You are on page 1of 4

11-1112 ( West Rigel (CS60) )

Daily activities summary list

Date : Monday, May 11, 2015

COMMISSIONING
No Time Place to meet PIC Sub System Sub System Description Remarks
1 09:00:00 HV/LV Switchboard Room 4 865.19 11 KV/690V, 4000 KVA, Topside Transformers Step 2.4.66 to 2.4.71
2 09:00:00 Shaker house roof 347.01A Pipehandling Crane 2401 Commission with gripper yoke on the same day.
3 10:00:00 TOPSIDE sWITCHBOARD 3 875.08 230V Lighting & Small Power Dist. Panel LP#8 STEP 1.1.1 TO 2.4.9
4 13:00:00 LIR AND DCR 875.27 DES 230V LIR and DCR Lighting & Small Power Dist. STEP 1.1.1 TO 2.4.9
Panel LP#1
5 13:30:00 Mud Pump Room 734.02 Pneumatic Control Valve System Commissioning manual testing of valves

ENERGIZING
No Time Place to meet PIC Sub System Sub System Description Equip Tag Description
1 09:30:00 AM Thruster Pump Room 1P 722.02 Auxillary Fresh Water Cooling System 722PA002B-DE01 Fresh Water Auxiliary Cooling
Pump #2 AC Motor
2 09:30:00 AM HV/LV Switchboard Room #4 873.04 690V Topside Switchboard No 4 873EN004 690V Topsides SWBD No.4
3 1:00:00 PM P-Tank Room 320.00 Mud Control System 329A1-IB106 MCS RIO cabinet
4 9:15:00 AM Thruster Pump Room 1P 721.05B Auxiliary SW Cooling (P) 721PA002B-DE01 Sea Water Auxiliary Cooling
Pump #2 AC Motor

Daily Inspection
No Time Place to meet PIC Sub System Sub System Description Equip Tag/ Type of Inspection
Package No
1 08:30:00 AM PURUSH 2632 314.01 Dual Wireline Riser Tensioners 314.01-J-001 Cables TP
2 08:30:00 AM PURUSH 2632 314.01 Dual Wireline Riser Tensioners 314.01-J-003 Cables TP
3 08:30:00 AM PURUSH 2632 324.03 Mud Transfer and storage system, incl Tank Washing 324.03-J-003 Cables TP
OBM Soap Injection Unit, Agitator, High Rate Mixer
4 08:30:00 AM PURUSH 2632 332.01 BOP & Diverter Control System 332.01-P-001 Cables TP
5 08:30:00 AM PURUSH 2632 423.01 LAN (Local Area Network) 423.01-N-015 Cables TP
6 08:30:00 AM PURUSH 2632 731.03 Starting Air System - Engine Room No.3 731.03-J-002 Cables TP
7 08:30:00 AM PURUSH 2632 804.01 Deck Drainage System - Non Hazardous 804.01-P-001 Cables TP
8 08:30:00 AM PURUSH 2632 811.00 Fire and Gas System (F&G, Cause & Effect) 811.00-J-003-02 Cables TP
9 08:30:00 AM PURUSH 2632 811.00 Fire and Gas System (F&G, Cause & Effect) 811.00-J-003-03 Cables TP
10 08:30:00 AM PURUSH 2632 814.01 Fire Fighting Water Mist System 814.01-N-001 Cables TP
11 08:30:00 AM PURUSH 2632 873.72 690V Drilling SWBD/ MCC No 2 873.72-J-002 Cables TP
12 08:30:00 AM PURUSH 2632 875.01 230V Lighting & Small Power Dist. Panel LP#1 875.01-L-007 Cables TP

Page 1 of 4
11-1112 ( West Rigel (CS60) )
Daily activities summary list

Date : Monday, May 11, 2015


13 08:30:00 AM PURUSH 2632 875.17 230V Lighting & Small Power Dist. Panel LP#17 875.17-L-004 Cables TP
14 08:30:00 AM PURUSH 2632 875.17 230V Lighting & Small Power Dist. Panel LP#17 875.17-L-005 Cables TP
15 08:30:00 AM PURUSH 2632 875.17 230V Lighting & Small Power Dist. Panel LP#17 875.17-L-017 Cables TP
16 08:30:00 AM PURUSH 2632 875.18 230V Lighting & Small Power Dist. Panel LP#18 875.18-L-021 Cables TP
17 08:30:00 AM PURUSH 2632 875.21 230V Lighting & Small Power Dist. Panel LP#21 875.21-L-003 Cables TP
18 08:30:00 AM PURUSH 2632 875.21 230V Lighting & Small Power Dist. Panel LP#21 875.21-L-017 Cables TP
19 01:30:00 PM PM HASHIM Thruster/Pump Room 1P Z 01 01 Compartment
20 02:00:00 PM PM HASHIM Ballast Water Treatment Room (P) V 01 05 Compartment
21 08:30:00 AM ONBOARD @TK-B Wahid Liquid Mud Tank (LQM) 1P 324 TK 01 Compartment
22 08:30:00 AM ONBOARD @TK-B Wahid Liquid Mud Tank (LQM) 2P 324 TK 02 Compartment
23 09:00:00 AM PM HASHIM FRESH WATER DRAIN TANK 722 TK 03 Compartment
24 09:00:00 AM KANNAN Braking Resistor Room A 00 11 Compartment
25 09:00:00 AM KANNAN Main HPU Room U 00 43 Compartment
26 09:00:00 AM PM HASHIM Ballast Water Treatment Room (S) X 01 05 Compartment
27 09:33:00 AM PM HASHIM Ballast Water Tank (BWT) 5S 801 TK 05 Compartment
28 09:00:00 AM NAUNG 323.03 DP31 ProCut Sack Cutting Unit (including motor) 323A1-CH101 Equip ITR
29 09:00:00 AM NAUNG 324.05 Agitator No. 1 For Active Pit No. 2 WBM 324A1-CJ215 Equip ITR
30 09:00:00 AM NAUNG 324.05 Agitator No. 2 For Active Pit No. 2 WBM 324A1-CJ216 Equip ITR
31 09:00:00 AM NAUNG 324.05 Agitator No. 1 For Active Pit No. 1 WBM 324A1-CJ218 Equip ITR
32 09:00:00 AM NAUNG 324.05 Agitator No. 2 For Active Pit No. 1 WBM 324A1-CJ219 Equip ITR
33 09:00:00 AM NAUNG 324.05 Agitator No. 1 For Chemical Pit 324A1-CJ220 Equip ITR
34 09:00:00 AM NAUNG 324.05 Agitator No. 2 For Chemical Pit 324A1-CJ221 Equip ITR
35 09:00:00 AM NAUNG 324.05 Agitator No. 1 For Reserve Pit No. 3 WBM 324A1-CJ222 Equip ITR
36 09:00:00 AM NAUNG 324.05 Agitator No. 2 For Reserve Pit No. 3 WBM 324A1-CJ223 Equip ITR
37 09:00:00 AM PURUSH 2632 425.01 PAGA System B Battery Rack 425EB001B Equip ITR
38 09:00:00 AM PURUSH 2632 814.01 Main Control Panel (I/O Panel #1) 814EC001 Equip ITR
39 09:00:00 AM PURUSH 2632 814.01 Pump Starter Panel (I/O Panel #2) 814EC002 Equip ITR
40 09:00:00 AM PURUSH 2632 814.01 Valve Operating Panel 814EC003 Equip ITR
41 09:00:00 AM PURUSH 2632 814.01 Water Mist Supply Pump Motor 814PA003-DE01 Equip ITR
42 09:30:00 AM NAUNG 324.03 Tank Washing Machines-A (RMP 3 WBM) 326A1-BY114 Equip ITR
43 09:30:00 AM NAUNG 324.03 Tank Washing Machines-B (RMP 3 WBM) 326A1-BY115 Equip ITR
44 09:30:00 AM NAUNG 324.03 Tank Washing Machines- (Chemical Pit#1) 326A1-BY116 Equip ITR
45 09:30:00 AM NAUNG 324.03 Tank Washing Machines- (Chemical Pit#2) 326A1-BY117 Equip ITR

Page 2 of 4
11-1112 ( West Rigel (CS60) )
Daily activities summary list

Date : Monday, May 11, 2015


46 09:30:00 AM NAUNG 324.03 Tank Washing Machines-A (AMP 1 WBM) 326A1-BY118 Equip ITR
47 09:30:00 AM NAUNG 324.03 Tank Washing Machines-B (AMP 1 WBM) 326A1-BY119 Equip ITR
48 09:30:00 AM NAUNG 324.03 Tank Washing Machines-A (AMP 2 WBM) 326A1-BY121 Equip ITR
49 09:30:00 AM NAUNG 324.03 Tank Washing Machines-B (AMP 2 WBM) 326A1-BY122 Equip ITR
50 01:00:00 PM MAIN STORE nor 579.61 Air Conditioning System - Upper Hull Port 579.62-H-002(S) HVAC TP
51 01:00:00 PM MAIN STORE nor 579.61 Air Conditioning System - Upper Hull Port 579.62-H-003(E) HVAC TP
52 02:00:00 PM SHAKER HOUSE DECK nor 579.08 FCU in Drilling SWBD Rooms & LER Rooms 575.50-H-004(E) HVAC TP
53 02:00:00 PM SHAKER HOUSE DECK nor 575.50 Ventilation System -Shaker House, HVAC Room 2 & 575.50-H-004(S) HVAC TP
Shaker Operation Room, Air Lock (Shaker Deck)
54 02:00:00 PM SHAKER HOUSE DECK nor 575.50 Ventilation System -Shaker House, HVAC Room 2 & 575.50-H-005(E) HVAC TP
Shaker Operation Room, Air Lock (Shaker Deck)
55 02:00:00 PM SHAKER HOUSE DECK nor 579.08 FCU in Drilling SWBD Rooms & LER Rooms 575.50-H-005(S) HVAC TP
56 09:00:00 AM LQ WHEEL HOUSE DECK nor 571.07 Air Conditioning System - Living Quarter WheelHouse 571.07-H-001 (E) HVAC TP
Deck
57 10:00:00 AM LQ MAIN DECK nor 571.02 Air Conditioning System - Living Quarter Main Deck 571.02-H-004(E) HVAC TP
58 10:00:00 AM LQ MAIN DECK nor 571.02 Air Conditioning System - Living Quarter Main Deck 571.02-H-007 (E) HVAC TP
59 10:30:00 AM LQ UPPER DECK nor 571.04 Air Conditioning System - Living Quarter Upper Deck 571.04-H-001(S) HVAC TP

Page 3 of 4
11-1112 ( West Rigel (CS60) )
Advance call out/ One day look ahead activities

Date : Tuesday, May 12, 2015

COMMISSIONING
No Time Place to meet PIC Sub System Sub System Description Remarks
6 09:15:00 Mud Pump Room 734.02 Pneumatic Control Valve System Commissioning manual testing of valves
7 13:00:00 866.03 General UPS system GENERAL UPS 2, LER Room 4

Page 4 of 4