Maintenance of Transformer at Pahlawan Power Sdn Bhd

Item Description Qty Unit Price


No RM
Maintenance of GTG1 Generator Step Up Ttansformer 1 LOT
Specification and Job Scope

Transformer Capacity : 110/155 MVA 11.5 KV/13.2 KV


Oil Volume 37,960 Liters
Vector group: YNd1

1 Main Tank Oil Purification (optional - Shell Diala S4 ZX-1)


To execute at least three complete cycle to achieve Dielectric
Breakdown Voltage of more than 60KV and Moisture Content
less than 10ppm.

2 General Inspection & Replacement of Rubber Bellow


To perform cleaning of transformer body c/w inspection of
rusted sections and antirust painting application at the body.
All LV chambers, radiator flanges, transformer guard and
bushing inspection.To conduct transformer guard tests by actual
simulation for triggering the guards that verified by TKPS
personnel's .
To supply gaskets / o-rings if leakage happens:
Type: Neoprene Rubberized Cork Sheet Gasket
Make: James Walker
Type: Nebar White N6/25
Sizes: Custom cut with thickness of 6.4mm, 10mm or
12.5mm (following thickness of existing gasket replaced)
To supply and replace all bolts and nuts at the HV & LV Bushing
with brass-type.
To supply and replace all rubber bellows at the HV & LV side
with 5mm THK.

3 Electrical Testing (3 days)


To perform these tests
Tan Delta Testing on Transformer Winding and Bushing
IR/PI for Transformer Winding
Turns Ratio Test
DC Winding Resistance Test

TOTAL

AGC217083 - Global E-Technic Transformer leaking rectification and filteration work


Maintenance of Transformer at Pahlawan Power Sdn Bhd

Item Description Qty Unit Price Extended Price


No RM RM

Maintenance of GTG2 Generator Step Up Transformer 1 LOT

Specification and Job Scope

Transformer Capacity : 110/155 MVA 11.5 KV/13.2 KV


Oil Volume 37,960 Liters
Vector group: YNd1

1 Main Tank Oil Purification (optional - Shell Diala S4 ZX-1)


To execute at least three complete cycle to achieve Dielectric
Breakdown Voltage of more than 60KV and Moisture Content
less than 10ppm.

2 General Inspection & Replacement of Rubber Bellow


To perform cleaning of transformer body c/w inspection of
rusted sections and antirust painting application at the body.

All LV chambers, radiator flanges, transformer guard and


bushing inspection.To conduct transformer guard tests by
actual simulation for triggering the guards that verified by
TKPS personnel's .
To supply gaskets / o-rings if leakage happens:
Type: Neoprene Rubberized Cork Sheet Gasket
Make: James Walker
Type: Nebar White N6/25
Sizes: Custom cut with thickness of 6.4mm, 10mm or
12.5mm (following thickness of existing gasket replaced)
To supply and replace all bolts and nuts at the HV & LV
Bushing with brass-type.
To supply and replace all rubber bellows at the HV & LV side
with 5mm THK.

3 Electrical Testing (3 days with GT2 Unit Aux. Tx)


To perform these tests
Tan Delta Testing on Transformer Winding and Bushing
IR/PI for Transformer Winding
Turns Ratio Test
DC Winding Resistance Test

TOTAL -

AGC217083 - Global E-Technic Transformer leaking rectification and filteration work


Maintenance of Transformer at Pahlawan Power Sdn Bhd

Item Description Qty Unit Price Extended Price


No RM RM
Maintenance of ST Generator Step Up Transformer 1 LOT
Specification and Job Scope

Transformer Capacity : 110/155 MVA 11.5 KV/13.2 KV


Oil Volume 34913 Liters
Vector group: YNd1

1 Main Tank Oil Purification (optional - Shell Diala S4 ZX-1)


To execute at least three complete cycle to achieve Dielectric
Breakdown Voltage of more than 60KV and Moisture Content
less than 10ppm.

2 General Inspection & Replacement of Rubber Bellow


To perform cleaning of transformer body c/w inspection of
rusted sections and antirust painting application at the body.

All LV chambers, radiator flanges, transformer guard and


bushing inspection.To conduct transformer guard tests by
actual simulation for triggering the guards that verified by
TKPS personnel's .
To supply gaskets / o-rings if leakage happens:
Type: Neoprene Rubberized Cork Sheet Gasket
Make: James Walker
Type: Nebar White N6/25
Sizes: Custom cut with thickness of 6.4mm, 10mm or
12.5mm (following thickness of existing gasket replaced)
To supply and replace all bolts and nuts at the HV & LV
Bushing with brass-type.
To supply and replace all rubber bellows at the HV & LV side
with 5mm THK.

3 Electrical Testing (3 days with GT1 Unit Aux. Tx)


To perform these tests
Tan Delta Testing on Transformer Winding and Bushing
IR/PI for Transformer Winding
Turns Ratio Test
DC Winding Resistance Test

TOTAL -

AGC217083 - Global E-Technic Transformer leaking rectification and filteration work


Maintenance of Transformer at Pahlawan Power Sdn Bhd

Item Description Qty Unit Price Extended Price


No RM RM
Maintenance of ST Unit Auxiliarry Transformer 1 LOT
Specification and Job Scope

Transformer Capacity : 10/12.5 MVA 11.5 KV/ 6.6 KV


Oil Volume 8000 Liters
Vector group: Dyn11

1 Main Tank Oil Purification (optional - Shell Diala S4 ZX-1)


To execute at least three complete cycle to achieve Dielectric
Breakdown Voltage of more than 60KV and Moisture Content
less than 10ppm.

2 General Inspection & Replacement of Rubber Bellow


To perform cleaning of transformer body c/w inspection of
rusted sections and antirust painting application at the body.

All LV chambers, radiator flanges, transformer guard and


bushing inspection.To conduct transformer guard tests by
actual simulation for triggering the guards that verified by
TKPS personnel's .
To supply gaskets / o-rings if leakage happens:
Type: Neoprene Rubberized Cork Sheet Gasket
Make: James Walker
Type: Nebar White N6/25
Sizes: Custom cut with thickness of 6.4mm, 10mm or
12.5mm (following thickness of existing gasket replaced)
To supply and replace all bolts and nuts at the HV & LV
Bushing with brass-type.
To supply and replace all rubber bellows at the HV & LV side
with 5mm THK.

3 Electrical Testing (3 days with ST Generator Step Up)


To perform these tests
Tan Delta Testing on Transformer Winding and Bushing
IR/PI for Transformer Winding
Turns Ratio Test
DC Winding Resistance Test

TOTAL -

AGC217083 - Global E-Technic Transformer leaking rectification and filteration work


Maintenance of Transformer at Pahlawan Power Sdn Bhd

Item Description Qty Unit Price Extended Price


No RM RM
Maintenance of GT1 Station Transformer 1 LOT
Specification and Job Scope

Transformer Capacity : 8 MVA 11.5 KV/ 6.6 KV


Oil Volume 6122.3 Liters
Vector group: Dyn11

1 Main Tank Oil Purification (optional - Shell Diala S4 ZX-1)


To execute at least three complete cycle to achieve Dielectric
Breakdown Voltage of more than 60KV and Moisture Content
less than 10ppm.

2 General Inspection & Replacement of Rubber Bellow


To perform cleaning of transformer body c/w inspection of
rusted sections and antirust painting application at the body.

All LV chambers, radiator flanges, transformer guard and


bushing inspection.To conduct transformer guard tests by
actual simulation for triggering the guards that verified by TKPS
personnel's .
To supply gaskets / o-rings if leakage happens:
Type: Neoprene Rubberized Cork Sheet Gasket
Make: James Walker
Type: Nebar White N6/25
Sizes: Custom cut with thickness of 6.4mm, 10mm or
12.5mm (following thickness of existing gasket replaced)
To supply and replace all bolts and nuts at the HV & LV
Bushing with brass-type.
To supply and replace all rubber bellows at the HV & LV side
with 5mm THK.

3 Electrical Testing (3 days with GT1 Generator Step Up Tx)


To perform these tests
Tan Delta Testing on Transformer Winding and Bushing
IR/PI for Transformer Winding
Turns Ratio Test
DC Winding Resistance Test

TOTAL -

AGC217083 - Global E-Technic Transformer leaking rectification and filteration work


Maintenance of Transformer at Pahlawan Power Sdn Bhd

Item Description Qty Unit Price Extended Price


No RM RM
Maintenance of GT2 Station Transformer 1 LOT
Specification and Job Scope

Transformer Capacity : 8 MVA 11.5 KV/ 6.6 KV


Oil Volume 6122.3 Liters
Vector group: Dyn11

1 Main Tank Oil Purification (optional - Shell Diala S4 ZX-1)


To execute at least three complete cycle to achieve Dielectric
Breakdown Voltage of more than 60KV and Moisture Content
less than 10ppm.

2 General Inspection & Replacement of Rubber Bellow


To perform cleaning of transformer body c/w inspection of
rusted sections and antirust painting application at the body.

All LV chambers, radiator flanges, transformer guard and


bushing inspection.To conduct transformer guard tests by
actual simulation for triggering the guards that verified by TKPS
personnel's .
To supply gaskets / o-rings if leakage happens:
Type: Neoprene Rubberized Cork Sheet Gasket
Make: James Walker
Type: Nebar White N6/25
Sizes: Custom cut with thickness of 6.4mm, 10mm or
12.5mm (following thickness of existing gasket replaced)
To supply and replace all bolts and nuts at the HV & LV
Bushing with brass-type.
To supply and replace all rubber bellows at the HV & LV side
with 5mm THK.

3 Electrical Testing (3 days with GT1 Generator Step Up Tx)


To perform these tests
Tan Delta Testing on Transformer Winding and Bushing
IR/PI for Transformer Winding
Turns Ratio Test
DC Winding Resistance Test

TOTAL -