You are on page 1of 12

Commissioning

& Start-up Directory

INTEGRATED SERVICE SOLUTIONS


Index

1
CHAPTER INTRODUCTION 4

2
CHAPTER COMMISSIONING & START UP SERVICE 5
2.1 Commissioning Standard Implementation Path 6
2.2 The Home Office Phase 7
2.2.1 (Pre-) Commissioning Engineering 8
2.2.2 (Pre-) Commissioning and Start-up Manuals 11
2.3 The Site Phase 14
2.3.1 Mechanical Completition Check & Interim Handover 14
2.3.2 Pre-Commissioning Period 15
2.3.3 Commissioning & Start-Up Period 16
2.4 System Turnover Management 17

3
CHAPTER DEDICATED TOOL 18
1 2
CHAPTER Introduction CHAPTER Commissioning
& Start-up Service

ISS International is well experienced in Pre-Commis- The senior technicians and the engineers who make up The standard definitions used are as follows:
sioning and Commissioning activities and can provide our staff have been all chosen on the basis of the pro-
the in-deph experience, guidance and qualified per- fessionalism, versatility and ability to adapt themselves Pre-Commissioning Pre-Commissioning activities start when the plant, or system, achieves Mechanical Completion. Fre-
sonnel necessary to deliver a unit Safely prepared and to the different environment and industrial culture of our quently however, Pre-Commissioning activities overlap Mechanical Completion activities and for this
ready to achieve a successful Start-up. customers covering both Home-Office and Site reason the plant should be separated into easily manageable system package, each system pack-
phases providing specific services as well as the im- age will be Pre-Commissioned as a whole and isolations at the boundaries of the system package
plementation of fully integrated projects even on a will be maintained until the completion of Pre-Commissioning activities.
Turn-Key approach. Pre-Commissioning activities include: checking for design conformity, checking the status of elec-
trical, mechanical and instrument installations, running-in of equipment, flushing and cleaning ac-
tivities, drying, etc.

Commissioning Commissioning is the phase in a project when design process fluids are introduced to the process.
Note that for hydrocarbon systems the commissioning activities commence with inerting operations.

Manage your business even before you turn the key


Commissioning activities normally consist of activities associated with running or operating the plant
and include operating adjustments necessary for satisfactory operation of the plant or part thereof.
Also included are Functional checks which are methods used to prove that an item of mechanical
equipment or control system functions correctly.

Start-up Start-up is the point in a project where process fluids and conditions are established with the intent
of making products.

System A section of the plant or facility that can be Pre-Commissioned and commissioned independently,
but in parallel, with other sections of the plant or facility under construction.

Unit Ready for This is the point in a project where all utilities are commissioned and operational and the
Commissioning unit is ready to accept the introduction of hydrocarbons.

Unit Ready for This is the point in a project where the unit is ready to establish process conditions with
Start-up the intent of making product.

4 Commissioning & Start-up Directory Commissioning & Start-up Directory 5


2.1 COMMISSIONING STANDARD IMPLEMENTATION PATH 2.2 THE HOME OFFICE PHASE

ISS International Standard Pre-Commissioning, Home Office Phase During this phase the preparation of Tool for measure- (Pre-)Commissioning & Start-Up Manual
Commissioning and Start-up Methodology is organized Preparatory Works ment and reporting of Pre-Commissioning & Commis- a. Development of (Pre-)Commissioning and Start-
considering the entire project frame and having in mind (Home office Activities). sioning activities Progress, project detailed plan, Up Manuals
the following objective: TO CONDUCT THE PLANT IN Site Phase project detailed and operative deployment plan, prepa- b. Quality Manual
OPERATION. Mechanical Completion Check ration of detailed procedures, etc. take place. Quality Control Plan
(according to API 700 Sec. 3 & 4) During this phase the following activities will be carried Quality Control Forms
The entire Commissioning Service process is devel- Pre-Commissioning out, but not limited to:
oped according to the following phases: Commissioning & Start-Up
Performance Tests. (Pre-)Commissioning Engineering
a. System/Subsystem definition
The ISS International Standard implementation path Marked-up P&ID by System
is shown in the following figure: b. Detailed Pre-Commissioning / Commissioning Ex-
ecution Plan
Organization Chart
Deployment plan per activity
c. Generic Method Statement
Preparatory
Tool for Measurement and reporting of Turnover management system

d. Commissioning Plan and Critical Path Network


works
(Home office Pre-Comm & Comm. Activities (CWPMS) operating manual
Progress, preparation of details (planning, etc.) & Procedures check and/or preparation

Activities to be performed by System


activities)

Mechanical API 700 sec. 3&4 Interim Handover Certificate e. Organisation Roles And Responsibilities
f. Punch-listing method Statement
Completion Filed inspections, documentation inspection verification (P/L oustanding)
verification (outstanding Item verification)

g. Commissioning input to the Design Process


P&ID Review
HazOp Reviews
Precommissioning Inspections, Punch-list issuing, utilities comm, cleaning, Ready for commissioning
flushing blowing, chemical cleaning, non operating adjustment, Certificate

h. Commissioning Spare Parts & Consumables


motor run-in, catalyst, internal inspection, ...

i. Sample and Testing Schedule System Turnover


Commissioning Cooling water start-up, spring hangers check, Ready for Start-up

j. Equipment Data Logging a. Handover: The Turnover Management System for


operating adjustment, purging, pressure test, ... Certificate

Start-up Commissioning (TMSCOM). Tool implementation


and configuration.
Oil-In Ready for performance test

Performance Conduct performance tests Provisional Acceptance Certificate


Tests

END

6 Commissioning & Start-up Directory Commissioning & Start-up Directory 7


2.2.1 (Pre-)Commissioning Engineering Hydro-test boundaries should coincide with system A vendor schedule will be developed that identifies ven- Punch-Listing Method Statement
boundaries, where possible. dor requirements for each item of equipment. Support- A system will be developed to identify (see TMSCOM
ISS International commissioning and technical person- Systems should be defined by colour coding a set of A3 ing documentation will provide information on required Para.), record and correct damaged, incomplete and
nel will produce a number of deliverables. The docu- P&IDs. System boundaries should be flagged in RED vendor activities, support required and approximate du- incorrect installation and/or fabrication. Items which are
ments will entirely fulfil the contractual requirements for and system numbers should be clearly marked at reg- ration of each major activity. inaccessible or unsafe will be incorporated into this sys-
the pre-commissioning, commissioning, start-up and ular intervals on the respective line-work and equip- tem. The system will be able to allow categorisation of
initial operation of the complex as per customer docu- ment. Generic Method Statements punch-list items as follows:
ments. System summary sheets should be prepared which list Generic method statements is developed for each ac-
Main activities of these phase can be summarized as the system content by line and equipment numbers. tivity type (Cleaning, Leak Test, Inerting, etc.). Each Category A Items that must be cleared prior to
follows: statement will form the basis for the development of start of Pre-commissioning
Detailed Pre-Commissioning / Commissioning Ex- safe and efficient detailed procedures. The method Category B Items that can be cleared during
System/Subsystem Definition ecution Plan statements will contain information on the methodol- pre-commissioning
To enable a smooth transition from construction to com- A plan is developed that identifies all of the major pre- ogy, acceptance criteria and HSE implications. Category C Commissioning Items
missioning it is required to complete construction work commissioning activities by system. The plan will be de-
in small packages (known as systems). This enables veloped in reverse and will clearly identify system Commissioning Plan and Critical Path Network The system will be able to track outstanding items by
Pre-Commissioning work to progress from an earlier ready for pre-commissioning milestones. A network is developed those indexes and identifies all system, category and discipline.
point in the schedule, thus reducing the final pre-com- Commencement of system turnover from construction start up activities.
missioning peak workload substantially. However, sys- to commissioning should ideally commence at ap- Parallel and consecutive activities will be identified. Commissioning input to the Design Process
temised turnover is more complex to co-ordinate and proximately 70% erection completion. From this point Each activity will have an expected duration and will log- Input of commissioning experience to the design
manage due to the: handover of systems should be made on a regular ically link into the next related activity. process will ensure that:
increase in boundaries between the construction basis. Safety is impaired when there is a period of low Each activity will have a summary sheet to identify in Commissioning and operating safety is addressed
and commissioning groups. activity followed by a period of high activity to achieve checklist format the necessary actions to be under- in the design
increase in parallel activities during the final stages target-pre-commissioning progress. taken to achieve the completion of the activity. All phases of the initial start-up (Including one-off
of construction. A method of pre-commissioning progress monitoring A strategy will be developed to achieve the following re- special procedures) are adequately covered in the
The size and content of a system changes for each will be developed to allow progress to be monitored by: quirements within the agreed contractual milestones. design specifically including definition of systems
project, however it is essential to take the following Overall pre-commissioning completion for the com- and system turnover sequence
points into consideration when defining system size plex Organisation Roles And Responsibilities Consideration has been given to the pre-commis-
and content. Pre-commissioning completion by Process Unit The Commissioning Organisation will consist of an in- sioning of the process units
Units separated into a large number of systems Pre-commissioning completion by system tegrated Company, PMC and EPC team. The organi- To achieve this commissioning group representa-
have high manpower expenditure for the pre-com- Discipline completion by system sation will change as commissioning progresses from tives will attend and provide input at P&ID reviews,
missioning phase. Vendor Schedule. design, through Pre-Commissioning and start-up ac- HAZOP Reviews and Model Reviews: They will also
Units separated into a low number of systems have tivities. This evolution will be managed through regular review cause and effect diagrams and spare parts
an uneven workload pattern throughout the pre- reviews of the relevance of the commissioning organi- orders.
commissioning phase. sation structure to that stage of progress.

8 Commissioning & Start-up Directory Commissioning & Start-up Directory 9


2.2.2 (Pre-)Commissioning The main list of the procedures to be carried out is:
and Start-up Manuals Mechanical Preparation
Chemical Cleaning Instructions
2.2.2.1 Pre-commissioning Physical Cleaning Instructions
and Commissioning Manuals Mechanical Restoration
Pre-commissioning and Commissioning manuals will Machinery Run in
be supplied as a collection of pre-commissioning pro- Tightness test
cedures; these procedures are operating instructions Electrical testing/functional tests/energizing
for the activities to be carried out during the performing Instruments calibration and functional test
of pre-commissioning and commissioning activities. Loading of chemicals
Loading of catalyst
Heaters drying
Chemicals boil out of steam generation facilities
Verification of Mechanical Completion

Non-Energised Energised

Working Commission State Commission


Acceptance Acceptance

Pre Preparation Start-Up &


Construction Commissioning Performance Operations
Commissioning for Start-Up
Testing

Engineering
Design data A Checksheets B Checksheets
MC Certificates FTC Certificates
Punchlists Punchlists

Commissioning Spare Parts & Consumables Sample and Testing Schedule


A commissioning Spare Part list will be developed by Stream sample and testing schedules will be devel-
Commissioning Comm. Reports
Preparation & & Certificates
Engineering Construction Handover Package Comm. Notices

checking the individual equipment requirements. Using oped which addressed licensor and Client require-
Documentation Punchlists Certificates
As-Builts
Performance Data

the detailed pre-commissioning procedures as a basis, ments. One schedule will be developed to cover the
a list of consumables will be generated to allow prepa- initial start-up phase, one to cover the test run period
Systems Commissioning Completion Dossiers

ration and reinstatement of all systems. Particular at- and one to cover normal on-going operation of all
tention will be paid to spool, dummy spool and gasket process units. Requirements will be developed for each
requirements. case indicating the stream reference, frequency re-
Acceptance
Facility Documentation Transfer of

quirement and test requirement.


title & docs.

10 Commissioning & Start-up Directory Commissioning & Start-up Directory 11


2.2.2.2 The Start-Up Procedures 5. STARTUP PROCEDURE 2.2.2.3 Safety Manual/Quality Manual 6. PERMIT TO WORK PROCEDURE
Start-up Procedures will be prepared; ISS Interna- (for each configuration) A recommended general index for plant safety manu- 6.1 Lockout and Tagging
tional can develop also, for each Process Unit, a de- als is shown below. 6.2 Working Inside Energized Buildings
tailed Operating Manual. 6. NORMAL OPERATION The index consist of section titles (one digit numbering) 6.3 Vessels/Confined Space Entry
A general index for plant operating manual is shown and paragraph titles (two digits numbering).
below. 7. NORMAL SHUTDOWN PROCEDURE Sub paragraph titles exceeding two digits do not ap- 7. PROJECT SAFETY FORMS
pear in the general index. A detailed section index list- 7.1 Permits to Work
Operating Manual General Index 8. EMERGENCY SHUTDOWN PROCEDURE ing all subparagraphs titles is given before each section 7.2 Lockout/Tagging
1. INTRODUCTION of the manual. 7.3 General
1.1 General 9. ANALYTICAL REQUIREMENTS
1. INTRODUCTION 8. SAFETY CONCEPTS
2. BASIS OF DESIGN 10. ATTACHMENTS 1.1 General 8.1 General
2.1 Duty of plant 8.2 Codes and Standards
2.2 Environmental conditions 2. PRE-COMMISSIONING AND COMMISSIONING 8.3 Climatic Condition
2.3 Feedstock and product specifications Note: EMERGENCY PROCEDURES 8.4 Hazardous Area Classification
2.4 Battery limit conditions Start-up and shut-down procedure will include detailed 2.1 Emergency Contact Numbers 8.5 Fire Protection
2.5 Specifications and consumptions of utilities, equipment procedure. Systems will be divided into 8.6 Personal Protection
chemicals and catalysts main equipment, such as turbines, special motors, 3. GENERAL SITE HAZARD 8.7 Fire and Safety Point Shelters
etc., and common equipment. For each Main Equip- 3.1 Pressure Testing and Air Freeing of Process 8.8 Fire & Gas Detection
3. PROCESS DESCRIPTION ment will be developed a specific TAG procedure Plant on Site 8.9 Fire Proofing
3.1 Process theory while for the common equipment, such a centrifugal 3.2 Safety in Plant Commissioning
3.2 Description of flow pumps, exchangers, etc, will be developed a typical 3.3 General Fire Protection and Prevention 9. GENERAL INFORMATION
3.3 Process variables equipment configuration procedure non referred to a 9.1 Fire Water Network - Overview
specific TAG. 4. PROTECTIVE CLOTHING AND EQUIPMENT 9.2 Deluge System - Overview
4. PREPARATION FOR INITIAL STARTUP 4.1 Respiratory Protective Equipment 9.3 Inert Gas System Overview
4.1 General 4.2 Compressed Air Breathing Apparatus 9.4 Fire Equipment Overview
4.2 Plant inspection 4.3 Escape Filter
4.3 Cleaning of piping and equipment 10. MATERIAL SAFETY DATA SHEETS
4.4 Specific pre-startup operations 5. PRE-COMMISSIONING AND COMMISSIONING
SAFETY TRAINING
5.1 Safety Training Concept
5.2 Training Modules Common to Pre-Commis-
sioning and Commissioning Activities
5.3 Safety Training Modules Content

12 Commissioning & Start-up Directory Commissioning & Start-up Directory 13


2.3 THE SITE PHASE 2.3.1 Mechanical Completion Check & Vessel Internals - This would include going through Commissioning Subcontractor Team would review the
Interim Handover each tower and vessel to check the installation of trays, test program and the methods used to ensure satis-
During this phase an integrated organisation performs baffles, demisters, spargers, etc., and verifying that the factory tightnes.
all of the activities addressed in Home Office phase. Immediately prior to the hydrotest of each system, a dimensions of all weirs, downcomers, distributors, ther-
The activities will be monitored and witnessed as nec- Punch-List will be performed by an integrated Punch- mowells, etc., are within specification and are properly 2.3.2 Pre-Commissioning Period
essary by relevant parties. All activities and reporting List team consisting of construction, and EPC Com- oriented, as well assuring the internal cleanliness of
should be system based and fulfil the requirements of missioning Engineers (from relevant disciplines). each vessel prior to final closure. The site phase of the project will commence at approx-
the respective acceptance criteria. When all A type items have been cleared and a small Non-operating Adjustments - All non-operating ad- imately 60% construction completion and activities will
The site phase can further be separated into the main but manageable amount of B type items are left, a justments, packing of pumps and valves and cold be mainly centred on:
periods: handover can be progressed from the construction to alignment of equipment performed by the construction Progression of all of the procedures developed dur-
the commissioning group. Since mechanical comple- subcontractors should be spot-checked, witnessed or ing the Home office phase of the project
a. Mechanical Completion Verification & Interim Han- tion has been achieved with agreed exception items, it periodically inspected to ensure proper records are Co-ordinating system turnover and completion
dover is classed as an interim handover to permit construc- being kept and recorded for turn over. Monitoring and reporting progress
tion completion and Pre-Commissioning activities si- Piping - Check lists would be prepared on each hydro- Co-ordinating resources, including sub-contract
b. The Pre-Commissioning Period multaneously. Control and responsibility of work on the static test system before the system is released for hy- and vendor support
System turnover system rest with the commissioning group. Any con- drostatic testing. Completion of this punch lists by the Liaising with licensors.
Plant cleaning struction work will require written permission from the construction contractor would be required before the Main activities developed during Pre-Commissioning
Punch-Listing Lead-commissioning Engineer of the particular test system is released for testing. Post-hydro punch phase are:
Leak testing Process Unit. Permission will be granted on a job by job lists would be prepared and followed through on to en-
Inerting basis. sure that the systems were fully completed and ready Punch-Listing
. This would involve a line-by-line detailed check of the for pre-commissioning. Punch-Listing will be undertaken on a systems basis. An
Pre-Commissioning complete. actual physical installation against the latest P&I dia- Electrical Installation - Each electrical circuit and motor integrated team will be formed to participate in Punch-
grams issue, job specifications, piping hanger and sup- installation and their electrical polarity check and insu- Listing. An initial Punch-List will be undertaken immedi-
c. The Commissioning & Start-Up Period port drawings, vendor drawing, etc., for erection of the lation resistance measurement would be demonstrated ately prior to system handover for Pre-Commissioning
Ready for Commissioning unit in accordance with all drawings and applicable by electrical subcontractor to the Commissioning Sub- purpose. This will probably occur at around the hydrotest
Commissioning critical path specification. The systems would also be checked from contractor Team. time. Punch-List items generated at this stage will be in-
Start-up procedure an operating viewpoint for proper location and orienta- Instrument Installation - Review of instrument installa- corporated into the Project master Punch-List system.
Licensor/Vendor support tion of valves, vents, drains, steam tracing and traps, tion of correctness according to the instrument draw- A final Punch-List will be undertaken by system imme-
Conduct and supervise all activities during the Intro- sample connections, etc. Punch lists of deviations, in- ings and specification. The Commissioning diately prior to the commencement of commissioning
duction of Feedstock to the Units stallation errors, missing items, etc., shall be prepared Subcontractor Team would witness and/or approve all activities. This will be a less stringent Punch-List and
Stabilize the Unit and given to the appropriate construction department instrument calibration and check out procedures or aimed at checking the system over before introducing
Conduct Performance Test Run. for correction or completion. Also included in this in- work performed by instrument subcontractor. hydrocarbons. Utilisation of the Pre-Commissioning
spection and check-out would be: System Pressure Testing - Although the construction check sheets will assist in completing a full range of re-
contractor is responsible for the actual pressure testing quired checks. Punch-Listing progress will be recorded
of each system prior to mechanical completion, the on an A3 set of P&IDs.

14 Commissioning & Start-up Directory Commissioning & Start-up Directory 15


System Cleaning 2.3.3 Commissioning & Start-Up Period c. Stabilize the Unit d. Conduct Performance Test Run
This would include directing the cleaning of systems ei- The Commissioning Team will provide to work with The Commissioning Team will pompon the procedures
ther by flushing, blowing or chemical cleaning by issu- Once the unit is precommissioned, the Commissioning process licensors (if required) on how to bring the units guarantee and documentation and witnesses the in-
ing directives for the necessary temporary connections, Team will conduct the following main activities: on stream and up to design rate. Control variables and strument calibration. During the execution of Perform-
utilities and proper line up of the system to be cleaned. Purging flow rates will be specified to stabilize the unit at design ance Test the Initial Operation Team will conduct the
When the services of a chemical cleaning subcontrac- Leak Test / Tightness Test rate in preparation for the acceptance test and during plant according to the procedure already agreed be-
tor are required, the Commissioning Team will monitor Spring Hanger Check the performance test. tween the ISS International and the Client.
his performance to ensure a satisfactory cleaning job.
Before each system is closed for operating, the lines to start with initial Start-up operations assuring that
and equipment would be inspected for cleanliness. every activity is accomplished smoothly and safely.
2.4 SYSTEM TURNOVER MANAGEMENT
Cleaning progress will be recorded on an A3 set of The Commissioning Subcontractor Team would take
P&IDs. System Handling Pre-Commissioning Complete
care in troubleshooting any operating or process prob-
Construction will progress from a bulk-area comple- When the Pre-Commissioning work on each utility sys-
lems, should they arise, and would investigate any op-
Equipment Run-In tion basis to a system basis approximately 60% tem is complete it can then be commissioned provid-
erating deviations as they occur. Team will:
This would include planning and co-ordinating Vendor through the erection programme. It will be essential to ing it is safe to do so. For non-utility systems the point
a. Develop and Review Specific Operating Instruction
representatives for the running in of the equipment and control and co-ordinate the temporary and permanent at which the process Unit is considered to be ready for
The procedures and practices outlined in each units op-
obtaining the necessary utilities to accomplish the run- transfer of systems from one group to another to Start-up is when all non-hydrocarbon systems have
erating manual will be followed. As these manuals can-
in for equipment such as blowers, pumps, compressor, progress construction completion, Pre-Commissioning been pre-commissioned. At this stage the Unit is pre-
not cover every conceivable operating situation, it will be
motors, turbines, and other machinery or mechanical and commissioning work. A Systems Co-ordinator will sented as Ready for Commissioning This triggers
necessary to develop specific operating instructions to
equipment without process fluids before start-up. provide the necessary link between construction and several safety activities as follows:
cover critical areas of operating as they arise. Any addi-
commissioning. The co-ordinator will be responsible for A final Punch-List to determine if the unit is ready to
tional operating procedures and practices will be given
Vessel Loading developing system completion strategies on a daily accept hydrocarbons
either in writing, if time permits, or verbally, if immediate
This phase would ensure that all catalysts, packing, basis to ensure a smooth handover process. A pre-start up safety review
action is required, to operating supervisors. An operat-
resins and desiccant loading is performed in a proper Each system will have a turnover package of commis- The introduction of a full permit to work and safety
ing logbook will be kept in order to record the instruc-
manner and accurate records and samples of each sioning dossier associated with it. A co-ordination pro- system.
tions and relevant changes in the operating conditions.
material loaded are retained. cedure will be utilised for the offering or receiving of
b. Conduct and supervise all activities during the
When all the activities foreseen in the Pre-Commis- systems. At the schedule date for system turnover, the Commissioning Complete
Introduction of Feedstock to the Units
sioning phase (the Process Units will be ready to re- construction group will compile diagrams, equipment When all commissioning for a process unit is com-
Licensors process and operation specialists will be
ceive hydrocarbons, most of the utility systems will be list, instrument lists, exception lists, inspection reports pleted the unit is declared Ready to Start-up. At this
present for providing advice during the critical first start-
live to the respective units and all of the hydrocarbon and other QA/QC documentation for that system. point normal conditions are established to produce the
up from a technical point of view and will help trou-
lines will be positively isolated at the unit battery limits) The routing of each system will be from the construction designed products.
bleshoot any problems that arise or investigate any
have been performed successfully a Ready for Com- group to the commissioning group. The commission-
deviations that occur. The Commissioning team will
missioning Certificate will be issued and so Commis- ing group will have an internal handover mechanism to
monitor the plant operations and make any operating
sioning activities can start. recognise the importance of introducing hydrocarbons
changes for stable, efficient operation.
to a process unit for the first time.

16 Commissioning & Start-up Directory Commissioning & Start-up Directory 17


3
CHAPTER Dedicated Tool Manage mechanical completion progress, certifi- Manage ready for commissioning turnover progress,
cates and activities certificates and activities
Manage reinstatement progress, certificates and ac- Manage performance test turnover progress, certifi-
tivities cates and activities
Manage ready for pre-commissioning turnover Manage provisional acceptance turnover progress,
progress, certificates and activities certificates and activities.
In order to control the commissioning activities that construction, Pre-Commissioning and commissioning
should be integrated with the construction activities, activities from the plants area definition up to the final System Flow Chart
ISS International has been developed an In-House hand-over of the plant reducing time and costs related
software: TMSCOM (Turnover Management System to this kind of activities given a time by time progress.
for Commissioning). The TMSCOM is a modular and tailored tool that
allow more then 10 users to access together into the
SYSTEM START-UP

system for on-line up-date and view using a normal


TCP/IP network.
It shall be the direct link between Construction and
PASSWORD

Commissioning activities.
In details, the TMSCOM allows to:
USERS AREA PASSWORD ADMINISTRATORS AREA

Manage QA/QC certificates


Manage Construction piping activities
Manage Construction electrical activities Construction Commissioning

Manage Construction instrument activities


Manage Construction machinery activities
Manage Construction punch lists
Piping Electrical Instrument Machinery Mechanical Completion

Have Construction progress per area


Flushing

Welding Type 1 Preinst. Type 1

Have Construction overview progress


Tighteness Test

Piping Type 2 Installat. Type 2

Have day by day reports


Performance Test
Reports & Progress
Hydrotest Type 3 Operation Type 3

The purpose of the Plant turnover Management System Manage the transaction between construction and
Provisional Test

Reinstat. Type 4 Type 4

is to provide the appropriate tool to follow the ISS In- commissioning activities
Acceptance Test

Loop Check

ternational policies, procedures and quality (QA/QC) Manage pre-commissioning activities based on con- Dossier Filling

checks, in order to administrate all the documentation struction progress Handover Management

and to control the Turnover of the facilities from ISS In- Manage punch list outstanding items
Punch List Management

ternational to its Client / the Owner. Manage pre-commissioning and commissioning


ISS International has developed the above men- punch list
Outstanding Item
management

tioned tool that allows the turnover engineer to follow Manage Turnover progress and certificates

18 Commissioning & Start-up Directory Commissioning & Start-up Directory 19


ISS International/Main/Final Clients

System Details Pictures

Main Password Main Menu Punch List

Discipline Tag Main Menu TAG Mng System Plant System Mng

To see our
Partner network, www.iss-international.it at the Reference Clients section
visit our web site:

20 Commissioning & Start-up Directory


WE GLOBALIZE
JUST FOR YOUR BUSINESS

ISS International SpA ISS International SpA - Training Center


Headquarters Via Magna Grecia, 117 - 00183 Rome, Italy
Via Magna Grecia, 117 - 00183 Rome, Italy
Phone: +39 06 4522821 ISS International is certified:
Fax: +39 06 45200351 ISO 9001 EA35
www.iss-international.it ISO 9001 EA37
ISO 14001
OHSAS 18001

The present document is property of ISS International SpA and shall not be totally or partially, directly or indirectly, transferred,
reproduced, copied, disclosed or used, without the authorization of ISS International SpA.

You might also like