You are on page 1of 34

ENGINEERING MANUAL

SEM - 3069E
Piping Design

Compressor & Turbine Piping Design Standard

REV. : 3
DATE : 2004. 08. 20
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE i OF ii
Piping Design Standard

Table of Contents

Page
1. General

1.1 Purpose ------------------------------------------------- ----------------- 1


1.2 Scope --------------------------------------------------------------------- 1
1.3 Reference ----------------------------------------------------------------- 1

2. COMPRESSOR General

2.1 Compressor Types and Characteristics -------------------------------------- 1


2.2 Compressor Comparison ----------------------------------------------------- 2

3. COMPRESSOR/TURBINE LAYOUT

3.1 Layout General ------------------------------------------------------------ 3


3.2 Compressor House Layout --------------------------------------------------- 3
3.3 Installation Height ------------------------------------------------------- 5
3.4 Operation & Maintenance --------------------------------------------------- 6

4. Piping LAYOUT

4.1 Compressor Connecting Pipe ------------------------------------------------ 9


4.2 Turbine Connecting Pipe --------------------------------------------------- 11
4.3 Oil System Connecting Pipe ------------------------------------------------ 12
4.4 Strainer Installation ------------------------------------------------------ 12
4.5 Expansion Joint Installation ---------------------------------------------- 14

5. NOZZLE Load Calculation Procedure & Consideration

5.1 Standard ------------------------------------------------------------------- 14


5.2 Calculation & Review Procedure ---------------------------------------------- 14
5.3 Consideration -------------------------------------------------------------- 15
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE ii OF ii
Piping Design Standard

6. PIPING SUPPORT

6.1 Compressor/Turbine Support General ---------------------------------------- 15


6.2 Support Consideration by Compressor ----------------------------------------- 16
6.3 Consideration by Support Type --------------------------------------------- 16
6.4 Structure Strength by Support --------------------------------------------- 20

7. Work Activity by Design Phase ------------------------------ ------------------- 21

8. Revision History --------------------------------------------------------------- 22

APPENDIX

. Compressor Pipe Fixed Point Selection Method


. Compressor Pipe Construction Method(SAMPLE)
. Reference Plot Plan (MOP, GSP-5, PEMEX-Tula, IOCL)
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 1 OF 24
Piping Design Standard

1. General

1.1 Purpose

This Manual aims to reinforce and standardize the Piping Layout (Incl Supports) for Compressor
/Turbine systems for oil refinery and Chemical Plants designed by SECL.

1.2 Scope

This Manual applies to large Compressor/Turbine Piping of all plants to be implemented by SECL.
For Any Disparity With The Client Spec, the latter shall prevail.

1.3 Reference

1.3.1 SEM-2002E "Plant Layout Standard"


1.3.2 SEM-3002E "Piping Design Instruction"
1.3.3 SEM-3039E "Piping Design Standard"
1.3.4 SEM-3040E "Pipe Support"

2. COMPRESSOR General

2.1 Compressor Types and Characteristics

2.1.1 Centrifugal Compressor


It uses a rotating disk or impeller in a shaped housing to force the gas to the rim of
the impeller, increasing the velocity of the gas. It comes usually in Package Type,
and is composed of Inter-cooler, After-cooler, Lube Oil System, Seal Oil System,
Surface Condenser, Automatic Control,etc. Motor or Turbine is used as Driver and its
advantage is that Oil-free air/gas is supplied.

2.1.2 Reciprocating Compressor


The intake gas enters the suction manifold, then flows into the compression cylinder
where it gets compressed by a piston driven in a reciprocating motion, and is then
discharged. It is composed of Lubricated Type and Non-lubricated Type. Non-lubricated
Type is used for Instrument Air. It is used for capacity of Air below 30 N/min and
discharge Pressure(max. 50,000 Psi.a).

2.1.3 Screw Compressor


It is a type of gas compressor which compresses gas in rotor cavity and achieves
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 2 OF 24
Piping Design Standard

pressure. It is capable of achieving pressure range around 7.0 ~ 8.5 Kgf/. It is not
suitable for high pressure.

2.2 Compressor Comparison

Screw Compressor Reciprocating Compressor

Type Rotary Small, Light Low Speed Reciprocating, Large

Consideration screw reciprocating

Efficiency low volumetric efficiency high volumetric efficiency


Stepless Capacity Control is Step by Step Capacity Control Feature
Capacity (100, 75, 50, 25%)
possible in On-load/Off-load type
Control
partial load Feature (100-0%)
Friction can occur in part of Piston,
Mechanical No effect on efficiency as
Mechanical Friction only in Piston Ring, Rod, Cylinder, Rod Packing,
Friction Bearing
Efficiency decreases with friction.
Damage of Valve, Plate & Spring due to
Operating Valve No
Suction Valve, Discharge Valve
Pulse Less More

Vibration Less More

easy to find measures for hard to take measures for soundproofing


Noise soundproofing due to high frequency due to low frequency noise
noise
Power Factor, efficiency is good Power Factor, efficiency is poor due to
Motor due to high speed motor (small low speed motor (large size)
size)
Base Small large

Installation large
Compact
Space
Credibility good poor due to friction, damage of
Durability operating valve
great care is to be taken due to noise,
Operation simple, remote control possible temperature, pressure. difficult to find
damage on friction part and valve.
Pressure Range limited High pressure possible

[reference] lecture, Machinery Design "Rotary Machinery"

3. COMPRESSOR/TURBINE LAYOUT
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 3 OF 24
Piping Design Standard

3.1 Installation General

3.1.1 Should be installed near Road for an easy access to Mobile Equipment for Maintenance.as
per requirements of layout.

3.1.2 Layout shall be as per Regulations of Oil, Noise, Fire Fighting & dangerous object, etc.

3.1.3 Requirement of Compressor Shelter or Room shall be as per below:

Type Climate Condition Other Condition Note


Outdoor Type Warm Zone
Danger of Explosion is expected
Open Below Type Tropical Zone
due to Process Fluid Leak
Enclosure Type Extreme Cold Zone No Danger from Process Fluid Leak

3.2 Compressor House Layout

Compressor House Layout is to be selected in consideration of Plant Overall Layout and Features
of each House Layout as below. See SEM-2002E "PLANT LAYOUT Standard" Appendix as Compressor
Layout Reference.

3.2.1 Short Rectangle (Parallel Arrangement)


(1) It is easier to manage if Compressor comes in multiple.
(2) Less Number of Columns
(3) There is less room in case of more than 3 of compressor, compressor / turbine &
annexed device (Condenser, Cooler, Separator, Lube & Seal Oil System )
(4) Cost would increase due to Width Extension of Traveling (or Overhead) Crane &
Architecture
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 4 OF 24
Piping Design Standard

[Figure 3-1] Short Rectangle Compressor House

3.2.2 Long Rectangle (Series Arrangement)


(1) Architecture Area can be made smaller in case less than 3 of Compressor.
(2) It is easy for Condenser Arrangement & Installation, Piping Plan.
(3) It reduces the Width of Traveling Crane & Architecture.
(4) For warm climate with less rainfall Lube & Seal Oil System is usually installed
outside.
(5) Architecture would result in a narrow and long shape so is susceptible to Area when
the overall Plant is set in place.

[Figure 3-2] Long Rectangle Compressor House

3.2.3 L-Shape Type


(1) Compressor layout can be arranged conveniently around Building
(2) It could be functional from the viewpoint of integrated Arrangement.
(3) Drop Area will be in 2 places, transportation vehicles should be accessible to both
drop areas.
(4) 2 Traveling Cranes would be installed.
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 5 OF 24
Piping Design Standard

[Figure 3-3] L-Shape Type Compressor House

3.3 Installation Height

Generally Installation Height, Configuration, etc. is to be based on the requirements of


Compressor Vendor. But, Final Installation Height of Compressor is to be decided after review
thoroughly each Height of the below items required by Compressor Type.

3.3.1 Centrifugal Compressor


(1) Min. Straight Run Requirements of Compressor Inlet Pipe
(2) NPSH Requirements of Vertical Condensate Pump
(3) Slope Requirements of Lube Oil, Seal Oil System Location and Pipe
(4) Maintenance Space Height of Annexed Device such as Condenser, Lube & Seal Oil System
(5) Overhead Clearance
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 6 OF 24
Piping Design Standard

[Figure 3-4] Centrifugal Compressor Installation Height Consideration

3.3.2 Reciprocating Compressor


(1) Install overall as close to ground as possible to minimize Piping Vibration
(2) Sleeper Height (Usually 300 ~ 450mm) & Piping Support Type
(3) Pulsation Dampener Size
(4) Minimum Distance between Beam Size & Dampener for Operating Platform

[figure 3-5] Reciprocating Compressor Installation Height Consideration


SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 7 OF 24
Piping Design Standard

3.4 Operation & Maintenance Space

3.4.1 Floor & Platform


(1) It is to be easy for Plant Operator to reach and operate Valves, Switches, Control
Panel instruments.
(2) Appropriate Number of Doors, Stairs and Ladders are to be installed to evacuate in
case of emergency.
(3) Floor Level around Compressor is to be arranged on the basis of Top of Common
Header as [Figure 3-6] "Top Style"
(4) Floor Standard according to Device Arrangement in Compressor House is to be based on
5.2.4 of SEM-2002E "Plant Layout Standard"

Top Style (preferred) Bottom Style

[Figure 3-6] Floor Arrangement Style around Compressor

3.4.2 Traveling Crane


(1) Compressor, Turbine is to be arranged within Operation area of Traveling Crane Run
(2) Running Range of Crane is to be designed for loading in Truck directly from
Traveling Crane. That is, Travel Crane is to be extended upto Lay-down Area(or Drop
Area).
(3) Traveling Crane Installation Height is to be decided after review the below items
thoroughly.
1) As per Requirement by Compressor Vendor (maximum priority)
2) The Max. Size among Compressor/Turbine Parts(Casing Cover, Turbine Soundproof
Cover, etc.)
3) The Max. Size among the upper connecting Pipes of devices to be dismantled (to
the part where Break Flange is installed)
4) Basic Length from Rail to Hook for Crane
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 8 OF 24
Piping Design Standard

(4) Generally Removal Space of Compressor/Turbine Top is to be considered 3 ~ 4 times


of its Height. But, decide based on item (4) and [Figure 3-7] & [Table 3-1] in case
Specific Information of (3) is not available.

[Figure 3-7] Traveling Crane Installation Height

[Table 3-1] Travel Crane Installation Height (Reference)

Type Height for Reference Note


Small Compressor 4.0 m
H1 Medium Compressor 5.0 m
Large Compressor 7.0 m
20 ton 2.6 m
H2 30 ton 2.8 m Span: Max. 26m
40 ton 3.0 m

3.4.3 Condenser, Cooler, Condensate Pump


(1) In case they are to be installed at the bottom of Compressor Deck, Make provision for
Installation & Removal.
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 9 OF 24
Piping Design Standard

(2) Provide Space for Cooler Tube Bundle Maintenance


(3) In case Condensate Pump is Vertical Type,Ensure Space for Shaft.

3.4.4 Lube & Seal Oil System


(1) It has to be accessible from Road and, and it should be at convenient place to install
and load.
(2) It is to be installed on the 1st Floor adjacent to Compressor to meet Gravity Flow
Requirements.
(3) If Compressor House is closed type, Upper Floor (2nd F) of Oil System Installation
should be of removable type (Grating) for Maintenance.
(4) Control Panel and Piping shall not to be installed in Grating Area of the above(3).
(5) Oil Console to be installed such that Traveling Crane can be used in case of
Maintenance.
(6) Access for Filter Element to be provided.
(7) Pathway for Operation (Width Min. 800) is to be ensured enough around Oil Console.
(8) Seal Oil Head Tank is to be installed in the place where it is not interfering with
Traveling Crane Operation.
(9) Seal oil head tank are to be installed outside of Compressor House in case there is no
problem of Freezing or when the Capacity is above 2 ton.
(10) Installation Height of Seal Oil Head Tank is to be complied with Vendor's requirements.
(11) Installation Height of Oil Trap is to complied with Vendor's requirements.

3.4.5 Drop Area


(1) It is to be the place where truck can have an easy access and direct unloading/loading
from Road.
(2) Drop Area is to be designed within operating area of Traveling Crane.
(3) Drop Area Section is to be based on the max. Size of the below items.
1) Compressor or Turbine Removal Part Size
2) Casing Cover or Turbine Soundproof Cover Size
3) Cylinder Size (Reciprocating Compressor)
4) The Max. Size among the upper connecting Pipes of devices to be dismantled

3.4.6 Control Panel


(1) Compressor House is to be installed close to outer wall in order not to interfere
Compressor Operation and Maintenance.
(2) Min. 2m Space is to be ensured in front of Control Panel for operation.
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 10 OF 24
Piping Design Standard

4. Pipe LAYOUT
Pipe connecting to Compressor or Turbine is to be installed in order of High Temperature, Large Bore,
Heavy-wall. Detailed Standard by Pipe Type is be based on the below.

4.1 Compressor Connecting Pipe


4.1.1 Suction Pipe is to be designed as short and as direct as possible.

4.1.2 A Min. of 2D (D: Diameter) Straight Run of same size as of suction Nozzle is to be ensured
for even flow. But, if Vendor Requirement is available, then, this shall be taken up at
priority.

4.1.3 In case Tee is used instead of Elbow in Suction Nozzle, Min. 6D of Straight Run is to be
ensured. But, again Vendor Requirement shall govern.

4.1.4 In case Injection Nozzle is to be installed in Vertical Straight Run right before the
Suction Nozzle as per Straight Run shall be from the Nozzle to injection nozzle weld point.

[Figure 4-1] Suction Pipe Minimum Straight Run

4.1.5 Avoid using Tee, Short Radius Elbow & Direction Change Fitting as much as possible in
Suction/Discharge Lines.

4.1.6 Be sure to install Break Flange for Dismantlement and Alignment of Compressor.

4.1.7 In case By-pass Pipe for Minimum Flow connecting Suction and Discharge, install Pipe and
Support to minimize vibration generated by Pressure Difference.
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 11 OF 24
Piping Design Standard

[Figure 4-2] Minimum Flow By-pass

4.1.8 In case Check Valve is to be installed in Discharge Pipe according to Process Requirement,
it is to be installed as close to Nozzle as possible.

4.1.9 Check Valve (Non-slam, etc.) in Discharge should indicate Pressure Drop, P clearly in
Special Part Data Sheet.

4.1.10 Low Point or Pocket shall be designed to minimize Condensate formation.

4.1.11 In Suction Pipe Pocket, Drain Valve is to be installed close to Equipment Nozzle.

4.1.12 In case Valve Body is Low Point according to overall Pipe Arrangement, Drain Valve is to be
installed to Valve Body.

4.1.13 In case Suction Pipe is branched from Main Header, branch shall be from top of Main Header
to prevent Condensate Flow to compressor/turbine.
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 12 OF 24
Piping Design Standard

[Figure 4-3] Branch Method & Drain Installation Standard

4.1.14 Provide permanent or temporary Strainer in Suction Pipe to protect Compressor.

4.1.15 Valve, Chest & Casing Drain Nozzle Connecting Pipe installed in Compressor is to be
connected to individual Drain Funnel.

4.1.16 Maintenance Area not to interfere with Strainer Screen Installation and Removal.

4.1.17 See No.6 for Compressor Connecting Pipe Support Design.

4.2 Turbine Connecting Pipe


4.2.1 Break Flange is to be installed if necessary in consideration of Device Dismantlement in
case of Turbine Connecting Steam Pipe.

4.2.2 Main Valve of Suction Steam Pipe is to be installed adjacent to Turbine as close as possible
for access to instrument and equipment while operating.

4.2.3 Decide Installation Location of Main Valve according to Operation Condition


(Solo-run, Warming-up, etc.).

4.2.4 Install Steam Trap at Pocket in Suction Steam Pipe.

4.2.5 Discuss with Process if Steam Trap is necessary in case Suction Pipe to Turbine Nozzle is
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 13 OF 24
Piping Design Standard

without Pocket but Straight length is too long.

4.2.6 Install Steam Trap right before Vertical Pipe to Turbine Nozzle (as shown in [Figure 4-4])
with Drip Pot to prevent Condensate flow.

[Figure 4-4] Drip Pot Installation Method

4.2.7 See related Specification and SECL Pipe Hand Book(Sheet No.5-21) for Drip Pot
Configuration and Detailed Size.

4.2.8 Be sure to design Steam Pipe connected to Turbine by "", "" on the basis of equipment
to minimize Thermal Stress affecting Nozzle.

4.2.9 Design Steam Pipe connected to Turbine to prevent any problem in case of Steam Blow-out.

4.2.10 See No.6 for Turbine Connecting Pipe Support Design

4.3 Oil System Connecting Pipe


4.3.1 Be sure to comply with Slope Requirement with Compressor Vendor or P&ID.

4.3.2 Be sure not to arrange Oil Pipe at top of Steam line or other high temperature Pipe to
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 14 OF 24
Piping Design Standard

prevent Fire.

4.3.3 Be sure to check Temperature Maintenance Requirement by Steam Tracing in Lube & Seal Oil
System.

4.3.4 Be sure to design foreign matter not to pile up at welding part by using Butt Welding
Fitting in case of small bore Pipe.

4.3.5 Be sure to arrange Pipe for Chemical Cleaning & Oil Flushing.

4.3.6 Be sure to install Break Flange at an interval of every certain length in case of cleaning
Pipe by Wash Vessel.

4.4 Strainer Installation


Be sure to install near Suction Piping Nozzle for the purpose of damage prevention of Compressor,
Impeller or Blade of Turbine, and Branch Pipe, Temperature Indicator, Pressure Gauge, etc is not
to be installed in the lower part of Strainer.

4.4.1 Temporary Type

[Figure 4-5] Temporary Type

(1) Be sure to install spool piece with Flange as [Figure 4-5] for Installation and
Maintenance of Cone Type Strainer.
(2) Generally over 400LB Pipe is not followed Flange.
(3) Be sure to consider Support not to interfere Compressor Alignment in case of Piece
Removal for Strainer
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 15 OF 24
Piping Design Standard

4.4.2 Low-Pressure T-Type


(1) It is generally applied to Low pressure Pipe of below 300LB.
(2) Make sure that it does not effect Compressor Alignment in case of Strainer
Maintenance.

[Figure 4-6] Low Pressure T-Type

4.4.3 High Pressure T-Type


(1) It is generally applied to High pressure Pipe of above 400LB.
(2) Relatively it requires small Strainer Maintenance Area.
(3) Provide Drain Valve as Double Block in case of High Pressure(above 600LB) as per
Process Requirement.

[Figure 4-7] High Pressure T-Type


SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 16 OF 24
Piping Design Standard

4.5 Expansion Joint Installation

4.5.1 Expansion Joint can be used for inadequate Flexibility for large bore Pipe of Suction
Side. comply with Client's or Process Requirements.

4.5.2 Normally Expansion Joint is used with Transition Piece in Turbine and Condenser Connecting
Pipe.

4.5.3 Refer EJMA Standard or ANSI/ASME B 31.3 Appendix X for Bellows Pressure and Life Span
Calculation.

5. NOZZLE Load Calculation Procedure & Consideration


5.1 Standard

[Table 5-1] Code Standard

Type Stnadard Note

Centrifugal Compressor API STD 617 (NEMA X 1.85) Size or Formula by Vendor is to be
Turbine NEMA SM-23 taken a priority.

5.2 Calculation and Review Rocedure


1. Criteria for Allowable Nozzle Force , [Vendor Data Submit Request]
Moment Standard
1. , M om ent [ Vendor D ata basic
-SECL provides Design
]
2. 2.Nozzle
N ozzle S ize
Size -
Standard
(Ambient
Temperature,
3. N ozzle ( , )
3. Nozzle Movement Operating Temperature, etc.)
4. N ozzle ,
4. 5.Nozzle
Location,
Alignment
5. Other Spec.

Thermal Stress Analysis


C om puter
by Computer

1. Review , Method Change


1. ,
Allowable
No 2.2.Review
R Pipe
oute Route
Change

Review
Value
3.3.Review Equipment
Layout Layout
Change
Yes

Reflection to

Design
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 17 OF 24
Piping Design Standard

5.3 Consideration
5.3.1 Base Temperature for Pipe Expansion Calculation is as below and Vendor should provide
Nozzle Thermal Movement.
(1) Pipe of Normal Operating Temperature is over 0: lowest average Temp. of ambient
temp.
(2) Pipe of Normal Operating Temperature is below 0: Highest average Temp. of ambient
temp.

5.3.2 It is usually safe to apply installation temp.(ambient average temp.), be sure to review
actual condition in case it is extremely cold or Compressor House is Enclosure Type.

5.3.3 Be sure not to use Cold Spring or Counter Weight in order to reduce reaction force of
Compressor, Turbine Nozzle, or adjust Support Load.

5.3.4 Be sure to consider appropriate measures in case of the below load condition.

[Table 5-2] Measure according to Load Condition

Load Condition Measure


Support Distance around Nozzle & Balance
Piping Weight and Bending by Weight Adjustment
Spring Load Balancing
Rod, Turnbuckle Style Application
Friction force from Support Use Teflon in Resting Support (Friction factor
reduction)
approx. 5%, If variability load is over 100kg,
Spring Hanger Variability
Adjustment in Site is required.
Piping Welding, installation Thorough Construction & Alignment Management
tolerance, Welding Distortion

Settlement Equipment & Support Common Foundation, Separate


Foundation for Support

6. PIPING SUPPORTS

6.1 Compressor/Turbine Support General


6.1.1 Be sure to review by Computer from the basic Design Stage and not only Support Structure
Type, & Installation Method but also Civil/Architecture Information in detail at the same
time.

6.1.2 Give Civil/Architecture Information clearly, and provide for Design Adjustment.
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 18 OF 24
Piping Design Standard

6.1.3 Be sure to consider Loading Data for Hydro Test, Insert Plate Configuration & Allowable
Deflection of Structure for Support

6.1.4 While selecting Hanger Type, consider affect by of Friction force.

6.1.5 Be sure to design to be able to adjust Support around Nozzle in each direction of X, Y,
Z because Pipe is to be adjusted in case of Nozzle Alignment.(Use adjustable supports if
reqd.)

6.1.6 Be sure to use Support of which structure is simple and fabrication and installation is
easy but do not to use Support Type as [Figure 6-1] in Compressor, Turbine Pipe.

[Figure 6-1] Support Type not to use

6.2 Support by Compressor Consideration


6.2.1 Centrifugal Compressor
(1) Compressor,Turbine Connecting Pipe is to be supported in House Floor or Structural
Member.
(2) In case Compressor, Turbine Connecting Pipe is not connected by break-up Flange for
Alignment, Design Support to minimize deflection by Piping Weight.
(3) Consider Support and Bracing for Vibration Prevention or Shock Absorption
(4) Support Load, Welding, Hole drilling is prohibited in on Compressor, Turbine body or
bed.

6.2.2 Reciprocating Compressor


(1) Support adjacent to Compressor Nozzle is to be installed on Separate Foundation for
Support (not Equipment foundation or Structure) or Concrete Sleeper.
(2) Install Hold-Down Support for Vibration in Suction/Dicharge Pipe.

6.3 Consideration by Support


6.3.1 Spring (Hanger) Support
(1) Use Spring Support to minimize Load and Moment transmitted to compressor/Turbine
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 19 OF 24
Piping Design Standard

Nozzle.
(2) Design Spring Support around Nozzle by putting hanger in two locations as
[Figure 6-2] or Base Type to prevent misalignment.

[Figure 6-2] Support Installation for Alignment

(3) Spring Support Load Calculation is to be based on Computer Analysis, See SEM-3040E
for Calculation.
(4) Use Variable Type as much as possible and use Constant Type in case movement is
large and influence on Nozzle is more.
(5) Base Type is not usually used but be sure to reduce Friction by using Sliding Plate
like Teflon or Graphite Pad if necessary.
(6) Use Hanger Type to reduce Horizontal Force & Moment which is transmitted to
Friction Force and Nozzle.
(7) Sway Strut can also be used to reduce Nozzle Load by reducing Friction Force (See
Fig 6-3)

[Figure 6-3] Sway Strut & Sliding Plate Installation


SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 20 OF 24
Piping Design Standard

(8) Enhance Accuracy of Stress Analysis and Load Value by using Trunnion Weight for
Spring Load Calculation.

6.3.2 Directional Stop (DS)


(1) Design as the structure of function and role identical to Input condition in case
Stress Analysis.
(2) Rod Turnbuckle Style is selected based on Directional Stop Function as required by
Stress Analysis. Another advantage is that Fabrication and Installation is
comparatively simple.
(3) Turnbuckle Style as Left of [Figure 6-4] is to be applied because Guide Style as
right of [Figure 6-4] Guide doesn't conform with Restraint Purpose due to Friction
Force, Fabrication and Installation Tolerance, etc.

Turnbuckle Style (Preferred) Guide Style


[Figure 6-4] Turnbuckle & Guide Style

(4) Attachment to cause Elastic deformation by heat like Clamp can't be used for the
purpose of Direction Stop. Use only Lug Plate(or Rib Plate) is attached directly to
Piping as [Figure 6-5] and Reinforcing Ring is attached to Clamp in addition.

Clamp Type - DO NOT USE Lug Type - CAN BE USED

[Figure 6-5] Clamp & Lug Type


SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 21 OF 24
Piping Design Standard

(5) Even if Directional Stop is required in one direction,provide in both directions as


[Figure 6-6].

Wrong Installation

Right Installation

[Figure 6-6] Directional Stop Installation Method

(6) In case Directional Stop is to be installed by using Trunnion, Provide reinforcement


to prevent Elastic deformation of Trunnion as shown below.

[Figure 6-7] Trunnion Reinforcement Method

(7) IF Directional Stop is to be installed around Compressor, Turbine Nozzle as shown in


[Figure 6-8]. Give Insert (or Corner) Plate & Information on Support Beam including
Loading Data to Civil/Architecture in advance.
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 22 OF 24
Piping Design Standard

[Figure 6-8] Directional Stop around Nozzle

6.4 Structure Strength by Support


6.4.1 Load shall be reflected in Civil/Architecture & Structure Design as shown below. Be sure
to adjust Piping Support Location, Form, etc. if it exceeds the standard.
(1) Allowable Vertical Load per Compressor Foundation
(2) Vertical & Horizontal load per Local Foundation
(3) Load per Insert Plate

[Figure 6-9] Structure & Insert Plate Installation

6.4.2 Support Structure should have enough strength, be sure to send information on Allowable
deflection within 1mm including Loading Data to person in charge of Civil/Architecture.
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 23 OF 24
Piping Design Standard

6.4.3 Be sure to use Insert Plate, Anchor Bolt in case Support is to be fixed in Concrete.

6.4.4 Be sure to specify information on Loading Date, Material, Configuration, Installation


Location and Quantity of Insert Plate accurately on drawing and send it to person in
charge of Civil/Architecture.

7. Work Activity by Design Phase


Basic Plan & Layout Planning Study Detail Design
(1) Job Contract & Client's (1) P&ID (AFP) (1) P&ID (AFD or AFC)
Requirements (2) Line Schedule (2) Final Approved DWG. of
(2) Process Flow Diagram (3) Equip.(Vendor) DWG. Equip., Instrument, Valve
(3) Compressor, Turbine (Assembly DWG., Vendor (3) Foundation & Steel
Information for Requirements P&ID) Structure Final DWG.
Piping Work (4) Compressor annexed (4) Allowable Forces &
Equip. Arrangement, Moments
Height Location Drawing (5) Nozzle movement
(5) Electrical/Instrument, (6) Vendor Requirements
Civil/Architecture (7) Electrical/Instrument,
Requirements Civil/Architecture
Information
(8) Each Information
(1) Layout Study (1) Completion of Piping (1) Piping Design Drafting
(2) Compressor Room Size & Work List of Basic Planning (2) Piping ISO DWG. Creation
Configuration Decision Phase (if necessary Trunnion,
(3) Information for (2) Range and Standard etc. Support reflection)
Traveling Crane Spec. Decision of Thermal Stress (3) Review by Check List
Decision Analysis (4) B/M Calculation
Piping Work & (4) Equip. Loading, (3) Support location, (5) Spring Load Calculation
Check List Assembly, Dismantling Installation Method Decision (6) Support Detail Creation
Method (4) Thermal Stress Analysis
(5) Piping & Electrical Review Result, Allowance
/Instrument Cable Route and Comparison (Force & Moment)
Space (5) Civil/Architecture
(6) Machinery, Electrical Information: (Insert, Loading
/Instrument Information Data PF, Local FD'N , etc)
(7) Civil/Architecture (6) Consider prospecting
Information problem in case of Site
Piping Test (Break Flange,
etc. )
SEM - 3069E
ENGINEERING MANUAL
REV. 3
Compressor & Turbine Surroundings
DATE : 2004.08.20 PAGE 24 OF 24
Piping Design Standard

8. Revision History

No. Date Page Reason for Revision


0 1981. 7. 30 (1) Establishment Process
The Standard of Piping Design around Large Compressor
was not available. It resulted in the the difficulty
to standardize the consistency when it comes to Job
execution. So SECL Manual is established according to
Japan TEC co. Bng'g Manual.
(2) Department : Piping Team
Prepared by : Yoo Jae-ryong, Kim Ki-pil
Supervised by : Cheong Young-keun
1 1998.5.10 - Revision Process
It is based on the Piping Team Manual Revision Plan.
It was revised and supplemented according to the error or
items to be supplemented in the process of Job execution..
- Department : Piping Team
Prepared by : Lee Joo-sang
Reviewed by : Kim Ki-pil
Approved by : Lee Myung-hak
2 1998.10. 26 - Revision Process
It was based on Piping Team '98 Major Execution Plan.
- Department : Piping Team
Prepared by : Chang Hong-jin, Lee Joo-sang
Reviewed by : Kim Ki-pil
Approved by : Lee Myung-hak
3 2004.08.20 - Revision Process
Whole Page It revised errors and deleted general explanation from
the manual and it is revised and supplemented by
practical method of actual job and contents
recommended by reference.
- Department : Piping Team
Prepared by : No Hee-kwon
Reviewed by : Kim Chang-rae, Koo Young-hoe,
Ahn Jun-hwan
Approved by : Kim Seok-ki
APPENDIX
Appendix : Compressor Pipe Fixed Point Selection Method SEM - 3069E
REV. : 3
PAGE 1 OF 1

Piping Fixed Point Selection Method is as below to minimize Load and Moment to affect Compressor or
Turbine Nozzle by connecting Pipe. But, be sure to receive the final approval from a person in charge of
Stress Analysis in case it is to be applied to Actual Job Execution because the below is a simplified
method.

1. Fixed Point Selection on plan


As below , if Equipment Nozzle "A" moves as muchx mm in the direction of X by Heat Expansion ,
length is to be made as Fixed Point on Pipe "B" x=.

here,
x : axial direction Nozzle Movement (mm)
: piping expansion ratio (mm/m)
: Distance(m) From Nozzle "A" to
Fixed Point "B"

2. Vertical Fixed Point Selection

As below, if Equipment Nozzle "A" moves in the direction of Y or Z by Heat Expansion, Fixed Point is
to be decided as "C" or "D" according to movement.
APPENDIX
Appendix : Compressor Pipe Construction Method (sample) SEM - 3069E
REV. : 3
PAGE 1 OF 2

Great Care is to be taken in Piping Construction because Compressor piping is big comparing to other
equipment and so Compressor body can be moved by external force of Pipe. Especially, be sure not to
inflict unreasonable force to Compressor body. Tips for Piping Construction in Site is described as below.

1. In case Compressor location is not set up, be sure to leave 1 adjustment place in each direction and
weld from Point ~. ( SR is to be performed in case Welding is required to the part of Stress
Relieve(SR) )

2. After Compressor Location is set up, connect Nozzle Flange and Pipe Flange by using the half of Bolt
quantity and weld Point , temporarily by adjustingS-135, S-136. If necessary, be sure not to put
unreasonable weight on the Compressor body by installing Support(S-138, DS-134). In this case, leave
Lock Pin of Spring Support as it is installed.
3. Weld Point ~ by adjusting each direction. Be sure not to add unreasonable weight in welding.

4. Remove the temporary welding of Point , . In this case, weld Point permanently without
separating Nozzle Flange and Pipe Flange and then handle SR if necessary.

5. Be sure to set Nozzle Flange and Pipe Flange accurately (around half of the whole quantity of bolt),
and check if Piping Alignment Requirements and Flange Distance "T" complies with the below API RP 686
Chapter 6, Paragraph 4.6 standard and weld Point permanently and perform SR.

Item Standard Note


Distance of departing from the center of Equip. &
Max. 1.5mm
Pipe Flange Bolt Hole
Slope between Equip. Flange and Piping Flange Max. 10m/1) Max. 750m

Distance between Flange ("T") Space 1.5mm per Gasket

* Note 1) Flange Outer Diameter Standard

6. Remove Temporary Support installed in Spool No.301-10-01 ~ 06, and install Permanent Support(S-138, DS
-134, DS-133, S-136, S-135, DS-132).

7. Install Permanent Support(DS-131, S-134, RS-152, RS-153) in Spool No.301-10-07 ~ 10

8. Right before operating after Completion of Site Pressure Test and Flushing Work, be sure to adjust
balance by removing Lock Pin(S-134 S-135 S-136 S-138) from a distant place which is
installed in Spring from Compressor.

9. Be sure to perform after approval from SECL's Piping Supervisor in case executing Job from the above
No.2 to 8 Job Execution should be performed with the participation of person in charge of Piping or
Piping Design Construction from SECL in principle.

10. Consideration in Construction


(1) 1F(1 Pass or Root Pass) welding is be done as TIG Welding in principle.
(2) Be sure to weld by 2 workers in the symmetrical location at the same time in principle.
(3) Trimming of Welding is to be performed by Instrumental Process.
(4) Be sure to clean inside Pipe before connecting pipe, weld without foreign matters.
(5) In case of piping installation, check centering by using Dial Gage between Coupling and connect
Pipe after checking the offset is below 3/100mm. But Vendor Requirements has to be taken a priority.
(6) Install Cover in Pipe Flange of Spool No.301-10-01 and manage not to let foreign matters get in.
(7) Be sure to get approval from SECL's Supervisor for other unclear item.
APPENDIX
Appendix : Reference Plot Plan (MOP, 3-Main Compressor) SEM - 3069E
REV. : 3
PAGE 1 OF 4
APPENDIX
Appendix : Reference Plot Plan (GSP-5, Gas Compressor) SEM - 3069E
REV. : 3
PAGE 2 OF 4
APPENDIX
Appendix : Reference Plot Plan (PEMEX-Tula, Gas Compressor) SEM - 3069E
REV. : 3
PAGE 3 OF 4
APPENDIX
Appendix : Reference Plot Plan (IOCL, Gas Compressor) SEM - 3069E
REV. : 3
PAGE 4 OF 4

You might also like