a) Updated/latest SLD with lengths and name of conductor written on it.

b) Monthly statement showing maximum load of Transmission Lines.


c) Monthly statement showing maximum load of Transformers.
d) Bus Bar capacity/name of bus bar conductor and arrangement of bus bars at grid
stations.
e) Latest in service capacitor bank statement of 132 and 11 kV.
f) Coincident load of all grid stations on 03-06-2017 at 2100 hrs (System Peak)
g) Coincident load of all grid stations on time when the peak of PESCO occurred.
h) Any limitations of transmission line, Power Transformer, CT ratio, Jumper etc.
i) MW, MVAR, pf, amps and voltage of each grid station.
j) Rating of switchgear installed at each grid station.
k) Generation at 132 kV and/or below.