Indias longest flyover

constructed in the shortest time


T he 3.6 km long Panipat flyover constructed by Larsen
& Toubro Limited is Indias longest six lane flyover on
the countrys NH network. It is the fastest constructed urban
infrastructure, completed within 28 months, well ahead of
schedule.

When opened to traffic in June 2008, the 10 km Panipat


elevated expressway will provide a comfortable, hindrance-
free, smooth sail-through at Panipat, where traffic snarls,
congestion bottlenecks and crowded market places have so
far been the order of the day. Not only that, the project will
now ensure smooth, hassle-free traffic flow throughout the
Chandigarh-Delhi National Highway.

Commencing the work in January 2006, L&T completed the project eight months ahead of schedule,
as against the contractual commitment of 36 months scheduled for completion by January 2009.

L&T Panipat Elevated Corridor Limited a Special Purpose Vehicle (SPV) was formed to design,
engineer, finance, construct, operate and maintain the flyover. The total concession period including
the construction period is 20 years. ECC, L&Ts Construction Division, executed this six-lane
dedicated expressway on NH-1 in Haryana in a record time.
Panipat, the war city of India situated Delhi and rest of the country. In the Panipat. The elevated portion of this
at 90 km from National Capital, Delhi, event of border skirmishes or a war, expressway is 3.6 km long (3,048 m
has a glorious history. It is said that this road will also serve as a vital of viaduct and 560 m of ramps)
at the time of battle of Mahabharat link to Wagha border area as three covering the central built-up Panipat
one of the five villages which were Cantonments - Delhi, Ambala and section. The flyover covers Gohana
demanded by the pandavas was Jalandhar - are situated along this Road, Sanuli Road, Assandh Road
Panpat which was later renamed road. Traffic intensity on this road is Crossings, city bus stand and Skylark
as Panipat. Three major battles were very high. The congested junctions
Tourist Complex.
fought at this place in 1526, 1556 and thick concentration of industries
and 1761. Famous for the handloom around Panipat create hurdles in A separate two-lane peripheral
products, Panipat is called the the movement of the heavy flow of road with paved shoulders is also
City of Weaver. vehicles. provided on either side of the
access-controlled six-lane highway
National Highway No.1 connecting Thus, this gave rise to Indias longest
Delhi-Panipat-Ambala-Amritsar and flyover, which is part of Panipat for the local Panipat traffic, which
going up to Indo-Pak border, is a Elevated Expressway Project. The will not use the elevated structure.
vital road network. NH-1 connects project scope included widening the The 20-lane toll plaza with semi-
Northern part of the country including existing four-lane to six lanes for a automatic system and dedicated
states of Jammu & Kashmir, Punjab, 10-km stretch from km 86 to km 96, automatic lane on either direction
Himachal Pradesh and Haryana with passing through the historic City of ensures smooth toll collection.
Salient Features
Access controlled 6-lane highway in the reach
km 86.000 to km 96.000
Separate 2-lane peripheral road with paved shoulder on either
side of access controlled 6-lane highways for the local traffic.
Three underpasses to accommodate 4-lane divided carriageway
Construction of 2 new minor bridges at
Ch: 91.400 and Ch: 96.000
Widening/construction/reconstruction of culverts,
drains, ducts for services
Construction of toll plaza, lighting at toll plaza, street lighting,
road furniture and markings, traffic signals at junctions

Elevated Portion project most efficiently ahead of


the construction schedule with cost
This 6-lane 3.6 km - long flyover
savings.
has been built using state-of-the-art
technology. The foundations of this To ensure smooth ride, modular type
bridge consisting of 1282 piles were expansion joints were imported and
installed using rotary drilling rig, over provided at every 5 spans. RE Wall
which pile caps and piers have been Technology was extensively used in
built. Two parallel elevated carriage this project for a length of 4040m.
ways of 100 spans each (average At every pier location, the I-girders
span length 31m) comprised 6 were cross connected with diaphragm
precast pretensioned I girders each which was rested on two pot PTFE
weighing 45 tonnes. Totally 1200 I bearings.
girders precast in a nearby casting Underpasses
yard were transported to site through Pavement In order to provide interconnectivity to
specially modified trailers and erected
The project scope covers widening peripheral road on either side of the
using gantries and heavy lift cranes.
of roads from 4 to 6 lanes. Flexible access controlled main carriageway,
For the first time in India, precast deck road has been provided for the entire three underpasses have been built at
slab panels have been used as load stretch except at Toll Plaza, where Ch: 87.365, Ch:91.900 and Ch:93.600.
bearing members in combination with rigid pavement was constructed. These underpasses have a minimum
cast in-situ deck slab. This innovative The minimum crust thickness of the vertical clearance of 5.5m with 20m
method helped L&T to execute the flexible road is 695 mm. effective span to accommodate a
4-lane divided carriageway covering
the median and 1.5m footpath on
either side.

Cross Drainage Works


A total of 10 culverts (7-Box, 2-Pipe
and 1-Slab) have been constructed
and widened on the stretch. The
cross drainage work also includes
construction of 2 minor bridges at
Ch: 91.400 and Ch: 96.000.

Street Lighting
For the first time in this part of the
country, twisted decorative lighting
poles with bird wings are used.
Imported from Malaysia, these poles
are added attraction to the project.
Toll Plaza during construction period indicated
that there was an increase in the
A 20-lane Toll Plaza has been
average flow of traffic when compared
constructed at Ch: 94.775 with all
to the flow before commencement
the modern facilities imported from
of the project. A large number of
European countries. It has the
heterogeneous traffic ranging from
provision for local vehicles to use smart
cards and automatic classification of bullock carts, hand pulled rickshaws
vehicles. Adequate lighting and safety to heavy industrial vehicles at all
systems are installed in the toll plaza hours made it compulsory to have a
with Rigid Pavement (Pavement well developed traffic management
Quality concrete) from Ch: 94.775 to plan. Traffic Management system
Ch: 95.118. devised and implemented by L&T and ushers them to an era of growth
in this project is one of the biggest and prosperity. Strategically located,
Landscaping achievements. This not only ensured this flyover serves as a transportation
Landscape treatment has been a safe and smooth movement of traffic, link and enhances all-round
done through planting of trees at but also won the hearts of the people. development in industrial, residential
appropriate locations. Shrubs of low General public, local administrators and commercial zones of the City.
height are planted in the median of and the traffic police complimented all
the project section. the efforts of L&T. Thanks largely to impeccable
planning and advanced construction
Traffic Management Project Significance techniques, L&T has been able to
Constructing the flyover without This flyover relieves the people of complete this unique and landmark
disturbing the traffic movement was Panipat from the endless traffic jams, urban infrastructure project in a record
the critical task. A survey carried out the tedium of waiting for long hours, time of 28 months.

This bridge stands as more than an emblem of engineering and construction excellence. It is a
symbol of L&Ts commitment to create a high quality national infrastructure for a vibrant economy
of India. An enduring contribution to the lifelines of a nation, bridging distance and linking people.
Project Highlights
Project Name : Widening of existing 4 lane road from
km 86 to km 96 passing through Panipat
city on NH1 in Haryana to 6 lane
including 3.6 km elevated structure and
2 lane peripheral roads on either side
Employer : National Highways Authority of India
Concessionaire : L&T Panipat Elevated Corridor Limited
Independent Consultant : Consulting Engineering Services (India)
Pvt. Limited
Design Consultant : L&T Ramboll
EPC Contractor : Larsen & Toubro Limited - ECC Division
Agreement Date : 27/07/2005
Appointed Date : 22/01/2006
Completion period : 36 months from Appointed Date
Schedule Completion Date : 22/01/2009
Concession period : 20 years from Appointed Date
Total Length of Project : 10 km
Length of Elevated portion : 3.6 km (3,048m of viaduct and
560m of ramps)
No. of Underpasses : Three
No. of Minor Bridges : Two
Substructure : Bored Cast in situ Piles, Pile cap,
Pier and Piercap
Super Structure : PSC Pretension I Girders with deck
slab, Kerbs, Barriers and handrails