PROJECT: SADIYAT ROTANA HOTEL ( SRH)
22KV PERMANENT POWER SUPPLY - ADDC PROCEDURES
[Link] DESCRIPTION Status
A H.V SWITCH GEAR
1 ADDC Approval on Material submittal
2 Delivery to site
3 Installation of 22KV HV Switchgear
4 Delivery of 22KV cable between tapping station to HV Switchgear
5 Delivery of 22KV cable between HV Switchgears to Transformers
6 Installation of Plug in termination kit and HV cable termination in HV Switchgear
7 Earthing work to be completed
8 Laying and termination of 22KV cable between tapping station to HV Switchgear
a) Awaiting CDC from ASK-JV Headoffice for TDIC to give approval for Excavation Permit
b) TDIC approval on Excavation Permit
c) ASK-JV to start and complete the Excavation
d) 22KV HV cable laying inside trench
e) 22KV HV cable protection Tile and cable identification labels installation
B TRANSFORMER
1 Installation of Transformers
2 Neutral CT Relay installation and necessary wiring in Transformer
3 Cable laying and termination of Transformer secondary side from Transformer to MDB's
4 Laying and terminationof cables between HV Switchgears to Transformers
C LV PANELS/ CAPACITOR BANKS
1 Installation of LV panel - MDB's
2 Cable laying from MDB to SMDB and its related termination
3 Installation of Capacitor bank
4 Cable laying from MDB to Capacitor bank and its related termination
5 SMDB cable Incoming and Outgoing Termination .
6 Earthing work to be completed
D ADDC INSPECTION / APPROVAL & ENERGIZATION OF POWER
1 HV Switchgear Relay Setting Calculation submittal and approval from ADDC
2 HV Switchgear relay setting inspection and witness test by ADDC.
3 Testing of HV Switchgear and submission of SAT reports for ADDC approval.
4 Testing of Transformers and submission of SAT reports for ADDC approval.
5 Submission of Application for the Request of ADDC Inspection before energization of HV Switchgear .
6 Testing of Transformers and submission of SAT reports for ADDC approval.
7 ADDC inspection for 22KV cable installation / HV Switchgear / Transformer .
8 ADDC approval on item no: 7
9 Shut down request and approval from TIC / ADDC
10 Tapping Joint of 22KV HV cable
11 Energization upto HV panels and padlock by ADDC
12 Submission of Energy Meter application to ADDC ( Form 4)
13 Inspection and approval by ADDC Metering Department before supplying Meters .
14 Installation of Energy Meters by ADDC
15 Clearance from ADDC Metering section
16 Application for ADDC LV Inspection ( Form 5)
17 Building Inspection by ADDC LV section .
18 Approval by ADDC LV Inspection and provide Clearance to energize power from HV panel to LV Panel .
19 Connection Fees Estimation by ADDC
20 Payment of Connection fees to ADDC ( By ASK-JV)
21 Transfer of power from HV panel to LV panel by ADDC
Remarks