PROGRESS TAGET FOR THE MONTH OF AUG

(BASED ON AVAILABLE RESOURCES)

Mr. Sunil
No. of Weekly Form work
Activity Description Program Per Team Teams Total Manpower Qty per 2B Productivity Target Till 30/8/17 sets
Program Skilled Helpers Total Skilled Helpers Total
Footing Rft 2 Days 7 7 14 3 20 20 41 8.12 0.3 9 33
Plinth Beam Rft 2 Days 5 6 11 2 11 12 23 6.56 0.3 6 22
Neck Columns Rft 1 Day 5 6 11 2 11 12 23 3.29 0.3 12 22
Footing Shuttering 2 Days 12 6 18 2 24 12 36 254 7 3 11 2
Plinth Beams Shuttering 3 Days 17 9 26 1 17 9 26 550 7 1 4 1
Neck Columns Shuttering 2 Days 5 3 8 1 5 3 8 110 7 2 6 0

Mr. Srinivas
No. of Weekly Form work
Activity Description Program Per Team Teams Total Manpower Qty per 2B Productivity Target Till 30/8/17 sets
Program Skilled Helpers Total Skilled Helpers Total
Footing Rft 2 Days 7 7 14 3 20 20 41 8.12 0.3 9 33
Plinth Beam Rft 2 Days 5 6 11 2 11 12 23 6.56 0.3 6 22
Neck Columns Rft 1 Day 5 6 11 2 11 12 23 3.29 0.3 12 22
Footing Shuttering 2 Days 12 6 18 2 24 12 36 254 7 3 11 2
Plinth Beams Shuttering 3 Days 17 9 26 1 17 9 26 550 7 1 4 1
Neck Columns Shuttering 2 Days 5 3 8 1 5 3 8 110 7 2 6 0