Professional Documents
Culture Documents
Successful Instrument and Control System Design PDF
Successful Instrument and Control System Design PDF
8th-Jul-2011
Agenda
Chapter 15 Panel Arrangement
Chapter 16 Procurement
Chapter 17 Quality Control
The Integrated Design Check
Chapter 18 Phase Three
Construction Support
1
2011/6/26
2
2011/6/26
Set up a scale
Metric units or Imperial units
Design the panel
How many terminals are needs?
What kinds of terminals should be used?
Most specifications require 50% spare capacity on a
new installation.
Explosion proof and enclosure protection.
For each item, place at least one bubble and leader. And
generate a bill of materials on the left side of graphic.
3
2011/6/26
Summary
4
2011/6/26
Chapter 16 Procurement
A design package is built from the conceptual
to the actual and procurement is about as
actual as it gets.
A frequent lament from the construction
partner is How can I build something if I
dont have the parts
Primarily two types of material are specified
by the I&C design team:
Electrical material
Mechanical material
Bulk Materials
Electrical material
Including cable, conduit, enclosure, and termination
hardware.
Mechanical material
Including pneumatic tubing, flanges gaskets, and
mounting brackets.
These types of materials are called bulk materials.
Instruments, items that require long lead time for
manufacture, or other equipment items that require
individual specifications do not fall into the bulk
materials category.
5
2011/6/26
6
2011/6/26
Material Classification
Cost-effective
Most vendors allow quantity discounts. The amounts
of these discounts very as the quantity rises, so it is
desirable to make large orders.
Wastage and contingencies
We must always allow for wastage as the excess ends
will be clipped and disposed. We usually allow for at
least 20% wastage, plus about another 5-10% for
contingencies.
Takeoff quantity * 1.25 = Procured quantity
7
2011/6/26
Summary
8
2011/6/26
Checkpoints
9
2011/6/26
10
2011/6/26
11
2011/6/26
summary
12
2011/6/26
Construction Support
There are two kinds of construction support:
on-site and off-site. It is a good idea to
determine ahead of time the periods that are
critical for on-site support and have people
available continuously through those periods.
Otherwise, having someone on call off-site is
usually acceptable.
The construction phase breaks down into
several periods, each with a different set of
needs in terms of the design team.
13
2011/6/26
Kickoff Meeting:
Each construction activity should begin with a kickoff
meeting. At this meeting, the phase-three lead for
the design team should present the package. The
presentation should cover, at a minimum, the
following topics:
1. Bill of material
2. Design overview
3. Off-site support infrastructure
4. On-site support plan
14
2011/6/26
15
2011/6/26
16