Professional Documents
Culture Documents
HISTORY:
It was learnt that this generator was manufactured by G.E for COOL WATER COALGASIFICATION
PROGRAM and commissioned in 1983 and was in service only for less than two years. Afterwards it
was lying idle. In the year 2004 M/s GE Energy Services studied this unit for reapplication on Indian
50Hz system. Recommendation accepted was to operate the turbine at its original speed of
3600rpm and include reduction gear 3600/3000rpm in between turbine and generator to operate
generator at 3000rpm.
DETAILS OF GENERATOR:
GENERATOR DATA
S. no.
A
B
01
02
03
04
05
C
01
02
03
04
05
06
Data Description
Generator number
Name plate Data
No. of poles
No. of phases
Type of stator winding connection
Frequency
Total temperature at rating guaranteed not to exceed:
Rating:
MVA
Armature Amps
Armature Volts
Field Amps
Excitation Volts
Power Factor
Data
316X423
2
3
wye
60HZ
at 60HZ
67
2803
13.8kv
485 A
250V
0.9
at 50HZ
54.00
2711
11.5
473
0.9
Inspection Report:
For commissioning the unit on 50Hz system 13.8KV generator has to operate at 11.5kv. For that
matching transformers were used in P.T circuit and excitation power transformer circuit to get
specified voltages for control and protection circuits.
No changes made in C.T circuits.
Original electromagnetic relays were retrofitted with two numbers numerical relays to have 100%
hot standby.
Generator control and metering panels were also retrofitted with new panels.
Because of spares and other problems original A.V.R was replaced with new A.V.R of local make.
Initial wedge tightness report not enclosed as rewinding of complete stator winding was done.
Finally on 14th August 2008 unit was synchronized with Indian Karnataka State grid.
New A.V.R started giving problem with frequent thyristor fuse failure. Hence it was also replaced
by M/s A.B.B make.
In the year 2010 unit experienced vibrations problem and found they were because of shorts in
rotor winding. The rotor was wound with new winding.
Now the unit is in service. Maximum generation went up to 50 MW.
ANNEXURE:
Generator Preliminary Visual Inspection Report
Dates of inspection: 29th to 31st May 06
Client: m/s Satavahana Ispat Ltd., Kudathini plant
E225U04
wedges
197867
E213UR01
Item
STATOR
SLOT PORTION
Front core
s.no
A
End windings
Core
Frame
End winding supports are firm and coils ties are tight
at some locations partial discharge activity noticed
between coil sides. End winding insulation has not
shown any softness because of oil leakage. Lot of oil
leaked on turbine end. Slight oil vapour deposit found
slip ring end.
Checked the resistance values of r.t.ds.The values are 10 ohms for all and corressponds
to 25 0 c.no physical damage for those visible at present. R.t.ds provided for cooler inlet
temp. will be checked for any physical damages, when coolers are taken out for
inspection.
Mechanical erection group will be attending to the bearings, and seals. In view of oil
leakage into frame of generator the seals clearances please be checked for their
clearances limits. Insulation material for slip ring end bearing assembly and oil deflector
assemblies to be searched, if not available to be procured and the material fibre glass of
good quality. Pitting not observed on bearings babbit material.
INSTRUMENTATION
Instrumentation
ROTOR WINDING,SLIP
RINGS,JOURNALS,BEARINGSETC.
INSPECTION FINDINGS:
i
STATOR
The following abnormalities noticed are to be taken up on priority
1) Deposits at both end of core
2) Partial discharge activities in end windings
3) Peeling of top insulation layer of winding bars
1) Deposits at both end of core
Formation of deposits mostly at the core ends pointing towards bar vibrations occuring
only at the ends of the core. It is mostly due to the bars being held off the bottom of
the slot. Wear can occur with very small clearance, perhaps less than 5 mils. Clearance
less than 30mils cannot be seen directly or with a boroscope, nor measured by feeler
gauge and to be verified with the use of standard bar jack and core mounted dial
indicator.
Therefore it requires thorough inspection by generator winding specialist of same voltage
class. It is a must to ensure about bar vibrations. Except these no core heating traces
found.
2) Partial discharge activities in end windings
at different locations of end winding and take off leads of phase and neutral leads
deposits
of partial discharges noticed. Colour of these deposits can be because of the discharges
in presence of oil vapours. These spots to be further examined to ensure that the
discharges have not cut into the insulation. If they have not cut into the insulation,
cleaning is only required.
This can also be discussed with winding specialist.
3) Peeling of top insulation layer of winding bars
at many locations of end windings of both ends peeling of top layer insulation of bars
noticed. This is to be repaired and to be discussed with winding specialist during above
defects inspection.
ii
Rotor
a)Heating of rotor has to be co-ordinated with the insertion of rotor, such that the rotor will
not be outside for long time after heating activity
as informed earlier, rotor heating requires suitable D.C source (D.C welding machine),
copper clamps for connecting the leads to rotor winding slip rings, suitable d.c ammeter,
good quality winding resistance measuring unit, tent arrangement and exhaust fan to take
off moisture released etc. are to be made available.
after completion of winding heating A.C impedance test will be conducted along with other
tests.
b) In brush holder rigging unit some components of brush holders are missing hence new to
be procured. Along with them two sets of carbon brushes to be procured. Recommended
carbon brush grade is " National Carbon 634 "
c) For assembly of slip ring end bearing, oil seals insulation materials to be made ready
if not available to be procured.
d) Fixed guide vanes to be numbered and checked for any damages and their fixing
hardware materials to be kept ready.
e) As lot of leakage observed at turbine end, the seals to be checked for their clearances
limits.
iii
iv
Coolers
Coolers inspection could not be done because of space constraint to take them off.
as there are no manhole covers on generator frame to inspect back core, it will be tried
when coolers are removed.
Shaft earthing device
Shaft earthing device with the use of carbon brushes is not that effective. It may be
modified using copper flexible. For it slight modification of the unit is necessary.
Partial discharges and / or top insulation tape of bars peeling off areas over end windings
Turbine end slot ares
S09
S10
S11
S12
S - 33
S - 20
S - 37
S - 23
S - 37
S - 23
S - 38
S - 24
S - 38
S - 25
S - 39
S - 25
S - 39
S - 26
S - 26
S - 40
S - 41