are obtained in a line spaced ______ inch apart.
7. When measuring the thickness of thermal spray coatings on a complex geometry,
a minimum of _____ readings are obtained in a _______ inch diameter spot.
8. Powder coating may be cured using ______________ or ___________________
9. List seven inspection check points associated with powder coating application.
_____________________________ _________________________________
_____________________________ _________________________________
_____________________________ _________________________________
_____________________________
10. Application of a liquid coating over a galvanized surface is known as a
___________________ system.
11. __________________ galvanizing is optimum for coating, while _______
galvanizing is difficult to coat.
12. If sweep blasting of galvanizing is specified, the inspector may be required to
measure the ______________ _______________ __________________ prior to
sweep blasting operations.

71

PCI Study Guide- October 2007

13. Most Type 1 and Type 2 DFT gages display the ___________________ thickness
of the galvanizing and coating layers.
14. On overcoating projects, the inspector should verify that visible ______________
and ________ contamination are removed prior to _______________
________________________.
15. Areas of sound coating adjacent to repair areas should be __________________
to ensure a smooth transition for the new coating and to prevent
________________ of the existing coating.
16. If a brush-off blast (SSPC-SP___) is specified for an overcoating project, the
inspector may be required to measure __________ _____________ and verify
proper abrasive type to ensure neither is too aggressive.
17. Pressure washing to remove dirt, chalking, etc. must be carefully inspected to
ensure _________________ removal prior to overcoating.
18. Prior to application of the overcoat material, an inspector should obtain
________________ measurements on the __________________ _____________.
19. The thickness of the overcoat can be isolated from the thickness of the existing
coating by using a ________ ___________.
20. List three toxic metals that may be in existing coatings:
_________________________________ _____________________________
_________________________________
21. A containment is designed to protect the ________________________________.
22. Ventilation inside a containment is designed to protect _____________________.
23. SSPC Class __ containment provides the highest level of protection.
24. Negative pressure is monitored _______________ or by reading a
_____________________ gage.
25. Air flow inside a containment can be monitored using a ______________
_______ ______________________________.
26. List two devices for monitoring air quality outside of a containment:
___________________________
____________________________
27. Pre- and post-project ____________ and/or ______________ sampling and
analysis may be required to verify effectiveness of the containment.
72

PCI Study Guide- October 2007

28. List three things a coatings inspector should never do inside a regulated area:
_________________________________ _____________________________
_________________________________
29. Hazardous waste can only be transported by ______________ _______________.
30. List two SSPC Guides that govern containment and hazardous waste management
procedures:
_________________________________ _____________________________

73

PCI Study Guide- October 2007

Module Eight: Coating Failures: Investigation Procedures and Case Studies


Module Eight explains how knowledgeable coatings inspectors can help avoid coating
failure. The role of the coatings inspector and the types of inspection activities that can
play a role in preventing the failures are described. Case histories of actual coating
failures are presented. The cause, fault and repair procedures are explored, and
avoidance methods are discussed.
Learning Outcomes
At the completion of this module you should be able to:
- Describe how coatings inspection can help prevent premature coating failures
Describe How Coatings Inspection Can Help Prevent Premature Coating Failures
Coatings can fail for a variety of reasons. When a coating failure occurs, an investigation
is often performed to determine the cause, determine the part responsible and assess the
degree of repair necessary to ensure the integrity of the substrate. The consequences of
coating failure can include substrate repair or replacement, costly rework and down time,
and aesthetics. When investigating a coating failure, six issues should be considered,
including what was to be done; does it make sense; what was actually done; what caused
the failure to occur; who is the responsible party; and what can be done now. A coating
failure investigation includes both a site investigation and a laboratory investigation. The
site investigation includes document acquisition, a determination of the construction
sequence and obtaining the structure and painting history, visual observations, sample
and data collection, acquisition of batch retains and other coating samples, and
photography. The laboratory investigation can include a variety of forensic tests,
depending upon the nature of the coating failure. Coating inspection aids in coating
failure avoidance by detecting problems and nonconformities (and verifying they are
corrected) prior to putting the coating or lining into service. Coatings inspection however
cannot aid in failure avoidance when a coating is improperly formulated or when a faulty
specification is generated and work is completed based on a faulty contract.
The role of the coating inspector can be critical in a failure investigation. Well-prepared,
thorough records and photographic documentation can greatly help to narrow the cause of
the failure.

74

PCI Study Guide- October 2007

Module Eight: Coating Failures: Investigation Procedures and Case Studies


Quiz 8
1. List six possible causes of premature coating failure:
________________________________
________________________________
________________________________
________________________________
________________________________
________________________________
2. List four consequences of coating failures:
_______________________________
________________________________
________________________________
________________________________
3. Describe how a coatings inspector can help prevent coating failures from occurring.
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
4. What key item maintained by an inspector is critical to a coating failure investigation?
_____________________________________________________________________

75

PCI Study Guide- October 2007

Module Eight: Coating Failures: Investigation Procedures and Case Studies


Supplemental Reading List
- Failure Analysis of Paints and Coating (SSPC Item #04-14)
- Visual Comparison Manual: Application and Coating Defects (SSPC Item #99-01)
- Paint Film Degradation (SSPC Item #01-14)

76

PCI Study Guide- October 2007

Module Nine: Inspector Safety


Module Nine describes basic inspector safety. Fabrication shops and construction sites
often pose significant safety concerns for a coatings inspector. While Module Nine is not
designed to provide comprehensive safety training, it makes the coatings inspector aware
of potential hazards and methods of prevention. Safety issues described in Module Nine
include fall prevention/protection, respiratory protection, sight and hearing protection,
protection from toxic metals, and confined space entry hazards. Module Nine also
describes the purpose of site specific environmental, safety and health hazards planning
and the inspectors responsibility for personal safety.
Learning Outcomes
At the completion of this module you should be able to:
- List potential safety hazards associated with coatings inspection
- Describe the common personal protective equipment used by a coatings inspector
List Potential Safety Hazards Associated with Coatings Inspection
Coatings inspection are frequently classified as workers and held by law to be
responsible, as far as is reasonable, for their own safety. Everyone at the jobsite should
keep a look-out for unsafe acts or operations. An inspector who is aware of a serious
safety violation but fails to report it to the effected workers supervisor may put
themselves at risk of legal action if an accident occurs. The coatings inspector can face
general risks, personal risks, and legal risks. The inspector is responsible to know what
the risks are, and to take reasonable steps to avoid them.
The coatings inspector can encounter hazardous materials, hazardous environments and
hazardous activities on a project. Hazardous materials include cleaning solvents,
abrasives and dusts, toxic metals, coating components, thinners, chemical strippers and
acidic and caustic solutions. Hazardous environments include heights, confined spaces,
electrical, fire and explosion hazards, slippery or obstructed walkways, excessive heat,
inadequate lighting, noise, vehicles and moving heavy parts on cranes, etc. Hazardous
activities include solvent cleaning, abrasive blast cleaning, high pressure waterjetting,
power tool cleaning and airless spraying.
Material Safety Data Sheets (MSDS) are mandated under OSHAs Hazard
Communication (Hazcom) regulation and are the primary document that describes the
hazards associated with the chemicals used on a project and the personal protective
equipment required to safely handle the product.
Describe the Common Personal Protective Equipment Used by a Coatings Inspector
While the inspector receives a shorter duration of exposure to hazards than workers, the
hazards themselves are similar and coatings inspector should wear similar, suitable safety
equipment and clothing. Personal protective equipment for an inspector typically
includes a hard hat and safety glasses, ear plugs in a noisy environment, respiratory

77

PCI Study Guide- October 2007


protection, a fall harness and shock absorbing lanyard (if working form heights greater
than 1.8 meters [six feet]), work boots and long sleeved coveralls.
Most battery-operated inspection equipment is not intrinsically safe and should not be
used in a hazardous environment (greater than 10% of the LEL) without the appropriate
permit.

78

PCI Study Guide- October 2007

Module Nine: Safety


Quiz 9
1. The coatings inspector shares in the responsibility for the safety of
______________ and the _______________.
2. A coatings inspector that observes an imminent hazard that may cause death or
serious injury should take _______________________ action to prevent the
_____________________.
3. Who should an inspector obtain guidance from regarding their role relative to
safety issues? ___________________________________________________
4. List an example of a General Risk that a coatings inspector may be exposed to:
_______________________________________
5. List an example of a Personal Risk that a coatings inspector may be exposed to:
_______________________________________
6. What is the primary difference between exposure hazards associated with
inspection verses exposure hazards to painters? __________________________
________________________________________________________________
7. List two hazardous materials that will be present on every coatings project:
___________________________
_________________________________
8. The inside of a storage tank can be considered what type of hazardous
environment? _______________________________
9. Why is airless spraying categorized as a hazardous activity?
______________________________________________________________
10. The effect of hazardous materials on an inspectors health depends on the
________________, __________________ and route of ________________.
11. List four items that are of the greatest value to an inspector on an MSDS:
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
12. What is the most frequent way solvents affect the body? ____________________

79

PCI Study Guide- October 2007


13. Polyurethane coatings contain a chemical known as _______________________,
which are strong irritants and ________________________.
14. Respirators equipped with ___________ filtration cartridges can filter
_____________________ sized-dust.
15. Heights greater than _____________ above a lower level require fall protection.
16. What type of lanyard is a component to a personal fall arrest system?
________________________________
17. List three items that an inspector should verify before entering a confined space:
________________________________
____________________________
________________________________
18. What electrical hazard cannot typically be locked-out/tagged-out?
________________________________________________________________
19. What hazard is associated with inadequate lighting? ______________________
20. List two basic types of respirators: _______________ & ___________________
21. Most coating inspection gages are not ___________________ safe and should not
be used in _______________________ environments.

80

PCI Study Guide- October 2007

Module Nine: Safety


Supplemental Reading List
- Industrial Lead Paint Removal Handbook (SSPC Item #93-02)
- Fall Protection for Construction (SSPC Item #132-K)
- Scaffolding Training Program (SSPC Item #106-K)
- Guides on Environmental Protection (SSPC Item #05-01)

81

PCI Study Guide- October 2007

Module Ten: Navigating Coating Specifications


Module Ten explains the purpose and content of coatings specifications. The coatings
specification is the inspectors rule book for a coatings project. It describes the scope
of work and the requirements of the contract, as well as lists the inspection checkpoints
for which the inspector is responsible. The importance of a properly prepared coatings
specification and the general layout and components in a specification are described in
Module Ten.
Learning Outcomes
At the completion of this module you should be able to:
- Describe the purpose and function of a coating specification
- List the various methods in which coatings are specified for use
- List the basic components of a coating specification
- Locate inspection check points in a coatings specification
Describe the Purpose and Function of a Coating Specification
A properly prepared specification is a key component to project success. A coatings
specification describes the project and the objective of the coating system. It also
describes the materials required to complete the work, the intended appearance of the
completed work and lists the inspection hold points/check points to help assure that the
work is done according to the requirements of the specification.
A coating specification is a legally binding document. It is a contract between the owner
and the contractor. While a coatings specification is a legal document, it must be
workable and understandable. A coating specification should also be practical, so that
the owner can effectively communicate the desired outcome, including the project
schedule. The specification should not be unreasonably restrictive, but should anticipate
problem areas that the contractor may encounter and must overcome to successfully
complete the contract.
There are two general types of specification for coating work: those involved with new
construction and those involved with maintenance painting of existing structures. The
content of the specification documents will be different in both cases.
List the Various Methods in Which Coatings are Specified for Use
There are a number of ways that coating systems can be specified for use on a project.
Some specifications are written around specific product trade names, and some are
written as trade name or equal. Others are based on a pre-established Qualified
Products Lists (QPL), or are based on a set of performance standards. While infrequent,
a coating system can also be specified based on a coating formulation or set of
formulations.
List the Basic Components of a Coating Specification
82

PCI Study Guide- October 2007


Most coating specifications contain three basic components: General; Products
(materials); and Execution.
Module Ten: Navigating Coating Specifications
Quiz 10
1. A coating specification is an inspectors __________ ____________ for a
coatings project.
2. An inspector should read and understand the coating specification ____________
the project begins.
3. List two types of specifications for coating work:
____________________________ ________________________________
4. What should an inspector do when the specification is poorly-prepared or does not
contain specific requirements? _________________________________________
__________________________________________________________________
5. What likely becomes the governing document when there is no specification for a
coatings project? __________________________________________________
6. List three basic parts to a coating specification: _____________________
________________________________
_____________________________
7. In which of the three Parts of a coatings specification listed in Question 6 are the
references and definitions found? _____________________________________
8. In which of the three Parts of a coatings specification listed in Question 6 are the
coatings listed that will be used on a project? ____________________________
9. In which of the three Parts of a coatings specification listed in Question 6 is the
degree of surface cleanliness identified? ____________________________
10. In which of the three Parts of a coatings specification listed in Question 6 is the
thickness range of each coat listed? _________________________________

83

PCI Study Guide- October 2007

Module Eleven: Specification Review and Pre-Construction Conference; Inspection


Plan Development for the Inspection of Fuel Tank Lining Installation
Module Eleven describes the purpose and content of a pre-construction conference and
explains how to prepare an inspection plan. After a careful review of the project
specification during the Module Ten workshop, a preconstruction conference will be
conducted. Participants are provided with an agenda of discussion items, photographs of
the project site and Product Data Sheets and MSDSs for the coatings selected for the
project. The course instructors represent the painting contractor and the coating
manufacturer. The participants are divided into two groups; one group role play the
Quality Assurance Inspector representing the facility owner, while the other group role
plays the contractors Quality Control Inspector.
**It should be noted that this module is completed in a team setting, which is
considered key to completing the practical exam with success. Opting out of the
classroom portion of the course does not permit access to this workshop.**
Learning Outcomes
At the completion of this module you should be able to:
- Completion of Module Eleven will enable the coatings inspector to participate in
pre-construction conferences and prepare an inspection plan/procedure.

84

PCI Study Guide- October 2007

Module Twelve: Simulated QA/QC Inspection of Fuel Tank Interior Lining


Installation
Module Twelve includes an inspection workshop which enables the participants to apply
learned skills from the previous eleven modules. Ten inspection stations are equipped
with instruments, visual guides and miscellaneous equipment and test plates. Participants
work in small groups to perform inspections at each station, document the results of the
inspections and compare the results to the project specification provided in Module Ten
and the inspection procedures developed in Module Eleven. After all the groups have
completed all of the stations, the participants reconvene and discuss any problems and
non-conformities observed.
**It should be noted that this module is completed in a team setting, which is
considered key to completing the practical exam with success. Opting out of the
classroom portion of the course does not permit access to this workshop.**
Learning Outcomes
At the completion of this module you should be able to:
- Completion of Module Twelve will enable the coatings inspector to perform
coatings inspection, document inspection data, and compare inspection results to
specification requirements.

85

PCI Study Guide- October 2007


Appendix A
Quiz Answer Keys

A-1

PCI Study Guide- October 2007


Appendix A
Quiz Answer Keys

A-1

PCI Study Guide- October 2007


Appendix A
Quiz Answer Keys

A-1

PCI Study Guide- October 2007

SSPC PROTECTIVE COATINGS INSPECTOR (PCI) TRAINING


MODULE 1 QUIZ ANSWER KEY

1. Corrosion is defined as the deterioration of metallic surfaces


2. Carbon steel releases energy during the corrosion process.
3. The use of protective coatings is the most widely used method of corrosion control.
4. List four elements of a corrosion cell:
Anode
Metallic Pathway

Cathode
Electrolyte

5. Which of the four elements in question 4 does a protective coating prevent from
contacting the steel? Electrolyte
6. When corrosion occurs, the anode depletes or decays.
7. If a copper pipe is connected to an aluminum pipe without an insulator, which metal
represents the anode? Aluminum
8. List two dissimilar metals that are intentional coupled in the protective coatings
industry as a method of corrosion prevention?
zinc and aluminum
9. What type of chemical will deteriorate uncoated weathering steel? Salt
10. Lamellar pigments form plate-like layers and provide barrier protection to steel
surfaces.
11. What two elements are prevented from contacting the steel when a barrier-type
coating is employed? Water (electrolyte) and air (oxygen).
12. Zinc-rich primers protect the steel by barrier and sacrificial protection.
13. Thermal spray metallizing and galvanizing protect the steel by barrier and sacrificial
protection.
14. Borates, chromates, phosphates and other pigments protect the steel by inhibition.
15. Cathodic protection can be in the form of sacrificial anode or impressed current.
16. Sacrificial anode is considered passive cathodic protection.
A-2

PCI Study Guide- October 2007

17. Impressed current is considered active cathodic protection.


18. Cathodic protection is used in conjunction with protective coatings.
19. Aluminum and copper are metals that form a protective oxidation layer.
20. When corrosion occurs, the steel is releasing (giving up) energy.

A-3

PCI Study Guide- October 2007

SSPC PROTECTIVE COATINGS INSPECTOR (PCI) TRAINING


MODULE 2 QUIZ ANSWER KEY

1. Quality Control is performing observations and tests, and documenting that the work
meets/exceeds the specification requirements.
2. Quality Control is the contractors responsibility.
3. Quality Assurance is the process to verify the quality of work performed as reported by
quality control personnel.
4. Quality Assurance is performed by the owner or a third party on behalf of the owner.
5. When an _owner performs QA with his direct staff, he has a contractual relationship
with the contractor and can exert control.
6. When a third party performs QA for the owner, he does not have a contractual
relationship with the contractor and can only advise and document, and advise the
contractors QC.
7. Independent of whether Quality Assurance personnel are on-site, the contractor
remains responsible for quality control.
8. When work is halted for an inspection, it is known as a hold point inspection.
9. List six common hold point inspections:
Pre-cleaning
Intermediate Coat Application
Surface Preparation
Topcoat Application
Primer Application
Cure
10. Which party should inspect the completed work first, QA or QC? QC
11. If the inspected area is deficient, which party should inspect the surface first after the
rework is completed, QA or QC? QC
12. QA observations and test results typically supersede those of QC.
13. Prior to a pre-construction conference an inspector should review the specification

.
A-4

PCI Study Guide- October 2007


14. List seven topics that should be discussed at a pre-construction conference:
Contractors Proposed Operation
Lighting
Inspector Safety and Access
Product Information
Inspection & Measurement
Visual Standard
Inaccessible Areas
15. An inspection plan can contain three columns, titled as:
Inspection Chechpoint
Inspection Method
Acceptance Criteria
16. The content of the acceptance criteria section for an inspection plan comes from the
specification.
17. A Work Plan should cover the individual phases of a project, including both
production and inspection.
18. A Work Plan is also known as a Process Control Plan.
19. One of the most important responsibilities of a coatings inspector is to document the
results of inspections.
20. Fraudulent documentation, falsification of time/expense reports and acceptance of
gifts in exchange for lenient inspection are ethical breaches.

A-5

PCI Study Guide- October 2007

SSPC PROTECTIVE COATINGS INSPECTOR (PCI) TRAINING


MODULE 3 QUIZ ANSWER KEY

1. Preparing a surface for coating application is the most critical and typically the
most costly step.
2. List five common responsibilities of a coatings inspector relating to surface
preparation:
Abrasive Cleanliness
Compressed Air Cleanliness
Removal of Grease/Oil Contamination

Surface Cleanliness
Surface Profile (roughness)

3. The two-fold purpose of surface preparation is to clean and roughen the substrate.
4. ASTM International and NACE International have prepared a standard and a
recommended practice for measurement of surface profile.
5. The specification dictates the required surface profile depth.
6. The surface profile or anchor pattern must be compatible with the entire coating
system.
7. List two fabrication defects that may be addressed in a coating specification.
Weld Spatter Edges/Corners
Laminations/Slivers
8. List three methods that can be used to inspect surfaces for the presence of
grease/oil:
Visual (rag) Black Light Water Break Test
9. Pack Rust occurs between mating surfaces, while stratified rust forms on the
surface of the steel.
10. Chemical contaminants like chloride trapped beneath a coating film can cause
osmotic blistering, underfilm corrosion and premature failure.
11. Testing for chemical contamination involves two steps: Extraction and Analysis.
12. Immersion environments are more conducive to coating deterioration caused by
chemical contamination beneath the coating film than atmospheric environments.
13. Suggested thresholds for soluble salt concentrations are found in the appendix to
SSPC SP12/NACE No. 5, High and Ultra-High Pressure Water Jeting
A-6

PCI Study Guide- October 2007


14. The depth and shape of the surface profile generated by abrasive blast cleaning is
determined by the type and size of abrasive and the hardness of the surface.
15. Abrasives fall into two general categories, Expendable and Recyclable.
16. SSPC AB 1 categorizes abrasives according to Type, Class and Grade.
17. The abrasive cleanliness requirements in SSPC abrasive specifications AB1, AB2
and AB3 are indirect requirements of the SSPC abrasive blast cleaning surface
cleanliness standards.
18. List four tests that an inspector can perform in the field to verify conformance to
SSPC AB1:
Water soluble contaminants
Surface Profile Yield
Oil Content
Particle Size Distribution (sieve analysis)
19. SSPC AB2 governs the quality of recycled ferrous metallic abrasives.
20. Steel grit produces an angular-shaped surface profile.
21. Steel shot produces a round-shaped surface profile.
22. List three tests that an inspector can perform in the field to verify conformance to
SSPC AB3:
Size
Cleanliness
Conductivity
23. List one test that an inspector cannot perform in the field to verify conformance to
SSPC AB2: Lead Content
24. The diameter of an S330 steel shot abrasive is 0.330mm.
25. Which abrasive is larger, G25 or G50? G25.
26. Centrifugal blast machines often incorporate a blend of steel shot and steel grit
abrasives.
27. Wet abrasive blast cleaning is used when airborne dust must be controlled.
28. High pressure water jetting incorporates pressures from 35 to 69 MPa.
29. Chemical strippers do not remove rust or mill scale and will not generate a
surface profile.
30. Three methods used to prepare concrete for coating include:
Mechanical methods Chemical methods
Thermal methods

A-7

PCI Study Guide- October 2007


31. SSPC surface cleanliness standards become contract law once they are invoked by
the specification.
32. SSPC-SP1, Solvent Cleaning is an indirect requirement of the SSPC surface
cleanliness standards.
33. SSPC-SP2 Hand Tool Cleaning requires the removal of all loosely adhering
rust, mill scale & paint.
34. SSPC-SP2 requires the use of a dull putty knife as the inspection tool.
35. SSPC-SP3 Power Tool Cleaning requires the removal of all loosely adhering
mill scale, rust & paint.
36. What is the primary difference between SSPC-SP15, Commecial Grade Power
Tool Cleaning and SSPC-SP11, Power Tool Cleaning to Bare Metal?
SSPC-SP15 allows up to 33% staining to remain in each 9 square inches of
surface, where SSPC-SP11 does not permit any staining.
37. In addition to solvent cleaning compressed air cleanliness is an indirect
requirement of SSPC-SP3, SP15 and SP11.
38. Which two SSPC surface cleanliness standards invoke a minimum surface profile
requirement? SSPC-SP11 and SSPC-SP15
What is the minimum requirement? Minimum of 1 mil (25 microns)
39. List three possible indirect requirements of the SSPC abrasive blast cleaning s
tandards:
Solvent cleaning (SSPC-SP1)
Abrasive cleanliness
Compressed air cleanliness (ASTM D4285)
40. The amount of staining allowed by the SSPC abrasive blast cleaning standards is
based on what area? 9 square inches (58 cm2)
41. SSPC-SP7/NACE No. 4, Brush-off Blast Cleaning requires the removal of all
loosely adhesring rust, paint & mill scale.
42. SSPC-SP14/NACE No. 8, Industrial Blast Cleaning allows up to 10% intact
rust, paint or mill scale to remain. The amount of staining is unlimited.
43. The only difference between SSPC-SP 6/NACE No. 3, Commercial Blast
Cleaning and SSPC-SP10/NACE No. 10, Near-White Blast Cleaning is the
percentage of allowable staining. SP6 allows up to 33% staining, where SP10
allows up to 5% staining (of each 9 square inches of surface).

A-8

PCI Study Guide- October 2007


44. SSPC-SP6/NACE No. 3 allows up to 33% staining to remain on each 9 square
inch area.
45. SSPC-SP10/NACE No. 2 allows up to 5% staining to remain on each 9 square
inch area.
46. SSPC-SP5/NACE No. 1 allows no paint, rust, mill scale or straining to remain.
47. SSPC-SP12/NACE No. 5, level WJ-2 allows up to 5% of the surface to contain
straining or tightly adhering matter.
48. The L in SSPC SP12-WJ-3-L indicates light flash rusting is permitted by the
specification.
49. ISO St2, Thorough Hand and Power Tool Cleaning requires removal of all
poorly adhering materials.
50. ISO Sa 2 1/2, Very Thorough Blast Cleaning allows only stains to remain on
the surface.
51. The SSPC/NACE and ISO cleanliness standards prohibit the use of magnification
when inspecting surface cleanliness.
52. Prior to final surface preparation, it is recommended that the inspector verify that
the surface temperature is at least 5oF (3oC) higher than the dew point
temperature.
53. Dehumidification equipment removes moisture from the air.
54. List three methods of dehumidification: Compression; Refrigeration; Dessication
55. Cooling air below the dew point for dehumidification of the air is the
Refrigeration method.
56. Products that absorb moisture from the air as a means of dehumidification use the
Dessication method.
57. Indicate the procedure for conducting a compressed air cleanliness test, below:
Conduct the test down stream of moisture and oil separation.
Position the air outlet 18 from the collector
Exhaust the compressed air onto the collector for approximately one minute.
58. To conduct a vial test, fill a clear container with 1/3 abrasive and an equal
amount of clean tap water. Allow the shaken blend to settle for 30 minutes.

A-9

PCI Study Guide- October 2007


59. The maximum abrasive conductivity according to the SSPC abrasive
specifications is 1000 S.
60. The minimum level of lighting for inspection is 538 Lux.
61. The recommended level of lighting for inspection is 200 ft/candles.
62. The visual standard reference G2 SP14 in SSPC VIS 1 indicates:
Weathered coating system over mill scale with moderate pitting abrasive blast
cleaned to an Industrial Blast level
63. The visual standard reference F SP3 PWB in SSPC VIS 3 indicates:
Previously painted steel surface; mostly intact zinc-rick primer applied to a blast
cleaned surface, power tool cleaned using a power wire brush
64. The visual standard reference D WJ3 M in SSPC VIS 4/NACE VIS 7 indicates:
Rusted and pitted steel surface prepared by thorough water jetting; with
moderate rust back permitted
65. The visual standard reference C WAB 6 H in SSPC VIS 5/NACE VIS 9
indicates: Rusted steel surface prepared by wet abrasive blast cleaning to a
Commercial Blast level; with heavy rust back permitted
66. The visual standard reference A Sa3 in ISO 8501-1:1988 indicates: Steel
surface containing adhering mill scale, blast cleaning to a visually cleanlevel
67. Surface profile is defined as the maximum peak-to-valley depth.
68. Profile generation increases the surface area of the steel.
69. An increase in peak count reportedly enhances coating adhesion and a greater
resistance to corrosion undercutting.
70. The G/S comparator disc is selected for inspection of surface profile when garnet
abrasive is used to perform abrasive blast cleaning.
71. 3.0SH76 on a comparator disc segment indicates: 3 mil surface profile; Shot
comparator disc; 1976.
72. Verify zero-set on a surface profile depth micrometer using a glass plate.
73. The measuring range of X-Coarse replica tape is 1.5-4.5 mils.
74. The thickness of the Mylar film on replica tape is 2 mils.
75. Each grade of replica tape is most accurate in the middle of the range.

A-10

PCI Study Guide- October 2007


76. Complete the following chart:
Parts Per Million Chloride
Amount of Extraction Liquid
Micrograms of Chloride
Area Extracted
Micrograms per cm2 chloride

176
2 mL
352 g
12.25 cm2
28.7 g/ cm2

77. Complete the following chart:


Conductivity of sample
Conductivity of blank
Net Conductivity of sample

120 S/cm
8.7 S/cm
111.3 S/cm

78. Convert 35 S/cm to surface chloride concentration using the formula on Page
3-147.
E = 0.3 x S x (V/A)
0.3 x 35 x (212.25)= 1.71g/cm2
79. A pH of 10 is considered alkaline
80. A pH of 3 is considered acidic

A-11

PCI Study Guide- October 2007

SSPC PROTECTIVE COATINGS INSPECTOR (PCI) TRAINING


MODULE 4 QUIZ ANSWER KEY
1. Average the following set of surface profile measurements: 3.5, 3.7, 2.9, 3.1, 4.0
3.4 mils
2. Convert 39% to decimal format.

0.39

3. Calculate the amount of thinner to add to 10 gallons of mixed coating to be


reduced 20%. 2 gallons
4. Calculate the area of a square that is 4.5 feet x 13.6 feet. 61.2 square feet
5. Calculate the area of an I-beam that is 40 feet in length, has 12 wide flanges, a
48 web, and 8 stiffeners (4 wide x 48 long). 491 square feet
6. Calculate the exterior surface area of a tank that is 45 feet in height and 90 feet in
diameter.
C = 3.14 x 90 feet = 283 feet
Area of roof (A) = 90 2 = 45; 3.14 x 452 = 6359 sq. ft.
45 x 283 = 12,735 sq. ft.
12,735 + 6359 = 19,094 sq. ft.
Calculate the volume of water the tank in Question 6 will hold.
(3.14 x 452) x 45 = 286,133 cubic feet
286,133 cu. Ft. x 7.48 gallons/cu. Ft. = 2,140,275 gallons
7. Convert 2.4 pounds/gallon VOC to grams/Liter. 288 g/L
8. Convert 64oF to oC. 18oC
9. Convert 275 micrometers to mils 11 mils
10. Calculate the quantity of primer required to coat 15,000 square feet of blast
cleaned steel, based on the following data:
Specified Dry Film Thickness:
3-5 mils
Volume Solids Content:
84%
Mixing/Application Loss Estimate: 25%
Surface Roughness Loss Estimate: 20%
Recommended Thinner Addition: One pint per gallon
1604 5 mils = 321 sq. ft./gal.
321 x 0.84 = 270 sq. ft./gal.
270 x 0.75 = 203 sq. ft./gal.
203 x 0.80 = 163 sq. ft./gal. 15,000 sq. ft. 163 sq. ft./gal. = 92 gallons
A-12

PCI Study Guide- October 2007

SSPC PROTECTIVE COATINGS INSPECTOR (PCI) TRAINING


MODULE 5 QUIZ ANSWER KEY
1. A product data sheet is considered an instruction manual for a coating.
2. Calculate a target wet film thickness based on the following data:
Dry film thickness:
Volume solids content:
Thinner addition:

5-7 mils
72%
12.5%

8-11 mils WFT

3. During a material receipt inspection, the inspector should record the following
seven items:
Name of Coating Manufacturer
Thinner Manufacturer
Product Name
Thinner Name/No.
Product No.
batch No. of Thinner
Batch No. of Each Component
4. Most coating manufacturers prohibit mixing of partial kits.
5. Most industrial coatings must be mixed using a shear-type mixing blade.
6. Boxing a coating is not recommended for which two generic types of coatings?
Inorganic zinc-rich primers Moisture-cure Urethanes
7. When inspecting mixing of zinc-rich primers, the zinc powder component should
be slowly sifted into the liquid component while under agitation.
8. Straining of a zinc-rich primer is typically required by the specification or coating
manufacturers PDS.
9. Pot agitation is typically required for zinc-rich primers, except moisture-cured
single component zinc-rich primers.
10. What is the first step when considering adding thinner to a coating? Determine
whether thinning is permitted by the manufacturer and specification
11. What is the second step when considering adding thinner to a coating? Determine
the type and amount of thinner to be added
12. List three consequences of adding an unknown quantity of thinner to a coating.
Net effect on VOC content is unknown
Target WFT is unknown
May result in sagging and/or accelerated surface drying
A-13

PCI Study Guide- October 2007

13. Application of coating to welds, edges, bolt/nuts, and rivets prior to full scale
application is known as stripe coating.
14. Daubers are used to coat crevices and between back-to-back angles.
15. Airless spray is the most common method used to apply industrial/marine
coatings.
16. What is the paint pressure when the regulator on 45:1 airless spray pump is set to
60 psi? 2,700 psi
17. What does the marking 723 indicate on an airless spray tip? 14 fan when gun is
positioned 12 from the surface; 0.023 tip opening
18. Proper distance of an airless spray gun from the surface is 12 inches.
19. The upper control on a conventional spray gun controls the shape of the fan
pattern.
20. The lower control on a conventional spray gun controls the amount of paint that
exits the spray tip.
21. Proper distance of a conventional spray gun from the surface is 6-8 inches.
22. The diameter of the holes in an HVLP spray air cap are larger than the holes in a
conventional spray air cap.
23. Plural component spray is used to apply coatings with what characteristics? Short
Pot Life and 100% Solids
24. For plural component spray, what method is typically used to reduce viscosity of
the components? Heated material hoses
25. An applicator should overlap spray passes 50% to build a consistent thickness.
26. List ten common inspection checkpoints that are performed on nearly every
industrial coatings project:
Verification of correct materials
Verification of correct materials
Verification of current shelf life
Verification of correct materials
Measuring ambient conditions & surface temp.
Mixing procedures
Measuring coating temperature
Assessing intercoat cleanliness
Measuring DFT
Verification of rcoat times/temperatures

A-14

PCI Study Guide- October 2007

27. What two values are used to determine the relative humidity and dew point
temperature when using a sling or battery powered psychrometer in conjunction
with the US Weather Bureau Psychrometric Charts?
Air Temperature
Depression of wet bulb thermometer (from dry bulb)
28. Ambient conditions should be measured where the work will be performed
29. The temperature of the surface to be coated must be at least 5oF (3oC) above the
Dew Point Temperature.
30. The wet bulb temperature is considered to be stabilized when two readings taken
within 20-30 seconds are within 0.5o of one another.
31. A coating material with a six hour pot life and a 45 minute induction has a useable
pot life of 5 hours & 15 minutes.
32. The wet film thickness reading on a wet film thickness gage is considered the
highest (wetted) numbered tooth (step) on the gage.
33. According to SSPC PA2, the accuracy of a coating thickness gage should be
verified before and after each period of use.
34. A Type 1 gage is known as a magnetic pull-off gage.
35. A Type 2 gage is known as an electronic gage.
36. The accuracy of Type 1 gages is verified using calibration blocks.
37. The accuracy of Type 2 gages is verified using non-metallic foils or plastic shims.
38. The effect of surface roughness on a coating thickness gage measurement is
known as a base metal reading.
39. The BMR is subtracted from the coating thickness to determine the thickness of
the coating above the peaks of the surface profile.
40. If the tolerance of a coating thickness gage is +/- 5% and the tolerance of the
standard used to verify gage accuracy is +/- 3%, what is the tolerance of the
reading on a 6.4 mil test block? 6-6.8 mils (+/- 6%, which is +/-0.4 mil)
41 The BMR is not necessary to measure when a Type 2 gage is verified for
accuracy using plastic shims placed onto the prepared, uncoated steel.
42. How many spot measurements are obtained within an area? 5

A-15

PCI Study Guide- October 2007


43. How many individual readings comprise a spot measurement? Minimum of 3
44. The surface to be assessed for DFT represents 600 square feet
No. of areas to measure: 3
Total No. of spots: 15
Minimum no. of individual gage readings: 45
45. The surface to be assessed for DFT represents 24,000 square feet
No. of areas to measure: 26
Total no. of spots: 130
Minimum no. of individual gage readings: 390
46. The surface to be assessed for DFT represents an I-beam that is 40 feet in length,
has 12 wide flanges, a 48 web.
No. of areas to measure: 5
Total no. of spots: 70
Minimum no. of individual gage readings: 210
47. According to SSPC PA2, what is the tolerance of a spot measurement for a
project specification that specifies 2-4 mils of primer? 1.6 4.8 mils
48. When spot or area DFT measurements do conform to the specification
requirements, then each 100 square foot area coated during the same work shift
must be inspected.
49. What is the cumulative thickness range of the primer and intermediate coats for a
project specification that requires 4-6 mils of primer and 8-10 mils of intermediate
coat? 12-16 mils
50. If the coating thickness is 12-15 mils, what Tooke gage tip should be used to
make an incision through the coating film to assess layer thicknesses? 2X
51. The following data was acquired when viewing an incision (made with a 10X
cutting tip) through a Tooke Gage lens. What is the thickness of each layer?
Primer: 10 divisions: 1 mils
Intermediate: 12 divisions: 1.2 mils
Topcoat: 20 divisions: 2 mils
52. Amine exudate or blush can occur on epoxy coatings that are applied and/or
cured during high humidity, cool conditions.
53. Application of coatings over an amine exudate may result in what type of coating
failure?
Intercoat delamination
54. A pinhole is a tiny void in the coating that penetrates to the substrate.

A-16

PCI Study Guide- October 2007

55. A holiday is a skip or miss in the lining system application.


56. Low voltage, wet sponge pinhole detection is can be used on nonconductive
coatings (up to 20 mils) applied to a conductive substrate.
57. High voltage, spark testing is can be used on nonconductive coatings applied to a
conductive substrate.
58. According to NACE RP0188-99, the suggested voltage for testing a coating
system that is 41-55 mils thick is 4000 volts.
59. The most reliable method for determining the cure of an ethyl silicate inorganic
zinc-rich primer is the solvent rub test.
60. If a 3H pencil will not scratch or gouge the coating film, but a 4H pencil will,
what is the pencil hardness of the coating? 3H
61. Tensile adhesion testers assess the pull-off strength of coatings; while tape
adhesion assesses the coatings resistance to peel-back.
62. The cross-cut method (Method B) of the tape adhesion test is used for coatings
that are less than 5 mils thick.
63. When a coating breaks cleanly from the substrate, the location of break is
adhesion.
64. What is the primary difference between conducting an adhesion test per ASTM
D3359 (method A) and ASTM D6677? Tape is not used on the X-cut when
conducting testing per ASTM D6677
65. The gage for measuring the thickness of coatings on concrete (nondestructively)
employs an ultrasonic (ultrasound) principle of measurement.

A-17

PCI Study Guide- October 2007

SSPC PROTECTIVE COATINGS INSPECTOR (PCI) TRAINING


MODULE 6 QUIZ ANSWER KEY

1. The resin, solvent and additives are known as the vehicle of a coating that carries
the pigment to the surface and binds it into the film.
2. List five functions of pigment in an industrial/marine coating:
Color
Barrier protection
Hiding power
Corrosion (inhibitive) protection
Gloss level of coating
3. Solvents are part of the wet film, but are not part of the dry film.
4. Primary solvents are used to reduce viscosity; secondary solvents are used to help
the coating flow and knit together.
5. Coatings that dry rather than cure form a solid film by a process known as
solvent evaporation.
6. Waterborne coatings cure by a process known as coalescence.
7. Coatings that cure by a reaction with oxygen cure by oxidation.
8. Multi-component epoxy and polyurethane coating cure by polymerization.
9. Coatings that hydrolyze are said to moisture cure.
10. What is the primary function of an intermediate coat? Barrier Protection
11. Which coating system is recommended for use on surfaces with an elevated
temperature in a waste water treatment plant? Inorganic zinc primer/silicone
topcoat
12. Mounting test panels containing candidate coating systems in the actual
environment where the new coating will be installed is known as a facilityspecific performance evaluation.
13. Coatings contain two categories of ingredients: Non-volatile and Volatile.
14. Thinner addition increases the VOC content of a coating.
15. Prior to selecting a coating system, the facility owner must properly identify the
prevailing service environment.
A-18

PCI Study Guide- October 2007

SSPC PROTECTIVE COATINGS INSPECTOR (PCI) TRAINING


MODULE 7 QUIZ ANSWER KEY

1. The primer used on connection points of I beams must often have a Class A or
Class B slip coefficient if the connection is slip critical.
2. List four inspection concerns relating to application of primers on slip-critical
connections.
Primer thickness
Amount of thinner used
Type of thinner used Cure time prior to boling the connection
3. List three forms of metallized spray:
Flame sray Arc spray
Plasma spray
4. What is the minimum surface cleanliness and surface profile depth for metallizing
applied to structures for marine or immersion service? SSPC-SP5; minimum 2.5
mil angular surface profile
5. Which form of metallizing feeds two wires to a spray gun? Arc spray
6. When measuring the thickness of thermal spray coatings on flat surfaces, a
minimum of 5 readings are obtained in a line spaced 1 inch apart.
7. When measuring the thickness of thermal spray coatings on a complex geometry,
a minimum of 5 readings are obtained in a 1.6 square inch diameter spot.
8. Powder coating may be cured using heat or ultraviolet (UV) light.
9. List seven inspection check points associated with powder coating application.
Powder material
Thickness
Surface preparation Continuity
Curing
Hardness
Appearance
10. Application of a liquid coating over a galvanized surface is known as a Duplex
system.
11. Weathered galvanizing is optimum for coating, while new galvanizing is difficult
to coat.
12. If sweep blasting of galvanizing is specified, the inspector may be required to
measure the nozzle air pressure prior to sweep blasting operations.
A-19

PCI Study Guide- October 2007

13. Most Type 1 and Type 2 DFT gages display the total thickness of the galvanizing
and coating layers.
14. On overcoating projects, the inspector should verify that visible grease and oil
contamination are removed prior to surface preparation.
15. Areas of sound coating adjacent to repair areas should be feathered to ensure a
smooth transition for the new coating and to prevent lifting of the existing coating.
16. If a brush-off blast (SSPC-SP 7/NACE No. 4) is specified for an overcoating
project, the inspector may be required to measure nozzle air pressure and verify
proper abrasive type to ensure neither is too aggressive.
17. Pressure washing to remove dirt, chalking, etc. must be carefully inspected to
ensure adequate removal prior to overcoating.
18. Prior to application of the overcoat material, an inspector should obtain thickness
measurements on the existing coating.
19. The thickness of the overcoat can be isolated from the thickness of the existing
coating by using a Tooke Gage.
20. List three toxic metals that may be in existing coatings:
Lead Chromium
Hexavalent Cadmium
21. A containment is designed to protect the environment and the public
22. Ventilation inside a containment is designed to protect workers.
23. SSPC Class 1 containment provides the highest level of protection.
24. Negative pressure is monitored visually or by reading a magnehelic gage.
25. Air flow inside a containment can be monitored using a rotating vane
anemometer.
26. List two devices for monitoring air quality outside of a containment:
Total Suspended Particulate (TSP) Particulate matter 10 microns and smaller
(PM-10)
27. Pre- and post-project soil and/or water sampling and analysis may be required to
verify effectiveness of the containment.
28. List three things a coatings inspector should never do inside a regulated area:
Eat
Drink
Use tobacco products

A-20

PCI Study Guide- October 2007

29. Hazardous waste can only be transported by licensed hauler.


30. List two SSPC Guides that govern containment and hazardous waste management
procedures:
Containment: SSPC Guide 6
Waste: SSPC Guide 7

A-21

PCI Study Guide- October 2007

SSPC PROTECTIVE COATINGS INSPECTOR (PCI) TRAINING


MODULE 8 QUIZ ANSWER KEY

1. List six possible causes of premature coating failure:


Improper surface preparation
Improper formulation
Improper coating application
Poor quality raw materials
Improper coating system selection
Design of the structure
2. List four consequences of coating failures:
Substrate repair/replacement
Downtime
Costly rework
Aesthetics
3. Describe how a coatings inspector can help prevent coating failures from occurring.
By verifying that each step in the surface preparation and coating/lining installation
process meets the requirements of the project specification. By identifying deficiencies as
they occur and working with the contractor to bring the deficient areas into conformance
with the specification before additional work progresses.
4. What key item maintained by an inspector is critical to a coating failure investigation?
Thorough, complete, dated and signed inspection documentation

A-22

PCI Study Guide- October 2007

SSPC PROTECTIVE COATINGS INSPECTOR (PCI) TRAINING


MODULE 9 QUIZ ANSWER KEY

1. The coatings inspector shares in the responsibility for the safety of other workers
and the public.
2. A coatings inspector that observes an imminent hazard that may cause death or
serious injury should take immediate action to prevent the accident.
3. Who should an inspector obtain guidance from regarding their role relative to
safety issues? Employer and/or counsel
4. List an example of a General Risk that a coatings inspector may be exposed to:
Explosion; hazardous atmosphere; scaffold collapse; Inadequate hazard
warnings around site
5. List an example of a Personal Risk that a coatings inspector may be exposed to:
Entering a confined/hazardous space; falling; breathing in toxic metals
6. What is the primary difference between exposure hazards associated with
inspection verses exposure hazards to painters? The magnitude or duration of
exposure may be less for an inspector
7. List two hazardous materials that will be present on every coatings project:
Solvents/thinners and coating components
8. The inside of a storage tank can be considered what type of hazardous
environment? Confined space
9. Why is airless spraying categorized as a hazardous activity? High pressure and
an injection hazard
10. The effect of hazardous materials on an inspectors health depends on the level,
duration and route of exposure.
11. List four items that are of the greatest value to an inspector on an MSDS:
Health hazards (sign & symptoms of exposure)
Primary routes of entry into the body
Precautions of safe handling and use
Controls measures and PPE
12. What is the most frequent way solvents affect the body? Skin contact
A-23

PCI Study Guide- October 2007

13. Polyurethane coatings contain a chemical known as isocyanates, which are strong
irritants and sensitizers.
14. Respirators equipped with HEPA filtration cartridges can filter respirable sizeddust.
15. Heights greater than six feet above a lower level require fall protection.
16. What type of lanyard is a component to a personal fall arrest system? Shockabsorbing
17. List three items that an inspector should verify before entering a confined space:
Verify it has been tested and cleared for entry
Proper personal protective equipment is employed
Current training
18. What electrical hazard cannot typically be locked-out/tagged-out? Energized 3rd
rails; overhead transmission wires
19. What hazard is associated with inadequate lighting? Trips and falls
20. List two basic types of respirators: Air purifying & Supplied air
21. Most coating inspection gages are not intrinsically safe and should not be used in
hazardous environments.

A-24

PCI Study Guide- October 2007


Appendix B

Glossary
A
Abrading. (1) Erosion by mechanical or particulate impact. (2) Surface preparation of
concrete that is intended to roughen the surface profile and remove foreign materials.
Methods classified as abrading include mechanical abrasion, waterjetting, and abrasive
blast cleaning. Abrading methods are defined in ASTM D 4259.
Abrasion Resistance. The ability of a coating to resist being worn away and to maintain
its original appearance and structure when subjected to rubbing, scraping, or wear.
[ASTM]
Abrasive. (1) A material used for wearing away a surface by rubbing. (2) A fine,
granulated material used for blast cleaning. Abrasive particles of controlled mesh sizes
are propelled by compressed air, water, or centrifugal force to clean and roughen a
surface. Blast cleaning abrasives often are simply referred to as metallic or non-metallic
and as shot- or grit-like. [PCG]
Abrasive Air Blast Cleaning. See Air Abrasive Blast Cleaning.
Abrasive Blast Cleaning. Also called abrasive blasting, a surface preparation method
that uses an abrasive propelled by air pressure, centrifugal force, or water pressure to
clean and usually to profile a surface. Stand-off distance, angle of attack, and dwell time
are the three most important variables under the control of an operator that can affect the
quality and effectiveness of the blast cleaning. [PCG]
Abrasive Blasting. See Abrasive Blast Cleaning.
Abrasive Mix. Also called work mix or operating mix, the mixture of metallic or
recyclable non-metallic abrasive sizes that results from the periodic addition of new
abrasive to recycled abrasive during a blasting operation to maintain cleaning rate and
surface profile.
Abrasive Wheels. Metallic wheels mounted on a rotary power tool, commonly used to
grind welds and remove weld spatter. Also used to remove rust and mill scale from
localized areas. See Power Tool Cleaning.
Accelerator. See Catalyst.
Activator. See Catalyst.
Adhesion. The degree of attraction between a coating and a substrate or between two
coats of paint that are held together by chemical or mechanical forces or both. Adhesion
often is called the bonding strength of a coating. Adhesion should not be confused with
cohesion, which is the force holding a single coating layer together. [PCG]
Adhesion Failure. A breakdown between two distinct coating layers or between the
substrate and the first layer of coating. See Adhesion Test, Tensile (Pull-Off).
Adhesion Test, Crosscut. Also called crosshatch test, a coatings adhesion test in which a
crosshatch pattern is scribed onto the coated surface, then tape is applied and pulled off.
Adhesion is assessed according to surface area from which flaking has occurred (ASTM

B-1

PCI Study Guide- October 2007


D 3359). Adhesion measured by the crosscut test is referred to as the shear (or knife)
adhesion.
Adhesion Test, Tensile (Pull-Off). A method for testing the greatest perpendicular force
that an area of coating can withstand before: (1) detaching from the surface (adhesion) or
(2) fracturing within a layer of coating or substrate (cohesion). The method can also be
used to determine whether a coating will remain intact at a particular applied tensile
force. This standard test method is defined in ASTM D 4541.
Aggregate. (1) A group of dry pigment particles held together by their surface forces; the
spaces between the particles are filled with air. [CED] (2) Granular material, such as
sand, gravel, crushed stone, crushed hydraulic-cement concrete, or iron blast-furnace
slag, used with a hydraulic cementing medium to produce either concrete or mortar.
[ACI]
Air Abrasive Blast Cleaning. Also called abrasive air blast cleaning, a surface
preparation method in which compressed air is used to propel abrasive particles against a
surface to be cleaned. Open blast cleaning indicates that a localized containment does
not surround the blast stream. Closed blast cleaning means that a localized containment
does surround the blast stream. [PCG]
Airless Spraying. A coating application method that uses hydraulic pressure instead of
air to atomize paint by forcing it through a spray nozzle with a small orifice at a pressure
of 2,000 to 3,000 psi (14-21 MPa). The spray pattern and flow of paint are controlled by
the size and shape of the orifice. The size of the orifice must be matched with the
viscosity of the paint and the size of the material pump. This process is aided if the
material is previously heated. [PCG]
Aliphatic. A class of organic hydrocarbon compounds composed of open chains. These
include paraffins, olefins, etc.
Alligatoring. Crazing or surface cracking with a definite pattern that looks like alligator
hide. The effect is often the result of weather aging of a coating. See also Cracking.
Ambient Conditions. The weather including: air temperature, relative humidity, dew
point, and wind velocity, which are monitored on the job site.
Amine. An organic compound derived from ammonia when one or more hydrogen atoms
is replaced with hydrocarbon radicals. It is used as a curing agent for epoxy resins.
Amine Blush. Surface opalescence (blush) on epoxy films caused by reaction of amine
co-reactant with carbon dioxide and water to form an amine carbamate.
Anchor Pattern. See Surface Profile.
Anhydrous. Moisture-free; a compound without water of crystallization. [PCG]
Anode. The electrode of an electrolytic cell at which oxidation occurs. Electrons flow
away from the anode in the external circuit. It is usually at the anode that corrosion
occurs and metal ions enter solution. Contrast with Cathode. [ASM]
Anodized. An electrochemical protective or decorative oxide film.
Anti-Fouling. A coating formulated to release noxious or poisonous substances at a
controlled rate to prevent the growth of barnacles, algae, and other organisms on the
underwater part of a ship hull. [PCG]
Arcing. Spraying a coating with the gun moving in an arc, rather than at a constant
distance from the substrate surface, so that a film of varying thickness results. Arcing
may also occur with abrasive blasting to produce a variable level of surface cleaning.
Arc Spraying. Metal spraying in which an electric arc is used to melt the metal.

B-2

PCI Study Guide- October 2007


Aromatic. Hydrocarbon containing an unsaturated ring of carbon atoms, typified by the
benzene ring structure. Xylene (xylol), toluene (toluol), and high-flash naphtha are
aromatic solvents used in coatings.

B
Ballast. Water stored in tanks on board ships to contribute to the trim and stability of the
vessel. Ballast is pumped in and out from the sea to adjust the draft and distribute weight
to control sag, hog, center of gravity, etc. This ballast can cause sweating on the exterior
surface, which can contribute to coating failure
Banana Gauge. An elongated magnetic dry film thickness gauge with a handle at one
end and a probe at the other end. Between the handle and the probe is a positioning base
and a thickness display dial. See Magnetic Gauge.
Barometric Pressure. Atmospheric pressure, referenced in the U.S. Weather Bureau
Psychrometric Tables. Used to aid in determining relative humidity and dew point, based
on the dry and wet bulb readings from the psychrometer.
Barrier Coat. (1) A coating or coating system that protects an underlying substrate by
minimizing or eliminating the penetration of moisture or vapors. (2) A coating used to
separate a layer of paint from a surface to prevent chemical or physical interaction.
[PCG]
Barrier Protection. See Barrier Coat.
Base. (1) The major component of a multicomponent coating system. In two-component
systems, the other component is usually called an accelerator, an activator, a
hardener, or a curing agent. (2) A subfloor slab or working mat, either previously
placed and hardened or freshly placed, on which floor topping is placed in a later
operation; also the underlying stratum on which a concrete slab, such as a pavement, is
placed. [ACI]
Bend Test. See Flexibility Test.
Binder. (1) Nonvolatile portion of the liquid vehicle of a coating. It binds or cements the
pigment particles together and the paint film as a whole to the material to which it is
applied. See Nonvolatile Vehicle. [CED] (2) Cementing material, either hydrated cements
or products of cement or lime and reactive siliceous materials; the kinds of cement and
curing conditions govern the general kind of binder formed; also materials such as
asphalt, resins, and other materials forming the matrix of concretes, mortars, and sanded
grouts.
Biofouling. Biological encrustation of surfaces in sea water by flora and fauna, e.g.,
barnacles.
Bisphenol A. Dihydroxydiphenyldimethylmethane, mol. wt. 224.1. Insoluble in water.
Used in the manufacture of phenolic and epoxy resins. Condensation product formed by
reaction of two (bis) molecules of phenol with acetone. This polyhydric phenol is a
standard resin intermediate, along with epichlorhydrin, in the production of epoxy resins.
[CED]
Bisphenol A Epichlorohydrin. Chemical name of epoxy resin that is reacted with
amines and other curing agents to form epoxy-based coatings.

B-3

PCI Study Guide- October 2007


Bisphenol F. Dihydroxydiphenyldimethylmethane. Used in the manufacture of phenolic
and epoxy resins. Condensation product of the reaction of two molecules of phenol with
formaldehyde.
Black Light. Popular term for ultraviolet (UV) radiation without any visible radiation..
[CED]
Blast Pot. A container that holds abrasive material until it is mixed with compressed air
in air abrasive blast cleaning systems. [PCG]
Blasting Pressure. The pressure, usually expressed in pounds per square inch (PSI) or
kiloPascals (kPa), of an air and abrasive mixture as it passes through the nozzle of an
abrasive blasting system.
Blistering. (1) The dome-shaped projections in paints or varnish films resulting from
local loss of adhesion and lifting of the film from an underlying paint film (intercoat
blistering) or the base substrate. The standard test method for evaluating the degree of
blistering of paints is described in ASTM D 714. [PCG, V1] (2) The irregular raising of a
thin layer at the surface of placed mortar or concrete during or soon after finishing, or in
the case of pipe after spinning; also bulging of the finish plaster coat as it separates and
draws away from the base coat. [ACI]
Blotter Paper. Soft, spongy, absorbent paper.
Blotter Test. The test for checking the cleanliness of compressed air supply as it reaches
the blasting nozzle (described in ASTM D 4285).
Blowdown. Removing dust from a surface with a stream of clean compressed air.
Blushing. Film defect that appears as a milky opalescence as the film dries; can be a
temporary or permanent condition. It is generally caused by rapid evaporation, moisture,
or incompatibility. [CED]
Bolted Connection. A mechanical fasting (connection) consisting of a threaded metal
rod or pin (bolt) joined to a metal nut.
Boottop. The area on the exterior hull of a ship between the light load line and the deep
load line. The boottop will be fully immersed when the cargo is fully loaded and above
water when the vessel is lightly loaded. This area is exposed to sun, wind, and water
when light and to immersion when fully loaded.
Bosuns Chair. A rigging device suspended from a single cable or rope and designed for
use by a single individual, who is limited to working in a sitting position. It allows access
to high work areas and provides good maneuverability and accessibility to areas not
easily reached by larger scaffolding systems. [PCG, V1]
Boxing. Pouring paint from one container into another several times to assure that no
unmixed material remains on the bottom and that the paint is uniformly mixed. [PCG]
Breathing-Type Coating. A coating that is sufficiently permeable to permit transmission
of water vapor without detrimental effect to itself. [CED]
Bresle Sampler. A latex rubber cell that adheres to a surface, used to aid in the extraction
of water-soluble surface contaminants.
Brookfield Viscometer. A viscometer in which a cylinder or disk is rotated in a test
liquid, and the torque necessary to overcome viscous resistance is measured. ASTM D
2196 covers the determination of the apparent viscosity and the shear thinning and
thixotropic properties of non-Newtonian materials in the shear range of 0.1 to 50 s-1.
[CED]
Brush Blasting. See Brush-Off Blast Cleaning.

B-4

PCI Study Guide- October 2007


Brush Down. To remove dust from a surface with a clean, soft brush.
Brush-Off Blast Cleaning. Blast cleaning standard with the lowest quality requirements.
According to SSPC-SP 7/ NACE No. 4, a brush-off blast cleaned surface is free of all
visible oil, grease, dirt, dust, loose mill scale, loose rust, and loose paint. Tightly adherent
mill scale, rust, and paint may remain on the surface. [PCG]
Brushout. The application of paint on a small surface for testing.
Bulkhead. (1) An upright partition or wall separating compartments, as in a ships hold.
(2) Wall retaining soil along waterfront.
Burnish. To polish or rub to a smoother or glossier surface. [CED]

C
Cadmium. Toxic heavy metal. Cadmium compounds have been used as color pigments
(e.g., orange, red, yellow) often mixed with other heavy metal compounds. Their use in
coatings is restricted because of toxicity.
Calcium Carbonate. A white crystalline substance used as an extender pigment. Also
known as calcite, marble dust, carbonate of lime, English whiting, limestone, and
cliffstone whiting. [PDC, PCG]
Calibrate. To check, adjust, or determine by comparison with a standard. [CED]
Calibration Plates. Precision plates used for calibrating magnetic dry film thickness
gauges. Most commonly used standard plates are from NIST.
Calibration Shims. Small color coded shims, usually plastic of various thicknesses that
are used for calibrating Type II (fixed probe) magnetic dry film thickness gauges.
Carbon Black. Finely divided carbon formed by any one of several processes. Synonym:
gas black. These carbon blacks vary in particle size and some of them may be surface
treated. [CED]
Carcinogen. A material that either causes cancer in humans, or, because it causes cancer
in animals, is considered capable of causing cancer in humans. [CED]
Catalyst. A reaction promoter. A substance that induces, alters, or accelerates a chemical
reaction. A true catalyst is unchanged by the reaction it creates. In the coatings industry,
catalysts (also called activators, accelerators, and promoters) are used to speed the curing
or crosslinking of certain coatings. Curing agents and hardeners (which enter into
chemical reactions) are also sometimes (incorrectly) referred to as catalysts. [PCG]
Cathode. The electrode of an electrolytic cell at which reduction is the principal reaction.
(Electrons flow toward the cathode in the external circuit.) Typical cathodic processes are
cations taking up electrons and being discharged, oxygen being reduced, and the
reduction of an element or group of elements from a higher to a lower valence state.
Contrast with Anode. [ASM]
Cathodic Disbonding. Mechanical lifting of a coating caused by hydrogen bubbles
formed when cathodic protection is excessive.
Cathodic Protection. (1) Reducing the corrosion rate by shifting the corrosion potential
of the electrode toward a less oxidizing potential by applying an external electromotive
force. (2) Partial or complete protection of a metal from corrosion by making it a cathode,
using either a galvanic or an impressed current. [ASM]
Caustic. A strong chemical base. [CED]

B-5

PCI Study Guide- October 2007


Centrifugal Wheels. Finned wheels on abrasive blasting equipment that pick up and hurl
abrasive at high speeds onto the steel plates or shapes in a centrifugal blasting machine.
See Abrasive Blast Cleaning.
Chalking. (1) Formation of a friable powder on the surface of a coating film caused by
the disintegration of the binding medium due to ultraviolet light breaking chemical bonds
in the binder. The chalking of a coating film is dependent upon the binder and
pigmentation, as well as the intensity of the ultraviolet light. The standard test method for
evaluating degree of chalking is described in ASTM D 4214. (2) Formation of a loose
powder resulting from the disintegration of the surface of concrete or of applied coating,
such as cement paint. [ACI]
Checking. (1) The development of breaks in the surface of a coating film that do not
penetrate to an underlying coating or the substrate. If an underlying coating or the
substrate is visible, the breaks are called cracks. Checking can be visible or
microscopic. See also Cracking. The standard test method for evaluating degree of
checking is described in ASTM D 660. [PCG, V1] (2) Development of shallow cracks at
closely spaced but irregular intervals on the surface of plaster, cement paste, mortar, or
concrete. [ACI]
Chemical Resistance. The ability of a material to resist degradation by reaction with,
dissolution by, or reduction of physical continuity from contact with a chemical agent or
agents, thereby retaining its capacity to perform as a structural or aesthetic entity. The
standard test method for chemical resistance of coatings is described in ASTM D 3912.
Chemical Treatment Tanks. Tanks used for the storage of the various chemicals in
either the water treatment or waste water treatment process. They may also be part of the
process system as to where the chemicals are injected into the tanks as the water passes
through them.
Chilled Iron. A metallic abrasive prepared by channeling molten metal into streams,
which then drop onto jets of water under pressure, atomizing the molten metal into
random sizes of shot that fall into a water-filled quenching pit.
Chipping. (1) Cleaning steel by removing paint or rust and scale, using a special
chipping hammer. (2) Flaking deterioration of dried paint film, usually as a result of
damage, impact, or wear. The ability of a coating or layers of coatings to resist total or
partial removal, usually in small pieces, resulting from impact by hard objects or from
wear during service. [PCG] (3) Treatment of a hardened concrete surface by chiseling.
[ACI]
Chloride Ion. Negatively charged ion (Cl-) derived from the element chlorine.
Chromium. Metal with salts (chromates) that are sometimes used as pigments in primers
for corrosion control.
Clean Air Act. U.S. Congress legislation designed to protect ambient air from pollution.
Closed Blast Cleaning. See Air Abrasive Blast Cleaning.
Coalescence. The formation of a film of resinous or polymeric material when water
evaporates from an emulsion or latex system, permitting contact and fusion of adjacent
latex particles. Action of the joining of particles into a film as the volatile evaporates.
Coal Tar. A dark brown to black cementitious material produced by the destructive
distillation of bituminous coal. [ASTM]
Coefficient of Thermal Expansion. Change in unit of length (or volume) accompanying
a unit change of temperature, at a specified temperature. [ASTM]

B-6

PCI Study Guide- October 2007


Cohesion. Propensity of a single substance to adhere to itself; the internal attraction of
molecular particles toward each other; the ability to resist partition from the mass;
internal adhesion; the force holding a single substance together. [CED]
Cohesion Failure. A failure or break within a given coat or material (the coating breaks
within itself). See Adhesion Test, Tensile (Pull-Off).
Coin Rub Test. A method of testing the cure of inorganic zinc-rich coatings.
Combustible. Capable of burning. Combustible liquids are those having a flash point at
or above 140F (60C).
Commercial Blast Cleaning. Moderate grade of blast cleaning. According to SSPC-SP
6/NACE No. 3, a commercial blast cleaned surface is free of all visible oil, grease, dirt,
dust, mill scale, rust, paint, oxides, corrosion products, and other foreign matter; staining
is limited to no more that 33 percent of each unit area of surface. [PCG]
Comparator. See Surface Profile Comparator.
Compressive Strength. (1) Maximum compressive stress that a material is capable of
developing. [CED] (2) The measured maximum resistance of a concrete or mortar
specimen to axial compressive loading; expressed as force per unit cross-sectional area;
or the specified resistance used in design calculations. [ACI]
Conductimetric Analysis. Chemical analysis made by determining the electrical
conductivity of a solution.
Conductive. Able to conduct electricity or heat.
Conductivity. See Electrical Conductivity.
Conductivity Meter. Field or laboratory instrument for measuring total electrical
conductivity of an aqueous solution.
Confined Space. An area that may be hazardous because a limited number of openings
could make escape difficult in an emergency, and because ventilation may be inadequate
to support life. The space may also present unknown hazards such as toxic or caustic
chemicals. The legal definition of a confined space (29 CFR 1910.146) is one that is large
enough and so configured that an employee can bodily enter and perform assigned work;
has limited or restricted means for entry or exit (for example, tanks, vessels, silos, storage
bins, hoppers, vaults, and pits); and is not designed for continuous employee occupancy.
Constant Pressure Probe Gauge. See Magnetic Fixed Probe Gauge, Type 2.
Contact Thermometer. A magnetic thermometer that is placed directly onto the steel
surface to determine surface temperature. See also Non-Contact Thermometer.
Containment. (1) A method to limit dust, debris, paint chips, paint dust, spent abrasives,
and overspray from contaminating the environment. The type, concentration, and toxicity
of the contamination determines the extent of containment required. Typical types of
containment systems include free-hanging enclosures, partial structure enclosures, and
total structure enclosures with or without negative pressure. [PCG] (2) Hermetically
sealed portion within the reactor building of a nuclear power plant that contains the
nuclear reactor.
Conversion Coating. A treatment, either chemical or electrochemical, of the metal
surface to convert it to another chemical form that provides an insulating barrier of
exceedingly low solubility between the metal and its environment, but which is an
integral part of the metallic substrate. [CED]

B-7

PCI Study Guide- October 2007


Convertible Coating. Irreversible transformation of a coating after its film formation to
a film insoluble in the solvent from which it was deposited. This should not be confused
with chemical conversion coating. See Thermosetting. [CED]
Co-Reactant. One of two or more chemical materials formulated to react with each other
to produce a desired end product.
Cosolvent. A solvent, sometimes called a coupling agent, that allows the mixing of two
immiscible liquids. [PCG, V1]
Couplant. A substance used between the probe and test surface to permit or improve
transmission of ultrasonic energy through an ultrasonic thickness gauge.
Coupling Agent. See Cosolvent.
Cracking. (1) The splitting of a dry coating film, usually the result of continuing curing
or aging that causes the film to become hard and brittle. Different types of cracking
include hair-cracking or hairlines, checking, cracking, crazing, crocodiling or
alligatoring, and mud cracking. The standard test method for evaluating degree of
cracking is described in ASTM D 661. (2) To break up into simpler chemical
components, as with cracking of petroleum
Crevice. A narrow opening; fissure.
Crosscut Adhesion Test. See Adhesion Test, Crosscut.
Crosshatch Test. See ADHESION TEST, CROSSCUT.
Crosslinking. Applied to polymer molecules, chemical links between the molecular
chains that form a three-dimensional or network polymer generally by covalent bonding.
[CED]
Curing. (1) The process by which a coating changes from a liquid state into a dry, stable,
solid protective film. Curing may involve chemical reaction with oxygen, moisture, or
chemical additives, or the application of heat or radiation. (2) Maintaining satisfactory
moisture content and temperature in concrete during its early stages so that desired
properties may develop. [ACI]
Curing Agent. An additive component, sometimes called a hardener or (incorrectly) a
catalyst, that helps a coating film or concrete cure by chemical reaction. Compare
Catalyst.
Curing Compound. A liquid that can be applied as a coating to the surface of newly
placed concrete to retard the loss of water or, in the case of pigmented compounds, also
to reflect heat so as to provide an opportunity for the concrete to develop its properties in
a favorable temperature and moisture environment. [ACI]
Cut Back. A solution of a coating binder material (e.g., coal tar or asphalt) in an organic
solvent to provide easy application of a film.

D
dB. See Decibel.
DBA. See Design Basis Accident.
Dead Mans Control. Safety cut-out device at blast nozzle connected to pressure relief
valve on blast-pot (blast-kettle). May be air operated or electrical.
Dechlorination. In wastewater treatment plants, treatment to reduce the chlorine level of
the effluent water before it is discharged. This can be done by injecting the effluent with
sulfur dioxide gas (at a 1:1 ratio to the amount of chlorine injected previously) as it leaves

B-8

PCI Study Guide- October 2007


the chlorine contact basins. Dechlorination is then completed by aerating the water either
through a cascade system or air injection.
Decibel. Abbreviated dB, unit of measurement for sound intensity.
Delamination. (1) The separation of a layer or layers of coating from the previous layer
or from the substrate. Failure of a coating to adhere to the previous coating. (2) In the
case of a concrete slab, a horizontal splitting, cracking, or separation of a slab in a plane
roughly parallel to, and generally near, the upper surface; found most frequently in bridge
decks and caused by the corrosion of reinforcing steel or freezing and thawing; similar to
spalling, scaling, or peeling except that delamination affects large areas and can often
only be detected by tapping. [ACI]
Density. A measure of mass per unit volume. The density of paint usually is expressed as
pounds per gallon or kilograms per liter. [PCG]
Depth Gauge. Instrument for measuring depth of a pit or crevice.
Depth Micrometer. See Depth Gauge.
Destructive Dry Film Thickness Gauge. See Dry Film Thickness Gauge, Destructive.
Detachment. See Delamination.
Detergent Cleaning. Removing contamination from a surface using an aqueous solution
of a surface-active agent.
De-Watering. (1) Term describing a type of accident in a nuclear power plant in which
water spills from the system to the extent that the fuel in the reactor is no longer
immersed. (2) Removing water from drydocks, locks, or other containments.
Dew Point. That temperature at which water pressure present in the atmosphere is just
sufficient to saturate it. When air is cooled below the dew point, the excess of water
vapor appears as tiny water droplets or crystals of ice depending on the temperature of
the air mass. [IUPAC, CED]
DFT. See Dry Film Thickness.
Disbonding. Failure of a coating to adhere to a substrate to which it is applied. Intercoat
disbonding is the failure of a coating to adhere to a previous coating layer or to the
substrate to which it has been applied. Intracoat disbonding is the failure of a coating
layer to cohere or hold itself together. See Adhesion, Cohesion.
Discontinuity. See Holiday.
Dissimilar Metal Corrosion. See Galvanic Corrosion.
Dolly. See Pull Stub.
Double Rub. The act of rubbing a solvent saturated cloth in one complete forward and
backward motion over the coated surface. [CED]
Dry Bulb Temperature. The temperature recorded by the dry bulb thermometer of a
psychrometer. [PCG]
Dry Bulb Thermometer. The thermometer on a sling or other psychrometer with a bulb
is directly exposed to the air (i.e., not covered with a wet sock). See Psychrometer.
Dry Film Thickness (DFT). Depth of cured film, usually expressed in mils (0.001 inch)
or micrometers (millionths of a meter). Standard methods for measuring dry film
thickness are defined in SSPC-PA 2, ASTM D 1005, ASTM D 1186, and ASTM D 1400.
Dry Film Thickness Gauge. An instrument used to measure the dry film thickness of a
coating.

B-9

PCI Study Guide- October 2007


Dry Film Thickness Gauge, Destructive. Instrument used to determine dry film
thickness as described in ASTM D 4138. It is capable of measuring the thickness of
individual coating layers.
Dry Film Thickness Gauge, Eddy Current. A dry film thickness gauge that measures
the thickness of non-conductive coatings on non-ferrous metal substrates.
Dry Film Thickness Gauge, Magnetic. See Banana Gauge; Magnetic Fixed Probe
Gauge, Type 2; Magnetic Pull-Off Gauge, Type 1; and Pencil-Type Pull-Off Gauge.
Drying Oil. An oil that possesses to a marked degree the property of readily taking up
oxygen from the air and changing to a relatively hard, tough substance when exposed in a
thin film to the air. [ASTM]
Dry Spray. (1) A rough, powdery, non-coherent, discontinuous film produced when an
atomized coating partially dries before reaching the surface. (2) Overspray or bounce
back falling dry on unintended surfaces and producing an adherent, sand-like covering.
[PCG]
Ductility. Tendency of a material to undergo deformation and extension without cracking
or splitting. [CED]
Durability. A term indicating degree of permanency, used to describe individual
properties, such as the gloss, or general characteristics. [PCG]
Durometer Hardness. An arbitrary numerical value that measures how well as surface
resists indentation by the durometers blunt indentor point. The value may be taken
immediately or after a very short specified time. [ASTM]
Durometer. Instrument for measuring the surface hardness of rubber, plastic, or
protective coatings. [CED]

E
Eddy Current Gauge. See Dry Film Thickness Gauge, Eddy Current.
Eddy Current Testing. Determining a coating dry film thickness on certain metals by
measuring opposing electrical (eddy) currents produced by the gauge.
Edge Failure. Undercutting (penetration of corrosion underneath the coating) as it occurs
at an unprotected or incompletely protected edge.
Edge retention. Percent of coating after application that remains on an edge as compared
to that remaining on a flat surface.
Edge-Retentive Coating. Coating with at least 70% edge retention.
Effluent. Any spent liquors or other waste material that are emitted by a source (waste
from plating shops, pickling tanks, sewage treatment plants, chemical manufacturing
plants, etc.). [IUPAC, CED]
Elastomeric. Rubberlike; relating to or having the properties of elastomers. [CED]
Electrical Conductivity. The property of a fluid or solid that permits the passage of an
electrical current as a result of an impressed electromagnetic field. It is measured by the
quantity of electricity transferred across unit area per unit potential gradient per unit time.
(In sampling and analysis, changes in this property are utilized to measure the presence of
certain ions and compounds such as sulfur dioxide.) [ASTM]
Electric Arc Gun. A type of thermal spraying equipment in which a metal wire is melted
continuously by electric arc and then atomized by an air jet. An electric arc gun is less

B-10

PCI Study Guide- October 2007


maneuverable than an oxy-fuel gas gun, but the deposit rate of the metal is two to three
times greater. See Thermal Spraying. [PCG]
Electrostatic Precipitator. An electrical device used to attract and separate suspended
particles from an exhaust system
Electrostatic Spraying. A method of applying a spray coating in which charged coating
particles are attracted to a grounded, conductive substrate. The mist travels around
corners of the substrate with the result that the article is coated more uniformly on all
sides and edges with very little overspray and bounce back. [PCG]
Elongation. A method of measuring coating flexibility; the increase in specimen length
from the point of initial load application to the point of film rupture in a tension test.
ASTM D 2370 covers the measurement of elongation as well as tensile strength and
stiffness (modulus of elasticity) of organic coatings when tested as free films. [ASTM,
CED]
Emulsion. Two-phase liquid system in which small droplets of one liquid (the internal
phase) are immiscible in, and are dispersed uniformly throughout, a second continuous
liquid phase (the external phase). [CED]
Emulsion Coating. A coating in which the vehicle is an emulsion of binder in water. The
binder may be oil, oleoresinous varnish, resin, or another emulsifiable binder. Not to be
confused with a latex paint in which the vehicle is a latex. [CED]
Enamel. A finish coat that dries to a smooth, gloss surface. [PCG]
Encapsulation. The process of enclosing a surface, especially of one containing
hazardous materials, on all sides. Encapsulants include drywall, fiber-filled coatings,
wood, or other materials. [PCG]
Engineering Standard. A document that provides options for construction work such as
coating different types of structures.
Epichlorhydrin. A chemical used in the production of epoxy resins.
Exothermic Reaction. Chemical reaction that produces heat.
Expansion Dam. The part of an expansion joint serving as an end form for placing
concrete at a joint. Also applied to the expansion joint device itself.
Expansion Joint. (1) A separation provided between adjoining parts of a structure to
allow movement where expansion is likely to exceed contraction. (2) A separation
between pavement slabs on grade, filled with a compressible filler material. (3) An
isolation joint intended to allow independent movement between adjoining parts. [ACI]
Exposure. Placing a specimen in test conditions. [PCG]

F
Fabricated Structural Steel. Steel members made by fastening steel shapes such as
plates and angles, together by riveting, bolting, or welding.
Feather Edging. (1) Reducing the thickness of the edge of a dry paint film, such as the
edge of a damaged area, by sanding or rubbing down prior to repainting. (2) Tapering the
edges of a coat of wet paint by laying off with a comparatively dry brush. [MPDA, PCG]
Ferrous. (1) A chemical compound that contains iron in the bivalent (2+) state. (2) Any
metal alloy based primarily on iron. [PCG]
Fiberglass. Glass in fibrous form used to provide reinforcement or other desirable
properties to a variety of products such as coatings and linings.

B-11

PCI Study Guide- October 2007


Fiberglass-Reinforced Plastic (FRP). Resin linings, usually polyester, vinyl ester, or
epoxy, into which layers of fiberglass are incorporated to optimize the linings
performance. The abbreviation FRP is also used for fiber-reinforced plastic, a
general term for a composite that is reinforced with cloth, mat, strands, or any other fiber
form.
Field Standard. A quality control reference product (e.g., surface) used for comparison
to construction work at the job site.
Filler. (1) A thick, pigmented material used to fill holes, defects, or pores in a surface
before coating. See also Block Filler. [PCG] (2) Finely divided inert material such as
pulverized limestone, silica, or colloidal substances sometimes added to Portland cement
or other materials to reduce shrinkage, improve workability, or act as an extender. (3)
Material used to fill an opening in a form. [ACI]
Fineness of Grind. A numerical assessment of the degree of pigment dispersion in the
vehicle of a coating, or of the presence of coarse particles in pigmented coatings as
determined by the protrusion of particles or agglomerates through the wet film at a given
thickness. [CED]
Fines. Finely crushed or powdered material, such as blasting abrasive residues.
Finish. (1) Final coat in a paint system. (2) Sometimes refers to the entire coating system:
the texture, color, and smoothness of a surface, and other properties affecting appearance.
[CED] (3) The texture of a concrete surface after compaction and finishing operations
have been performed.
Finishing. Leveling, smoothing, consolidating, and otherwise treating surfaces of fresh or
recently placed concrete or mortar to produce desired appearance and service. [ACI]
Fixed Probe Gauge. See Magnetic Fixed Probe Gauge, Type 2.
Flake-Filled. A coating filled with micaceous iron oxide or another pigment that
increases its barrier protection properties.
Flame Spraying. The spray application of a coating whereby metal wire, metallic
powder, or thermoplastic powder is melted using a spray gun with a torch-like flame and
then sprayed with compressed air. See also Metallizing, Plasma Spraying, and Thermal
Spraying. [PCG]
Flammability. Those characteristics of a material that pertain to its relative ease of
ignition and relative ability to sustain combustion. [ASTM]
Flash Point. The lowest temperature of a liquid at which it gives off sufficient vapor to
form an ignitable mixture with the air near the surface of the liquid or within the vessel
used. [CED] Materials with flash points below 100F (38C), such as most solvents and
solvent-borne coatings are considered dangerous. The standard method for flash point is
defined in ASTM D 3941. [PCG]
Flash Rusting. Rusting that occurs on metal within minutes to a few hours after blast
cleaning or other cleaning is complete. The speed with which flash rusting occurs may be
indicative of salt contamination on the surface, high humidity, or both. [PCG]
Flexibility. Degree to which a coating after drying is able to conform to movement or
deformation of its supporting surface, without cracking or flaking. [CED]
Flexibility Test. Test applied to cured films to determine if they are able to elongate
without fracture or disbondment. Syn: Bend test. [CED] See Elongation.
Flint Abrasive. Not flint at all, but actually a natural quartz (silicon dioxide) that
fractures into sharp-edged grains and is used on the common sandpaper for wood. [CED]

B-12

PCI Study Guide- October 2007


Flocculent. Having a loose, fluffy organization resembling wool. Used to describe degree
of pigment suspended in paint vehicle.
Fluid Tip. The removable end of an air-spray gun from which the atomized paint is
sprayed and in which the needle is seated. The fluid tip works in conjunction with the
needle to regulate the flow of fluids before they are atomized. [PCG]
Fluidized Bed Coating. Method of applying a coating in which a heated or
electrostatically charged article is immersed or passed over a fluidized bed of powdered
coating (the coating material adhering to the hot metal), then fused in an oven to provide
a smooth, continuous film. [CED]
Fluorescence. Optical phenomenon characterized by the reemission of absorbed radiant
energy by certain chemicals or materials. [CED]
Foot Candle. Unit of illumination equal to one lumen per square foot. [ASTM] The
preferred unit of illumination is the SI unit lux (one lumen per square meter).
Form Release Agent. Compound such as petroleum oil, wax, and silicone applied to
concrete forms to allow easy removal from poured concrete after it has cured. [PCG]
Freezer Room. A room where food or food ingredients are kept frozen, usually between
32 and -15F (0 and -8C).
FRP. See Fiberglass-Reinforced Plastic.
Fusion Bonded Epoxy (FBE). A powder coating commonly applied to pipelines, rebar,
etc., for corrosion control.

G
Galvanic Corrosion. Accelerated metal corrosion that occurs because of an electrical
contact with a more noble metal or nonmetallic conductor in a corrosive electrolyte.
[ASM] The term dissimilar metal corrosion is sometimes used when appropriate.
Galvanic Protection. (1) The selective use of galvanic corrosion to protect one metal
from deterioration by connecting it to another, more active (electrically negative),
sacrificial metal. Both metals must be in contact with the same body of an electrolytic
solution. Zinc, magnesium, or aluminum can be used as sacrificial metals for the galvanic
protection of steel. (2) Protecting a metal in contact with an electrolytic solution from
corrosion by the use of an impressed direct electrical current. (3) Protecting steel with
zinc-rich coatings. [PCG] See Cathodic Protection.
Galvanizing. Applying a zinc coating to steel by dipping it in molten zinc or by
depositing zinc on the steel electrolytically or mechanically. [PCG]
Gel Time. The period from the initial mixing of the reactants of a liquid material to the
time when gelation occurs, as defined by a specific test method. [ASTM]
Generic. (1) Belonging to an entire class or group. (2) Non-proprietary. [PCG]
Gloss. The degree to which a surface reflects visual images. It is a direct function of
coating formulation and the amount and size of pigment particles in the coating, the more
pigment particles and the larger the diameter, the lower the gloss. [PCG]
Gouge Hardness. In determining coating hardness by pencil testing (ASTM D 3363), the
hardest pencil that will leave the film uncut. See also Scratch Hardness.
Grit. (1) An angular material with sharp, irregular edges obtained from slag, steel,
minerals, and various other materials for use as a blast cleaning abrasive. (2) Small, hard
foreign particles sometimes found in paint and coating materials. [PCG]

B-13

PCI Study Guide- October 2007


Grit Blasting. See Abrasive Blast Cleaning. [PCG]

H
Hackle. Thin, needle-like or sliver-like protrusions, ranging from 3 to 6 mils (75 to 150
micrometers), found on steel plates that have been blast cleaned with steel shot or grit.
[PCG]
Hand Tool Cleaning. The use of manually operated impact, scraping, sanding, and
brushing tools to remove loose paint, rust, and mill scale. Such tools include slag
hammers, chipping hammers, scrapers, and wire brushes. The specification SSPC-SP 2,
Hand Tool Cleaning, is a consensus standard covering the procedures necessary for handtool cleaning of steel surfaces. [PCG]
Hardener. (1) Chemical agent used to promote or control the hardening or curing
reaction in coating or resin systems. See Curing Agent. (2) A chemical (including certain
fluosilicates or sodium silicate) applied to concrete floors to reduce wear and dusting.
[ACI]
Hardness. The property of a coating that allows it to resist damage or abrasion. [PCG]
Hardness Testing, Pencil Method. A method of testing coating hardness that uses a
series of lead pencils to determine which pencil will not cut through the coating and
which pencil will not scratch the coating. The hardest pencil that will leave the film uncut
defines the gouge hardness; the hardest pencil that will not scratch the film defines the
scratch hardness. This method is defined in ASTM D 3363.
Hazardous Waste. A solid waste, including liquid waste, that exhibits: ignitability,
corrosivity, reactivity, or toxicity, as defined in 40 CFR 261, Identification and Listing
of Hazardous Waste, or that is on a special list established by EPA. [ILPR, PCG]
HAZCOM. U.S. regulations governing hazardous chemicals in the workplace, issued by
OSHA in 1983; also known as the Right-to-Know regulations. The purpose of
HAZCOM is to ensure that workers are informed about chemical hazards in the
workplace, and that they are provided with information and training in how to safely
handle these chemicals.
Heat Resistance. The ability of a coating to resist deterioration when exposed
continuously or periodically to high temperatures at or below a given level, which
depends on the binder type and other coating ingredients. [PCG]
Heat-Shrink Sleeve. Cover, frequently polyethylene, that is placed around a structural
component, such as a pipe weld joint, and shrunk in place by heating.
Heavy Metal. Metallic element of high molecular weight, compounds of which are often
toxic.
Hiding Power. The ability of a coat of paint that has been properly applied to obscure
(hide) a surface or a previous coating on the surface. [PCG, V1]
High-Solids-Coating. A coating with a high non-volatile content. Currently, 70% solids
by volume is used as a benchmark measurement, at or beyond which a coating is said to
be high solids. Many new coatings contain no solvent and are called 100% solids
coatings.
Hog. The upward curvature of a ships bottom.
Hold Point. Critical point in an operation where work is stopped until the work to date
has been approved.

B-14

PCI Study Guide- October 2007


Holiday. Application defect whereby a small area is left uncoated. Synonyms: miss, skip,
void, discontinuity, vacation. [CED]
Holiday Detector, High-Voltage. Also called a spark tester, an instrument for detecting
holidays in a nonconductive coating applied over a conductive substrate. A spark test
instrument applies a voltage to the surface with a probe that creates a spark whenever a
holiday, pinhole, or other defect is found. The spark triggers an alarm or light on the
instrument. The voltage used depends on the coating and thickness.
Holiday Detector, Low-Voltage Wet Sponge. An instrument that uses 5-90 volts DC to
detect holidays in a coating. It is typically used for films of less than 20 mils (510
micrometers) dry film thickness.
Holiday Test. Test for detecting small areas of paint film that are incompletely coated
(holidays). Standard methods for holiday testing are defined in ASTM D 5162, ASTM D
4787, and NACE RP0188-90.
Hot Flocking Method. A method of powder coating application that relies on a nonelectrostatic spray of powder onto parts that have been preheated above the softening
point of the powder. The powder melts and clings to the preheated parts. In some cases,
the coating is fused/cured by residual heat in the parts, while in others, a post-heating step
is required.
Hot Spraying. Spraying hot lacquers or paints, the viscosities of which have been
reduced to spraying consistency by means of heat instead of by adding volatile solvents.
By such a process, it is possible to apply materials with higher-solid content and therefore
better build. [CED]
Hull. The frame or body of a ship exclusive of masts, deck houses, superstructure, and
rigging.
Hydraulic Adhesion Test Equipment (HATE). Commercial hydraulic instrument for
determining coating adhesion to a substrate by the pull-off method. See Adhesion Test,
Tensile (Pull-Off).
Hydroblasting. A cleaning process in which pressurized water is directed through a
nozzle to impact a surface. The term is used generically to describe cleaning with water
without abrasives from low pressure water cleaning to ultra-high pressure waterjetting.
See also Hydrojetting and Waterjetting.
Hydrocarbon Solvent. Aliphatic, aromatic, or cyclic (cycloparaffinic, naphthenic)
solvent containing only carbon and hydrogen. [PCG]
Hydrochloric Acid. An aqueous solution of hydrogen chloride gas. Dissolves many
metals, forming chlorides and liberating hydrogen. Used extensively in industry for
numerous purposes including concrete surface preparation.
Hydrojetting. A generic term describing the process in which pressurized water is
directed through a nozzle to impact a surface. See also Hydroblasting and Waterjetting.
Hydrolasing. A term commonly used for high or ultra-high pressure water blasting. See
Waterjetting and Hydrojetting.
Hydrolysis. Chemical reaction consisting of splitting a compound into two parts, one of
which combines with the H+ ion of water, and the other combines with the OH- ion of
water. [CED]
Hygrothermograph. An instrument for measuring and recording the air temperature and
relative humidity.

B-15

PCI Study Guide- October 2007


Hypodermic Pressure Gauge. A gauge with a hypodermic needle that is inserted into
the hose at various locations (e.g., just before the nozzle used with abrasive blasting
equipment) to determine air pressure.

I
Immersion-Grade Coating. A coating suitable for use during immersion in water or
other liquids.
Immersion Service. Use of a coating under water or another liquid; in this service, the
coating is frequently called a lining. [PCG]
Impact Resistance. Ability of a coating to resist a sudden blow; ability to resist
deformation from impact. [PCG]
Impact Strength. Resistance to damage from collision with another body.
Impressed Current Cathodic Protection. Cathodic protection applied with an external
DC power source. See Cathodic Protection. [ASTM]
Indicator. Reagent used in chemical analysis that changes in color as the chemical
environment changes.
Induction Time. Sometimes called sweat-in time, the interval that must elapse after
mixing the components of multicomponent paint before application can begin. [PCG]
Infrared (IR). Invisible part of the electromagnetic spectrum between radio waves and
the red portion of visible light, with wavelengths between 0.78 and 1.0 micrometer (780
to 1,000 nanometers). It produces a heating effect on impact with an absorptive surface,
and sometimes is used to cure coatings. Infrared radiation is also used to chemically
characterize materials in infrared spectroscopy. [PCG]
Inhibitive Pigment. A pigment that when formulated into a coating provides active
corrosion inhibition to a metal substrate or inhibits some other undesirable effect. [PCG]
Inhibitive Primer. Primer containing inhibitive pigment or other chemical material.
Inhibitor. (1) General term for compounds or materials that slow or stop an undesired
chemical reaction, such as oxidation, corrosion, drying, skinning, mildew growth, etc. (2)
In wet cleaning methods for steel, a material that can be added to the water or applied as
a rinse to prevent flash rusting. [PCG]
Initial Condition. See Rust Grade.
Initiator. See Catalyst.
Intercoat Adhesion. The ability of one coat of paint to adhere to the next. [PCG]
Intrinsically Safe. Electrical equipment designed to separate sparking from the external
environment, so that the equipment can be used in hazardous environments.
Intumescent Coatings. A fire-retardant coating that when heated forms a foam produced
by non-flammable gases, such as carbon dioxide and ammonia. This results in a thick,
highly insulating layer of carbon (about 50 times as thick as the original coating) that
serves to protect the coated substrate from fire. [ASTM]
Ionic Contaminants. See Soluble Salt Contaminants.
Isocyanate. A compound containing one or more of the chemical group -N=C=O.
Isocyanates comprise one major component of two-component polyurethane coatings.
When the isocyanate groups are crosslinked with a hydroxyl-containing material (polyol),
a polyurethane polymer is formed; when combined with a amino-containing material, a
polyurea polymer is formed. [PCG]

B-16

PCI Study Guide- October 2007

J
Job Specification. Written, legal document, usually part of a contract, that precisely
describes an item of work that is to be accomplished. See also Specification.

K
Knife Adhesion. See Adhesion Test, Crosscut.

L
Lacquer. Coating composition based on synthetic thermoplastic film-forming material
dissolved in organic solvent, which dries primarily by solvent evaporation. Typical
lacquers include those based on nitrocellulose, other cellulose derivatives, vinyl resins,
acrylic resins, etc. They are re-soluble in their original solvent. [CED]
Laitance. A layer of weak and nondurable material containing cement and fines from
aggregates, brought by bleeding water to the top of overwet concrete; the amount is
generally increased by overworking or over-manipulating concrete at the surface by
improper finishing or by job traffic. [ACI]
Laminar. Arranged in, consisting of, or resembling thin plates or scales.
Laminations. Relatively large surface flakes, scales, or layers that are formed on steel
during the rolling process. [PCG]
Latex. A coating containing a stable aqueous dispersion of synthetic resin, produced by
emulsion polymerization, as the principal constituent of the binder. Modifying resins may
also be present. [ASTM]
Lattice. A framework of cut lines used in adhesion testing. See Adhesion Test, Crosscut.
Lead. A heavy metal. Lead compounds have been used extensively in the past as hiding
pigments and/or inhibitive pigments. It is hazardous to health if breathed or swallowed,
causing mental retardation in children and dangers to workers generating lead-containing
dust. Residential use of lead-containing paint pigments has been eliminated in the United
States, and industrial use has been greatly reduced.
Lead-Containing Paint. There is no consensus definition for lead-containing paint in
industrial maintenance applications. The following definitions have been developed for
related applications: (1) Consumer Products: A paint or other, similar surface coating in
which the lead content (calculated as lead metal) exceeds 0.06 percent by weight of the
total non-volatile content of the paint or the weight of the dried paint film. The 0.06
percent level is equivalent to 600 ppm. [ILPR] (2) Residential Use: A paint that contains
at least 0.5 percent lead by weight of the dried paint film. The 0.5 percent level is
equivalent to 5000 ppm. [PCG]
Leafing. Particles of certain metallic and other pigments in the form of thin flat flakes in
aligning themselves with or floating on or near the surface of the vehicle. [CED]
LEL. See Lower Explosive Limit.

B-17

PCI Study Guide- October 2007


Leveling. A coatings ability to flow out on a surface so that brush or roller marks or
other irregularities produced during application are not apparent. [PCG]
Leveling Agent. Chemical added to coating to increase the ability of the wet film to
settle to a uniform thickness.
LFL. See Lower Flammable Limit.
Limpet (Soltz) Cell. A rigid cell used to collect soluble salt from a contaminated surface
in order to determine its concentration.
Line of Demarcation. On ships, the line of demarcation is where the above-water paint
system meets the underwater paint system. It is usually the deep load line or draft line on
the vertical sides of the ship.
Line Travel Machine. A machine that performs one of the cleaning or coating processes
while moving continuously on wheels or another means along the length of the pipeline.
Lining. (1) A material used to protect a container against corrosion and/or to protect the
contents of the container from contamination by the container shell material. Sprayable
linings, sheet liners, and drop-in liners can be used for this. [PCG] (2) Any sheet, plate, or
layer of material attached directly to the inside face of formwork to improve or alter the
surface texture and quality of the finished concrete. [ACI]
Litmus Test. The use of litmus or pH paper to measure the acidity or alkalinity (pH) of a
water solution. [PCG]
Loading Fixture. A component of an instrument (e.g., an adhesion tester) to which a
force (load) is applied to determine a physical property such as bonding strength.
Lockout. A means of protecting workers from injury or death caused by the accidental
start-up or release of stored energy from equipment. It involves blocking the flow of
energy from the power source to the piece of equipment with a padlock or chain, or by
removing a component such as a fuse or circuit breaker. See also Tagging.
Lower Explosive Limit (LEL). The concentration, at ordinary ambient temperatures, of
a compound in air below which an explosion will not occur if the mixture is ignited. The
concentration is expressed as a percent of the gas vapor in air by volume. When the
concentration of a substance in air is above the lower explosive limit and below the upper
explosive limit (UEL), the mixture will burn and explode. [PCG]
Lower Flammable Limit (LFL). The minimum concentration of a combustible
substance that is capable of propagating a flame through a homogeneous mixture of the
combustible and a gaseous oxidizer under the specified conditions of test. [ASTM]

M
Magnetic Base Reading (MBR). The measurement obtained when placing a dry film
thickness gauge on a magnetic substrate that has been blast cleaned.
Magnetic Fixed Probe Gauge, Type 2. A dry film thickness gauge that operates with
changes in magnetic flux within the probe or the instrument. The magnitudes of these
changes are an inverse (nonlinear) function of the distance between the probe and the
steel surface under the paint. Type 2 refers to the gauges designation in SSPC-PA 2.
Magnetic Gauge. See Dry Film Thickness Gauge, Magnetic.
Magnetic Pull-Off Gauge, Type 1. A dry film thickness gauge that uses a spring balance
to pull a small permanent magnet from the surface of the painted steel. The magnetic
force holding to the surface varies inversely as a non-linear function of the distance

B-18

PCI Study Guide- October 2007


between magnet and steel, i.e., the thickness of the dry paint film (plus any other films
present). Type 1 refers to the gauges designation in SSPC-PA 2.
Mandrel. In bend testing, the tool used to control the strain on the concave side of a bend
in a wrap-around bend test and also to apply the bending force in a semi-guided or guided
bend test. [ASTM]
Manufacturers Technical Data Sheet. Product instructions and information.
Mastic. (1) A high-build coating. (2) An adhesive material. [PCG]
Material Safety Data Sheet (MSDS). OSHAs established guidelines for the descriptive
data that should be concisely provided on a data sheet to serve as the basis for written
hazard-communication programs. The thrust of the law is to have those who make,
distribute, and use hazardous materials be responsible for effective communication.
[CED]
MBR. See Magnetic Base Reading.
Mechanical Adhesion Testing. Adhesion testing performed with a pull-off instrument.
An aluminum pull stub (loading fixture) is bonded onto a coated surface. After the
bonding adhesive cures, the force on the pull stub is continuously increased and
monitored until it detaches or until a specific force is attained (ASTM D 4541; Annex
A.1).
MEK. See Methyl Ethyl Ketone.
Mercury. A toxic heavy metallic element that is liquid at usual temperatures. Mercury
compounds have been used extensively in the past in paints as mildewcides. The
toxicities of these products vary depending upon the chemical compound in which they
occur.
Metallizing. Spraying a coating of metal onto a surface. See also Flame Spraying,
Plasma Spraying, and Thermal Spraying. [PCG]
Metal Spray Coating. A film of molten metal, often zinc or aluminum, dispersed
(sprayed) onto a surface, such as steel, for corrosion control.
Methyl Ethyl Ketone (MEK). A low-boiling strong solvent, similar to acetone but less
volatile. [PCG]
Methyl Ethyl Ketone Peroxide. A chemical used in small amounts to accelerate the
curing of polyester coatings.
Methyl Isobutyl Ketone (MIBK). A medium-boiling strong solvent. [PCG]
Microbiologically Influenced Corrosion (MIC). Corrosion that is affected by the action
of microorganisms in the environment, e.g., sulfate-reducing bacteria found in some
petroleum products and in sewage.
Micrometer. (1) One millionth of a meter, abbreviated as m. Also sometimes called a
micron. Coating thickness often is expressed in micrometers; 25.4 micrometers = 1 mil.
(2) A stationary or hand-held instrument used to measure thickness of free (unattached)
films. [PCG]
MIL. One thousandth (0.001) of an inch. 1 mil = 25.4 micrometers. Coating thickness is
often expressed in mils or in micrometers. [PCG]
Mil Profile. See Surface Profile.
Mill Coating. Shop coating.
Mill Scale. The heavy, bluish oxide layer formed during hot fabrication or heat treatment
of steel and other metals. [PCG]

B-19

PCI Study Guide- October 2007


Mineral Abrasive. Blast cleaning abrasive made from naturally occurring minerals, such
as silica sand, olivine, staurolite, flint, garnet, zirconium, novaculite.
Mineral Spirits. A petroleum-derived solvent used for thinning paint. Odorless mineral
spirits have been refined to remove some odorous constituents. [PCG]
Mist Coat. Also called a fog coat, a thin layer applied in a spray mist and used as a tack
or adhesive coat. [PCG]
Mixing Ratio. The ratio, usually by volume, of mixed components for a thermosetting
coating specified by the manufacturer for complete curing into the desired film.
Moisture Meter. Instrument used for determining water (moisture) content of materials,
such as wood or concrete, by measuring its conductivity.
Monomer. The starting compound for a polymerization reaction. A monomer can link
with itself or with other monomers to form a polymer. [PCG]
Monolithic. Material of uniform composition applied as a continuous surface or
structure. [ASTM] Monolithic concrete is concrete cast with no joints other than
construction joints. [ACI]
MSDS. See Material Safety Data Sheet.
Mud Cracking. A paint failure that looks like cracked mud. It normally is caused from
shrinkage of excessive thicknesses of coatings during curing. [PCG]
Muriatic Acid. An industrial form of hydrochloric acid used to clean concrete and
masonry. [PCG]
NDT. See Non-Destructive Testing.
Near-White Blast Cleaning. According to SSPC-SP 10/NACE No. 2, Near-White Blast
Cleaning, a near-white blast cleaned surface is free of all visible oil, grease, dirt, dust,
mill scale, rust, paint, oxides, corrosion products, and other foreign matter and staining is
limited to no more than 5% of each unit area of surface. [PCG]
Needle Gun. A power impact tool with a bundle of steel needles with chiseled ends
mounted in front of a piston that strikes them several times per second and pushes them
against the surface being cleaned. Needle guns work best at removing loose or brittle
material. Because each needle hits the surface individually, needle guns are useful for
cleaning irregular surfaces, such as corners and crevices, or around bolt and rivet heads.
[PCG]
NIST Standard Thickness Plates. Small, thin reference squares of 1010 steel covered
with different thicknesses of a non-magnetic metal (copper-chromium alloy with a nickel
finish); used to calibrate magnetic dry film thickness gauges; made by the National
Institute of Standards and Technology (NIST).
Non-Conductive. A surface or material that will not conduct electricity.
Non-Contact Thermometer. An instrument that determines surface temperature by
measuring the amount of energy the surface emits.
Non-Convertible Coating. Film-former which, after being deposited from a solution,
dries to give a film that is unchanged chemically from its original composition and can be
redissolved in a solvent from which it was originally deposited. See Thermoplastic.
[CED]
Nondestructive Testing (NDT). Determining physical or chemical properties without
damaging item being investigated.
Non-Ferrous. Not containing iron; pertaining to metals other than iron.

B-20

PCI Study Guide- October 2007


Nonvolatile Matter (NVM). Of a coating, the solid material remaining after the volatiles
(solvent) have been driven from the film under specified test conditions. The total
percentage volatile present is obtained by subtracting the nonvolatile content from 100.
Nonvolatile Vehicle. The coating binder dissolved or dispersed in the solvent (volatile
vehicle) that remains to form a film after solvent evaporation.
Non-Woven Abrasive Pad. A web of nylon fibers embedded with abrasive material in
different sizes and densities. These pads can be used to remove dried soil, debris, and
loose paint from many different surfaces, as well as loose rust and loose mill scale from
steel. They can also be used to feather, or blend the edges of a repair area, with the
surrounding surface. [PCG]
Notch Gauge. See Wet Film Thickness Gauge, Notch Type.
Novolac. Class of resins produced by the chemical reaction of phenol and formaldehyde;
often used in high performance phenolic or epoxy coatings. See Bisphenol F.
Nozzle Orifice Gauge. A tapered metal rod that can be inserted into the rear of a blast
cleaning nozzle to determine the size of its orifice. The nozzle normally is replaced when
the orifice size increases by 1/16 inch (1.6 mm). [PCG]
Nuclide. A species of atom characterized by the constitution of its nucleus and hence by
the number of protons, the number of neutrons, and the energy content.

O
Offshore Platform. A stationary steel structure in an ocean or bay that is used by oil and
gas industry operators for drilling or other production activities.
Oil Canning. Bowing edges of a steel plate caused by thermal expansion and
contraction. Oil canning can lead to a coating cracking at the edges.
Opacity. The degree to which a material obscures a substrate, as opposed to the
transparency, which is the degree to which a material does not obscure a substrate. [CED]
Open Blast Cleaning. See Air Abrasive Blast Cleaning.
Operating Mix. See Abrasive Mix.
Orange Peel. A coating film defect with the textured look of an orange peel. [PCG]
Organic Solvent. Liquid organic material including diluents and thinners that is used as a
dissolver, viscosity reducer, or cleaning agent.
Organotin. Tin compounds used in anti-fouling paints and wood preservatives. Their use
is currently curtailed because of toxicity concerns.
Osmotic Blistering. The raised areas (blisters) containing water that form on coating
films when water diffuses through the film to dissolve underlying solvents or salts. The
diffusion is caused by a difference in pressure or concentration between the metal-coating
interface and the exposed film.
Overblast. Areas where abrasive blasting has impinged on surfaces that were not
intended to be blasted.
Overspray. (1) Atomized coating particles that deflect from or miss the surface being
sprayed. (2) Spray particles that are not wet enough to fuse when they reach the surface
being sprayed. As a result, overspray may contaminate property beyond the surface being
sprayed. [PCG]
Oxidation. (1) In coatings, the introduction of oxygen into a molecule, thereby producing
a cured film. [Paint/Coatings dictionary] Alkyds and drying oil-based coatings cure by

B-21

PCI Study Guide- October 2007


oxidation. Oxidation during weathering can also destroy a film. (2) Metal corrosion and
degradation of other substances caused or accelerated by oxygen in the air. [PCG]
Oxygen Deficiency. Low oxygen in the atmosphere, generally below 19.5%, is a health
hazard.
Oxygenated Solvent. An organic solvent containing oxygen as part of its molecular
structure. Alcohols, esters, and ketones are oxygenated compounds often used as coating
solvents. [EPA, PCG]

P
Paint Thermometer. Instrument designed for measuring the temperature of liquid
coating materials by immersion.
Parts Per Million (PPM). Measure of proportional content (e.g., of small amounts of
contamination).
PEL. See Permissible Exposure Limit.
Pencil Testing. See Hardness Testing, Pencil Method.
Pencil-Type Pull-Off Gauge. A pencil-shaped magnetic pull-off gauge for determining
dry film thickness. See Magnetic Gauge.
Percent Solids. See Non-Volatile Matter.
Permissible Exposure Limit (PEL). The amount of a toxic material or harmful
substance to which a worker may be exposed under OSHA regulations. If OSHA has
established a PEL for a substance, by regulation the exposure must be kept at or below
that level. PELs are expressed as parts per million (ppm) or as micrograms per cubic
meter (g/m3) and typically are based on time-weighted average concentrations for a
normal 8-hour workday and a 40-hour work week. See also Threshold Limit Value.
[PCG]
Personal Protective Equipment (PPE). Devices worn to protect against hazards in the
environment. Respirators, gloves, and ear protectors are examples.
pH. The measure of the acidity or alkalinity of an aqueous solution. A pH of 7 represents
neutrality, i.e., the solution is neither acid nor alkaline. pH values from 0 to 7 are acidic,
the lower the pH value, the higher the degree of acidity; pH values from 7 to 14 represent
alkalinity. The higher the pH value above 7, the greater the degree of alkalinity. [CED]
Pigment. Finely ground, natural or synthetic, inorganic or organic insoluble particles
that, when dispersed in a liquid vehicle provide color and other properties, including
opacity, hardness, durability, and corrosion resistance to a coating. [IM]
Pigment Volume Concentration (PVC). Ratio of the volume of pigment to the volume
of total nonvolatile material (i.e., pigment and binder) present in a coating. The figure is
usually expressed as a percentage. [CED]
Pinhole. A holiday or discontinuity in a coating film approximately the size of a pin
point, and extending entirely through the applied film, normally caused by solvent
bubbling, moisture, or foreign particles. [PCG]
Pinhole Detection. See Holiday Test.
Pinpoint Rusting. Tiny, dispersed points of rust that can appear at pinholes and holidays
in a coating. Very dense pinpoint rusting can appear on painted steel surfaces where the
coating does not completely cover the blast cleaning profile. [PCG]

B-22

PCI Study Guide- October 2007


Pitting. (1) Localized corrosion on a metal surface, confined to a point or small area, that
takes the form of cavities. [ASM] (2) In concrete, pitting is localized disintegration, such
as a popout. [ACI]
Plasma Spraying. A spray application process in which metallic or thermoplastic
powders are introduced into a plasma arc cavity that contains the gas stream of a plasma
gun. After being melted, the powders are projected onto the surface being coated via the
flow of the plasma jet. See also Flame Spraying, Metallizing, and Thermal Spraying.
[PCG]
Plasticizer. (1) A paint, varnish, or lacquer additive designed to soften and promote
flexibility in the coating. [PCG] (2) A material that increases the plasticity of a fresh
cement paste, mortar, or concrete. [ACI]
Plural-Component Spraying. A coating application method that automatically
proportions and mixes two or more components of a paint material in the process of
delivering them to the spray gun. Plural-component spray equipment is used to apply
coatings with a pot life that is too short to permit mixing and application by conventional
air and airless spray equipment. [PCG]
Pneumatic Adhesion Tensile Strength Testing Instrument (Patti). An instrument for
determining the tensile adhesion of coatings to a surface, according to ASTM D 4541.
This instrument is self-aligning, and consists of detachable loading fixtures having a flat,
cylindrical base, a central grip for engaging the loading fixture, and a pressurized gas
system for applying a continuous pull to the loading fixture. See Adhesion Test, Tensile
(Pull-Off).
Pneumatic Power Tool. Tool that is run by air pressure.
Polymerization. Chemical reaction in which two or more small molecules (monomers)
combine to form large molecules (polymers, macromolecules) that contain repeating
structural units of the original molecules and have the same percentage composition as
the small molecules if the small ones were of the same kind. [CED]
Porosity. (1) Small interconnected voids, such as in concrete, which allow fluids to
penetrate an otherwise impervious material. (2) The ratio, usually expressed as a
percentage of the volume of voids in a material to the total volume of the material
including the voids. [ACI]
Pot Life. The time during which a coating material can be successfully applied to a
substrate after the container is opened, or after catalysts, activators, hardeners, or other
ingredients are added to initiate the curing reaction. Pot life often depends on temperature
and/or humidity. [PCG]
Powder Coating. (1) A 100% solids coating applied as a dry powder which, when baked
at a sufficiently high temperature, melts out to form a continuous film. For thermosetting
materials, a chemical reaction, either condensation or additional polymerization, also
takes place. This fused film has the uniformity, color, toughness, and other properties
generally associated with protective and decorative coatings. (2) A coatings application
method that utilizes a solid binder and pigment. The solid binder melts upon heating and
results in a pigmented coating upon cooling. [CED]
Power Grinding. Abrading a metal or other hard surface with a motor-driven tool.
Power Washing. The use of pressurized water (typically less than 5000 psi [34 MPa])
with or without chemical additives, detergents, etc., to remove contamination and debris
from a surface. [PCG]

B-23

PCI Study Guide- October 2007


Power Wire Brush. A power tool with a brush made of knotted or crimped wire bristles
in the form of a wheel or a cup used to clean steel, concrete, or masonry surfaces. [PCG]
PPE. See Personal Protective Equipment.
PPM. See Parts Per Million.
Pre-Job Conference. Meeting held before construction work is started to permit the
contractor, owner, and other concerned parties to come to a common understanding of all
work requirements.
Primary Containment. (1) The main method of storing a product, e.g., a steel storage
tank. (2) That portion of a nuclear power plant reactor building housing the nuclear
reactor, a Class I area.
Primer. First full layer of coating applied to a surface when a multicoat system is being
used. Primers provide adhesion to a new substrate (wood, metal, masonry, or concrete),
protect the substrate, and aid in the adhesion of additional coats of paint. The type and
condition of the substrate and the painting system specified for a job affect the selection
of the primer. Primers for steel work contain special anti-corrosive pigments. [PCG]
Procurement Documents. Written records that describe the general terms and conditions
of construction or other contracts.
Profile Depth. A measure of surface roughness based on the distance between its peaks
and valleys, sometimes expressed as an average. See Surface Profile. [PCG]
Profile Depth Gauge. Gauge with instrumented probe for determining the profile height
(depth) of abrasive blasted steel, as described in ASTM D 4417, Method B.
Psychrometer. An instrument used to measure the wet and dry bulb temperatures of air.
With the aid of psychrometric tables, these measurements can be used to determine the
dew point and relative humidity of the air. [PCG]
Psychrometric Tables. U.S. Weather Bureau Tables, originally published by the U.S.
Department of Commerce, used to determine the relative humidity and dew point
temperature from the dry and wet bulb readings obtained from the psychrometer.
Pull-Off Adhesion Test. See Adhesion Test, Tensile (Pull-Off).
Pull-Off Gauge. See Magnetic Pull-Off Gauge, Banana Gauge, and Pencil-Type PullOff Gauge.
Pull-Off Strength. Force necessary to pull a bonded probe from a coated surface in a
coating adhesion test.
Pull Stub. Also called a dolly or loading fixture, the part of an adhesion testing apparatus
that is affixed to the coated surface being tested.
PVC. Pigment Volume Concentration; Polyvinyl Chloride.

Q
Quality Assurance. The guarantee that the quality of a product is actually what is
claimed on the basis of the quality control applied in creating that product. Quality
assurance is not synonymous with quality control. Quality assurance is meant to protect
against failures of quality control. [IUPAC, CED]
Quality Control. The statement that a product specifically meets or exceeds some
minimum standard based on known, testable criteria. [CED]
Quantab Strip. Trade name for a commercial test strip used to determine the chloride
content of an aqueous solution.

B-24

PCI Study Guide- October 2007

R
Reference Cell. Standard receptacle containing an electrode and electrolyte used as a
point of reference for measuring electrical potentials; used in sacrificial anode and
impressed current cathodic protection.
Reflectance. The ability of a coating film to reflect or return the light that falls upon its
surface. [PCG]
Relative Humidity. The ratio of the actual pressure of existing water vapor to the
maximum possible (saturation) pressure of water vapor in the atmosphere at the same
temperature, expressed as a percentage. [ASTM, PCG]
Release Agents. Materials used to prevent concrete from bonding to a surface. [ACI] See
Form Release Agent.
Replica Tape. A specially constructed tape used to measure surface profile. It is pressed
against the surface to produce an impression of the profile; then, the impression in the
tape is measured with a micrometer. The use of replica tape is described in ASTM D
4417 and NACE RP0287.
Reservoir. Storage tank in which the diameter is greater than the height; the reverse is
true for a standpipe.
Resin. General term applied to a wide variety of more or less transparent and fusible
products, which may be natural or synthetic. They vary widely in color. Higher molecular
weight synthetic resins are more generally referred to as polymers. In a broad sense, this
term is used to designate any polymer that is a basic binder material for coatings and
plastics. [PCG]
Respirator. (1) A device that supplies oxygen or a mixture of oxygen and carbon dioxide
for breathing, used especially in artificial respiration. (2) A screenlike device worn over
the mouth or nose or both to protect the respiratory tract. There are quite a variety of
respirators, ranging from disposable dust masks to self-contained breathing apparatus. All
have specific uses and limitations. [CED]
Rigging. (1) The process of selecting and setting up supports, cables, and ropes, and
scaffolding systems to provide safe access to an elevated work area. (2) The cables,
ropes, and related equipment used with scaffolding. [PCG]
Right-To-Know Legislation. See HAZCOM.
Ring Extrusion Process. A method for extruding thermoplastic coatings onto pipe in
which the die slit encircles the advancing pipe and the thermoplastic is extruded without
seams as a plastic pipe over the steel pipe.
Rotary Peener. A rotary impact power tool that uses rotating action to impact different
shapes of heavy-duty steel cutters against a steel or concrete surface to remove heavy
coatings and contaminants. Rotary peeners also can be used to grind concrete. [PCG]
Rust Bloom. The first sign of rust on newly cleaned steel, indicated by slight surface
discoloration. See Flash Rusting. [PCG]
Rust Grade. In visual standards, the initial condition of unpainted steel before surface
preparation. SSPC-Vis 1, a visual standard for steel surface preparation, outlines four rust
grades: (1) Rust Grade A: the steel surface is completely covered with adherent mill
scale; little or no rust is visible. (2) Rust Grade B: The steel surface is covered with both
mill scale and rust. (3) Rust Grade C: The steel surface is completely covered with rust;

B-25

PCI Study Guide- October 2007


little or no pitting is visible. (4) Rust Grade D: The steel surface is completely covered
with rust; pitting is visible. [PCG]

S
Sacrificial Protection. (1) The use of a metallic coating, such as galvanizing or zinc-rich
paint, to protect steel. In the presence of an electrolyte, such as salt water, a galvanic cell
is set up and the metallic coating corrodes instead of the steel. (2) The use of metal
anodes that are slowly consumed to protect immersed or buried metals. See also Galvanic
Corrosion and Galvanic Protection. [PCG]
Sagging. (1) A coating surface irregularity caused by the downward flow of wet paint
that produces an uneven film with a thick lower edge. [PCG] (2) Subsidence of shotcrete,
plaster, or the like, due generally to excessive water in the mixture; also called sloughing.
[ACI]
Sag Resistance. The ability of a wet coating film to resist the downward flow that results
in an uneven film with thick edges and runs. [PCG]
Salt Spray Test. Test used to evaluate the resistance of coated metals or alloys to
corrosion. It consists of a fine mist or fog of common salt (sodium chloride) solution
sprayed on the surface. The test is described in ASTM B 117. [PCG]
Sanding Disc. Flat, circular, powered implement used to abrade a surface.
Saponification. Alkaline hydrolysis of fats, drying oils, or other esters whereby a soap is
formed. A saponified coating may become sticky and discolored. In severe cases, the film
may be completely liquefied by saponification. Loss of adhesion may occur as a
saponified layer develops next to the substrate. [PCG]
Scaffold. Equipment in variety of types, sizes, and rigging configurations used to support
workers, materials, and equipment at elevated or otherwise inaccessible work sites.
[PCG]
Scaling Hammer. Impact tool used to remove corrosion products and other undesired
materials from metal surfaces.
Scratch Hardness. In determining coating hardness by pencil testing (ASTM D 3363),
the scratch hardness is defined by the hardest pencil that will not scratch the film. See
also Gouge Hardness.
Scrub Resistance. The ability of a coating to resist being worn away or to maintain its
original appearance when rubbed repeatedly with an abrasive material. Typically, the
rubbing procedure can employ a brush, sponge, or cloth, wetted with an abrasive soap
solution, in which case it is more accurately referred to as wet scrub resistance. [CED]
Secondary Containment. A second or backup holding vessel surrounding a primary
holding vessel. Under 40 CFR 264.193, the EPA lists requirements for lining secondary
containment vessels so that they meet the standards for impermeability and for containing
the liquid in the primary containment vessel should a leak or spill occur. [PCG]
Sedimentation. Action or process of depositing matter (sediment) that settles to the
bottom of a liquid (sediment).

B-26

PCI Study Guide- October 2007


Self-Priming. A coating that can be used, perhaps in different consistencies, both to
prime and to coat a surface. [PCG]
Self-Curing. A coating that cures (crosslinks) without any special treatment after
application. [PCG]
Self-Leveling. The ability of a wet coating to form a uniformly flat or level surface.
Sensitization. A state of immune-response reaction in which further exposure elicits an
immune or allergic response. A person previously exposed to a certain material is more
sensitive when further exposed to it. [CED]
Shelf Life. The amount of time a coating or other material remains in usable condition
during normal storage. [PCG]
Shim. (1) A thin strip of non-magnetic plastic, metal, or other material of known uniform
thickness used to calibrate coating dry film thickness gauges. (2) A strip of metal, wood,
or other material employed to set base plates or structural members at the proper level for
placement of grout, or to maintain the elongation in some post-tensioning anchorages.
[ACI]
Short-Term Exposure Limit (STEL). Maximum quantity or concentration of toxic
material in a working environment for limited working times, usually 15 minutes.
Shot Abrasive. Smooth, rounded abrasive normally made of steel. [PCG]
Side-Extrusion Process. A method for extruding thermoplastic coatings onto pipe in
which the coating is extruded from a straight slit in a die located beside the revolving and
advancing pipe. The extruded coating forms a hot ribbon of plastic that flows onto the
pipe surface as a spiral wrap, the edges of each ribbon melting into and fusing with the
edge of the adjacent ribbon. Compare Ring Extrusion Process.
Sieve Analysis. A procedure for determining the size distribution of a blast cleaning
abrasive or other particulate matter based on the percentage of material that is retained on
and passed through one or more standard screens. [PCG]
Sieve Size. Size of an abrasive or other particulate matter determined from ability to pass
through a series of different screens; the lowest screen size through which it will pass.
Silica Sand Abrasive. A blast cleaning abrasive manufactured from material consisting
predominantly of the mineral quartz, which is washed, dried, and screened (sieved).
Exposure to breathable sizes of crystalline silica (10 micrometer [0.4 mil] or smaller) can
cause silicosis, a progressive lung disease. [PCG]
Silicate Resin. Inorganic polymer product with high temperature resistance based upon
the hydrolysis of alkali silicates (e.g., potassium silicate) or alkyl silicates (e.g., ethyl
silicate); used mostly for inorganic zinc-rich coatings.
Silicosis. A chronic lung disease caused by the continued inhalation of silica dust. [CED]
Skin Tanks. On ships, tanks constructed inside the hull for ballast, fuel oil, and void
spaces. Some tanks are bounded by the side shell or bottom plating. The shell of the
vessel is often referred to as its skin. The significance is that these tanks can contain hot
oil or cold water. This influences the temperature of the steel of the outside surface.
Skip Welds. Welds on metal components that are intermittent rather than continuous.
Slag Abrasive. A blast cleaning abrasive made from slag produced by metal-smelting or
coal-fired boilers and power plants. Most slags are processed by quenching in water,
crushing when necessary, washing, and screening to produce an acceptable abrasive. Slag
abrasive manufactured by an air-cooling process has a different mineral structure. The
quality and durability of the abrasive depends upon the processing and can vary widely

B-27

PCI Study Guide- October 2007


from batch to batch and from source to source. Typical slag abrasives include copper and
nickel slag from metal smelting and coal slag from electric power generation. [PCG]
Sling Psychrometer. A psychrometer with wet bulb and dry bulb thermometers and a
swivel handle that allows the instrument to be whirled through the air to obtain constant
wet and dry bulb temperature readings. These temperatures can be used with
psychrometric tables to determine the relative humidity. See Psychrometer. [PCG]
Slurry Blasting. Surface preparation method using pressurized air to propel an abrasive
slurry. See Wet Abrasive Blast Cleaning.
Solids By Volume (%). The volume of the nonvolatile portion of a composition divided
by the total volume, expressed as a percent. Synonym: volume solids. [CED]
Soluble Salt Contaminants. Water-soluble inorganic compounds (such as chlorides and
sulfates) that contaminate a product. When soluble salts are present on a prepared steel
surface, they may cause premature coating failure.
Solvent. (1) Liquid, usually volatile, which is used in the manufacture of paint to dissolve
or disperse the film-forming constituents, and which evaporates during drying and
therefore does not become a part of the dried film. [CED] (2) Liquid used to dissolve and
remove oil, dirt, grease, soil, and waxes from metal surfaces. [PCG]
Solvent Cleaning. The use of organic solvents, detergents, alkaline cleaners, and steam
cleaning to remove oil, grease, dirt, soil, and other, similar organic compounds from a
surface. The specification SSPC-SP 1, Solvent Cleaning, is a consensus standard
covering the procedures necessary for solvent cleaning of steel surfaces. [PCG]
Solvent Resistance. The ability of a coating to resist solvent attack, solution, or
disfigurement. See Solvent Rub Test. [CED]
Solvent Rub Test. A practice for assessing the solvent resistance and/or cure of an
organic coating that chemically changes during curing. ASTM D 4752 is the preferred
solvent resistance test for ethyl silicate zinc-rich primer. [CED]
Spark Tester. See Holiday Detector, High Voltage.
Specification. A word that is used in several ways in the coatings industry. The term job
specification refers to the written, legal document, usually part of a contract, that
precisely describes an item of work that is to be accomplished. Many technical
organizations prepare documents called specifications that describe products, procedures,
or conditions. For example, SSPCs Volume 2 includes many specifications covering
surface preparation, abrasives, paints and paint systems, and paint application. Military,
federal, state, and other agencies also have paint and related specifications. The Army
and Navy also have documents called guide specifications (formerly called type
specifications), which are called engineering standards by private industry.
Specular Gloss. Reflection of light in one path, as from a mirror, as opposed to diffuse
reflection in all directions.
Spiral Wrap. The technique for applying a continuous ribbon or tape to a length of a
pipe. The ribbon is positioned at an angle (less than 90 degrees) to the axis of the pipe
such that each revolution of wrap results in one side of the ribbon being applied over the
previous wrap and the other side being applied to the bare pipe surface. The amount of
overlap is governed by the width of the ribbon and the angle the ribbon makes with the
pipe. Compare to Cigarette Wrap.
Spot-Blast. Localized high-pressure cleaning as used in surface preparation for
maintenance painting.

B-28

PCI Study Guide- October 2007


Spray Pattern. Shape of the area where atomized paint is deposited during air or airless
spray application. [PCG]
Squaring Up. A field term often used where production blasting and painting is
conducted on a large area that will require several days for completion. An area (e.g.,
1,000 ft.2) is chosen each day, using natural partitions as far as possible, that can be
readily blasted, inspected, and primed (squared up) that day. The term may also be used
to describe the application of topcoats on subsequent days according to a selected time
schedule.
Stainless Steel. Any of several steels containing 12 to 30% chromium as the principal
alloying element; they usually exhibit passivity in aqueous environments. [ASM]
Steel Abrasive. Cast steel shot or grit used for abrasive blast cleaning. Cast steel shot
consists of nearly spherical particles of steel obtained by granulating a molten stream of
metal with water or air, or by other methods. Cast steel grit consists of angular particles
produced by crushing steel shot. [PCG]
STEL. See Short Term Exposure Limit.
Stitch Welding. See Skip Welding.
Stress Corrosion Cracking. Cracking caused by corrosion together with the stresses in a
metal. [PCG]
Striping. Painting the edges of a surface or welds to give them extra protection. Striping
is done before priming or before the application of a full coat of paint. [PCG]
Superplasticizer. A (high-range) admixture capable of reducing water or flowability
without causing undue set retardation or air entrainment in mortar or concrete. [ACI]
Superstructure. (1) The part of the ship above the main deck. (2) The entire portion of a
bridge structure that primarily receives and supports highway, railway, canal, or other
traffic loads and in, its turn, transfers the resulting reactions to the bridge substructure.
The superstructure may consist of beam, girder, truss, trestle or other types of
construction.
Surface Conditioner. Chemical material that prepares a surface to receive a coating or
other material.
Surface Preparation. Any method of treating a surface to prepare it for coating. Surface
preparation methods include washing with water, detergent solution, or solvent; cleaning
with hand or power tools; water washing or jetting with or without abrasive; or abrasive
blast cleaning. SSPC and NACE International have a number of written and visual
standards describing surface preparation prior to coating application. [PCG]
Surface Profile. The contour of a blast-cleaned surface on a plane perpendicular to the
surface. For steel, surface profile is the roughened surface that results from abrasive blast
cleaning or power tool cleaning to bare metal, also call the anchor pattern. For wood and
concrete, surface profile is simply the texture of the cleaned surface. Surface profile of
steel is classified by its depth and its texture (rounded or angular). Surface profile depth is
defined as the average peak-to-valley height of the roughness and typically ranges from
less than 1 mil up to 5 mils (25 to 127 micrometers). See Profile Depth.
Surface Profile Comparator. An instrument used to determine the profile of a blast
cleaned surface by visual or tactile comparison of the surface with a series of reference
surfaces of known profile depths. [PCG]

B-29

PCI Study Guide- October 2007


Surfacer. Pigmented composition for filling minor irregularities to obtain a smooth,
uniform surface preparatory to applying finish coats; usually applied over a primer and
sandpapered for smoothness. [ASTM]
Sweat-In Time. See Induction Time.
Sweep Blast Cleaning. A fast pass of the abrasive blasting pattern over a surface to
remove loose material and to roughen the surface sufficiently to successfully accept a
coating. This method of cleaning is sometimes specified as SSPC-SP 7, Brush-off Blast
Cleaning. See also Brush-Off Blast Cleaning. [PCG]
Swing Scaffold. A scaffold with a platform or stage suspended from a structure by two
ropes or cables so it can be raised or lowered as needed. The scaffold height can be
adjusted either manually or with a hoist powered by electricity or compressed air. [PCG]

T
Taber Abraser. An instrument used to measure abrasion resistance (ASTM D 4060).
Specimen on a turntable rotates under a pair of weighted abrading wheels that produce
abrasion through side slip. [CED]
Tack-Free. Absence of tack or stickiness in an applied coating. A coatings freedom
from tack after suitable drying time. [PCG]
Tagging. A means of protecting workers from injury or death caused by the accidental
start-up or release of stored energy from equipment. It involves placing a tag on the
power source as a warning not to restore energy to the piece of equipment. See also
Lockout.
Tape Test. See Adhesion Test, Crosscut.
Tensile Adhesion Test. See Adhesion Test, Tensile (Pull-Off).
Tensile Strength. The maximum tensile stress that a material is capable of sustaining.
Tensile strength is calculated from the maximum load during a tension test carried to
rupture and the original cross-sectional area of the specimen. [ASTM]
Test Strip. Paper strip dipped into solution to estimate of amount of contaminant or other
material present.
Thermal Spray Coating (TSC). Solid coating materials melted before dispersion
(spraying) on a surface.
Thermal Spraying. A process for applying metallic wire, metallic powder, and
thermoplastic powder. The material is melted and sprayed onto a surface to produce a
uniform coating. Gas wire and electric arc guns are used for spraying metallic wire;
plasma guns are used for spraying metallic and thermoplastic powders. See also Flame
Spraying, Metallizing, and Plasma Spraying. [PCG]
Thermit Reaction. Explosive effect that occurs when aluminum and iron oxide are
heated. Aluminum pigmented paints associated with rusty steel are susceptible to the
effect, leading to potential problems in hazardous environments such as gas, fuel oils, etc.
Thermoplastic. A material that becomes soft when heated and hard when cooled without
undergoing chemical change. While the material is soft, it can be reformed or molded. As
used in the coatings industry today, the original meaning of the term thermoplastic has
changed somewhat. It is now used to classify coating types according to how the resins
cure, and the solubility of the cured film. The term thermoplastic is virtually synonymous
with the term non-convertible. See Non-Convertible Coating. [PCG]

B-30

PCI Study Guide- October 2007


Thermoplastic Powder. Powdered organic polymeric materials that are melted by heat;
some are sprayed through a flame to melt them, applied to a substrate as a liquid, and
then solidified on cooling to form a protective film without undergoing chemical change.
Thermosetting. A material that permanently sets when subjected to heat, catalysts,
ultraviolet light, or chemical reaction, and cannot be softened and reformed by reheating.
As used in the coatings industry today, the original meaning of the term thermosetting
has changed somewhat. It is now used to classify coating types according to how the
resins cure, and the solubility of the cured film. Thus, the term thermosetting is virtually
synonymous with the term convertible. See Convertible Coating. [PCG]
Thinner. (1) The portion of a paint, varnish, lacquer, or printing ink, or related product
that volatilizes during the drying process. [ASTM] (2) Any volatile liquid used for
reducing the viscosity of coating compositions or components; it may consist of a simple
solvent or diluent or a mixture of solvents and diluents. [CED]
Thixotropic. Having a gel consistency that becomes liquid when stirred or brushed to
permit application but returning to its original consistency upon standing. Thixotropic
coatings are less likely to drip from a brush than other types and can be applied in rather
thicker films without running or sagging. [V1]
Threshold Limit Value (TLV). The TLV is the concentration of chemical substances in
the air that workers may be exposed to daily without adverse effect. TLVs are
recommended exposure limits and are not required by law to be met. [PCG]
Tie-Coat. A paint specifically formulated to provide a transition from a primer or
undercoat to a finish coat. Tie-coats may be used to seal the surface of a zinc-rich primer,
to bond generically different types of coatings, or to improve the adhesion of a
succeeding coating. [PCG]
Tie Rod. A mechanical connection in tension used to prevent concrete forms from
spreading due to the fluid pressure of fresh unhardened concrete. Also called a form tie.
[ACI]
Time Weighted Average (TWA). Maximum allowed exposure to toxic materials over a
working period, usually 8 hours.
Tin. A soft, silvery-white metallic element. Organotin compounds, once widely used in
anti-fouling coatings, have been widely restricted because toxic tin compounds were
picked up by marine organisms and got into their food chain.
Titanium Dioxide TiO2. A high-opacity, bright white pigment, used as a prime pigment
in paints, rubber, plastics. [CED]
Titration. In chemical analysis, determining the reactive capacity, usually of a solution,
especially, the analytical process of successively adding measured amounts of a reagent
(as a standard solution) to a known volume or weight of a sample or sample solution until
a desired end point is reached. [ASTM]
Tolerance. The total range of variation (usually bilateral) permitted for a size, position,
or other required quantity; the upper and lower limits between which a dimension must
be held. [ASTM, CED]
Toluene. An aromatic solvent used in paint manufacturing and as a thinner and cleanup
solvent. The flash point of toluene is about 30F (-1C). [PCG]
Tooke Gauge. See Destructive Dry Film Thickness Gauge.
Top Coat. The last coating material applied in a coating system, specifically formulated
for aesthetic and/or environmental resistance. Also referred to as the finish coat. [PCG]

B-31

PCI Study Guide- October 2007


Topside. The area on the sides of the ships hull that are above the deep load line.
Topside usually refers to the area from the deep load line to the rail (above the boottop).
Sometimes the word encompasses the decks and areas above deck, such as hatches,
masts, pipes, etc. These areas are exposed to the weather as opposed to immersion in the
sea.
Total Solids. See Nonvolatile Matter.
Toxicity. The capacity of a substance to injure by chemical means. [PCG]
Turbidity. Term used to indicate the degree of water sample cloudiness, which is caused
primarily by the presence of colloidal matter. [IUPAC, CED]
Type 1 Magnetic Pull-Off Gauge. See Magnetic Pull-Off Gauge, Type 1.
Type 2 Magnetic Fixed Probe Gauge. See Magnetic Fixed Probe Gauge, Type 2.

U
Ultrasonic Gauge. Instrument for measuring material thickness by the time sound takes
to travel through it.
Ultrasonic Thickness Measurement. Determining thickness of a solid substrate, such as
steel, through equipment that applies wave energy above the normal hearing range and
then times its retroreflection.
Ultraviolet (UV). A band of electromagnetic radiation between 10 and 400 nanometers
in wavelength. The part of the UV spectrum in the actinic region (280 to 315 nanometers)
is especially destructive to paint films. Ultraviolet energy also sometimes is used to cure
a coating. Black light is a popular term for UV radiation. [PCG]
Undercutting. The penetration of a coating and the spread of delamination or corrosion
from a break or pinhole in the film or from unprotected edges. [PCG]
Upper Explosive Limit (UEL). The concentration at ordinary ambient temperatures of a
compound in air above which an explosion will not occur if the mixture is ignited. UEL
is expressed as a percent of the gas vapor in air by volume. When concentrations of a
substance in air are below the upper explosive limit and above the lower explosive limit
(LEL), the mixture will burn and explode. See also Lower Explosive Limit. [PCG]

V
Vacuum Blasting. Abrasive blast cleaning using a vacuum shroud to capture dust,
debris, and other materials while they are being generated and prevent them from
escaping into the environment. See Abrasive Blast Cleaning. [PCG]
Vehicle. The liquid portion of paint, in which the pigment is dispersed; it is composed of
binder and thinner. [CED]
Viscometer. An instrument for measuring flow properties. [CED]
Viscosity. The quality or property of a fluid (i.e., paint) that causes it to resist flow. A
high viscosity coating is thick; a low viscosity coating is thin. [PCG]
Viscosity Cup. A laboratory or field instrument for measuring the viscosity of a liquid by
timing the liquids flow through an opening in the bottom of a small bowl.
Visual Comparator. One of several systems used to visually estimate the profile of an
abrasive blasted steel surface. See Surface Profile Comparator.
VOC-Compliant. Conforming to VOC regulations. See Volatile Organic Compound.
B-32

PCI Study Guide- October 2007


Volatile. (1) Easily evaporated. (2) Any liquid that evaporates quickly. [PCG]
Volatile Organic Compound (VOC). (1) Any organic compound that reacts in the
atmosphere with nitrogen oxides in the presence of heat and sunlight to form ozone. (2)
Any organic compound (other than those designated by EPA as having negligible
photochemical reactivity) that is emitted into the atmosphere during the application or
curing of a coating. It is detected by reference methods such as EPA Method 24 or
ASTM D 2369. [PCG]

W
Washability. Ease with which the dirt can be removed from a paint surface by washing;
also refers to the ability of the coating to withstand washing without removal or
substantial damage. [CED]
Wash Primer. A carefully balanced one- or two-component system containing an
inhibiting chromate pigment, phosphoric acid, and a synthetic resin binder mixed in an
alcohol. On clean, light alloy or ferrous surfaces, and on many nonferrous surfaces, such
primers provide excellent adhesion, partly due to a chemical reaction with the substrate,
and a corrosion-inhibiting film that is a good basis for the application of subsequent coats
of paint. [CED]
Water Blast Cleaning. A water cleaning method in which abrasive is injected into the
water stream.
Waterborne Coatings. Paint, the vehicle of which is a water emulsion, water dispersion,
or ingredients that react chemically with water. Also called water-based and waterreducible coatings.
Water Break. The appearance of a discontinuous film (beads) of water on a surface,
signifying nonuniform wetting and usually associated with a surface contamination.
[ASTM, CED]
Water Cleaning. A method of using pressurized water, heated or unheated, with or
without detergent, to prepare surfaces for coating. Low-pressure water cleaning uses
pressures up to about 34 MPa (5,000 psi); high-pressure water cleaning ranges from 34
MPa (5,000 psi) to 170 MPa (25,000 psi); and ultrahigh-pressure water cleaning uses
pressures above 170 MPa (25,000 psi). When pressures exceed 69 MPa (10,000 psi), a jet
nozzle is used and the process is called waterjetting.
Waterjetting. The use of water at high or ultrahigh pressure to prepare a surface for
recoating. High pressure waterjetting is cleaning performed at pressures from 69 to 170
MPa (10,000 to 25,000 psi). Ultrahigh pressure waterjetting is cleaning performed at
pressures above 170 MPa (25,000 psi). [SSPC-SP 12/NACE 5].
Water Trap. A structural feature in which liquid (such as rainwater) may accumulate
from the environment.
Weathering. Behavior of coating films when exposed to natural weather or accelerated
weathering equipment, characterized by changes in color, texture, strength, chemical
composition, or other properties. [CED]
Weathering Topcoats. Exterior finishes designed to resist deterioration from ultraviolet
light, rain, and other natural destructive elements in the atmosphere.
Weld Spatter. Beads of metal produced during the welding process that adhere to the
surface near the weld. [PCG]

B-33

PCI Study Guide- October 2007


Wet Abrasive Blast Cleaning. Surface preparation method using conventional dry
abrasive blasting equipment supplemented with modules to inject water into the abrasive
stream. Ideally, the water encapsulates the abrasive particles with a thin film of moisture
to suppress and contain the dust generated by the impact of the abrasive with the
substrate.
Wet Bulb Depression t tw. The difference between the dry-bulb temperature and the
wet-bulb temperature. [ASTM]
Wet Bulb Temperature, tw. The temperature recorded on a wet bulb thermometer. See
also Dry Bulb Temperature and Psychrometer. [PCG]
Wet Bulb Thermometer. The thermometer on a sling or other psychrometer with a bulb
covered by a wet cotton sock. See Psychrometer.
Wet Film Thickness (WFT). Thickness of the liquid coating film immediately after
application. [CED]
Wet Film Thickness Gauge, Notch Type. Gauge with one or more faces cut in a series
of notches that is used to determine coating wet film thickness as described in ASTM D
4414.
Wetting. Ability of a vehicle to spread uniformly and rapidly over the surface of pigment
particles. A vehicle with good wetting properties assists in the grinding or dispersion of
pigments and the ability to wet the surface to which the finished coating is applied.
[CED] (2) The ability of a coating to come into close contact with the surface over which
it is applied. [PCG]
Wetting Agent. Material used in a coating to reduce the surface tension of the vehicle or
binder in order to assist in grinding or dispersing pigments or to improve the ability of the
coating to wet the surface. [PCG]
White Metal Blast Cleaning. Highest grade of blast cleaning. According to SSPC-SP
5/NACE No. 1, a white metal blast cleaned surface is free of all visible oil, grease, dirt,
dust, mill scale, rust, paint, oxides, corrosion products, and other foreign matter. [PCG]
Wire Brush Cleaning. Cleaning a surface with a hand or power tool wire brush. [PCG]
Work Mix. See Abrasive Mix.
Work Permit. Formal instruction, issued daily or weekly, to allow work to take place in
a hazardous environment.
Woven Roving. A cloth consisting of glass fibers woven in a pattern to impart strength
when used to reinforce a coating or other composite system.

X
Xylene. An aromatic solvent used in the manufacture of paints. It also is used widely as a
thinner and cleanup solvent. The flash point of xylene is about 80F (27C). [PCG]

Z
Zinc. A hard, metallic element with a bluish tinge. Zinc or its compounds are used as
reinforcing and corrosion-resistant pigments. Zinc dust is used in zinc-rich coatings to
provide galvanic protection to steel. It is also the basis for galvanizing and sprayed zinc
coatings.

B-34

PCI Study Guide- October 2007


Zinc-Rich. High in zinc dust content; a generic type of coating described in SSPC Paint
20.
Zinc-Rich Coating. Anti-corrosive coating for iron and steel. Zinc-rich coatings use zinc
dust in a concentration sufficient to provide electrical conductivity in the dried film. This
enables the zinc metal to corrode preferentially to the ferrous substrate, giving galvanic
protection. [PCG] See also Galvanic Protection.

Bibliography
ACI: Cement and Concrete Terminology. ACI International: Farmington Hills, MI, 2000.
ASM Metals Handbook. ASM International: Metals Park, OH, 1987.
ASTM Annual Book of Standards. ASTM: West Conshohocken, PA, 2003.
Bridge Inspectors Training Manual/90. U.S. Department of Transportation/Federal
Highway Administration: Washington, DC, 1979.
Coatings Encyclopedic Dictionary (CED). Stanley LeSota, ed., Federation of Societies
for Coatings Technology: Blue Bell, PA, 1995.
Dictionary of Architecture and Construction (DAC). C.M. Harris, ed., McGraw-Hill:
New York, 1975.
EPA: Glossary for Air Pollution of Industrial Coatings Operation. U.S. Environmental
Protection Agency: Washington, DC, 1983.
Industrial Lead Paint Removal Handbook (ILPR). Kenneth A. Trimber, ed., SSPC:
Pittsburgh.
IUPAC Glossary of Atmospheric Chemistry Terms. Atmospheric Chemistry Division,
National Center for Atmospheric Research: Boulder, CO, 1990.
MPDA: The Master Painters Painting and Decorating Terminology Glossary. Master
Painters & Decorators Association: Burnaby, B.C., 1997.
PDC: Painting and Decorating Craftmans Manual and Textbook. Painting and
Decorating Contractors of America: Fairfax, VA, 1975.
Protective Coatings Glossary. SSPC: Pittsburgh, 2000.

B-35

PCI Study Guide- October 2007


Appendix C

Arithmetic

C-1

PCI Study Guide- October 2007

C-2

PCI Study Guide- October 2007

C-3

PCI Study Guide- October 2007

C-4

PCI Study Guide- October 2007

C-5

PCI Study Guide- October 2007

C-6

PCI Study Guide- October 2007

C-7

PCI Study Guide- October 2007

C-8

PCI Study Guide- October 2007

C-9

PCI Study Guide- October 2007

C-10

PCI Study Guide- October 2007

C-11

You might also like