Professional Documents
Culture Documents
1
CHAPTER INTRODUCTION 4
2
CHAPTER COMMISSIONING & START UP SERVICE 5
2.1 Commissioning Standard Implementation Path 6
2.2 The Home Office Phase 7
2.2.1 (Pre-) Commissioning Engineering 8
2.2.2 (Pre-) Commissioning and Start-up Manuals 11
2.3 The Site Phase 14
2.3.1 Mechanical Completition Check & Interim Handover 14
2.3.2 Pre-Commissioning Period 15
2.3.3 Commissioning & Start-Up Period 16
2.4 System Turnover Management 17
3
CHAPTER DEDICATED TOOL 18
1 2
CHAPTER Introduction CHAPTER Commissioning
& Start-up Service
ISS International is well experienced in Pre-Commis- The senior technicians and the engineers who make up The standard definitions used are as follows:
sioning and Commissioning activities and can provide our staff have been all chosen on the basis of the pro-
the in-deph experience, guidance and qualified per- fessionalism, versatility and ability to adapt themselves Pre-Commissioning Pre-Commissioning activities start when the plant, or system, achieves Mechanical Completion. Fre-
sonnel necessary to deliver a unit Safely prepared and to the different environment and industrial culture of our quently however, Pre-Commissioning activities overlap Mechanical Completion activities and for this
ready to achieve a successful Start-up. customers covering both Home-Office and Site reason the plant should be separated into easily manageable system package, each system pack-
phases providing specific services as well as the im- age will be Pre-Commissioned as a whole and isolations at the boundaries of the system package
plementation of fully integrated projects even on a will be maintained until the completion of Pre-Commissioning activities.
Turn-Key approach. Pre-Commissioning activities include: checking for design conformity, checking the status of elec-
trical, mechanical and instrument installations, running-in of equipment, flushing and cleaning ac-
tivities, drying, etc.
Commissioning Commissioning is the phase in a project when design process fluids are introduced to the process.
Note that for hydrocarbon systems the commissioning activities commence with inerting operations.
Start-up Start-up is the point in a project where process fluids and conditions are established with the intent
of making products.
System A section of the plant or facility that can be Pre-Commissioned and commissioned independently,
but in parallel, with other sections of the plant or facility under construction.
Unit Ready for This is the point in a project where all utilities are commissioned and operational and the
Commissioning unit is ready to accept the introduction of hydrocarbons.
Unit Ready for This is the point in a project where the unit is ready to establish process conditions with
Start-up the intent of making product.
ISS International Standard Pre-Commissioning, Home Office Phase During this phase the preparation of Tool for measure- (Pre-)Commissioning & Start-Up Manual
Commissioning and Start-up Methodology is organized Preparatory Works ment and reporting of Pre-Commissioning & Commis- a. Development of (Pre-)Commissioning and Start-
considering the entire project frame and having in mind (Home office Activities). sioning activities Progress, project detailed plan, Up Manuals
the following objective: TO CONDUCT THE PLANT IN Site Phase project detailed and operative deployment plan, prepa- b. Quality Manual
OPERATION. Mechanical Completion Check ration of detailed procedures, etc. take place. Quality Control Plan
(according to API 700 Sec. 3 & 4) During this phase the following activities will be carried Quality Control Forms
The entire Commissioning Service process is devel- Pre-Commissioning out, but not limited to:
oped according to the following phases: Commissioning & Start-Up
Performance Tests. (Pre-)Commissioning Engineering
a. System/Subsystem definition
The ISS International Standard implementation path Marked-up P&ID by System
is shown in the following figure: b. Detailed Pre-Commissioning / Commissioning Ex-
ecution Plan
Organization Chart
Deployment plan per activity
c. Generic Method Statement
Preparatory
Tool for Measurement and reporting of Turnover management system
Mechanical API 700 sec. 3&4 Interim Handover Certificate e. Organisation Roles And Responsibilities
f. Punch-listing method Statement
Completion Filed inspections, documentation inspection verification (P/L oustanding)
verification (outstanding Item verification)
END
Non-Energised Energised
Engineering
Design data A Checksheets B Checksheets
MC Certificates FTC Certificates
Punchlists Punchlists
checking the individual equipment requirements. Using oped which addressed licensor and Client require-
Documentation Punchlists Certificates
As-Builts
Performance Data
the detailed pre-commissioning procedures as a basis, ments. One schedule will be developed to cover the
a list of consumables will be generated to allow prepa- initial start-up phase, one to cover the test run period
Systems Commissioning Completion Dossiers
ration and reinstatement of all systems. Particular at- and one to cover normal on-going operation of all
tention will be paid to spool, dummy spool and gasket process units. Requirements will be developed for each
requirements. case indicating the stream reference, frequency re-
Acceptance
Facility Documentation Transfer of
Commissioning activities.
In details, the TMSCOM allows to:
USERS AREA PASSWORD ADMINISTRATORS AREA
The purpose of the Plant turnover Management System Manage the transaction between construction and
Provisional Test
is to provide the appropriate tool to follow the ISS In- commissioning activities
Acceptance Test
Loop Check
ternational policies, procedures and quality (QA/QC) Manage pre-commissioning activities based on con- Dossier Filling
checks, in order to administrate all the documentation struction progress Handover Management
and to control the Turnover of the facilities from ISS In- Manage punch list outstanding items
Punch List Management
tioned tool that allows the turnover engineer to follow Manage Turnover progress and certificates
Discipline Tag Main Menu TAG Mng System Plant System Mng
To see our
Partner network, www.iss-international.it at the Reference Clients section
visit our web site:
The present document is property of ISS International SpA and shall not be totally or partially, directly or indirectly, transferred,
reproduced, copied, disclosed or used, without the authorization of ISS International SpA.