PERT ANALYSIS CALCULATOR

USER SUPPLIED ESTIMATES


OPTIMISTIC TYPICAL PESSIMISTIC
Critical Path Tasks
MARK UTILITIES 1 3 5
DIG HOLES 2 4 7
PLANT TREES 1 3 6
PLANT FLOWERS 1 3 5
INSTALL EDGING 1 2 4

SUM

Enter Desired Completion Time >>> 15 Probability of Completion >>>>>

(Sample project - change task names & number of tasks as necessary - be sure to adjust formula
SIS CALCULATOR
PERT
EXPECTED Std. Deviation Variance
DURATION
3.00 0.667 0.444
4.17 0.833 0.694
3.17 0.833 0.694
3.00 0.667 0.444
2.17 0.500 0.250

15.50 2.528

robability of Completion >>>>> 37.66%

necessary - be sure to adjust formulae to reflect the number of tasks)