Hidro testing jsa.

Activities hazard
control measure
Foarm work. And its precaution

and back strain for steel fixers

A planned, written health and safety method statement must be prepared before work commences
and all associated with the work made aware of its contents. It must then be followed. Any deviations
from the method statement must be communicated to all concerned.

Workers must be provided with safe access to the work.


Guard rails must be put in place as work progresses
Access ladders must be properly erected, tied and project at least 1 metre above the landing
platform.
Ladders or an access scaffold must be used for access.
Equipment must be in good order before use. Original manufacturers pins must be used in
adjustable props.
Formwork, falsework and temporary supports must be checked, properly tied, footed, braced
and supported before loading and before pouring walls or columns.
Workers must be protected from wet concrete by use of protective gloves and boots and
from the effects of silica dust by avoiding the need to scabble by using a retarder or by the
provision of respirators.
There is a planned striking procedure that everyone is made aware of before the work
commences.