You are on page 1of 29

STAGE 1 DESIGN PACKAGE.

CLIENT: EMPACT.
DATE: 2/04/2017

TABLE OF CONTENTS.
1.0 INTRODUCTION. 1-2

1.1 The Project. 1


1.2 This Document. 1
1.3 Deadlines. 1
1.4 Project Requirements. 1
1.5 Project Goal. 1
1.6 Innovators Co. 1

2.0 DRAWINGS.

2.1 Programs. 3

3.0 SPECIFICATIONS. 4-7

3.1 Materials of Constructions. 4-5


3.2 Suppliers. 5
3.3 Required Tools. 5
3.4 Methodology. 6-7

4.0 TENDER EVALUATION CRITERIA. 8-11

4.1 Introduction. 8
4.2 General Knowledge. 8-9
4.3 Safety Awareness. 9
4.4 Experience. 9-10
4.5 Understanding the design. 10
4.6 Time Management. 10-11
4.7 Communications. 11

5.0 RISK MANAGEMENT PLAN. 12-17

5.1 Introduction. 12
5.2 Key Terms. 12
5.3 Design stage safety evaluation. 13-14
5.4 Construction Stage safety evaluation. 15
5.5 Testing Stage safety evaluation 16-17
5.6 Risk Matrix. 17

6.0 GANTT CHART. 18-19


LIST OF APPENDICES.
Appendix 1- 2D Drawings
Appendix 2- 3D Models.
1.0 INTRODUCTION

1.1 THE PROJECT.

We are Innovators Co. which was hired by EMPACT. Our mission is to design
a prototype Mars Lander for an upcoming bid to contribute to an international
space exploration consortium. This assignment has four stages which are as
follows:

Stage 1: Design
Stage 2: Tendering
Stage 3: Construction
Stage 4: Testing

1.2 THIS DOCUMENT.

This document mainly includes the Stage 1 component of the process which
includes:

Drawings.
Specifications.
Tender Evaluation Criteria.
Risk Management Plan.
The Gantt Chart.

1.3 DEADLINES.

This project needs to be progressively completed over a due date. The results
of this project will rely on the designers and contractors following these
deadlines.

Design Package Due 2 nd April 2017


Contractors Tender Application Due 21st April 2017
Designers Tender Evaluation Due 5th May 2017
Testing Week 11

1.4 PROJECT REQUIREMENTS.

For our Mar rover to be successful it will have to,


Travel in a self-guided straight line for 2 metres down a slope set which
will be not less than 30 degrees.
Land and stay on its wheels after a vertical drop of 1 metre.
Carry a weight of 600ml water bottle which will be loaded onto the top.
The condition of the weight should be easy to assess (i.e. visual
inspection from ~1m distance)
Page 1 of 29
1.5 PROJECT GOAL.

The goal of this project is to mainly construct a Mars Lander which will pass the
test of rolling down a slope between 30-45 degrees for 2 metres and falling from
a height of 1 metre through vertical axes without any significant damage. Our
desire is to provide our client EMPACT the best product as possible.

1.6 INNOVATORS CO.

We are a small university based company that which is asked to design and
construct a Mars Lander/rover. Our team is as follows:
Arslan Muhammad Contractor
Weiyi Li Contractor
Vu Mai Linh Hoang Contractor
Shanraj Rai Designer
Ivan Dragovic Designer
Md Ishraque Anjum Designer

Page 2 of 29
2.0 DRAWINGS.

2.1 PROGRAMS.

Constant reference to these diagrams is required for successfully constructing the


product. We recommend of printing out all the necessary diagrams while constructing
a specific part. The 2D diagrams include every dimension required for the Mars Lander
to build for clear understanding of the product.

Page 3 of 29
3.0 Specifications.

3.1 Materials of Constructions.

The Table below shows dimensions and cost of the materials use in building
prototype Mars rover.

Materials Dimensions(m Quantity Unit Total


ms) Price(AUD). Price(AUD).
(L*H*W-where
applicable)
PROTOTYPE 320 x 160 x 150 1 N/A N/A
MARS (not including
LANDER wheels and axles
ROVER.

CARDBOARD (Pi*45^2 *36) + 1 6.41 6.41


(>3mm (160*320*2) +
thickness) (150*320) +
(160*150*2)
CARDBOARD ~25 WIDTH 6 INCLUDED INCLUDED
WHEELS. 90 DIAMETER. IN THE IN THE
CARDBOA CARDBOA
RD. RD.
BALSA WOOD 30 x 70 x 150 2 0.92 1.84
BOUNDARY
FRONT AND
BACK WALLS.
BALSA WOOD 90 x 70 x 150 2 2.76 5.52
PILLAR (i).

BALSA WOOD 35 x 70 x 150 2 1.07 2.14


PILLAR (ii).

BALSA WOOD 320 x 70 x 40 1 2.61 5.22


BOUNDARY
SIDE WALLS

SUPERGLUE n/a 2 0.60 1.2

Elastic Band n/a 4 0.10 0.4


(> 5mm Width)

Page 4 of 29
3.2 Suppliers.

All of the aforementioned materials are available, and can be purchased in any
Bunnings Warehouse store across Perth.

3.3 Required Tools.

The tools that are required for the construction of the prototype Mars rover are
as follows:

3D printer.

8 mm Drill Bit.

Drilling Machine

Screw Driver

Band saw

Box cutter knife.

Hammer.

Scissors.

Pencil

Compass

3.4 Methodology.

Steps:
Page 5 of 29
Step 1: Collect all the required materials as outlined in the materials list.

Each wheel will consist of 6 thinner circular sections that will be glued and stacked
together on top of each other to make up one whole wheel, and taped along the
circumference of the wheel, or wheel sections.

Step 2: Use the pencil, and the compass to mark out a circle of 45 mm radius on the
cardboard sheet, that will then be cut out with an appropriate blade. This will be one
of the six sections that make up each wheel.
Repeat this step 35 times to create the 36 circular sections that will be required for the
wheels (6 per each wheel).

Step 3: To assemble each wheel, use the superglue to connect 6 of the circular
sections on top of each other
Repeat this step 5 times to create the 6 wheels required for the rover.

Step 4: The flooring of the rovers chassis will be a single rectangular cardboard sheet
with dimensions of 320mm by 150mm, as illustrated in Figure ------. Use the pencil to
mark out this rectangle shape on the sheet of cardboard provided, according to the
dimensions described, and cut it out with the appropriate blade.

Step 5: Use the same process to carve out the rectangular side pieces of the
cardboard, which will be double-layered. Mark out the 4 rectangular pieces of
cardboard on the sheet (320mm by 160mm), and cut them out.
Then 2 of the cardboard pieces should be glued on top of each other to form one of
the double layered sides for the chassis. Repeat this for the other side of the chassis
with the other two pieces of cardboard that was also carved out.

Step 6: Draw another 2 identical rectangular sections on the initial cardboard sheet to
carve out (70mm height, 150 mm width). These will be the front and back sections of
the car.

Step 7: Use the provided 3-d printer for the construction of the plastic axles. Input the
dimensions of the axles as shown in the diagram, and 3-d print the 3 identical axles.

Step 8: Use a band saw to craft the 2 identical central columns/pillars that will fill the
inner chassis of the car, from the balsa wood, according to the dimensions provided.
Then, with the band saw, craft the front and back support wooden columns, as well as
the front and back upper columns, as illustrated in the diagrams, and dimensions.

Step 9: Use the box cutter to carve out the foam platform (dimensions 320 x 150 x 20
mm) from the foam material. On the rover, this will be connected above the wooden
support columns, and it is where the bottle will rest.

The previous steps guide through the creation of just the individual parts of the
rover. Once these steps have been completed, the rover itself is to be
assembled from these individual parts, as outlined in the following steps.

Step 10: Equip the drill with an 8mm drill bit, and use it to drill 3 holes in each of the
two side walls, so that the axle can later pass through these holes. The two chassis
Page 6 of 29
side walls can be superimposed or placed symmetrically on top of each other while
drilling, so that the wall can only be drilled 3 times to produce 6 holes, and so that the
position of the wholes only needs to be marked once.

Step 11: The side, front, back, and floor of the chassis should have connected to each
other with glue into a box shape.

Step 12: The 4 wooden support columns should be placed inside this box according
to what has been illustrated in the diagrams, leaving the 3 gaps for the axles. The
sides of these columns should be glued to all the cardboard walls of the chassis that
meet them. Then the screw driver should be used to drill screws into the wooden
columns through the cardboard sides, from the outside. At least 2 screws should be
used for each side for each column, but their exact positioning is of little importance.

Step 13: The foam platform (which has the same length and width as the body rover)
simply needs to be glued on top of the wooden support columns. After that, the top
wooden walls that will be surrounding the bottle also need to be glued along to the
edges of the rover on top of the foam platform.

Step 14: The plastic straps that will hold the bottle in place on the foam bed should
then be taped on top of the side wooden walls, going from one side wall, across to the
other wall, above the gap where the water bottle will sit. The water bottle is slid inside
from the back of the rover underneath the straps.

Step 15: Finally, a hole of 8mm diameter is drilled in the centre of each wheel, all 3
axles are slid inside the axle holes on the chassis, and then all 6 wheels are glued
onto each end of the 3 axles, such that there is a 1 cm of distance between a wheel
and the chassis of the rover.

4.0 TENDER EVALUCATION CRITERIA.

4.1 Introduction.

Page 7 of 29
The following criteria provided will be used by the Innovators to choose the best tender
application for construction of the Mars lander. Applicants are advised to go through
and provide detail for each criterion to get their application considered. Each criterion
will be marked out of 25 and no application will be considered if they score a mark of
less than 15 in any criteria.

4.2 GENERAL KNOWLEDGE.

4.2.1 Introduction:

Contractors for Innovators Co. for the Mars Rover project are required at least
some general background knowledge about Mars Rovers and the project itself. It is
essential for contractors to sit a short test, compose of 5 questions on multiple aspects
of this project.

4.2.2 Quiz:

1) What is the primary mission of mars rover?


_____________________________________

2) In what year was the first attempt of Mars Rover began?


a. 1960
b. 1973
c. 1966
d. 1955
3) What is the name of the first successful mars rover that arrived at Mars?
a) Marsnik 2
b) Sputnik 22
c) Mariner 4
d) Mars 1969B

4) Where should you store the prototype?


a) In a wet place
b) In a dry location
c) In a humidity environment
d) All of the above
5) Which one of the following is right when handling sharp equipment?
a) Keep your hands close to the tip of the equipment
b) Do not wear appropriate PPE
c) Uncover the object before it is time to use it
d) Keep the equipment pointing away from yourself

Criteria 5/5 4/5 3/5 2/5 1/5 0/5


Quiz Mark
Mark 25 20 15 10 5 0
Allocation
Page 8 of 29
4.3 Safety Awareness.

Safety awareness in our company is very important, as all workers should be able to
demonstrate their abilities to work safely and should always use personal protective
equipment while working. Personal protective equipment includes: safety gloves,
safety glasses, steel toe capped shoes etc. The workers should be able to identify
hazards and work out a way to mitigate the risk. Applicants can also outline any
previous experience, which have required minimum safety standards.

Criteria Have keen Have some Have less


knowledge of PPE knowledge of PPE knowledge and
and easily identify and can identify cant identify
hazard and hazards and hazards and
mitigate their risk mitigate their risk mitigate risk
Mark Allocation 25 15 5

4.4 Experience.

4.4.1 Experience in use of tools and resources

Introduction.
A serious occupational injury or illnesses can affect the lives of the employee. It may
result in a potentially lifelong injury or even death. On the other, people with more
experience parallels to a greater chance of producing a more professional and
accurate prototype for our Mars Rover. This is the reason why we desire some
experience of tools or resources. Marks will be allocated depending on the number of
team members in the group that have relevant experiences. Evidences needed to be
provided to receive the marks for this section.
Criteria All members in the Half or more than Less than a half
group a half of members
Mark Allocation 25 15 5

4.4.2 Previous employment.

Introduction:
Innovators Co. believes that good work experiences will increase the probability of
successes in their career. Exploring to different job environment helps employees get
a real sense of this industry. Thus, it is essential for team members to have some
relevant experience. Marks will be allocated depending on the number of team
members in the group that have been previously employed. Evidences needed to be
provided to receive the marks for this section.

Page 9 of 29
Criteria All group members Half or more than Less than a half
in the group a half
Mark Allocation 25 15 5

4.5 Understanding the design.

Introduction:
Understanding the design is the most important step to create an excellent product.
Innovation Co team desires a perfect design. Therefore, our team expects receiving
any criticism that you realize in the design package and your constructive idea for the
package. Below are the marks follow the criteria:

4.6 Time Management.

Introduction:

Criteria Providing the Providing the Non- providing any


detailed general extra information
information about information about about the package
specific part of package
design package
Mark Allocation 25 15 0

We at Innovators Co require effective time management and punctuality in project and


this demands the constructors commitment to follow schedule of the project. This
expects constructors submitting the product on time as weekly progress reports, the
design package stage one (Friday, 3pm). It is also preferred that constructors take the
responsibility for their teamwork because Innovator Co appreciates the values of each
member in group. Therefore, we can understand the spirit of responsibility and the
way to organize the work of constructors in the project.

4.6.1 Deadline submission the Design package:

This section will be marked depending on the submitted time of design Package at
stage 1 of the applying group. The evidence of the submission will be given by the
screenshot of the submission time of the moodle.

Page 10 of 29
Criteria Stage 1 Stage 1 Stage 1 Stage 1 Stage 1
Design Design Design Design Design
Package Package Package Package Package
was was was was was
submitted 2 submitted submitted submitted submitted
days or within 24- within 12-6 1 hour or late
more 12 hours hours less before
before before before deadline
deadline deadline deadline
Mark 25 15 10 5 0
allocation
4.6.2 Deadline submission the work assignment in-group.

This section will be marked by the submitted time of the assignment of each member
in the group. The evaluation criteria will be based on the weekly progress report of
the applying group.

Criteria Everyone Over due Over due Over due date


submitting on date once date 2 times every time
time
Mark 25 20 10 0

4.7 Communications.

We at Innovators Co. require good communications skills, both oral and written to
contact us. Everything should be well structured and comprehensible. Emails, texts
and calls can be an easy way to contact us and its better to contact during the working
hours (9am-5pm). When any of our team member makes contact, we appreciate an
appropriate and detailed response. The response is also expected to be made within
one working day, during the working hours. Meetings can also be arranged but inform
us at least two days before the meeting day and be specific about what you want to
discuss. We also prefer to get a weekly progress report and some feedback on our
designs too.

Criteria Excellent Good Fair


Communication Communication Communication
Skills and quick in Skills and a bit late Skills and takes
response in response long to respond

Mark Allocation 20 15 5

5.0 RISK MANAGEMENT PLAN


Page 11 of 29
5.1 Introduction.

The aim of this risk management plan is to identify and analyze potential risks
during the design, construction and testing stages of the mars rover project. By
considering the hazards and associated consequences within the three stages,
it ensures risks are mitigated and managed so that the project can be
successfully completed.

5.2 Key terms


Hazard: Potential sources that may be dangerous or cause harm
Risk: The possibility that the hazard will cause injury or loss
Likelihood: The degree to which the risk may happen
Severity: The intensity of the risk
Mitigation: To reduce and provide strategies to a situation
Residual risk: The remainder risks after applying mitigation

5.3 DESIGN STAGE SAFETY EVALUATION.


Page 12 of 29
HAZARD RISK LIKELIHOO SEVERIT MITIGATION RESIDUA
D Y L RISK
Computer Lose all Unlikely Significant -Keep backup Negligible
crashes or work and will have of all data on - As
hard drive designs to start allUSB/external everything
break that were over hard drive is backed
saved again and - Keep a up and
may not cloud back up everyone
finish on as well has a
time - Send copy so
everything to there is
all team less
members so chance of
everyone has losing
a copy. data.
Selecting Mars Possible Significant -Build a Minor
wrong Rover testing model
materials. doesnt of the design
operate to see if car
during the operates.
test. Assess the
faults with the
material
choices and
reselect
materials.
Computer or Can cause Possible Moderate - Brightness Minor -
laptop eyestrains of computer There is a
screens or screen less
headache should not be chance of
s, as a lot more than getting
of time will that of your eyestrain
be spent surroundings. or
on - Take 15-20 headache
computer minute due to
during the breaks and computer
designing divide the screen.
process. work among
your team
members.
Team The Likely- team Moderate - Get medical Minor -
member may designs members -As work treatment. Now there
get sick. will not be can be sick will get - Tell the is a less
finished on since delayed team chance of
time. weathers and might members as work
changing not soon as being
complete possible so delayed
on time. they divide

Page 13 of 29
the work
among
themselves.

Complication Contractor Unlikely Moderate - Make Minor


s in designs s will not everyone in
understan the group go
d how to through
make our designs to
project. make sure
contractors
from the
other group
will also
understand.
- Clarify the
measurement
s

Page 14 of 29
5.4 CONSTRUCTION STAGE SAFETY EVALUATION.

HAZARD RISK LIKELIHO SEVERITY MITIGATIO RESIDU


OD N AL RISK
Sharp Improper Likely Significant - - Use the Minor -
equipment, use of may cause tools risks are
such as knife dangerous some carefully reduced
and scissors tools can injuries thus - Read and when
cause delay the understood handling
injury progress of the properly
which will the project instructions
result in before
the loss of handling the
member in tool
a serious - Prepare the
situation first aid kit
and
medicine
Misunderstand Making Likely Significant - - Minor -
ing the design incorrect misinterpret Communicati minimal
constructi ed the ng frequently impact is
on of the design will with the left when
vehicle cause delay designers problems
and what in the from stage 1 were
was progress - Discuss been
expected any issues solved
from the that are arise
design of
designers
Rare materials Some Unlikely High - - Deal with Minor
or complicated materials progress designer to
equipment cannot be will be fix and work
found or interrupted out
hard to and can be
assemble behind the
schedule
Glue Contamin Unlikely Moderate - - Use the Negligibl
ate the improper glue properly e - risks
eye use of glue and safely will be
can result - Make sure minimize
in an eye the glue d when
infection. doesnt get following
in contact the
with your mitigation
eyes process
- Use safety
protections
- Use first
aid

Page 15 of 29
5.5 TESTING STAGE SAFETY EVALUATION

HAZAR RISK LIKELIHOO SEVERITY MITIGATIO RESIDUA


D D N L RISK
Weather The Likely Significant - - Store the Minor - the
prototype since prototype in risk of
might not cardboard is a dry and damaging
function not water- safe place the
probably, proof it is - Apply a prototype
since susceptible to waterproof can now
cardboar humidity and coating on it be reduced
d water damage when store
compose properly.
a major
part in
our
design,
continual
exposure
to water
will cause
the
cardboar
d to
become a
soggy
mess
Leakage Damage Unlikely Significant - a - Check any Negligible
in the the leakage in the damages on
water prototype water bottle the water
bottle will affect the bottle before
strength of the applying to
cardboard, the mars
which will rover
result in the
deconstructio
n of the
project.
Weight When it is Likely Minor -Before Negligible -
of water not conducting when the
bottle secured the water
properly, experiment, bottle is
during the ensure the secured,
landing water bottle and since
the water are placed the
Bottle properly prototype
might fly is not
out of the traveling at
prototype a high

Page 16 of 29
and injure speed, the
someone risk will be
minimized
Mars Tripping Unlikely Moderate -Allow a safe Minor -
rover over the distance keeping a
mars from the distance
rover mars rover from the
-Only allow prototype
one person will reduce
to conduct the risk of
the test tripping
over and
hurt
yourself

5.4 Risk Matrix.

Severity

https://www.google.com.au/search?q=risk+matrix&source=lnms&tbm=isch&sa=X&s
qi=2&ved=0ahUKEwiVg9eQwYDTAhXKvI8KHYXkAX4Q_AUIBigB&biw=1200&bih=8
55#imgrc=oAlI6qeSnjLQQM:&spf=247

Page 17 of 29
Week5 Week6 TFW TFW Week7 Week8 Week9 Week10 Week11 Week12
EFPC - Stage 1 - Stage 2 - Stage 2 - Handovers - Engineering - Oral
Deadlines Design Contractors Designers (19th April) identity presentation.
Package (2nd submission Submission (5th reflection
April) (21st April) May) (during - Unit reflection
workshop). (during lecture)
- Team action - Peer Review
plan (during Presentation
workshop) - Prototype
testing
Other - Mid - Synthesis - Reflective - Synthesis part - Group - Workshop
Deadlines Semester Test part 1 (ACOM) journal part 2 (ACOM) Report assessment
(mechanics) - Submission 2 (ACOM) - Mid Semester (ACOM) (calculus)
of workshop - Mid (EPROG) - Workshop
1,2,3 Semester assessment
(Calculus) (Calculus) (calculus)

Contractors All team - Reviewing - Address - Finalise - Attend - Construct - Finalise the - Bring handover - Write a
members to design TEC the tender Engineers the prototype prototype form for testing. reflection on
compile their packages and provided by application Australia and submit - Practice for experience of
work to set up the and submit seminars - Handover to presentation and stage 2 and/or
finalise the meetings with designing designers get feedback stage 3 during
design the designers company. from peers. final lecture.
package and to clarify - Prepare for - Give
submit designs - Write engineering presentation as
executive identity group and
summary reflection and answer
complete it questions from
during workshop the panel or
students

Page 1 of 29
Designers All team - Respond to - Attend - Go through - Evaluate - Help and - Designers to - Bring the - Write a
members to the meetings reviews by tender assist compare it prototype for reflection on
compile their contractors with the the applications contractors with their testing. experience of
work to contractors contractors against the one while they design and - Practice for stage 2 and/or
finalise the and write a in stage 1 construct. request for presentation and stage 3 during
design reflection. design package any changes if get feedback final lecture.
package and - Attend needed from peers. - Give
submit - Write - Submit the Engineers - Prepare for presentation as a
executive tender Australia - Submit the engineering group and
summary for evaluation Seminars prototype to identity answer
tender the client reflection and questions from
evaluation complete it the panel or
during workshop students

6.0 GRANTT CHART.

Page 2 of 29
APPENDIX 1

2D DRAWINGS.

Page 1 of 29
1. Balsa Wood. 2 3 *15* 7.
(Boundary wall)
2. Foam Base. 1 32*15*2

3. Card board box. 1 32*15*16

4. Balsa Wood 2 i) 9*15*7


pillars 2 ii)
3.5*15*7
5. Card board 6 9cm
wheels Diameter.
No. DESCRIPTION. QTY SIZE (L*D
{depth}*H)
cm
COMPONENTS.

COMPONENTS DRAWING NO:1 PAGE NO:2

TITLE: PROTOTYPE MARS LANDER. 1:2


SCALE AT A4

Page 2 of 29
1. Card Board 6 Diameter 9cm
wheel.
2. Axle. 3 Length 22cm, 8mm
Diameter.
3. Card board 2 Length 26cm.
boundary wall.
4. Water bottle. 2
5. Rubber Band. 2 Length 4cm*Width 0.5.

6. Balsa Wood 2 Width


Boundary Wall. 3*Length15*Height7(cm)
7. Bals wood 1 32 Length*4 Width *7
boundary side Height(cm).
wall
8. Cardboard box. 1 32 Length*15 Width
(cm).
REV DESCRIPTION. QTY SIZE

COMPONENTS.

COMPONENTS DRAWING NO:2 PAGE NO:

TITLE: PROTOTYPE MARS LANDER. 1:2


SCALE AT A4

Page 3 of 29
COMPONENTS DRAWING NO:3 PAGE NO:

TITLE: PROTOTYPE MARS LANDER. 1:2


SCALE AT A4
Page 1 of 29
COMPONENTS DRAWING NO:4 PAGE NO:

TITLE: PROTOTYPE MARS LANDER. 1:2


SCALE AT A4

Page 2 of 29
Appendix 2
3D Drawing.

Page 3 of 29
Page 4 of 29

You might also like