Andhra Pradesh Standard Data Buildings: BLD-CSTN
Andhra Pradesh Standard Data Buildings: BLD-CSTN
S No
Description
Unit
Quantity
BLD-CSTN-1
BLD-CSTN-1-1
BLD-CSTN-1-3
BLD-CSTN-1-4
BLD-CSTN-1-5
Amount
Rs.
6
MORTARS
1
Cement Mortar (1 : 1)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
BLD-CSTN-1-2
Rate
Rs.
5
kg.
1440.00
cum
1.05
cum
1.05
day
0.20
kg.
960.00
cum
1.05
cum
1.05
day
0.20
kg.
720.00
cum
1.05
cum
day
0.20
kg.
480.00
cum
1.05
cum
1.05
day
0.20
kg.
360.00
cum
1.05
cum
1.05
day
0.20
Grand Total
659
Remarks
7
BLD-CSTN
Index-code
S No
BLD-CSTN-1-6
1
6
BLD-CSTN-1-7
BLD-CSTN-1-8
Unit
Quantity
Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
kg.
288.00
cum
1.05
cum
1.05
Rate
Rs.
5
Amount
Rs.
6
day
0.20
kg.
240.00
cum
1.05
cum
1.05
day
0.20
kg.
180.00
cum
1.05
cum
1.05
day
0.20
Kg
cum
cum
400.00
0.90
0.45
cum
0.90
cum
0.45
BLD-CSTN-2
BLD-CSTN-2-1
Description
day
Mason 1st class
day
Mazdoor (unskilled)
kl
Water (including for curing)
Grand Total
Note : For Nominal Mix : Considering table 9 IS 456 : 2000,
the quantity of cement needed is 405 kgs / cum. Hence
proposed 400 kgs of cement for cum of CC M20
0.10
2.36
1.20
660
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-2-2
S No
1
10
Description
Unit
Quantity
Kg
220.00
cum
cum
cum
0.90
0.45
0.90
cum
kl
0.45
1.20
hour
1.00
day
0.10
day
1.39
Rate
Rs.
5
Amount
Rs.
6
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
BLD-CSTN-2-3
BLD-CSTN-2-4
11
12
13
BLD-CSTN-2-5
kg
275.00
cum
0.48
cum
0.54
cum
0.27
cum
0.09
kl
1.20
day
0.10
day
2.36
kg
162.00
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
day
0.10
day
2.36
kg
162.00
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
hour
1.00
661
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
day
0.10
day
1.39
-
kg
cum
129.60
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
day
0.10
day
2.36
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Water Charges 1%
Grand Total
BLD-CSTN-2-6
14
15
BLD-CSTN-2-7
Rate
Rs.
5
Amount
Rs.
6
plinth level.
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
BLD-CSTN-2-8
BLD-CSTN-2-9
16
17
kg
129.60
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
hour
1.00
day
0.10
day
1.39
kg
129.60
cum
0.90
cum
0.54
cum
0.90
cum
0.54
kl
1.20
day
0.10
day
2.36
kg
129.60
cum
0.90
cum
0.54
cum
0.90
cum
0.54
kl
1.20
662
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
hour
1.00
day
0.10
day
1.39
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
BLD-CSTN-2-10
BLD-CSTN-2-11
BLD-CSTN-2-12
18
19
20
Kg
220.00
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
day
0.10
day
2.36
Kg
330.00
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
hour
1.00
day
0.10
day
1.39
Kg
275.000
cum
0.540
cum
0.270
cum
0.090
cum
0.480
cum
0.900
cum
0.480
kl
1.20
hour
1.000
day
0.100
day
1.390
Rate
Rs.
5
Amount
Rs.
6
663
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-2-13
S No
Description
1
2
21 R.C.C. M-20 Nominal Mix
NEW RCC M- 20 Nominal mix (Cement:fine aggregate:
Unit
Quantity
cum
cum
Kgs
0.900
0.450
400.000
day
day
day
0.133
0.267
3.600
hour
Liters
Liters
kl
1.000
0.133
0.667
1.200
cum
cum
Kgs
0.900
0.450
400.000
day
day
day
0.167
0.167
4.700
hour
kl
1.000
1.200
cum
cum
Kgs
0.900
0.450
400.000
day
day
day
0.067
0.133
2.500
hour
kl
0.267
1.200
Rate
Rs.
5
Amount
Rs.
6
A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Cost of Diesel for Miller
Cost of Petrol for Vibrator
Water (including for curing)
BASIC COST per 1 cum
B
A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Water (including for curing)
BASIC COST per 1 cum
C
A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Water (including for curing)
BASIC COST per 1 cum
664
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
22
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-2-14
cum
cum
day
day
day
h
0.80
0.40
0.133
0.267
4.600
1.333
kl
1.200
cum
cum
day
day
day
H
kl
0.80
0.40
0.167
0.167
5.600
1.333
1.200
cum
cum
day
day
day
h
kl
0.80
0.40
0.067
0.133
3.077
0.308
1.200
Grade
Kgs
M 20
350
M 25
M 30
M 35
M 40
380
400
420
430
665
Remarks
7
BLD-CSTN
Index-code
S No
1
23
BLD-CSTN-2-15
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour
Transit mixer 4cum capacity for lead upto 1km
Concrete Pump
C. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total
Note : Wherever concrete is carried out using
batching plant, transit mixer, concrete pump, then
Admixtures @ 0.4% of weight of cement may be
added for achieving desired slump of concrete. If
concentrated Admixture is proposed, only 0.04% of
weight of Cement shall be used.
B
cum
0.80
cum
0.40
cum
0.80
cum
0.40
kl
1.20
hour
0.222
hour
0.222
day
0.222
day
0.056
day
0.056
day
0.917
cum
0.80
cum
0.40
cum
0.80
cum
0.40
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour
kl
1.20
hour
0.444
hour
0.444
Concrete Pump
C. LABOUR:
day
0.444
day
0.111
day
0.222
day
1.556
cum
0.80
cum
0.40
cum
0.80
cum
0.40
kl
1.20
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
666
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
hour
0.133
hour
day
0.133
0.133
day
0.033
day
0.067
day
0.433
B. MACHINERY
Batching plant at 20 cum per hour
Transit mixer 4cum capacity for lead upto 1km
Concrete Pump
C. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total
For Design mix concrete, allow Cement as follows (for
estimate purpose only) :
Rate
Rs.
5
Grade
Kgs
M 20
M 25
M 30
M 35
M 40
350
Amount
Rs.
6
380
400
420
430
24
BLD-CSTN-2-16
Description of Structure
Nil
for each
additional floor
(3.05 M) over
and above 2nd
floorNil
(6.1 M)
1.333
Hrs
10%
0.267
Hrs
10%
kgs
cum
320.00
0.90
cum
cum
cum
L.S.
0.45
0.90
0.45
hour
1.00
Unit = 25 sqm
A. MATERIALS:
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate
day
0.1
day
1.98
667
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-2-17
S No
Description
Unit
Quantity
1
25
2
Damp proof course 50mm thick with 1:2:4 cement
concrete Nominal mix, using 12mm hard broken stone
aggregate including cost of all materials, seigniorage
charges, excluding conveyance charges of materials
including the cost of machinery, labour charges,
mixing, placing in position, leveling, vibrating, curing
etc. complete for finished item of work. (Using
concrete mixer)
kgs
cum
cum
cum
cum
L.S.
320.00
0.90
0.45
0.90
0.45
hour
1.00
day
day
0.1
1.98
1.05
kg
6.00
day
day
2.00
1.025
each
70.000
Hr
10.00
kg
6.00
Unit = 20 sqm
A. MATERIALS:
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate
Rate
Rs.
5
Amount
Rs.
6
6.40
668
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
day
2.50
day
2.00
day
6.40
1.05
kg
6.00
day
day
2.00
27
11.8
BLD-CSTN-2-19
1000
&
1200
28
11.9
BLD-CSTN-2-20
1000
&
1200
Rate
Rs.
5
Amount
Rs.
6
6.40
1.025
each
70.000
Hr
10.00
kg
6.00
day
2.50
day
2.00
day
6.40
1.05
kg
6.00
day
day
2.00
6.40
669
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-3
BLD-CSTN-3-1
Mason 2 class
Mazdoor (unskilled)
Grand Total
Note : For Bricks 2.4 % wastage taken.
ii
iii
Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Bricks traditional
size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
nd
Mason 2 class
Mazdoor (unskilled)
Grand Total
kg
96.00
Nos
cum
512.00
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
kg
72.00
Nos
512.00
cum
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
kg
57.60
Nos
cum
512.00
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
670
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
Description
Unit
Quantity
kg
48.00
Nos
cum
512.00
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
kg
36.00
Nos
512.00
cum
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
kg
96.00
Nos
512.00
cum
0.20
cum
0.20
day
0.24
day
0.56
Mason 2 class
day
Mazdoor (unskilled)
Grand Total
Note : 1. When Mortar mix is changed as CM 1:4, 1:5, 1:6
and 1:8, proportionate quantity of cement has to be
substituted. No change in other data.
Rate
Rs.
5
Amount
Rs.
6
1.89
671
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-3-2
S No
1
30
i
Description
Unit
Quantity
ii
Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:4) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
nd
iii
Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
iv
100.60
520.00
0.21
cum
0.21
day
0.24
day
0.56
day
1.89
kg
75.60
Nos
cum
520.00
0.21
cum
0.21
day
0.24
day
0.56
day
1.89
kg
60.48
Nos
cum
520.00
0.21
cum
0.21
day
0.24
day
0.56
day
1.89
kg
50.40
Nos
cum
520.00
0.21
cum
0.21
day
0.24
Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:8) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
day
0.56
day
1.89
kg
37.80
Nos
cum
520.00
0.21
cum
0.21
iv
kg
Nos
cum
Rate
Rs.
5
Amount
Rs.
6
672
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
day
4
0.24
day
0.56
day
1.89
nos
565.000
31
BLD-CSTN-3-3
32
BLD-CSTN-3-4
BLD-CSTN-3-5
106.000
0.220
cum
0.220
day
0.600
day
0.600
day
Amount
Rs.
6
2.750
1.00%
Ground Floor :
A. MATERIALS:
II Class Bricks
C.M.(1:6)
B. LABOUR:
33
kg.
cum
Rate
Rs.
5
cum
512.000
cum
0.200
day
0.600
day
0.600
day
2.750
nos
kg.
520.000
48.00
673
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
cum
4
0.20
cum
0.20
Sand
Seigniorage charges for sand
B. LABOUR:
34
BLD-CSTN-3-6
35
BLD-CSTN-3-7
36
BLD-CSTN-3-8
Rate
Rs.
5
Amount
Rs.
6
day
0.57
Mason 1st class
nd
day
0.57
Mason 2 class
day
2.54
Mazdoor (unskilled)
1.00%
Add water charges 1%
Grand Total
Note : Compressive strength of individual Brick
shall not be less than 70 kg / cm2
Brickwork in arches in cement mortar 1:4
complete including centering and shuttering
excluding pointing and plastering as per
drawing and technical specifications Clauses
606 and 1205.1 MORD
Unit = cum
a) Material
Nos.
525.00
Brick 1st class
cum
0.24
Cement mortar (1:4)
b) Labour
day
1.88
Mazdoor (Unskilled)
day
2.00
Mason (1st Class)
c) Add for centering and shuttering @ 110% of
(a+b)
Grand Total
Note : 1 ) In case cement mortar 1:3 is used, proportionate rate is to be adopted.
2) Quantity of bricks for arches will be about 10 per cent more than that for ordinary
brickwork .
3) In case special arch bricks are used, the quantity of bricks per cum shall be taken as
580 Nos.
4) Rates for spandrel walls shall be taken same as for brickwork in substructure.
5) Rate for spandrel filling will depend on the filling material adopted
6) Compressive strength of individual Brick shall not be less than 70 kg / cm2
Honey Comb work with Bricks of traditional Size
and Plastered One Coat 10 mm. thick Cement
Mortar 1:5 including White Washing 2 Coats
Unit = cum
a) Material
Brick 2nd class 23 x 11 x 7
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Honey Comb work with Bricks of Modular Size
and Plastered One Coat 10 mm. thick Cement
Mortar 1:5 including White Washing 2 Coats
Unit = cum
a) Material
Brick 2nd class 19 x 9 x 9
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Nos.
750.00
cum
0.67
day
day
day
LS
6.60
2.41
6.21
LS
Nos.
790.00
cum
0.67
day
6.60
day
2.41
day
6.21
LS
LS
674
Remarks
7
BLD-CSTN
Index-code
S No
1
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-4
BLD-CSTN-4-1
Description
37
kg
115.20
cum
0.89
cum
0.16
cum
0.16
cum
0.16
day
day
1.05
2.45
day
3.50
day
2.80
BLD-CSTN-4-2
38
i
ii
iii
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:3) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:4) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
kg
201.60
cum
0.94
7Nos.
0.16
cum
0.28
cum
cum
0.28
1.10
day
day
2.50
2.32
kg
134.40
cum
0.94
7Nos.
0.16
cum
0.28
cum
cum
0.28
1.10
day
day
2.50
2.32
kg
100.80
cum
0.94
7Nos.
cum
0.16
0.28
cum
cum
0.28
1.10
day
day
2.50
2.32
675
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
BLD-CSTN-4-3
39
Description
Unit
Quantity
kg
67.20
cum
0.94
7Nos.
cum
0.16
0.28
cum
cum
0.28
1.10
day
day
2.50
2.32
kg
76.80
cum
0.94
cum
0.16
cum
0.32
cum
0.32
cum
1.10
day
Mason 1st class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted. No change in other data.
BLD-CSTN-4-4
Amount
Rs.
6
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
40
Rate
Rs.
5
1.50
2.32
cum
0.94
Nos.
0.16
cum
0.30
day
3.00
day
2.43
BLD-CSTN-4-5
41
Unit = 1cum
A. MATERIALS:
Cement
kg
57.60
cum
0.89
cum
0.16
0.16
cum
0.16
676
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
day
5.05
day
2.45
day
6.30
Rate
Rs.
5
Amount
Rs.
6
B. LABOUR:
BLD-CSTN-4-6
42
43
BLD-CSTN-4-7
LS
kg
cum
100.80
1.15
cum
cum
0.28
0.28
day
0.90
day
day
2.10
2.43
LS
0.40
cum
0.45
cum
0.54
cum
0.36
day
0.20
day
2.15
hour
0.40
II
Grand Total
RCC Grade M 25 (Design mix)
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
b) Labour
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
0.38
cum
0.45
cum
0.54
cum
0.36
day
0.20
day
2.15
hour
0.40
Grand Total
Note : The additional cost of centering and shuttering @ 50 per cent
of cost of material and labour shall hold good for arch spans of 6 m
and above. For lesser length of spans, the corresponding additional
cost can be taken as 40 per cent for spans above 4 m length and 30
per cent for spans less than 4 m.
677
Remarks
7
BLD-CSTN
Index-code
S No
BLD-CSTN-4-8
1
44
BLD-CSTN-4-9
45
Description
Unit
Quantity
RR Masonry in CM (1:6)
Unit = 1cum
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
RR Masonry in CM (1:8)
Unit = 1cum
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
kg
79.20
cum
0.44
cum
0.50
cum
cum
0.16
0.33
cum
cum
0.33
1.10
day
1.20
day
2.00
kg
59.40
cum
0.44
cum
0.50
cum
cum
0.16
0.33
cum
cum
0.33
1.10
day
Mason 1st class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity
of cement has to be substituted. No change in other data
BLD-CSTN-4-10
BLD-CSTN-4-11
46
47
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
1.20
2.00
cum
cum
1.04
0.16
cum
1.20
day
0.33
day
0.77
day
1.10
cum
cum
1.04
0.16
cum
1.20
day
0.45
day
1.05
day
1.10
678
BLD-CSTN
Index-code
S No
1
48
BLD-CSTN-4-12
Description
Unit
Quantity
sqm
10.50
cum
0.15
day
0.90
day
2.10
day
2.00
BLD-CSTN-5-2
49
50
BLD-CSTN-5-3
51
52
BLD-CSTN-5-4
Amount
Rs.
6
POINTING
BLD-CSTN-5
BLD-CSTN-5-1
Rate
Rs.
5
kg
14.40
cum
0.03
cum
0.03
day
0.50
day
0.74
kg
14.40
cum
0.03
cum
0.03
day
0.50
day
0.74
kg
28.80
cum
0.06
cum
0.06
day
0.50
day
0.74
cum
0.038
day
day
1.460
2.260
679
Remarks
7
BLD-CSTN
Index-code
S No
1
BLD-CSTN-6
BLD-CSTN-6-1
Description
Unit
Quantity
cum
0.15
cum
0.15
day
0.60
day
0.96
cum
0.15
cum
0.15
day
0.60
day
0.96
BLD-CSTN-6-3
cum
0.150
cum
0.150
day
0.60
day
0.96
BLD-CSTN-6-4
cum
0.15
cum
0.15
day
0.60
day
0.96
BLD-CSTN-6-5
cum
0.15
cum
0.15
day
0.60
day
0.96
Amount
Rs.
6
PLASTERING
53
BLD-CSTN-6-2
Rate
Rs.
5
54
55
56
57
680
Remarks
7
BLD-CSTN
Index-code
S No
BLD-CSTN-6-6
1
58
Description
Unit
Quantity
cum
0.19
cum
0.19
day
0.60
day
0.96
BLD-CSTN-6-8
59
cum
0.210
cum
0.21
day
0.94
day
1.60
60
cum
0.210
cum
0.21
61
BLD-CSTN-6-9
day
Mason 2nd class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
Plastering with CM 2 coats, 20 mm thick, base
coat in CM (1:6), 16mm thick and top coat in CM
(1:4), 4mm thick with Dubara sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:4), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
BLD-CSTN-6-10
Remarks
7
0.94
1.60
kg
43.00
cum
0.18
kg
14.50
cum
0.04
cum
0.22
day
Mason 1st class
nd
day
Mason 2 class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
62
Amount
Rs.
6
BLD-CSTN-6-7
Rate
Rs.
5
0.63
1.47
3.90
kg
31.70
cum
0.11
kg
19.20
cum
0.04
681
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
3
cum
4
0.15
63
BLD-CSTN-6-11
day
Mason 1st class
nd
day
Mason 2 class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
RCM FACIA WORKS
RCM facia 5cm thick in CM (1:3) for drop walls, fins with
rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara sponge finishing, including
cost & conveyance of all materials to site, seigniorage
charges, sales & other taxes on all materials, operational &
incidental, cost and conveyance of cement, wire mesh, water
to work site, centering, scaffolding and form work, lift
charges etc., complete for finished items of work but
excluding cost of steel & its fabrication charges, for finished
item of work. (APSS No.403 & 903)
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop)
Cement Mortar 1:3 for 25 mm thick
Dry Cement for making Lumps
12 mm Plastering 2 coats in 1:4 & 1:2 cm both sides
Excluding HYSD Steel/ Mild steel & Binding wire
B) LABOUR CHARGES
1st Class Mason
Miller Operator
Mazdoor (unskilled)
c) Machinery
Machine Mixing Mortar with Miller - Hire charges
BASIC COST per 10 sqm
64
BLD-CSTN-6-12
sqm
Rate
Rs.
5
Amount
Rs.
6
0.63
1.47
3.90
13.30
cum
0.25
kg
50.00
sqm
21.80
day
8.00
day
1.00
day
10.00
32.00
Hrs
2.00
cum
0.110
kg
52.800
cum
0.110
day
0.020
day
day
1.710
3.270
day
day
0.250
0.250
682
Remarks
7
BLD-CSTN
Index-code
S No
1
65
BLD-CSTN-6-13
Description
Unit
Quantity
cum
0.224
cum
0.100
kg
9.280
day
day
1.710
3.270
day
day
0.500
1.000
kg
6.000
kg
6.000
Rate
Rs.
5
Amount
Rs.
6
683
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
1
66
2
Pebble dash exterior plaster on walls upto a height of 10
metres above ground level with a mixture of washed
pebble or crushed stone graded from 6 mm to 12 mm
nominal size dashed over and including fresh cement
plaster in two coats, backing coat 10 mm cement plaster 1
: 3 (1 cement : 3 sand) and finishing coat 10 mm cement
plaster 1 : 3 (1 cement : 3 sand) mixed with 10% finely
grounded hydrated lime by volume of cement including
arrises, chamfers and/or rounded angles not exceeding 80
mm in girth
cum
kg
0.224
9.280
cum
0.100
day
day
1.710
3.270
day
day
0.500
0.610
cum
0.023
day
day
0.300
0.350
cum
0.023
day
day
0.300
0.350
cum
0.023
day
day
0.380
0.430
BLD-CSTN-6-14
Labour for backing coat and finishing coat :Mason llnd class
Mazdoor (unskilled)
Labour for pebble dashing
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Plain Cement Mortar Bands :
67
BLD-CSTN-6-15
Rate
Rs.
5
Amount
Rs.
6
684
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-6-16
S No
Description
Unit
Quantity
1
68
cum
0.224
day
day
2.200
2.700
cum
0.224
day
day
2.500
3.000
cum
0.224
day
day
3.000
3.500
cum
0.023
day
day
0.870
0.920
BLD-CSTN-6-17
69
Rate
Rs.
5
Amount
Rs.
6
70
BLD-CSTN-6-18
day
110.000
cum
0.100
B. LABOUR
Mason 1st class
day
0.420
685
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
day
4
0.920
day
day
0.700
2.100
sqm
11.00
kg.
21.60
kg.
33.00
kg.
20.00
cum
0.12
cum
0.12
day
3.10
day
1.10
day
0.86
sqm
10.50
kg.
21.60
kg.
9.60
cum
0.12
cum
0.02
cum
0.14
day
0.960
day
2.240
day
3.30
Rate
Rs.
5
Amount
Rs.
6
FLOORING
BLD-CSTN-7
71
BLD-CSTN-7-1
72
BLD-CSTN-7-2
686
Remarks
7
BLD-CSTN
Index-code
S No
1
73
BLD-CSTN-7-3
Description
Unit
Quantity
sqm
10.10
kg.
48.00
kg.
33.00
kg.
cum
5.00
0.20
cum
0.20
day
1.00
day
2.10
day
3.00
day
5.00
sqm
10.05
kg.
28.80
kg.
33.00
kg.
6.00
BLD-CSTN-7-4
Amount
Rs.
6
74
Rate
Rs.
5
Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22 mm thick (medium
shade)
kg.
cum
0.12
cum
0.12
day
0.960
day
2.240
day
3.30
687
Remarks
7
BLD-CSTN
Index-code
S No
1
75
BLD-CSTN-7-5
76
BLD-CSTN-7-6
Description
Unit
Quantity
sqm
10.10
kg.
21.60
kg.
33.00
kg.
6.000
Rate
Rs.
5
Amount
Rs.
6
cum
0.12
cum
0.020
cum
0.140
day
0.96
day
2.24
day
3.30
1.00%
sqm
10.10
kg.
21.60
kg.
33.00
kg.
2.00
cum
0.12
cum
0.12
day
0.96
day
2.24
day
3.30
1.00%
688
Remarks
7
BLD-CSTN
Index-code
S No
1
77
BLD-CSTN-7-7
Description
Unit
Quantity
sqm
10.10
kg.
36.00
kg.
33.00
kg.
6.00
78
BLD-CSTN-7-8
Rate
Rs.
5
Amount
Rs.
6
kg.
cum
0.20
cum
0.20
day
3.00
day
1.00
day
8.00
1.00%
Unit = 10 sqm
A. MATERIALS:
Marble tiles polished 8 mm thick
Cement for CM (1:8) for base coat
Cement for slurry
White cement for jointing & pointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR (including for polishing & rubbing)
Mason 1st class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
sqm
10.10
kg.
36.00
kg.
33.00
kg.
5.00
cum
0.20
cum
0.20
day
4.00
day
8.00
1.00%
689
Remarks
7
BLD-CSTN
Index-code
S No
1
79
BLD-CSTN-7-9
80
BLD-CSTN-7-10
Description
Unit
Quantity
sqm
10.10
kg.
48.00
cum
0.20
cum
0.20
day
4.00
day
Rate
Rs.
5
Amount
Rs.
6
8.00
1.00%
Unit = 10 sqm
A. MATERIALS:
Decorated white back ground glazed tiles
sqm
kg.
10.10
28.80
kg.
33.00
kg.
6.00
cum
0.12
cum
0.12
day
0.96
day
2.24
day
3.30
1.00%
690
Remarks
7
BLD-CSTN
Index-code
S No
1
81
BLD-CSTN-7-11
Description
Unit
Quantity
1000
Nos
kg.
0.255
21.600
kg.
6.000
10sqm
1.000
82
BLD-CSTN-7-12
cum
0.040
cum
0.120
cum
0.120
day
0.960
day
2.240
A. MATERIALS:
Plain cement Tiles 20 x 20 cms
day
Amount
Rs.
6
4.30
1.00%
1000
Nos
0.255
kg.
21.600
kg.
6.000
10sqm
1.000
cum
0.040
cum
0.120
cum
0.120
day
0.960
day
2.240
Rate
Rs.
5
day
3.30
1.00%
691
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-7-13
84
BLD-CSTN-7-14
85
86
BLD-CSTN-7-16
0.17
kg
120.00
cum
0.085
cum
0.085
day
1.25
day
0.06
day
3.00
1.00%
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete mixer
Stone Chippings 3.34 mm - 10 mm
Cement
B. LABOUR
BLD-CSTN-7-15
cum
cum
1.000
cum
0.250
kg
120.000
day
Mason 1st class
nd
day
Mason 2 class
day
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered over
with 12 mm thick in CM(1:3)
Unit = 10 sqm
A. MATERIALS:
cum
Cement Concrete 1:6:10 using concrete mixer
10 sqm
Plastering with CM (1:3), 12 mm thick
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered over
with 12 mm thick in CM(1:3) using Red oxid,
with polished surface
Unit = 10 sqm
A. MATERIALS:
cum
Cement Concrete 1:6:10 using concrete mixer
10 sqm
Plastering with CM (1:3), 12 mm thick
kg
Red oxid
0.150
0.350
5.40
1.00%
1.00
1.00
1.00
1.00
10.00
692
Remarks
7
BLD-CSTN
Index-code
S No
1
87
BLD-CSTN-7-17
Description
Unit
Quantity
Nos
1.10
kg
17.000
B. LABOUR
Masons for polishing
Grand Total
6 mm thick terrazzo flooring in situ with white,
black, chocolate, gray, yellow or green superior
marble chips, over 20 mm thick base coat of CM
(1:3) laid over CC bed already laid or RCC roof
slab, including cost of all materials like cement
marble powder, marble chips, sand & water etc.,
complete including polishing to get high smooth
finishing, seigniorage charges, etc., complete
for finished item of work, but excluding the cost
of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Marble Powder
Marble Chips
Cement for top layer
Cement for base coat in CM (1:3)
Sand for base coat
Seigniorage charges of sand
B. MACHINERY
Polishing Charges
C. LABOUR
88
BLD-CSTN-7-18
cum
0.060
kg.
50.000
kg.
96.000
cum
0.200
cum
0.200
sqm
10.000
day
0.960
day
2.240
day
3.30
sqm
10.00
cum
0.12
kgs
57.60
kgs
33.00
kgs
6.00
cum
0.12
day
0.77
day
0.80
Rate
Rs.
5
Amount
Rs.
6
693
Remarks
7
BLD-CSTN
Index-code
S No
1
89
BLD-CSTN-7-19
Description
Unit
Quantity
sqm
10.10
BLD-CSTN-7-20
Amount
Rs.
6
90
Rate
Rs.
5
cum
0.12
kg
57.60
kg
33.00
kg
5.00
RM
66.67
RM
67.67
cum
0.12
day
2.10
day
4.90
day
4.00
day
4.00
sqm
cum
kgs
kgs
kgs
cum
10.10
0.12
34.56
33.00
2.00
0.12
day
day
day
0.96
2.24
3.30
1.00%
Mason 2 class
Mazdoor (unskilled)
Add water charges 1%
Grand Total
694
Remarks
7
BLD-CSTN
Index-code
S No
1
91
BLD-CSTN-7-21
Description
Unit
Quantity
sqm
10.10
cum
kgs
kgs
kgs
cum
0.12
57.60
33.00
5.00
0.12
day
day
2.10
0.80
4.90
1.00%
sqm
10.10
cum
kgs
kgs
cum
0.12
57.60
33.00
0.12
day
day
day
0.96
2.24
3.10
1.00%
Rate
Rs.
5
Amount
Rs.
6
92
BLD-CSTN-7-22
materials
Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Cuddapah stone
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
695
Remarks
7
BLD-CSTN
Index-code
S No
1
93
BLD-CSTN-7-23
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
materials
Unit = 10 sqm
A. MATERIALS:
sqm
25 mm thick polished Shahabad stone (White)
cum
Sand for cm 1:3 base coat
kgs
Cement for cm 1:3 base coat
kgs
Cement for slurry
cum
Seigniorage charges of sand
B. LABOUR
day
Mason Ist class
Mason 2nd class
day
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted for all Skirting Items.
94
BLD-CSTN-7-24
10.10
0.12
57.60
33.00
0.12
0.96
2.24
3.10
1.00%
0.44
3.00
1.95
4.55
5.40
696
Remarks
7
BLD-CSTN
Index-code
S No
1
95
BLD-CSTN-7-25
Unit
Quantity
cum
1.53
day
1.10
day
0.50
kgs
103.09
nos
47.91
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-8
96
BLD-CSTN-8-1
Description
nos
nos
43.90
nos
91.82
nos
91.82
litre
0.14
litre
0.20
day
0.84
day
0.91
day
0.06
day
0.06
day
0.14
day
0.14
LS
LS
Grand Total
Rate per 10 sqm = Grand Total/10
697
Remarks
7
BLD-CSTN
Index-code
S No
1
97
BLD-CSTN-8-2
98
BLD-CSTN-8-3
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
kgs
126.07
nos
47.91
nos
43.90
nos
91.82
nos
91.82
litre
0.14
litre
0.20
day
0.84
day
0.91
day
0.06
day
0.06
day
0.14
day
0.14
kgs
154.80
nos
47.91
nos
43.90
nos
91.82
nos
91.82
litre
0.14
litre
0.20
day
0.84
day
0.91
day
0.06
day
0.06
698
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-4
BLD-CSTN-8-5
S No
Description
Unit
Quantity
Amount
Rs.
6
0.14
0.14
0.15
22.03
22.03
22.03
0.43
0.54
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
1000 No
1560
1000 No
470
10RM
Teak Reepers 50 x 12 mm
kgs
Wire Nails 40 mm long
cum
Lime
cum
Lime Mortar
B. LABOUR
day
Carpenter
day
Bricklayers
day
Man mazdoor
day
Woman mazdoor
LS
Sundries including tarring reepers, extra labour / for
pointing the underside of flat tiles and white
washing the same.
Grand Total
Sub Analysis :
Lime Moratar 1:2
cum
lime
cum
Sand
cum
Grinding Lime Mortar
Total
Rate
Rs.
5
75.000
0.500
0.008
0.300
0.800
2.200
1.100
5.400
LS
0.500
1.000
1.000
699
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-6
S No
Description
Unit
Quantity
1000 No
1560
10RM
kgs
cum
107.000
0.700
0.120
day
day
day
day
1.100
1.400
1.100
3.200
1000 No
1560
RM
25
100 No
150
Bamboo mats
10 sqm
10.500
cum
0.120
day
day
day
day
1.100
1.400
1.100
3.200
1000 No
160
1000 No
470
1
2
101 Best Tiled Roofing with Pan tiles and Lime
197 mortar Borders including Teak Reapers at 100
mm. centres
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime Moratar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Grand Total
BLD-CSTN-8-7
BLD-CSTN-8-8
Rate
Rs.
5
Amount
Rs.
6
10RM
Teak Reepers 50 x 12 mm
kgs
Wire Nails 40 mm long
cum
Lime
cum
Lime Moratar
B. LABOUR
day
Carpenter
day
Bricklayers
day
Man mazdoor
day
Woman mazdoor
LS
Sundries including tarring reepers iron wind ties 30
x 3 mm, G.I. Screw, washers etc., and extra labour
for pointing the underside of flat tiles and white
washing the same.
75.000
0.500
0.008
0.380
0.800
1.600
1.100
4.300
LS
Grand Total
700
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-9
S No
Description
1
2
104 Best Tiled Roofing with
200 including Teak Reepers
Mangalore
Quantity
1000 No
160
10RM
Teak Reepers 50 x 12 mm
kgs
Wire Nails 50 mm long
cum
Lime Moratar
B. LABOUR
day
Carpenter
day
Bricklayers
day
Man mazdoor
day
Woman mazdoor
Grand Total
105 Best Tiled Roofing with Mangalore tiles over
201 Ceiling Tiles with Air Spaces and including Teak
Reepers
Unit = 10 sqm
A. MATERIALS:
36.000
0.500
0.090
with 10 sqm
10.000
Rate
Rs.
5
Amount
Rs.
6
tiles
Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification)
BLD-CSTN-8-10
Unit
B. LABOUR
Bricklayers
Woman mazdoor
Grand Total
0.500
0.500
1.100
2.200
100 No
156
day
day
0.500
1.100
cum
cum
cum
LS
0.670
1.000
1.000
cum
cum
cum
0.180
0.080
0.023
day
day
LS
3.200
6.500
LS
Sub Analysis :
Lime Mortar (1: 1.5) :
Unit = 1 cum
BLD-CSTN-8-11
Lime
Fine Sand
Grinding Mortar (Spl Grinding)
Sundries
Total
106 Plastering with Lime Mortar 3 Coats, 25 mm
thick (Sebara Rendering)
Unit = 10 sqm
Lime Mortar (1:2)
Lime Mortar (1:1.5)
Lime
LABOUR
Bricklayers
Mazdoor (unskilled)
Sundries
Total
701
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-12
S No
Description
1
2
107 Terrace Roofing with Brick on edge 75 mm.
204 Concrete 2 Courses of Flat Tiles at Top and
Unit
Quantity
2000
100 No
900
cum
Broken brick 20 mm cube
cum
Lime
cum
Lime Moratar
Pointing with cement mortar 1:3 (for rate - vide 10 sqm
relevant schedule item)
cum
Cement Mortar 1:3
B. LABOUR
Bricklayers
Mazdoor (unskilled)
Grand Total
day
day
Rate
Rs.
5
Amount
Rs.
6
0.980
0.380
0.210
1.000
0.240
4.300
6.500
Note : The quantity proposed for broken brick allows for the
brick powder formed, replacing sand for concrete layers.
BLD-CSTN-8-13
10.000
cum
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate - vide 10 sqm
relevant schedule item)
B. LABOUR
day
Bricklayers
day
Woman mazdoor
LS
Sundries including crude oil
Grand Total
Sub Analysis :
RCC (M 20) using 20 mm HG graded metal using
Concrete mixturefor Roofing 125 mm thick
0.260
1.000
BLD-CSTN-8-14
900
2.200
2.200
cum
1.250
10 sqm
1.000
Form Work
Total
109 Reinforced cement Concrete Roofing 140 mm
206 thick with CC (M 20) using 20 mm graded metal
and 2 courses of Flat Tiles at Top including
Pointing with Cement Mortar (1:3)
Unit = 10 sqm
A. MATERIALS:
Rate of "Reinforced cement Concrete Roofing 125 mm 10 sqm
thick and 2 courses of Flat Tiles at Top including pointing
with Cement Mortar (1:3)"
Add :
For extra thickness of roofing slab
Grand Total
cum
1.000
0.150
702
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-15
S No
Description
1
2
110 Reinforced cement Concrete Roofing 150 mm
207 thick with CC (M 20) using 20 mm graded metal
Unit
Quantity
Add :
For extra thickness of roofing slab
Grand Total
BLD-CSTN-8-17
Amount
Rs.
6
BLD-CSTN-8-16
Rate
Rs.
5
cum
1.000
0.250
1.000
0.250
1.000
1.000
10 sqm
1.000
kgs
1.500
703
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-18
S No
Description
1
2
113 Complete Surface Repairs to Leaky Terrace
208 Roofs with Flat Tiles
Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm
Unit
Quantity
1000 No
450
cum
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate - vide 10 sqm
relevant schedule item)
BLD-CSTN-8-19
B. LABOUR
day
Bricklayers
day
Man Mazdoor
Clean removal of lime plaster from terraced roofs 10 sqm
and raking out joints 12 mm deep (for rate - vide
relevant schedule item)
Sub Analysis :
Day
Mazdoor (unskilled)
Day
Mate
LS
Sundries including crude oil
Grand Total
114 Best Sloping Bengal Terrace with 3 courses of
209 Flat Tiles at Top including Teak Wood Reepers
Rate
Rs.
5
Amount
Rs.
6
0.110
1.000
1.100
1.100
1.000
Unit = 10 sqm
A. MATERIALS:
1000 No
1350
cum
cum
10 RM
0.008
0.150
75.000
kgs
Wire Nails 40 mm long
Plastering with lime mortar 3 coats (for rate - vide 10 sqm
relevant schedule item)
0.500
1.000
B. LABOUR
Carpenter
Bricklayers
Woman mazdoor
Sundries including tarring reepers
Grand Total
day
day
day
LS
0.800
2.200
2.200
704
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-20
S No
1
2
115 Removing Old Tiles and Retiling with New Pan
212 Tiles over Old Teak Reepers including New
Unit
Quantity
BLD-CSTN-8-21 116
213
117
BLD-CSTN-8-22 214
BLD-CSTN-8-23
Description
cum
Lime Moratar
B. LABOUR
day
Bricklayers
day
Man Mazdoor
day
Woman mazdoor
LS
Sundries
Grand Total
Shifting Pan Tiles (Labour Only)
Unit = 10 sqm
day
Bricklayers
day
Man Mazdoor
Grand Total
Shifting Pan Tilesand forming new White
Washed Lime Mortar Boarders, 230 x 50 mm at 2
Metres Intervals
Unit = 10 sqm
10 sqm
Rate of "Shifting Pan Tiles"
LS
Add : Lime Mortar Borders and White Washing
Grand Total
118 12 mm. Teak Wood Plank Ceiling Tongued and
222 Grooved Planking
Unit = 10 sqm
A. MATERIALS:
cum
Teak Wood Planks 150 x 12 mm
100
No
Screws 40mm long
B. LABOUR
Carpenter
Man Mazdoor
Sundries
Grand Total
Note : Deduct 4.3 Nos Carpenters if plank rate is
for tongued and grooved ready planned.
day
day
LS
Rate
Rs.
5
Amount
Rs.
6
1560
0.120
1.400
1.100
4.300
1.100
0.800
1.000
0.132
300
6.500
5.400
BLD-CSTN-8-24 223
mm Teak Wood Battens
Unit = 10 sqm
Rate for "12 mm. Teak Wood Plank Ceiling 10 sqm
Tongued and Grooved Planking"
10 RM
Teak Wood Battens 40 x 12 mm
Brass screws 25 mm long
Deduct :
Carpenter
Sundries
Grand Total
10.000
66.000
100 No
240
day
LS
1.100
705
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
120 Providing impervious coat to exposed RCC roof
BLD-CSTN-8-25
BLD-CSTN-8-26
BLD-CSTN-8-27
BLD-CSTN-8-28
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
Unit
Quantity
cum
0.210
kg
2.000
day
0.660
day
1.540
day
3.70
sqm
11.00
day
2.50
day
2.00
sqm
11.00
day
2.50
day
2.00
sqm
11.00
day
2.50
day
2.00
Rate
Rs.
5
Amount
Rs.
6
706
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
124 Providing & fixing plain AC sheet ceiling of
BLD-CSTN-8-29
Unit
Quantity
sqm
11.00
day
2.50
day
2.00
cum
0.05
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-8-30
BLD-CSTN-8-31
kg
0.75
sqm
10.20
kg
219.76
day
2.60
day
1.60
day
2.62
day
1.62
day
377.00
sqm
1.03
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards
707
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
RM
Nos
0.64
1.84
RM
2.30
RM
0.84
RM
Nos
Nos
Nos
Kgs
RM
Lits
0.40
0.64
0.64
18.00
0.55
1.46
0.15
day
day
day
day
day
day
day
0.40
0.40
0.08
0.08
0.04
0.08
0.24
Hrs
Hrs
0.32
0.64
1%
sqm
1.00
RM
0.40
RM
1.60
RM
1.60
RM
Nos
Nos
Nos
1.28
1.28
1.28
5.36
Ceiling Angle
25 mm x 10 mm x 0.55 mm
Connecting Clips
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm thick
Rawl Plug
Soffit Cleats
Drywall Screws - 25 mm
Jointing Compound
Jointing Paper Tape
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
Gyp Board Fine Line Grid false ceiling
BLD-CSTN-8-32
Rate
Rs.
5
Amount
Rs.
6
127 Supplying and fixing Gyp Board Fine Line Grid false ceiling
(GS-FLC-4.6 as per India Gypsum) in size 600 mm x 600
mm using 12.5 mm thick/ 9.5 mm thick Gyp Board sheet
tiles of size 595 mm x 595 mm or 595 mm x 1195 mm
conforming to IS 2095 - 1982 fixing to Gyp steel precoated
GI wall angle of size 25 mm x 25 mm x of 0.70 mm thick
along the perimeter of ceiling screw fixed to brick work/
partition at 610 mm c/c and suspending the frame work
using precoated GI Tee section (24 mm x 38 mm x 0.7
mm) from soffit at 1220 mm c/c fixed with GI Soffit Cleat,
rawl plugs and steel expansion fasteners & connecting clip
to the GI T section with 4 mm dia GI Rod with galvanised
spring steel level clip of PVC unversal holding clips system
at 1200 mm c/c and fixing the 12.5 mm / 9.5 mm
Gypboard Sheet tiles of size 595 mm x 595 mm or 595 mm
x 1195 mm and finishing two coats of drywall topcoat
complete for finished item of work as per Idia Gypsum Ltd
specification.
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm / 9.5 mm - Gypboard Tiles
Either - 595 mm x 595 mm Or - 595 mm x 1195 mm GI Angle - Precoated
25 mm x 25 mm x 0.7 mm
GI - Precoated - T Section - 3600 mm long
24 mm x 38 mm x 0.7 mm thick
GI - Precoated - T Section - 600 mm long
24 mm x 38 mm x 0.7 mm thick
GI Rod - 4 mm Dia
Connecting Rod
Rawl Plug
Soffit Cleats
Unversal Holding Clips
708
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
Lits
4
0.15
day
day
day
day
day
day
day
0.40
0.40
0.08
0.08
0.04
0.04
0.24
Hrs
Hrs
0.32
0.32
1%
sqm
1.00
RM
0.40
RM
1.60
RM
1.60
RM
Nos
1.28
1.28
day
day
day
day
day
day
day
0.40
0.40
0.08
0.08
0.04
0.04
0.24
Hrs
Hrs
0.32
0.32
1%
BLD-CSTN-8-33
Rate
Rs.
5
Amount
Rs.
6
UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x 600
Hotdipped GI Angle - Precoated - Grid
19 mm x 19 mm
Polyster painted GI - T Section - 1200 mm
(1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross Tee)
Polyster painted GI - T Section - 300 mm
24 mm x 27 mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
6 mm Nylon Rawl Plug
B) LABOUR CHARGES
PER UNIT 1 sqm
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
709
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
sqm
1.00
RM
0.40
RM
3.20
Nos
Nos
1.28
1.28
day
day
day
day
day
day
day
0.36
0.36
0.00
0.00
0.02
0.04
0.20
Hrs
Hrs
0.16
0.32
1%
cum
0.005
L.S
day
day
LS
0.11
0.22
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-8-34
UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600
Alumninium Angle
24 mm x 24 mm
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
Rawl Plugs
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
BLD-CSTN-9
BLD-CSTN-9-1
710
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
131 White washing two coats with lime of approved
BLD-CSTN-9-2
BLD-CSTN-9-3
Unit
Quantity
cum
0.007
L.S
day
day
LS
0.160
0.32
cum
0.009
L.S
day
day
day
day
day
LS
0.220
0.43
Rate
Rs.
5
Amount
Rs.
6
133 White
BLD-CSTN-9-4
1.20
day
day
0.11
0.22
0.50%
711
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
cum / kg
2.00
1
134 White
BLD-CSTN-9-5
L.S
BLD-CSTN-9-7
Amount
Rs.
6
BLD-CSTN-9-6
Rate
Rs.
5
B. LABOUR
day
Brick Layers / Painter
day
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
135 White washing three coats with whiting of
approved quality to give an even shade after
thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but
excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
cum / kg
Whiting / White Cement
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
day
Brick Layers / Painter
day
Mazdoor (unskilled)
Total cost for 10 sqm
136 Colour Washing, One Coat
254 Unit: 10 sqm
10 sqm
Rate for "White Washing" one coat
0.210
0.320
1.00%
2.800
0.300
0.430
1.000
BLD-CSTN-9-8
BLD-CSTN-9-9
10 sqm
1.000
kg
1.340
day
day
0.500
1.300
1.000%
712
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-9-10
S No
Description
1
2
139 Distempering, 2 Coats with Oil Bound Distemper
257
Unit: 10 sqm
A. MATERIALS :
Distemper
B. LABOUR
Painter
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
PAINTING & VARNISHING
BLD-CSTN-10
Unit
Quantity
kg
1.700
day
1.200
1.000%
Lts
Nos
Nos
Lts
Nos
Nos
0.50
0.08
0.19
1.70
0.36
0.84
kg
1.00
day
0.700
0.500%
kg
2.000
day
day
0.300
1.500
1.000%
kg
3.500
day
day
0.500
1.500
1.000%
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-10-1
PRIMARY COAT:
BLD-CSTN-10-2
Cost of Primer
Painter I st class
Pianter Iind class
Cost of washable Oil Bound Distemper
1st class painter
II class painter
Total cost
141 Painting, Priming Coat on New
270 Surface
142
BLD-CSTN-10-3 284
143
BLD-CSTN-10-4 285
Plastered
Unit: 10 sqm
A. MATERIALS :
Cement Primer
B. LABOUR
Painter
Sundries including brushes, soaps, putty etc.,
Total cost for 10 sqm
Painting Walls with Snowcem or other equal
and approved Water Proof Cement Paint over
Priming Coat, One Coat (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 5 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Total cost for 10 sqm
Painting Walls with Snowcem or other equal
and approved Water Proof Cement Paint over
Priming Coat, 2 Coats (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 3 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Total cost for 10 sqm
713
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
144 Painting to new walls with 2 coats of water proof
Unit
Quantity
kg
day
day
kg
1.00
0.21
0.49
3.50
day
day
day
0.15
0.35
1.50
0.700
day
0.700
1.000%
0.70
day
0.70
L
L
0.800
0.600
day
day
0.700
0.700
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-10-5
BLD-CSTN-10-6 268
Unit: 10 sqm
A. MATERIALS :
Wood Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
146 Painting, Priming Coat on New Iron Work
BLD-CSTN-10-7 269
Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
714
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-10-9
S No
Description
1
2
148 Varnishing to Wood Work, Two Coats
282
Unit: 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
149 Painting with Ready mixed oil paint (all colours)
Unit
Quantity
L
L
1.200
1.100
day
day
1.100
1.100
kg
1.600
day
LS
0.700
kg
2.800
day
LS
1.200
kg
1.500
day
LS
0.700
kg
2.4.
day
LS
1.200
kg
1.200
day
LS
0.700
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-10-10 256
to
i. One Coat - New Wood Work :
265
ii
iii
iv
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
One Coat - Old Wood Work & New Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - Old Wood Work & New Iron Work:
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
One Coat - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
715
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
1
vi
kg
2.100
day
LS
1.100
kg
3.400
day
LS
1.500
kg
3.900
day
LS
1.600
0.500
day
0.700
0.400
day
0.700
0.900
day
1.200
Rate
Rs.
5
Amount
Rs.
6
ii
iii
716
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
vi
vii
Description
Unit
Quantity
0.800
day
1.200
0.800
day
1.100
0.700
day
1.100
1.200
day
1.600
1.100
day
1.500
0.700
day
0.700
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
viii Plastic Emulsion paints - Three Coats for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
151 Painting with Synthetic Enamel paints - One
BLD-CSTN-10-12 i Coat - for New Wood Work, Old Wood Work &
New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Rate
Rs.
5
Amount
Rs.
6
717
Remarks
7
BLD-CSTN
Index-code
S No
1
ii
iii
iv
Description
Unit
Quantity
0.500
day
0.700
1.200
day
1.200
1.100
day
1.200
1.100
day
1.100
0.900
day
1.100
1.700
day
1.600
Rate
Rs.
5
Amount
Rs.
6
vii
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Three
Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
718
Remarks
7
BLD-CSTN
Index-code
S No
1
viii
Description
Unit
Quantity
1.600
day
1.500
kg
0.500
day
day
LS
0.800
0.800
0.650
day
day
LS
0.800
0.800
kg
L
0.228
1.630
day
LS
3.200
cum
1.000
day
day
17.700
8.800
LS
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
152 Polishing on wood work with readymade wax
BLD-CSTN-10-13
polish of approved brand and manufacture
New Work :
A. MATERIALS :
Readymade wax polish
B. LABOUR
Painter
Healper
Sundries including brushes, soap, cloth etc.,
Total cost for 10 sqm
BLD-CSTN-10-14
Rate
Rs.
5
Amount
Rs.
6
coat)
New Work :
A. MATERIALS :
Melamine polish
B. LABOUR
Painter
Healper
Sundries for Spraying Machine etc.,
Total cost for 10 sqm
154 French Spirit polishing Two or more coats on
BLD-CSTN-10-15
new works including a coat of wood filler.
A. MATERIALS :
Shellac
Spirit
B. LABOUR
Painter
Sundries such as pigment, terpentaine, sand paper, putty,
wood filler, white woolen cloth, linseed oil, cotton etc.,
BLD-CSTN-11
BLD-CSTN-11-1
WOOD
WORK,
ALUMINUM
WINDOWS, VENTILATORS Etc.,
DOORS,
719
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
156 Best Teak Wood wrought and put up over 2
BLD-CSTN-11-2
BLD-CSTN-11-3
BLD-CSTN-11-4
BLD-CSTN-11-5
Unit
Quantity
cum
1.000
day
day
17.700
8.800
LS
cum
1.000
day
17.700
day
8.800
Rate
Rs.
5
Amount
Rs.
6
Unit = 1 cum
Materials :
Teak wood large scantlings over 2 m and below 3 m
in length
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
158 Best Teak Wood wrought and put up for trusses
including straps and all iron work (Schedule
Item No 289)
Unit = 1 cum
Materials :
Teak wood large scantlings
Iron Work (average)
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
159 Fully Panelled doors - External or Internal Moulded panels (Schedule Item No 290)
A Single Shutter
i
800 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
ii
LS
cum
1.000
kg
112.000
day
26.500
day
8.800
LS
cum
0.083
sqm
1.600
LS
cum
0.088
sqm
1.800
720
Remarks
7
BLD-CSTN
Index-code
S No
1
iii
iv
Description
Unit
Quantity
cum
0.109
sqm
2.200
1100 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
900 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
cum
0.123
sqm
2.520
cum
0.094
sqm
1.890
LS
cum
0.159
sqm
3.600
Amount
Rs.
6
LS
Rate
Rs.
5
LS
cum
0.096
sqm
1.800
cum
0.104
sqm
2.000
cum
0.134
sqm
2.860
iii
721
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
Description
Unit
Quantity
cum
0.147
sqm
3.220
cum
0.068
sqm
0.720
sqm
1.600
1400 x 2300 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-6
ii
iii
Single Shutter
800 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
LS
cum
0.071
sqm
0.870
sqm
1.800
cum
0.100
sqm
1.160
sqm
2.520
LS
1300 x 2200 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters inclusive of holdfasts and all wind
Sundries
appliances (Vide relevant standard specification)
cum
0.106
sqm
1.390
sqm
2.860
cum
0.077
sqm
0.880
sqm
1.890
LS
722
Remarks
7
BLD-CSTN
Index-code
S No
1
vi
B
i
Description
Unit
Quantity
cum
0.091
sqm
0.880
sqm
2.100
cum
0.082
sqm
0.710
sqm
1.800
*Teak wood
cum
0.088
sqm
0.820
sqm
2.000
*Teak wood
cum
0.090
sqm
sqm
0.940
2.200
*Teak wood
cum
0.123
sqm
sqm
1.900
3.600
cum
sqm
sqm
0.130
1.280
3.600
1000 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
Double Shutter
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Rate
Rs.
5
Amount
Rs.
6
1000 x 2000 mm
1100 x 2000 mm
1400 x 2300 mm
1500 x 2400 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind appliances
(Vide relevant standard specification)
723
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-11-7
S No
Description
Unit
Quantity
Item 292)
Top Tower bolts (Ave : Size)
Nos
Nos
Nos
Nos
Nos
293)
Top Tower bolts (Ave : Size)
Nos
Nos
Nos
Nos
cum
0.072
sqm
0.470
sqm
1.600
1
2
161 Furniture - Iron - for External doors (Schedule
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-8
BLD-CSTN-11-9
294)
A
i
ii
iii
iv
Single Shutter
800 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1200 x 2100 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1300 x 2200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
LS
cum
0.076
sqm
0.560
sqm
1.800
LS
cum
0.106
sqm
0.760
sqm
2.520
LS
cum
0.115
sqm
0.870
sqm
2.860
LS
724
Remarks
7
BLD-CSTN
Index-code
S No
1
B
i
ii
iii
iv
Description
Unit
Quantity
cum
0.087
sqm
0.420
sqm
1.800
Rate
Rs.
5
Amount
Rs.
6
Double Shutter
900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1000 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1100 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1400 x 2300 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1500 x 2400 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
* Note : Average rate for respective size scantlings
and rough planks.
LS
cum
0.092
sqm
0.510
sqm
2.000
LS
cum
0.096
sqm
0.600
sqm
2.200
LS
cum
0.123
sqm
1.060
sqm
3.220
LS
cum
0.130
sqm
1.280
sqm
3.600
LS
725
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-11-10
S No
Description
1
2
164 Furniture - Same as for Fully Panelled Doors
Unit
Quantity
cum
0.107
sqm
2.000
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-11
ii
BLD-CSTN-11-12
296)
1000 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)
Total for each door
* Note : Average rate for respective size scantlings
and rough planks.
LS
cum
0.127
sqm
2.520
LS
1000 x 2000 mm
Country wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)
cum
sqm
0.107
2.000
LS
ii
cum
0.127
sqm
2.520
LS
cum
0.083
sqm
1.600
LS
LS
726
Remarks
7
BLD-CSTN
Index-code
S No
1
ii
Description
Unit
Quantity
cum
0.100
sqm
2.100
1000 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for size - 2
Nos Chain and slopes country make.
Total for each door
Note : * Average rate for respective size scantlings
and rough planks.
Rate
Rs.
5
Amount
Rs.
6
LS
LS
BLD-CSTN-11-15
ii
cum
0.083
sqm
1.600
LS
LS
cum
0.100
sqm
2.100
LS
LS
BLD-CSTN-11-16
cum
0.035
sqm
1.530
sqm
1.800
727
Remarks
7
BLD-CSTN
Index-code
S No
1
ii
Description
Unit
Quantity
cum
0.037
sqm
1.820
sqm
2.100
cum
0.028
sqm
0.390
sqm
0.720
cum
0.037
sqm
0.500
sqm
0.960
cum
0.041
sqm
0.700
sqm
1.200
cum
0.061
sqm
0.710
sqm
1.440
cum
0.072
sqm
0.920
sqm
1.800
cum
0.059
sqm
0.970
sqm
1.700
1000 x 2100 mm
*Teak wood
Flush Shutter 35mm thick (Vide relevant standard
specification)
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and all wind
appliances (Vide standard specification)
Total for each door
*Note : Average rate for respective size scantlings.
Rate
Rs.
5
Amount
Rs.
6
Single Shutter :
600 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)
ii
B
i
ii
iii
iv
728
Remarks
7
BLD-CSTN
Index-code
S No
1
BLD-CSTN-11-18
BLD-CSTN-11-19
BLD-CSTN-11-20
172
173
174
BLD-CSTN-11-21 175
A
i
ii
B
i
ii
Description
Unit
Quantity
each
each
each
each
Rate
Rs.
5
Amount
Rs.
6
LS
each
each
each
LS
each
each
each
cum
0.039
sqm
0.720
cum
0.043
sqm
0.840
cum
0.051
sqm
0.960
cum
0.059
sqm
1.200
cum
0.081
sqm
1.440
729
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
Description
Unit
Quantity
cum
0.056
sqm
1.080
cum
0.036
sqm
0.070
sqm
0.720
cum
0.052
sqm
0.100
sqm
1.080
cum
0.077
sqm
0.120
sqm
1.440
cum
0.094
sqm
0.150
sqm
1.800
each
each
each
each
each
each
each
each
900 x 1200 mm
**Teak wood
Labour, wrought and putup in position frame &
shutters
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-22
B
i
307)
Single Shutter
600 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances (Vide standard specification)
Total for each window
Double Shutter
900 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)
ii
730
Remarks
7
BLD-CSTN
Index-code
S No
1
i
Description
Unit
Quantity
cum
0.034
sqm
0.720
iii
iv
Amount
Rs.
6
LS
cum
0.048
sqm
0.960
LS
cum
0.052
sqm
1.080
LS
cum
0.052
sqm
1.200
Rate
Rs.
5
LS
BLD-CSTN-11-25
800 x 500 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron hold fasts where
such are necessary say in 30 cm wall.
ii
iii
cum
0.012
sqm
0.240
sqm
0.190
sqm
0.400
LS
cum
0.014
sqm
0.310
sqm
0.240
sqm
0.500
LS
cum
0.018
sqm
0.480
sqm
0.290
sqm
0.720
LS
731
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-11-26
S No
Description
1
2
181 Swing Ventilators - Glazed (Schedule Item No.
i
ii
iii
313)
800 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres brass
ring iron cleats and window card - vide relevant
standard specifications.
Total for each Ventilator
1000 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres brass
ring iron cleats and window card - vide relevant
standard specifications.
Total for each Ventilator
1200 x 600 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres brass
ring iron cleats and window card - vide relevant
standard specifications.
Total for each Ventilator
*Note : Average rate for respective size scantlings
and rough planks.
Unit
Quantity
cum
0.021
sqm
0.190
sqm
0.400
Rate
Rs.
5
Amount
Rs.
6
LS
cum
0.025
sqm
0.024
sqm
0.500
LS
cum
0.030
sqm
0.390
sqm
0.720
LS
BLD-CSTN-11-27
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminimum Partition partly glazed
day
0.947
day
1.158
day
0.105
day
0.211
day
0.632
Hrs
0.842
Hrs
1.684
Nos
0.211
1%
732
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
183 Supply and fixing of aluminimum Partition partly
BLD-CSTN-11-28
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
ALUMINIUM SECTION
PARTICLE BOARD - Prelaminated
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
as per design
as per design
as per design
B) LABOUR CHARGES
day
1.042
day
1.042
day
0.104
day
0.139
day
0.347
Hrs
0.833
Hrs
1.111
Nos
0.174
1%
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
as per design
as per design
Alum.Anodised.PC Handles
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
as per design
as per design
as per design
as per design
day
0.360
day
1.081
733
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
day
4
0.360
day
0.360
day
1.081
Hrs
2.883
Hrs
2.883
Nos
0.360
BLD-CSTN-11-30
Rate
Rs.
5
Amount
Rs.
6
1%
UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles
as per design
as per design
as per design
as per design
as per design
B) LABOUR CHARGES
day
0.347
day
1.042
day
0.347
day
0.347
day
1.042
Hrs
2.778
Hrs
2.778
Nos
0.347
1%
734
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-31
UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles
Hydraulic Floor Spring/ Door Closure
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
187 Removing white wash or colour wash by steel wire
brushing and/or scraping; sand papering and
preparing the wall surface smooth including
BLD-CSTN-11-32
necessary repairs to scratches complete
as per design
as per design
as per design
as per design
as per design
as per design
day
0.417
day
0.833
day
0.417
day
0.417
day
1.250
Hrs
3.333
Hrs
3.333
Nos
0.417
1%
0.010
0.170
735
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
189 Removing white wash or colour wash by steel wire
BLD-CSTN-11-34
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
10 sqm
day
0.080
10 sqm
BLD-CSTN-11-36
day
day
0.010
0.170
day
day
0.010
0.170
BLD-CSTN-11-38
736
Remarks
7
BLD-CSTN
Index-code
S No
1
BLD-CSTN-12
BLD-CSTN-12-1
BLD-CSTN-12-2
BLD-CSTN-12-3
Description
Unit
Quantity
day
1.220
day
2.440
day
4.880
day
4.320
day
4.090
day
day
0.500
0.500
Rate
Rs.
5
Amount
Rs.
6
737
Remarks
7
BLD-CSTN
Index-code
S No
1
197 Dismantling
Unit
Quantity
day
day
day
0.100
0.200
0.050
day
day
day
0.130
0.270
0.070
day
day
0.060
0.120
day
day
0.080
0.160
ii
3.150
day
day
day
0.090
0.250
0.250
ii
BLD-CSTN-13
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-12-4
BLD-CSTN-12-5
Description
BLD-CSTN-13-1
738
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
200 Providing and fixing aluminium step edging 'L'
BLD-CSTN-13-2
Unit
Quantity
3.150
day
day
day
0.090
0.250
0.250
day
day
1.000
0.100
1.310
day
day
day
0.100
0.400
0.400
1.310
day
day
day
0.100
0.400
0.400
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-13-3
BLD-CSTN-13-4
Cement Mortar
Labour :Mason, II Class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 3 m
Cost per m
202 Providing and fixing 25 mm bore galvanised M.S.
tube (light grade) outlet in cement mortar 1:3(1
cement: 3 fine sand) including cutting and making
good the wall
Details of cost for 10 pipes 12.5 cm long day i.e.,
1.25 metres
Materials:
Galvanised mild steel tube (light grade) 25 mm
nominal bore 10 x 12.5 cm = 1.25 metre with
wastage of 5%
Labour :For cutting and fixing in position
Assistant fitter
Mason.
Mazdoor (male).
Sundries
Add for water charges @ 1 %
Cost for 1.25 m
Cost per m
203 Providing and fixing 1.80 metre long RCC fencing
BLD-CSTN-13-5
739
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-13-6
S No
Description
Unit
Quantity
cum
0.336
kg
26.440
cum
0.336
sqm
9.880
day
day
day
0.120
0.120
0.250
10 sqm
1.000
Deduct - CM 1:3
cum
0.025
cum
30.000
Rate
Rs.
5
Amount
Rs.
6
740
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
kg
9.380
Rate
Rs.
5
Amount
Rs.
6
0.2770*
3x0.165x0.75=0.3712
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.6992 Sq.m..
For ten posts=10 x 0.6992 = 6.992 Sq.m.
Quantity
of
surface
plaster
12.50+7.60+7.60=27.70 Cm.
xr=3.1416x5=15.71Cm./43.41Cm
1.05=0.4560 Sq.m.
BLD-CSTN-13-7
area
0.434
4x0.165x0.75=0.4950
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.9882 Sq.m.
For 10
posts = 10 x 0.9882=9.88 Sq.m.
205 Supplying and fixing galvanised steel barbed wire
(IS : 278-1962 Type I) weighing 9.38 Kg per 100
metres (min.), Straining and fixing to any type of
standard, rails, straining bolts, including securing
with and provision of galvanised mild steel wire,
stapples or steel pins, etc., as directed (Posts and
struts of wood, concrete, steel, etc.) and straining
bolts shall be paid for separately).
Details of Cost per 100 metres (day line of wire)
Materials:
Galvanised steel barbed wire IS type I weighing
9.38 Kg/100 metre
BLD-CSTN-13-8
LS
day
day
day
0.150
0.150
0.300
kg
cum
19.500
0.040
day
day
0.080
0.160
741
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
Amount
Rs.
6
ANTE-TERMITE TREATMENT
BLD-CSTN-14
BLD-CSTN-14-1
Rate
Rs.
5
Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable concentrate of
20%
Lit
4.100
Liters
0.41
4.51
1%
day
day
3.0
0.22
Total Quantity
B) Add Water Charges @ 1%
C) Labour Charges
Man Mazdoor
Sprayer
D) Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity
10%
3%
1.50%
Add OH & CP
BASIC COST per 1 sqm
Note: CPWD - Rate Analysis per 9 Sqm
BLD-CSTN-15
BLD-CSTN-15-1
Vertical
Chloropyriphos
Earthwork excavation
Beldar
Horizontal
Chloropyriphos
Vertical
Beldar
Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity
Add OH & CP
CENTERING, FORM WORK etc.
208 Providing traditional centering, shuttering and
scaffolding using Cashewrina balli props and
bracings supporting wooden brackets, wooden wall
plates, wooden runners and steel plate form work
as per the approved plan and other accessories as
per the standard trade practice including hire
charges for ballies, runners, wooden members and
cost and conveyance of all other consumable
accessories, taxes etc complete for finished item of
work
(I)
Lit
cum
Nos
Lit
Nos
Nos
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Nos
2.40
742
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
3
Nos
4
1.44
BLD-CSTN-15-2
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
(II) Unsupported Roof Height up to - 4.60 M (15'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Wall Plate Brackets / beam bottom supports
Wedge Plate fixture
Runner beams of approximately 4" x 4" size
Steel Plate - form work plates B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
(III) Unsupported Roof Height up to - 7.30 M (24'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Wall Plate Brackets / beam bottom supports
Wedge Plate fixture
Runner beams of approximately 4" x 4" size
Steel Plate - form work plates B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
209 Providing rigid Steel centering, shuttering and
scaffolding using steel pipes, adjustable Jack screw
props, acro spans, couplers, tie rods, bracings
members, supporting brackets, acro span beams
and steel plate/ ply-wood form work as per the
approved shuttering designs & plan and other
accessories as per the IS Norms and stability
calculations including hire charges for jack pipes,
acro spans, runners, wooden members and cost
and conveyance of all other consumable
accessories, taxes etc complete for finished item of
work
(I)
Nos
1.44
RM
sqm
16.00
1.86
day
day
day
day
Rate
Rs.
5
Amount
Rs.
6
0.00
0.16
0.28
0.48
0.04
1%
1%
1%
Nos
Nos
4.32
1.44
Nos
RM
sqm
1.44
16.00
1.86
Nos
Nos
Nos
0.20
0.36
0.68
Nos
0.06
1%
1%
1%
Nos
Nos
Nos
RM
sqm
5.76
1.44
1.44
16.00
1.86
Nos
Nos
Nos
Nos
0.28
0.52
1.08
0.08
1%
1%
1%
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class
Pipes
for vertical props placed @ 3'0" c/c in bothways
Approximately 33'-0" x 33'-0" roof area
743
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
Kgs
62.51
day
day
day
day
0.22
0.38
0.72
0.04
1%
Rate
Rs.
5
Amount
Rs.
6
(II)
1%
1%
Kgs
112.635
day
0.32
day
0.52
day
1.28
day
0.06
1%
1%
1%
744
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Note : Cost of Centering charges with different centering & scaffolding materials for
different structures may be calculated as per the guidelines given Below
TYPE OF STRUCTURE
UNIT
COS
CENTERING AREA T OF
CENT
ERIN
A
B
RCC
STRUCTU
RE UNIT
MEASUR
EMENT
C
FOOTINGS
3.88 sqm
per 1 cum
PEDESTALS
6.17 sqm
per 1 cum
PLINTH BEAMS
9.35 sqm
per 1 cum
LINTELS
7.94 sqm
per 1 cum
CHAJJAS - SUNSHADES
1.22 sqm
per 1 sqm
COLUMNS
11.15 sqm
per 1 cum
BEAMS
9.35 sqm
per 1 cum
1.05 sqm
per 1 sqm
1.09 sqm
per 1 sqm
1.14 sqm
per 1 sqm
3.85 sqm
per 1 sqm
2.70 sqm
per 1 sqm
10.63 sqm
per 1 cum
10.78 sqm
per 1 cum
DOME SLABS
17.19 sqm
per 1 cum
HELICAL STAIRCASES
1.31 sqm
per 1 sqm
For calculating centering charges of RCC Structures, using either cashewrina balli
scaffolding or steel pipe scaffolding, the respective cost may be arrived by taking the
above
values.
Therefore,
Centering charges for any structure:C= A x B
210 Providing STAGE SCAFFOLD with staging using
BLD-CSTN-15-3
(I)
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Scaffold Boards - Bamboo scaffolds - Bamboos 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Nos
2.40
Nos
2.70
day
0.04
day
0.30
day
0.48
day
0.04
1%
745
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
4
1%
(II)
BLD-CSTN-15-4
4.32
Nos
2.70
day
0.08
day
0.38
day
0.68
day
0.06
Nos
5.76
Nos
2.70
day
0.12
day
0.54
day
1.08
day
0.08
UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Scaffold Boards - Bamboo scaffolds - Bamboos 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
Amount
Rs.
6
1%
Nos
(I)
Rate
Rs.
5
1%
1%
1%
1%
1%
1%
Nos
1.74
Nos
0.72
day
0.07
day
0.11
day
0.2
day
0.04
1%
1%
1%
Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
746
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
Nos
4
1.74
Nos
0.38
day
0.12
day
0.22
day
0.36
day
0.04
Rate
Rs.
5
Amount
Rs.
6
1%
1%
1%
BLD-CSTN-15-5
(I)
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
(II)
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class
Pipes
for vertical props placed @ 3'0" c/c in bothways
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Unsupported Roof Height up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Kgs
39.26
day
0.04
day
0.34
day
0.60
day
0.04
1%
1%
1%
Kgs
112.635
day
0.12
day
0.58
day
1.20
day
0.08
1%
1%
1%
747
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-15-6
S No
Description
1
2
213 Providing ACCESS SCAFFOLD using Steel Scaffolding
Pipe Frames made of 40 mmd ia MS Pipes and bracings
with scaffold boards including hire charges for MS Pipe
Frames scaffolds boards etc., and cost and conveyance of
all other consumable accessories, taxes etc complete for
finished item of work for ELEVATION AREA
(I)
Unit
Quantity
Kgs
19.7496
day
0.07
day
0.11
day
0.24
day
0.04
Rate
Rs.
5
Amount
Rs.
6
UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
1%
1%
1%
Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
Kgs
19.14
day
0.12
day
0.22
day
0.44
day
0.04
1%
1%
1%
Rs. A
(Rs. A - Rs. B)
C
748
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
2
(Usually B = A * 10%)
Period of Hire of Scaffolding materials, in years =
Life of Scaffolding materials, in years =
Therefore, Hire Charges of scaffolding Materials:
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
C
D
[(Rs. A - Rs. B)*C]
D
Note: While calculating the Capital Cost of the materials, deprication shall be allowed
based on the service life of the materials.
Number of uses of Scaffolding materials (C )
Wooden Materials - No of Uses - 10 Times (C)
Period of Hire of Steel Scaffolding materials, in years = 1.64 (200 days per Annum)
Life of Steel Forms & Scafholding Material - 3 Years (D)
Period of Requirement of Centering Material
Slabs : 14 + 4 = 18 days
Columns : 1.50 days
Foundations : 2 days
749
Remarks
7