You are on page 1of 3

1 December 2014

Ref: AFC/AFF/AC586/L/0000
Page: 1 of 1

Al Fahad Tiles & Mosaic Factory


P.O.Box – 24087
Dubai, UAE

Attn : Mr. Surendran – Design & Technical Manager

Proj : HODP-PR-5002 - Hotel 1 at City Walk

Subj : Stone works Package


Delays to Contract Programme

Dear Sir,

As advised on numerous occasions / meetings, both verbally and by Email, AFC are becoming
increasingly concerned regarding your current level of Delays in terms of Technical submittals and
approvals which are delaying following activities.

1. Finalization of Scope of Work


2. Shop Drawings Submittals
3. Technical Submittals
4. Materials Submittals
5. Delay in delivery of materials to Site

Please refer the Time line of your package works shows the delay in actions in terms of Technical submittals
and approvals. M/s Al Fahad Tiles & Mosaic Factory had sufficient time to submit all the drawings and technical
submittals to get approval from Consultant ahead of the contract programme based on the Pre-let issued
dated 22/09/2014.

S.No Description of works Actioned by Date Remarks


18 May 2014
1 Final Agreed Quote issued Al Fahad 24 May 2014
11 Aug 2014

2 LOI Issued to M/s Al Fahad AFC LOI not required

3 Pre-Contract Meeting AFC/Al Fahad N/A

Material submission & approval as per


4 Al Fahad 17 Sep 2014
programme
In the pre-let meeting it is noted that all
5 Pre - Let meeting AFC/Al Fahad 22 Sep 2014 the works should be as per contract
programme.

6 Kick-off Meeting with Design Department AFC/Al Fahad 22 Sep 2014

Agreed Minutes sent to M/s Al Fahad for


7 AFC 25 Sep 2014
signature

Shop Drawings submission & approvals as


8 Al Fahad 09 Oct 2014
per Contract Programme
1 December 2014
Ref: AFC/AFF/AC586/L/0000
Page: 1 of 2

Sign / stamp pre-let returned by M/s Al


9 Al Fahad 13 Oct 2014
Fahad

Material and Procurement log submitted


10 Al Fahad 23 Oct 2014
by M/s Al Fahad

Contract Issued to M/s Al Fahad for


11 AFC 18 Nov 2014
signature

Contract signed & returned by M/s Al


12 Al Fahad Awaiting - Not yet returned
Fahad

25 Nov 2014 Under review by AFC submitted on


13 All Shop Drawings submittal Al Fahad
Planned date 29/11/2014

26 Nov 2014 Under review by AFC submitted on


14 Material submittal by M/s Al Fahad Al Fahad
Planned date 25/11/2014

15 Further Programme / Technical Meeting AFC/Al Fahad To be confirmed

Including mitigation of the delay - Yet to be


16 Construction Programme submission Al Fahad
submitted

Delivery Date of Materials - As per


17 Al Fahad 16 Jun 2015
programme

18 Completion of Package works Al Fahad 02 Jul 2015

Taking into consideration of above time line M/s Al Fahad Tiles & Mosaic Factory are already in delay of
47 days in line with Contract Programme.

Further failure in meeting the dates as agreed for technical submittals, approvals and Delivery of
material will affect the overall completion of Hotel 1 at City walk Project and also hindrances to other
trades which will also create delays to other subcontractors.

Please address this issue as a matter of urgency & serious and ensure to mitigate your current delay
and complete your works as per contract programme.

Yours faithfully,
For Al Futtaim Carillion LLC

Anthony Cantwell
Project Director
AC/WM/msa

Encl: Photographs

Cc: AFC

Responds to: None


Response requested: No
Response required by: N/A

You might also like