TAKEDOWN

Kraft Pulping Building Modifications 15


15 Takedown.xls

ENGINEERING with the SPREADSHEET


Copyright 2006 American Society of Civil Engineers
A B C D E F G H I J K L M
KRAFT PULPING 24 May 84
This is a sample from an actual job.
Loads must be tallied and factored for column and foundation design.

Column A2 Loads Take Down


New Existing
A2 DL LL Piping Piping Sum
Roof 6.45 0 0 6.45
2 wall 2
8.45
Conveyor flr 21.5 floor 2.6 9.4 33.5
2 21.5 conveyor 23.5
8.6 8.4 17 82.45
Operating flr 21.5 6.6 28.1
2 wall 2
112.55
Mezzanine 6.5 36.4 42.9
31 at ES 31
9.6 9.6 196.05
Ground floor

Figure 15-1 Structure Elevation 92.95 30.1 11 62 196.05 196.05