Pear and Aom Complete proposal including posting 21/4/17 Find general information about
it in e-portfoilio Singapore and Malaysia
-Completed
Aom and Pear Start finding the general information 23/04/17 Finding fun facts of Singapore and
about the country Malaysia
-Completed
Pear and Aom Start to find information about 24/04/17 Continue to research about
significant historical figures of historical figures
Malaysia -almost completed [Finish
researching information for people
that need to include but still
consider of adding first prime
minister]
Aom Find the information about the 24/04/17 Continue to research about the
biography of the important people in important people in Singapore
Singapore - Not complete
Pear Research information about holiday 25/04/17 Start finding information about
including national day in Malaysia political system in Malaysia
- Not quite done yet
Aom Continue to Find the information of 25/04/17 Start finding the information about
the important People in Singapore. the event in Singapore
- Not Complete
Aom Complete the information of the 27/04/17 Complete finding the information
important people of Singapore and about the event in Singapore
Start finding the event in Singapore - Not completed
Pear Continue to research about historical 28/04/17 Start to research about the
figure in Malaysia important events that happened in
Malaysia from the beginning to the
present
- Not completed
Aom Complete finding the information 28/04/17 Start to find the information about
about the event of Singapore. the holiday in Singapore.
Aom Completed the information about the 02 - 05/05/17 Buy the material for the Model and
holidays in Singapore. timelines.
- Completed
Aom Find the fun fact about Singapore. 07/05/17 Completed the Fun fact.
- Completed
Pear Start to build the model 07/05/17 Construct the first building of
petronas tower
- Not completed
Aom Start doing the Model 09/05/17 Construct the base of the building.
- Completed
Pear Continue to construct the first 09/05/17 Continue to construct the first
building building -Completed
Aom Start decorating the research to do 11/05/17 Continue to make another tower.
the timeline and continue to make the
model
Pear Begin to construct the second 11/05/17 Continue to construct the second
building building - Not completed
Aom Continue to build the second building 12/05/17 Start building the top part of the
building
- Completed
Pear Continue to construct the second 12/05/17 Begin to build the top part and the
building bridge that connect two towers
together - Completed
Aom Layout the information into 16/05/17 Continue to do the layout and print
piktochart and Decorates out
- Not completed
Aom Finish the designing of the 17/05/17 Finish the decoration, and print out
information in Piktochart and started to design the timeline.
- Not completed
Pear Start to build the timeline, and 18-19/05/17 Finish the timeline.
decorate it. - Not Completed
Aom Start to build the timeline, and 18/05/17 Finish the timeline.
decorate it. - Not Completed
Pear & Aom Continue to make the timeline 19/05/17 Finish the timeline
-Not completed
Pear & Aom Continue to make the timeline 22/05/17 Finish the model
-Completed
Pear & Aom Continue to make the timeline 23/05/17 Finish the timeline & Start doing
e-portfolio
-Not completed
Pear & Aom Continue to make the timeline & 26/05/17 Finish the timeline & E-portfolio
Continue doing the e-portfolio -Not completed