0% found this document useful (0 votes)
968 views8 pages

Addc Procedures For 22kv Permananet Power Supply

This document outlines the procedures for obtaining permanent 22kV power supply from the Abu Dhabi Distribution Company (ADDC) for the Sadiyat Rotana Hotel project. There are 22 steps that must be completed, including submitting material for approval, installing switchgear, transformers, cables, and panels; performing testing and inspections by ADDC; obtaining approvals from ADDC on relay settings, installations, and tests; applying for metering and energization; and paying connection fees. Upon completing all steps, ADDC will transfer power from the high voltage panels to the low voltage panels.

Uploaded by

basem_eng77
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
968 views8 pages

Addc Procedures For 22kv Permananet Power Supply

This document outlines the procedures for obtaining permanent 22kV power supply from the Abu Dhabi Distribution Company (ADDC) for the Sadiyat Rotana Hotel project. There are 22 steps that must be completed, including submitting material for approval, installing switchgear, transformers, cables, and panels; performing testing and inspections by ADDC; obtaining approvals from ADDC on relay settings, installations, and tests; applying for metering and energization; and paying connection fees. Upon completing all steps, ADDC will transfer power from the high voltage panels to the low voltage panels.

Uploaded by

basem_eng77
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
  • 22KV Permanent Power Supply Procedures
  • LV Panels/Capacitor Banks
  • ADDC Inspection / Approval & Energization of Power
  • Transformer Installation
  • Remarks

PROJECT: SADIYAT ROTANA HOTEL ( SRH)

22KV PERMANENT POWER SUPPLY - ADDC PROCEDURES

[Link] DESCRIPTION Status


A H.V SWITCH GEAR
1 ADDC Approval on Material submittal

2 Delivery to site

3 Installation of 22KV HV Switchgear

4 Delivery of 22KV cable between tapping station to HV Switchgear

5 Delivery of 22KV cable between HV Switchgears to Transformers

6 Installation of Plug in termination kit and HV cable termination in HV Switchgear

7 Earthing work to be completed

8 Laying and termination of 22KV cable between tapping station to HV Switchgear

a) Awaiting CDC from ASK-JV Headoffice for TDIC to give approval for Excavation Permit

b) TDIC approval on Excavation Permit

c) ASK-JV to start and complete the Excavation


d) 22KV HV cable laying inside trench

e) 22KV HV cable protection Tile and cable identification labels installation

B TRANSFORMER

1 Installation of Transformers

2 Neutral CT Relay installation and necessary wiring in Transformer


3 Cable laying and termination of Transformer secondary side from Transformer to MDB's

4 Laying and terminationof cables between HV Switchgears to Transformers

C LV PANELS/ CAPACITOR BANKS


1 Installation of LV panel - MDB's

2 Cable laying from MDB to SMDB and its related termination

3 Installation of Capacitor bank

4 Cable laying from MDB to Capacitor bank and its related termination
5 SMDB cable Incoming and Outgoing Termination .
6 Earthing work to be completed

D ADDC INSPECTION / APPROVAL & ENERGIZATION OF POWER

1 HV Switchgear Relay Setting Calculation submittal and approval from ADDC

2 HV Switchgear relay setting inspection and witness test by ADDC.

3 Testing of HV Switchgear and submission of SAT reports for ADDC approval.


4 Testing of Transformers and submission of SAT reports for ADDC approval.

5 Submission of Application for the Request of ADDC Inspection before energization of HV Switchgear .

6 Testing of Transformers and submission of SAT reports for ADDC approval.

7 ADDC inspection for 22KV cable installation / HV Switchgear / Transformer .

8 ADDC approval on item no: 7

9 Shut down request and approval from TIC / ADDC

10 Tapping Joint of 22KV HV cable

11 Energization upto HV panels and padlock by ADDC

12 Submission of Energy Meter application to ADDC ( Form 4)

13 Inspection and approval by ADDC Metering Department before supplying Meters .

14 Installation of Energy Meters by ADDC

15 Clearance from ADDC Metering section

16 Application for ADDC LV Inspection ( Form 5)

17 Building Inspection by ADDC LV section .

18 Approval by ADDC LV Inspection and provide Clearance to energize power from HV panel to LV Panel .
19 Connection Fees Estimation by ADDC

20 Payment of Connection fees to ADDC ( By ASK-JV)

21 Transfer of power from HV panel to LV panel by ADDC


Remarks

PROJECT: SADIYAT ROTANA HOTEL ( SRH)
22KV PERMANENT POWER SUPPLY - ADDC PROCEDURES 
S.NO
DESCRIPTION
Status 
A
H.V SWITCH GEA
d) 22KV  HV cable laying inside trench 
e) 22KV HV cable protection Tile and cable identification labels  installation 
B
TRA
4
Testing of Transformers and submission of SAT reports for ADDC approval. 
5
Submission of Application for the Request of AD
19
Connection Fees Estimation by  ADDC 
20
Payment of Connection fees to ADDC ( By ASK-JV) 
21
Transfer of power from HV pane
Remarks

You might also like