You are on page 1of 51

HVAC, Water, and Other

Critical Utility Qualifications

16th Annual Validation Week


Oct. 25-27th, 2010
Philadelphia, PA
Park Hyatt

CONTACT INFORMATION
for Course Leader

Stephen Nwodo PMP, ASQ-CSQE


Sr. Project Manager
Validation Technologies, Inc.
San Diego, CA
Office: 800-930-9222
Fax: 858-676-3677
Email: validation@validation.org
Website: http://www.validation.org

Validation Technologies Inc. 2

1
PRESENTATION OVERVIEW

9 SUPPORT DOCUMENTATION
9 CONSTRUCTION QUALIFICATION
9 QUALIFICATION OF CRITICAL SYSTEMS
9 ESTABLISHING A ROUTINE
ENVIRONMENTAL PROGRAM
9 TRENDING AND DATA SUMMARY
9 PROBLEM AREAS - UTILITY SYSTEMS
9 REVALIDATION

Validation Technologies Inc. 3

Part 1
Documents to Support
Equipment Qualification
DQ
PQ IQ

OQ
PV

IQ OQ
IQ/OQ Documentation
PQ VC

CQ

2
User Requirements Specifications
(URS)

The URS describes critical installation and


operating parameters and performance
standards that are required for the intended
use of the equipment, and provides the
basis for qualification and maintenance of
the equipment.
The URS documents the design
qualification and rationale for selection of
equipment.

Validation Technologies Inc. 5

Design Specifications

Validation in general is accomplished


first through proper design. Design
specifications for each system are
established based on the engineering
and manufacturer specifications.

A design review and design qualification


(DQ) are indicated as required by many
firms.

Validation Technologies Inc. 6

3
Purchase Requisitions

Document specifying the purchase of an


item and the documentation to support it.

Usually pre-empted by a bid request to


various vendors for cost comparisons.

Should be reviewed by QA or validation prior


to issuance.

Validation Technologies Inc. 7

Construction Documentation

During construction, documents are


generated indicating that items/systems
have been installed. These documents
would be things such as weld certifications,
material certifications, punch lists,
installation inspections, etc.

Validation Technologies Inc. 8

4
Vendor Documentation

These could be any of the following:


Specifications
Cut Sheets
Advertisement
Descriptions
Equipment Drawings
Maintenance Manuals
Vendor Test Protocols
Other manuals
Spare Parts Lists
Validation Technologies Inc. 9

Turnover Package

Documentation collected by the


vendor during the construction
activities to support installation
qualification. (submittals, purchase,
component cut sheets,
certifications, etc.

Validation Technologies Inc. 10

5
Acceptance Testing

FATs are standard tests that are


executed at the factory to verify
proper operations before the
system leaves the plant.
SATs are standard tests that are
executed at the end user site to
verify proper operations before the
system is ready for validation.

Validation Technologies Inc. 11

Piping & Instrumentation Drawings


(P&IDs)
Engineering drawings that indicates
piping and instrumentation size,
type, location, controls, alarms etc.
The base detail drawings for
systems
PFD (Process Flow Diagrams) are
predecessors to P&IDs.

Validation Technologies Inc. 12

6
Isometric Drawings

3-D renderings of piping diagrams. Usually


developed for the purpose of weld location.
Typically drawn for sanitary piping systems.

Validation Technologies Inc. 13

Equipment/Instrument Lists

Engineering documents, which lists all the


equipment and instruments associated with the
design of the facility. Typically these lists are
generated from the P&IDs. The instrument list
may not be an indicator of criticality. A separate
list should exist for this purpose.

Validation Technologies Inc. 14

7
Engineering Change Management
Documents

Engineering change management


system is used during the
construction and installation phase
of the project. Implemented before
systems qualification.

Validation Technologies Inc. 15

Calibration Reports

Calibration is a comparison of a
measurement system or device with
another, known good measurement
system or device (standard)

Validation Technologies Inc. 16

8
Standard Operating Procedures
(SOP)

A document required by cGMP


A document used to give
instruction typically by step, on how
to perform a specific task or
operation.

Validation Technologies Inc. 17

Master Plans

Validation Master Plan


A document which summarizes the firms overall
philosophy, intentions and approach for establishing the
reliability and consistency of the equipment, systems, and
processes in the facility, as well as the ongoing program for
maintaining a validated state of control.
Commissioning Plan
A document which summarizes the firms intentions,
philosophies, and policies regarding the commissioning or
facility equipment and systems.

Validation Technologies Inc. 18

9
Qualification Protocol

Establishing documented evidence which provides a high


degree of assurance that a specific process will consistently
produce a product, meeting its pre-determined specifications
and quality attributes1

Each of these systems, including many others, must be


evaluated in terms of installation and performance.

1. FDA definition (Guideline on Process


Validation)

Validation Technologies Inc. 19

Part 2
Critical Utility Project
Strategy

Plan the Work and Work the Plan

10
PROGRAMS REQUIRED FOR FACILITY & CRITICAL
UTILITIES QUALIFICATIONS

PROJECT DESIGN SPECIFICATION


VALIDATION MASTER PLAN
PROJECT SCHEDULE
CONSTRUCTION QUALIFICATION PACKAGES
INSTALLATION QUALIFICATION PROTOCOLS
FACILITY STARTUP/COMMISSIONING
STANDARD OPERATING PROCEDURES
CALIBRATION & MAINTENANCE PROGRAM
OPERATIONAL QUALIFICATION PROTOCOLS
ANALYTICAL METHODS VALIDATED
PERFORMANCE QUALIFICATION

Validation Technologies Inc. 21

VALIDATION MASTER PLAN

VALIDATION PROJECT ROAD MAP


VALIDATION PROJECT DESCRIPTION
FACILITY & PROCESS DESCRIPTION
EQUIPMENT & UTILITY LIST
VALIDATION PROGRAM
PROJECT RESPONSIBILITIES
REFERENCE DOCUMENTS
GENERAL ACCEPTANCE CRITERIA

Validation Technologies Inc. 22

11
PROJECT SCHEDULE
DEFINED CRITICAL PATHS
CONSTRUCTION ACTIVITIES
COLLECTION OF CONSTRUCTION QUALIFICATION CQ
DATA
DEVELOPMENT OF PROTOCOL FORMAT
WRITE IQ & OQ PROTOCOLS
EQUIPMENT INSTALLATION ACTIVITIES
EXECUTION OF IQ PROTOCOLS
COMMISSION OF SYSTEM
EXECUTION OF OQ PROTOCOLS
ANALYTICAL METHODS VALIDATED
WRITE & EXECUTE PERFORMANCE QUALIFICATIONS

Validation Technologies Inc. 23

GENERAL PROJECT MANAGEMENT

Contractor Selection Process

Proper education, experience, and training to


perform their job function. A rsum is the
document that shows this for your V/Q & C
contractors. Supplement training with
pharmaceutical manufacturers specific procedures
and/or policies. Be sure the rsum is filed in the
permanent record.

Validation Technologies Inc. 24

12
Facilities VMP

This plan describes what (in general )


will be done to qualify the
facilities/utilities.
It references specific protocols that are
to be developed for the specific things
to be qualified or validated (such as the
HVAC and the Process water systems.)
The real specific information should be
in the protocols not the plan.

Validation Technologies Inc. 25

Validation of Facilities/Utilities

With the exception of the performance


qualification of water systems, which requires
a full year of test data, the Validation Master
Plan (VMP) for the facilities and utilities is
completed prior to beginning the work of
validating the manufacturing processes.

Validation Technologies Inc. 26

13
CONSTRUCTION QUALIFICATION PACKAGE

CQ DATA COLLECTION
DAILY SITE INSPECTION SHEETS
VIDEO & PHOTO OF CONSTRUCTION SITE
PURCHASE ORDERS & SPECIFICATIONS
MATERIAL SAFETY DATA SHEETS
DRAWING LIST
CODE COMPLIANCE
SITE TEST VERIFICATION
CLEANING REPORTS

Validation Technologies Inc. 27

VALIDATION DOCUMENT FLOW


S p e c if i c a ti o n :
S y st e m R e q u i r e m e n t
D o c u m e n t,
D e s ig n ,
D r aw i n g ,
E n gi n e e r , D e s ig n
P u r c h a se ,
C o n s tr u c ti o n , Q u a lif ic a t io n
U s er R eq .
V e n d o r S u b m i t ta l s
M an u al s

P u r c h as e O r d e r s ,
P r oj e c t S p e c .,
P u r c h as e S p e c .,
D r a w i n g s,
C o n s t r u c t io n
T e st R e p o r ts , Q u a lif ic a t io n
W e l d i n g P r ogr am ,
C l ea ni ng R epo rts ,
P r e s s u r e T e s t,
M S D S,
C o n st r u c t i o n
B u ll e t i n s ,

I n s t a lla t io n
Q u a lif ic a t io n
Q U A L I T Y R E V IE W
P ro g r a m S u m m a r y D o c u m e n t
A p p r o v a l/ N o n - A c c e p t a n c e o f
S y s te m
C h a n g e C o n t ro l R e v ie w

O p e r a t io n a l
Q u a lif ic a t io n

P e r fo r m a n c e
Q u a lif ic a t io n
M e th o d s
V a lid a t io n

F i n al R e p or t

B ac k g r ou n d
T e st R e s u l t s S u m m a r y
E x h i b it s, G r a p h , P h o t o s
D a t a T r e n d in g / A n a l y s is
S t a t i st i c a l P r o c e s s C o n t r o l
C a l ib r a ti o n
D e v ia t io n s , D i s c r e p a n c ie s

R e vi e w & S u m m ar y of
A c c e p ta n c e C r it e r io n

C o n c l u s io n / C e r t if ic a t i o n
(A c c e p ta n c e / N o n -
A c c e p ta n c e )

Validation Technologies Inc. 28

14
INSTALLATION QUALIFICATION
PROTOCOL FOR CRITICAL UTILITIES
OBJECTIVE
IDENTIFICATION
SYSTEM DESCRIPTION
REFERENCES
RESPONSIBILITIES
PROCEDURE
ACCEPTANCE CRITERIA
SYSTEM COMPONENT INSPECTION
DRAWING
COMMENTS
DEVIATION/EXCEPTIONAL CONDITION

Validation Technologies Inc. 29

STANDARD OPERATING PROCEDURE


FOR CRITICAL UTILITIES

OPERATION AND MAINTENANCE


IQ, OQ & PQ PROCEDURES
FINAL REPORT PROCEDURE
CHANGE CONTROL
CALIBRATION
TEST METHODS
REVALIDATION PROCEDURE

Validation Technologies Inc. 30

15
CALIBRATION FOR CRITICAL
UTILITIES

CALIBRATION PROGRAM
SCHEDULE CALIBRATION FOR CRITICAL
INSTRUMENTS
LIST OF CRITICAL INSTRUMENTS

Validation Technologies Inc. 31

OPERATIONAL QUALIFICATION
PROTOCOL FOR CRITICAL UTILITIES
OBJECTIVE
IDENTIFICATION
SYSTEM FUNCTIONAL DESCRIPTION
REFERENCES
RESPONSIBILITIES
PROCEDURE
ACCEPTANCE CRITERIA
OPERATIONAL QUALIFICATION TEST
COMMENTS
DEVIATION/EXCEPTIONAL CONDITION
ATTACHMENTS

Validation Technologies Inc. 32

16
TEST METHODS QUALIFICATION

VALIDATED BEFORE THE START OF PQS


INTRODUCTION
METHODS
EQUIPMENT & MATERIALS
PROCEDURE
REPORT

Validation Technologies Inc. 33

Part 3
Commissioning and
Construction
Program

17
Good Engineering Practice (GEP)

Established Engineering methods and


standards that are applied throughout the
project lifecycle to deliver appropriate
cost-effective solutions

Validation Technologies Inc. 35

Good Engineering Practice (GEP)


GEP is comprised of the following:
Professional and competent project management
(processes, procedures, and staff)
Professional and competent engineering design,
procurement, construction and commissioning
Full consideration of applicable safety, health, and
environmental statutory requirements
Full consideration of operation and maintenance
requirements
Full consideration of recognized standards and guidance
Appropriate documentation for ongoing operation and
maintenance, and to demonstrate compliance with
applicable regulations and codes.

Validation Technologies Inc. 36

18
Good Engineering Practice (GEP)
GEP project scope
Documentation
Organization and Communication
Requirements Phase
Design Phase
Construction Phase
Project Controls
Commissioning and Qualification
Project Closeout and Turnover

Validation Technologies Inc. 37

Commissioning

A well planned, documented, and


managed engineering approach to the
start-up and turnover of Facilities,
systems, and equipment to the End User
that results in a safe and functional
environment that meets established
design requirements and stakeholders
expectations.

Validation Technologies Inc. 38

19
Commissioning

Term Commissioning typical


encompasses the following tasks:
Physical Completion and Inspection
Setting to Work
Regulation and Adjustment
Testing and Performance testing
Planning and preparation associated with
managing the above activities

Validation Technologies Inc. 39

Commissioning Strategy
Commissioning Strategy should contain the
following items: (Direct Impact Systems)
Scope
Plan Approval and Changes
System Overview
Deliverables
Roles and Responsibilities
Inspection (Construction and Installation Oversight)
System Walk Down
Regulations and Adjustment
Testing and Performance
Training
Turnover
Commissioning Plan Close Out

ISPE Commission and


Qualification Guidance Validation Technologies Inc. 40

20
Commissioning Testing
9 Organizing and Planning
9 Factory Acceptance Test (FAT)
9 Site Acceptance Testing (SAT)
9 Static Testing (pre-commissioning)
9 Operator Training
9 Walk Down & Tagging
9 Full Functional Testing
9 As-Built Documentation
9 System & Equipment Manuals
9 Spare Parts Management

Validation Technologies Inc. 41

Commissioning Plan
Commissioning Plan should contain the following
deliverables: (Direct Impact Systems)
Commissioning Plan
Commissioning Schedule
Commissioning Budget
Overall Test Plan
Factory Acceptance Test/Report
Site Acceptance Test/Report
Inspection Plan/Report
Functional Test/Report
System Test Summary Reports
Commissioning Summary Reports

Validation Technologies Inc. 42

21
Relationship between Systems
and Components

Critical Non-Critical
Direct
Impact
5 5
Systems

In-Direct/ X
No Impact
5
GEP only
Validation Technologies Inc. GEP + Qualification Practices 43

System Impact and Component


Criticality
Indirect Impact or No Impact system are
comprised of non-critical components only
Direct Impact system have both critical and
non-critical components. (Components
deemed non-critical may be managed within
Good Engineering Practices -GEP alone)
Design for Impact reduces the scope of the
system and components to Qualification
Practices allowing appropriate focus on the
components presenting a risk to product quality
Should an Indirect Impact or No Impact system
incorporate one or more critical components,
either the system has been misclassified or the
component was wrongly assessed.
Validation Technologies Inc. 44

22
Part 4
Qualification of
Critical Utilities
Systems

Design, Construct, Commission then


Qualify

Critical Utility Qualification

Construction Qualification
During construction, document procurement and
verification of construction activities, are critical
components of a successful Installation Qualification
(IQ).
Test Reports
Material Certifications
Purchase Specification & Orders
State and Local Code Compliance
ASME, ANSI and other Certifications
Pipe Specifications
Cleaning and Passivation Reports
Stainless Steel Weld Documentation
Vendor/Manufacturer's Submittals
Manufacturer's Mechanical Specifications
Instrumentation Specifications
Validation Technologies Inc. 46

23
Critical Utility Qualification

Installation Qualification - is a documented


plan for the performance of inspections and
the collection of documentation to verify
static attributes of a system.
System Location
System Description
Major Components Identification Summary
Field Inspection Report- Comparison of Actual to
Specified
Instrumentation List
Spare Parts List
Documentation/Drawings List

Validation Technologies Inc. 47

Critical Utility Qualification

Operational Qualification (OQ) - is a documented plan for the


performance of inspections and tests to verify specified
dynamic attributes of a system.
SOP Review
Calibration Review
Test of Critical Alarms
Test of Controls
Test of Interlocks
Start Up/Shutdown Sequence Verifications
Normal Run Mode Verification - Monitoring Applicable
Indications:
Pressure
Temperature
Time
Resistivity/Conductivity
Flow
pH

Validation Technologies Inc. 48

24
Critical Utility Qualification

Performance Qualification (PQ) - is a documented


plan for the execution of tests to demonstrate the
effectiveness and reproducibility of a
system/process as a fully integrated functional
entity.
All installed critical instruments shall be calibrated prior to
execution of the protocol.
All test instruments used to execute the protocol shall be
calibrated and certified prior to use.
Test methods, analytical procedures and sampling
techniques, when not defined in a protocol, shall be
written and approved as SOPs.
The system can consistently meet its predetermined
acceptance criteria.
Validation Technologies Inc. 49

PERFORMANCE QUALIFICATION PROTOCOL


FOR CRITICAL UTILITIES

OBJECTIVE
IDENTIFICATION
SYSTEM DESCRIPTION
REFERENCES
RESPONSIBILITIES
PROCEDURE
ACCEPTANCE CRITERIA
PERFORMANCE TESTS
COMMENTS
DEVIATION/EXCEPTIONAL CONDITION

Validation Technologies Inc. 50

25
Critical Utility Qualification

Example Performance Qualification (PQ) -


Standard Testing Intervals
Water For Injection Systems - 30 to 60 Days (30
- 40 days Standard @ Shut Down Recover Test)
Purified Water Systems - 30 Days
Clean Steam Systems - 30 Days
Gases/Clean Dry Air Systems - 14 Days or three
lots
HVAC System (Controlled Environment)-
Baseline (Before cleaning), Static States,
Dynamic (20 -30 days)

Validation Technologies Inc. 51

Part 5
Validation of Water
Systems

Water is used in aspects of GMP


Manufacturing Operations

26
Validation of Critical Water Systems

FDA Requirements: Phase 1


All water systems should have
documentation containing a system
description and accurate drawing.

The drawing needs to show all equipment in


the systems from water input to points of
use. It should also show all sampling points
and their designations.

Validation Technologies Inc. 53

Validation of Critical Water Systems

FDA Requirements: Phase 1


After all the equipment and piping has
been verified as installed correctly and
working as specified, the initial phase of
the water system validation can begin.

Validation Technologies Inc. 54

27
Validation of Critical Water Systems

FDA Requirements: Phase 1

During the initial phase the operational


parameters and cleaning/sanitation
procedures and frequencies will be
developed. Sampling should be daily after
each step in the purification process and at
each point of use for two to four weeks.

Validation Technologies Inc. 55

Validation of Critical Water Systems

FDA Requirements: Phase 1


The sampling procedures for point of use should
reflect how they are taken, e.g. use of hose, and
time for flushing. At the end of the two (2) or
four (4) weeks the firm should have developed
its SOPs for operation and maintenance of the
water system.

Validation Technologies Inc. 56

28
Validation of Critical Water Systems

FDA Requirements: Phase 2


The second phase of the water system
validation is to demonstrate that the system
will consistently produce the desired water
quality when operated in conformance with
SOPs.

Validation Technologies Inc. 57

Validation of Critical Water Systems

FDA Requirements: Phase 2

The sampling is performed as in the initial


phase and for the same period . At the end
of this phase the data should demonstrate
that the system will consistently produce the
desired quality of water.

Validation Technologies Inc. 58

29
Validation of Critical Water Systems

FDA Requirements: Phase 3


The third phase of validation is designed to
demonstrate that when the water system is
operated, in accordance with the SOPs,
over a long period of time it will consistently
produce water of desired quality.

Validation Technologies Inc. 59

Validation of Critical Water Systems

FDA Requirements: Phase 3


Any variations in quality of the feedwater,
that could affect the operation and ultimately
the water quality, will be noticed during this
phase of the validation.

Validation Technologies Inc. 60

30
Validation of Critical Water Systems

FDA Requirements: Phase 3


Sampling is performed according to routine
procedures and frequencies.

For Water for Injection systems samples


should be taken daily from a minimum of
one point of use, with all points of use
tested weekly.

Validation Technologies Inc. 61

Validation of Critical Water Systems

FDA Requirements: Phase 3


The validation of the water system is
completed when the firm has collected data
for a full year.

The FDA states that while the above


validation scheme is not the only way a
system can be validated, it contains the
necessary elements for validation of a water
system.

Validation Technologies Inc. 62

31
Validation of Critical Water Systems

FDA Requirements: Phase 3


First, there must be data to support the
SOPs.

Second, there must be data demonstrating


that the SOPs are valid and that the system
is capable of consistently producing water
that meets the desired specifications.

Validation Technologies Inc. 63

Validation of Critical Water Systems

FDA Requirements: Phase 3


Finally, there must be data to demonstrate
that seasonal variations in the feedwater do
not adversely affect the operation of the
system or the water quality. This last part of
the validation is the compilation of the data,
with any conclusions into the final report.

Validation Technologies Inc. 64

32
Microbiological/Chemical Limits

Test Portable USP PW USP WFI


TOC N/A 500ppbC USP <643>
Cond (S/cm) N/A 4.7 -5.8 USP <645>
Bacteria1 500cfu/ml 100cfu/ml 10cfu/100ml
Endo N/A N/S 0.25EU/ml

1- Total bacteria count free from objectionable organism

USP 32-NF27 2009 www.usp.org


FDA Guide to Inspections of High Purity Water Systems (7/93)
FDA Guide To Inspections of Microbiological Pharmaceutical Quality Control Laboratories (May, 1993)
CFU = Colony Forming Units
N/S = Not Specified
N/A = Not applicable

Validation Technologies Inc. 65

Critical Utility Qualification

Performance Qualification (PQ) -


Standard Testing Intervals
Water For Injection Systems - 30 to 60 Days (20
- 40 days Standard @ Shut Down Recover Test)
Purified Water Systems - 30 Days

Validation Technologies Inc. 66

33
ESTABLISHING ENVIRONMENTAL
MONITORING PROGRAM

When establishing a routine


environmental monitoring program, the
PQ study data should be the starting point
for determining the sampling sites and
testing frequencies.

Validation Technologies Inc. 67

PURIFIED WATER SYSTEMS


ENVIRONMENTAL MONITORING PROGRAM

Sample Site and Frequencies Determination


For Water for Injection systems samples
should be taken daily from all point of use.
For Purified Water systems samples should
be taken daily from a minimum of one point
of use, with all points of use tested within a
week.

Validation Technologies Inc. 68

34
Part 5
Validation of Clean
Steam Systems

Clean Steam is used in certain aspects of


GMP Manufacturing Operations

Validation of Critical Water Systems

FDA Requirements: Phase 1, 2 & 3


Same requirements as WFI system
Qualification.

Validation Technologies Inc. 70

35
Validation of Critical Water Systems

FDA Requirements: Phase 3


The validation of the clean steam system is
completed when the firm has collected data
for a full year.

Validation Technologies Inc. 71

CLEAN STEAM SYSTEM ENVIRONMENTAL


MONITORING PROGRAM

Sample Site and Frequencies Determination


For Clean Steam systems samples should be
before manufacturing process i.e. SIP,
autoclave, etc. and from a minimum of one point
of use, with all points of use tested bi-weekly.

Validation Technologies Inc. 72

36
CLEAN STEAM SPECIFICATIONS
Table: Microbiological/Chemical Limits
Tests Clean Steam

TOC 500 ppb


Conductivity Current USP Specifications/
method
Bacteria 10 cfu/100mL
Endotoxins 0.25 EU/mL
EN 285 Below

Non-condensable gases 3.5%


Dryness 0.90
Superheat Not greater than 5oC

Validation Technologies Inc. 73

Part 5
Validation of
Compressed Gas
Systems

There are many different types of gases


used in a GMP manufacturing operation

37
Compressed Gases Usage in
Pharmaceutical Production
Compressed Gases Requirements
Preserve the Status of product
Drying after cleaning
Assist Cell Growth
Instrument Actuation
Move Fluid

Validation Technologies Inc. 75

Compressed Gases Usage in


Pharmaceutical Production
Types Of Gases
Clean Dry Air
Nitrogen
Carbon Dioxide
Helium
Oxygen
Argon

Validation Technologies Inc. 76

38
COMPRESSED GAS SYSTEMS
ENVIRONMENTAL MONITORING PROGRAM

Sample Site and Frequencies Determination


For compressed gas systems samples should
be taken daily from a minimum of one point
of use, with all points of use tested weekly.
(Dew Point and Oil)
One sample per representative sample point
taken on any three non-consecutive days
distributed over the 14-day (initial PQ) period
for a total of three samples per representative
sample point (particulates only)

Validation Technologies Inc. 77

COMPRESSED GAS SPECIFICATIONS

Table: Microbiological/Chemical Limits


Tests Compress Gas

Dew Point < =-40 oC


Hydrocarbon as Oil < 1 ppm
Mist
Gas Content Current USP
Specifications/
method for Purity
Bacteria < 0.1 CFU/ft3
Non-Viable Particulate: Room Classification
cfu; = Colony Forming Units

Validation Technologies Inc. 78

39
Part 6
Validation of HVAC
Systems

HVAC is used in aspects of GMP


Manufacturing Operations

Clean Room Standards


This ISO committee will produce 10 new standards
documents that relate to cleanrooms or clean
zones (described below). The first two standards
have been published: ISO 14644-1 and -2.
The first document, ISO 14644-1, Cleanrooms
and associated controlled environments Part 1:
Classification of airborne particulates has been
released as a final document.
The second document, ISO 14644-2, Cleanrooms
and associated controlled environments Part 2:
Testing and monitoring to prove continued
compliance with ISO 14644-1; has been released
as a final document.

Validation Technologies Inc. 80

40
Clean Room Standards
By U.S. law, FS 209E can be superseded by new
international standards. It is expected that 209E will
be in use in some industries through the next five
years, but that eventually it will be replaced
globally by ISO 14644-1.

IES RP-CC-0006 This is a very popular test


standard that provides test procedures for most
environmental parameters that may be required,
some of these procedures include filter integrity
testing, room pressurization, temperature and
relative humidity, room recovery testing to name a
few. (See also NSF-49, ISO 14644-3)

Validation Technologies Inc. 81

Clean Room Standards


The cleanliness classification levels defined by FS209E
and ISO 14644-1 are approximately equal, except the new
ISO standard uses new class designations, a metric
measure of air volume and adds three additional classes

The second new ISO standard, ISO 14644-2, gives


requirements for monitoring a cleanroom or clean zone
to provide evidence of its continued compliance with
ISO 14644-1.

Validation Technologies Inc. 82

41
Clean Room Certification
Clean Room Certification Testing
Differential Air Flow
Humidity/Temperature
Supply Air Volume/Room Air Change Rate
Room Differential Pressures
DOP Test of HEPA Filters
Room Non-Viable Particulate Counts
Light Levels
Noise Levels
Recovery Time
Unidirectional and Parallelism
Enclosure Induction

Validation Technologies Inc. 83

Clean Room Certification

Clean Room Certification Testing


Establishing of Sampling location (ISO 14644-1
Annex B)
Derive the minimum number of sampling point
locations from equation:
NL = A
NL is the minimum number of sampling point locations
(rounded up to whole number).
A is the area of the cleanroom or clean zone in square
meters

Validation Technologies Inc. 84

42
Typical Clean Room Performance
Tests:
Non-
Unidirectional
Test Procedure Unidirectional Comments
Airflow Room
Airflow Room
This test may be performed
Supply Volume A,B,C A,B,C with an air velocity meter or
flow hood
Using an aerosol challenge
Filter Leak Test A,B A,B depending on product
sensitivity
Performed with an airborne
Airborne Particle particle counter with size
A,B,C A,B,C
Count sensitivity suitable for room
classification
Room Pressurization A,B,C A,B,C Using digital micromanometer
Using Dry Ice Fogger and
Room Airflow
A,B A,B visual, still photo or video tape
Uniformity
recording.
Using particle generator and
Room Recovery Test A,B A,B
airborne particle counter
A - Indicates the test is best performed in an "As Built" condition.
B - Indicates the test is best performed in an "At Rest" condition.
C - Indicates the test is best performed in an "Operational" condition
Validation Technologies Inc. 85

Typical Clean Room Performance


Tests:
Non-
Unidirectional
Test Procedure Unidirectional Comments
Airflow Room
Airflow Room
Room Recovery Using particle generator and
A,B A,B
Test airborne particle counter
Particle Fallout Using fallout plate monitors at
A,B,C A,B,C
Test critical locations
Room Lighting Using digital photometer per
A,B,C A,B,C
Level IES handbook
Generally performed for
Room Noise
A,B,C A,B,C contractual compliance or
Level
safety requirements.
Taken at each particle count
Temperature &
A,B,C A,B,C location or long term trend
Humidity
studies as required
Generally performed for
Vibration Level A,B,C A,B,C contractual compliance or
safety requirements.
Using RCS samplers, contact
Bioburden Test A,B,C A,B,C
plates or fallout plates.
Validation Technologies Inc. 86

43
Monitoring Program

Controls/Alarms reports verification


and review (procedure)
Weekly reports
Alert vs Action Limits
Failure investigations
Laboratory testing viable and non-
viable counts
Analysis of Trends (Quarterly)
Alert Limits
Refer to ISO-14644-2 and 14644-3 for
frequency guidelines and test
equipment recommendations

Validation Technologies Inc. 87

Maintenance Requirements

Preventive Maintenance procedures are being


followed
Repairs equivalent replacement parts
Changes following Change Control procedure

Validation Technologies Inc. 88

44
Calibration of Instrumentation

NIST Traceability
Calibration procedures per type of
instrument
Control software/hardware maintained as
per procedures

Validation Technologies Inc. 89

HVAC SYSTEMS ENVIRONMENTAL


MONITORING PROGRAM

Sample Site and Frequencies Determination


Would the act of sampling at a given site disturb the
environment sufficiently to cause erroneous data or
possibly cause the product to be contaminated?
At which site would the potential of microbial
contamination most likely affect product quality
adversely?
During the PQ study which sites were highest in
microbial contaminates.
What sites would be the most difficult to clean?
Should site selection involve statistical design or
should it be based on a grid profile?
How often is a particular area or process used?

Validation Technologies Inc. 90

45
CONTROLLED ENVIRONMENT

Nonviable (ft3) Viable


Classifications (ft3)
0.5 m 5.0 m (CFUsa)
Class 100 (ISO 5) 100 (3,520/m3) 0 (29/m3) 0.1
Class 10,000 (ISO 7) 10,000 (352,000 /m3) 70 (293 m3) 0.5
3
Class 100,000 (ISO 8) 100,000 700 (29,300/m ) 2.5
(3,520,000/m3)
Airborne nonviable and viable particulate class limits
a
Colony-Forming Units

Validation Technologies Inc. 91

SURFACE MONITORING

Table 2: USPs < 1116> microbial levels for Surface Monitoring


Classifications Zone Surface Personnel Frequency of
CFU/ 2 in2 CFU/ 2 in2 UP Montoring
Critical Area M 3.5 3 3 - gloves
Class 100 (floor/except) (5-mask/gown) Each Shift
Non-critical M 5.5 5 5-gloves Each Shift1
Class 10,000 (10 floor) (10-mask/gown) 2x/week2
Support Areas M 6.5 20 15-gloves Weekly
Class 100,000 (30-floor) (30-masks/gown)

1
Adjacent to Class 100
2
Support Areas - Product

Validation Technologies Inc. 92

46
Part 7
Maintenance
Program for Critical
Utility Systems

Maintenance of Critical Utility Systems


insure the life cycle approach to validation

CHANGE CONTROL PROGRAM

Change Control Program (CCP) Maintains Utility


Systems Life Cycle Approach To Validations
Supports Revalidation Activities.
Should have established Change Control Program
which includes critical review process when
changes are made to any critical utility system.
CCP should include changes made and extent of
validation required.

Validation Technologies Inc. 94

47
REVALIDATION PROGRAM

Annual review of change control forms for each


critical utility system.

Annual review of the maintenance and cleaning


logs associated with each critical utility system.
Annual review of routine environmental monitoring
data.
Annual abbreviated PQ study may be required
under certain conditions.

Validation Technologies Inc. 95

VALIDATION MAINTENANCE PROGRAM

Once the critical utility systems are


validated and turned over
Engineering/Facilities, Manufacturing and
QA will be responsible for maintaining the
validated state of each systems.

Validation Technologies Inc. 96

48
VALIDATION MAINTENANCE PROGRAM
(CONT.)
Validation Maintenance Requirements:
1. System Specific Operation, Maintenance, Cleaning Procedures
2. System Specific Routine Monitoring Programs
3. Trend Analysis
4. Calibration Program
5. Preventive Maintenance Program
6. Change Control Program
7. QA Auditing
8. Deviation /Investigation Reporting
9. Revalidation Program

Validation Technologies Inc. 97

PROBLEM AREAS - UTILITY SYSTEMS

No diagrams provided, no narratives


Diagrams not detailed
Validation data summaries insufficient
monitoring too infrequent
sampling plan inadequate
monitoring not performed during production
inappropriate parameter tested
validation period too short
inadequate alert and action limits and specs

Validation Technologies Inc. 98

49
PROBLEM AREAS - UTILITY SYSTEMS

Validation data summaries insufficient


no SOP for corrective actions
no historical data base development
No discussion of system / equipment
maintenance or calibration
Inadequate proposal for routine monitoring
program

Validation Technologies Inc. 99

SUMMARY

Project Strategy
Qualification of critical utility systems
Establishing routine environmental program
Problem areas
Revalidation

Validation Technologies Inc. 100

50
Thank you

Validation Technologies Inc. 101

51

You might also like