Gharo Cluster
80 MW 120 MW
(200 MW)
Gharo Cluster
85 MW 115 MW
(200 MW)
Gharo Cluster
150 MW 50 MW
(200 MW)
Recommendations:
1. Two Wind Power Plants (WPPs) i.e. 2x50MW WPPs from Gharo Cluster should be connected
to 220 kV Jhimpir.
2. The 132 kV circuits Jhimpir Kotri, Jhimpir Thatta, Thatta Sujawal should be re-
habilitated immediately especially 132 kV Jhimpir - Kotri line.
3. The generation of 18.8 MW Thatta PP and 20 MW Lucky PP (Kalu Kohar) should be kept
off bar.
4. Load Management of Thatta, Nooriabad and associated grid stations may be exempted.
5. The 132kV line openings of Phuleli Hala Road, Hyd NTPS Hala Road, Latifabad TM
Khan Road, Kotri Site Kohsar should be kept open.
6. 132 kV TM Khan TM Khan Road line should be energized in consultation with GSO
HESCO Hyderabad.