Project: ORT Podium Refurbishment Works

Location: Cruzada St. Makati City


Subject: Demolition of Planter Box Schedule
Date: July 24, 2017

SCHEDULE MONITORING
DURATION PLANNED CURRENT STATUS VARIANCE ACTION TAKEN July August
Description ACTUAL FORCAST PLANNED ACTUAL (%) ADVANCE SLIPPAGE DELAY TYPE
DAYS START FINISH START FINISH (%) (%) (%) REMARKS
26 27 28 31 1 2 3 4 5 7 8 9 10 11 12 14 15 16 17 18
I FABRICATION OF ACCESS 3 07/26/2017 07/28/2017 07/31/2017 07/31/2017 100% 100%
II PHASE 1 6 07/31/2017 5/8/2017 07/31/2017 5/8/2017 100% 100%
III PHASE 2 6 7/8/2017 12/8/2017
IV PHASE 3 6 08/14/2017 08/19/2017