You are on page 1of 4

Phased Array and TOFD in Lieu of RT

fabrication and in-service

Author
Norbert Trimborn
Strategic Business Leader Advanced NDT
Phased Array and TOFD in Lieu of RT
fabrication and in-service

Abstract
This paper will discuss the replacement of Radiography by Phased Array (PA) and Time of Flight Diffraction
(TOFD). Information will be given about the inspection requirements for pre-service and in-service inspections.
Based on these requirements, SGS has developed a PA inspection system for the inspection of boiler tube
welds. The advantages and disadvantages of this system will be discussed by giving information about general
advantages, combined with an overview about the differences in detection and sizing of different type of
defects.

A s the restrictions in the use of


Industrial Radiography (RT) has
increased over the years, the need for
factor when using the advanced
techniques, there can be huge savings
associated preventing the disruption of
detected in such an inspection, the
remaining life time of a component must
be calculated. This remaining life time
alternative weld inspections methods works within the area. In addition, the calculation is the main reason for this
and techniques such as Time of Flight speed of PA and TOFD shortens overall type of inspection, as it is not intended
Diffraction (TOFD) and Phased Array (PA) inspection time and also eliminates the for the detection weld defects unreported
has become more evident. lost time associated with RT. An inherent during the initial NDT inspection.
Generally, new developments in factor of using a more accurate Pre-service inspection requires
Non-Destructive Testing (NDT) are driven inspection technique is the higher repair acceptance criteria to confirm welds are
by improved performance of the new rate due to the more stringent meeting the requirements of relevant
technique and cost reduction. acceptance criteria of PA and TOFD. codes and standards and workmanship is
Increased confidence in the integrity of acceptable. Here we have several
For the pre-service inspection cost the product offsets the relatively small
reduction is generally given more options:
rise of repairs thereby decreasing any
consideration than improved significant influence total costs. 1) Use ASME acceptance criteria e.g.
performance, the rationale being that CC2235-9 for pressure piping and
inspections are acceptable as long as vessels.
welding satisfies the requirements of the
applicable codes and standards. I ts important to note that pre-service
inspections are not intended to detect
all defects that may lead to failure. This is
a. The problem with this is that the
acceptance criteria were
For in-service inspection, the developed in a wall thickness
performance and accuracy of the an impossible reality, as no NDT range starting at 12.4 mm
inspection is considered more critical as technique has a 100% detection rate. In although technically it is no
the risk of failure between shut downs order to test at 100% accuracy, each problem to use TOFD and PA
shall be as small as possible, therefore, component would require individual from 4 mm and upward.
requiring a higher probability of detection acceptance criteria based purely on its
unique fit for service acceptability as 2) Use European codes and standards;
and more accurate sizing of indication. Minimum wall thickness is 6 mm.
operation conditions, material, alloys and
When Phased Array and Time of Flight other factors vary. 3) Define your own acceptance criteria.
Diffraction techniques are performed
correctly, the quality of performance is For in-service inspection however, a a. Based on the confirmation of
superior when compared with higher detection rate is necessary in acceptable workmanship
radiography. This means that the order to prevent failure prior to the next b. Based on the determination of
confidence level of the structural integrity scheduled shutdown. This can only be fitness for purpose of the product
of products inspected with TOFD or PA is realised when supplementary NDT
techniques are used in parallel. In the presentation, the quality
higher than those inspected using performance of PA will be illustrated by
radiography. The inspection costs of PA In-service inspection places less an example in which radiography has
and/or TOFD are typically higher than the importance on normal acceptance been replaced by PA.
costs of conventional RT, however, criteria based on the size of a detectable
because dangerous radiation is not a indication. When critical defects are
SGS has developed a weld inspection system using Phased Array for boiler tube welds.
The System hasthe following

features benefits Drawbacks

Covers pipes from 21.3 mm (0.84 in) No health and safety implications Tube wall thickness has to be >4.5
to 114.3 mm (4.5 in) OD with using ionising radiation mm for detection and characterisation
Operates within 13 mm (0.5 in) Other work in vicinity mustnt be of defects and bore chamfering must
clearance (on all standard pipes), suspended during inspection be handled with care
permitting inspections in limited Elimination of radiation protection Skilled operators not readily available
access areas measures as technique is new
Can hold two Phased Array probes for Equal or higher reliability of Doesnt quite match radiography in
complete weld coverage in one pass examination in comparison to detection and characterisation of
Can be configured to make one-sided radiography inclusions and gas pores
inspections for pipe-to-component High cost savings
evaluations 100% coverage of weld
Design provides stable and Fast inspection nearly carried out
constant pressure around the full in real time
circumference of the pipe Possible to characterise and size
Can be manipulated from one side many defects
of a pipe Two dimensional sizing
Spring-loaded scanner can Direct assessment after test
be used on ferromagnetic and Possible to produce both hard- and
non-ferromagnetic pipes soft-copy results
Encoder resolution of 32 steps/mm
Two encoders on the scanner

Comparison with RT produced the following overview Conclusions


PA dramatically reduces health and
Phased Array Radiography
safety implications
Delectability Characterisation Delectability Characterisation
PA offers advantages in saving time
Porosity Acceptable Acceptable Good Good and money
Inclusions Acceptable Acceptable Good Good Advantages and limitations of each
technique have been presented
Lack of root fusion Good Good Poor Poor
Radiography offers benefits for
Lack of side wall fusion Good Good Poor Poor detection of inclusions and porosity
PA can detect all defect types and
Weld toe crack Good Good Acceptable good
characterise them in accordance with
Excess penetration Acceptable Acceptable Good Good acceptance criteria

Wormhole/piping Acceptable Acceptable Good Good


Weld root crack Good Good Acceptable Acceptable
Root concavity Good Acceptable Acceptable Acceptable
Lack of root penetration Good Good Good Good

For more information visit www.sgs.com/NDT or contact industrial.global@sgs.com


SGS is the worlds leading inspection, verification, testing and certification company.
SGS Group Management SA 2012 All rights reserved SGS is a registered trademark of SGS Group Management SA

WWW.SGS.COM

You might also like