[Regulation 4 of the Building Control (Temporary Buildings) Regulations (Cap 29, Rg 5)]
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
Location / Address:
*MK / TS:
Lot(s) No.:
2 I confirm that:
[ ] I have applied for a period which includes the duration for the construction and
demolition/removal of the temporary building / structure
[ ] The construction / installation of the temporary building / structure shall commence on
the start date and will be demolished / removed by the end date of the permit
The Permit is for a period of ________ days ________ months commencing from
____________________ to ____________________.
Example
: 23/07-2013-26/07/2013 27/07/2013-28/08/2013 28/08/2013-29/08/2013
Phase 1
BPM_PTB_BP09 Page 1 of 7
[Ver1.4.1_Dec_2014]
3 I confirm that the temporary building(s) fall(s) into:-
S/N Description of Building / Building works No of Structure
[ ] (a) A *shed / stage for *wedding/entertainment/funeral/religious
ceremony for more than 7 days
[ ] (b) A *stall / shed for *trade fair/fun fair/exhibition for more than 35
days
[ ] (c) A *protective hoarding / catch platform / fence on the street or
footway for building works
[ ] (d) A temporary building granted with temporary Written Permission
by the Competent Authority (URA)
[ ] (e) Other temporary buildings or structures ^
[ ] (f) Any *frame / panel / hoarding / object / support / other structure
that is designed or used primarily for the display of an
advertisement or signboard where the surface area exceeds 10
square metres
[ ] (g) Any * frame / panel / hoarding / object / support / other structure
that is designed or used primarily for the display of an
advertisement or signboard where the uppermost part of it is 4
metres and above from the ground
[ ] (h) A Temporary Building Permit for Extension for a duration not
exceeding 12 months
Notes: The fee payable shall be the total numbers of temporary building / Total =
structure in the categories multiply by $10/- per month or part thereof
^ Where the application contains 2 or more types of temporary buildings / structures, please attach a
summary list (Annex A) indicating all the temporary buildings / structures in the submission.
5 The fee amount of $__________________ ($10 per month or part thereof payable for each temporary
building / structure) is attached and paid by *Cash / Nets / Cheque or via E-Banking.
BPM_PTB_BP09 Page 2 of 7
[Ver1.4.1_Dec_2014]
SECTION I (Declaration by Applicant)
I confirm that:-
a)the particulars given above are correct.
Name & address of Applicant and the UEN (if a Name & NRIC / FIN No. of Applicant (if applicant is
Company, Firm or Organisation) a company):
Email:
Email:
_______________________________________
(Signature of Professional Engineer) Date:
BPM_PTB_BP09 Page 3 of 7
[Ver1.4.1_Dec_2014]
EXPLANATORY NOTES FOR APPLICATION
FOR A PERMIT TO ERECT TEMPORARY BUILDINGS
1 APPLICATION SUBMISSION
(i) Crossed cheques are to be issued in favour of Building & Construction Authority, Singapore.
(ii) The duration for the permit shall include the construction period, duration of use or the
occupation period for the temporary building and the proposed duration to demolish and remove
the temporary building from site.
(iii) Where a permit has been approved previously, please provide a copy of the approved permit
indicating the permit number. (Example:- Permit number as 2014/00001 or the 2014000001)
(iv) The permit fees shall be $10 per month or part thereof for each temporary building / structure.
(v) Where the application contains 2 or more types of temporary buildings / structures, please attach
a summary list (Annex A) indicating all the temporary buildings / structures in the submission.
(vi) The submission of the drawings and PE calculations in the application are to be endorsed by the
Professional Engineer (Civil/Structural Engineer) certifying that the Plans and calculations are
submitted for the Approval as Temporary Buildings on every sheet of the plans and each set of
calculations (On the cover page and last page).
2 PERMIT CONDITIONS
(i) Before your application is approved, you are not to commence the construction or erection of the
building or structure.
(ii) An applicant who applies for a permit to erect temporary buildings which is intended for
occupation or when the erection of which may affect the safety of the public, shall engage a
professional engineer to design, supervise and inspect the erection of the temporary building.
(iii) Grant of the permit does not constitutes to the approval of the advertisement licence application.
(iv) The Chief Planner, Urban Redevelopment Authority (URA) is to be consulted and, where
required, and the written permission (planning permission) is to be obtained and submitted
together with this application. (For an application where the duration exceeds 90 days or where
otherwise stated by the competent authority)
(v) Upon completion of the building works, the Professional Engineer (PE) shall submit the
Certificates of Supervision for Temporary Building Works and Lightning Protection System
(where applicable) before the occupation of the temporary building or display of the
advertisement / signages.
3 GENERAL PROVISIONS
(i) Where a permit is not required for the following types of temporary buildings:-
a. A workers quarters, site office, store, builders shed or other shed required in connection
with any building works relating to permanent buildings situated within or outside a
construction site or show-flat or show house situated within or outside a construction site,
such temporary building / structure are required to comply with Regulations 7 and 8 of the
Building Control (Temporary Building) Regulations.
b. Any frame, panel, hoarding, object, support or other type of structure that is designed or used
primarily for the display of signboard during celebration of a national event and required for a
period not exceeding 35 days.
c. A shed or a stage for or in connection with any wedding, entertainment, funeral or religious
ceremony not exceeding 7 days in duration.
d. A stall or shed situated in any open space and required for or in connection with a trade fair,
fun fair or other exhibition not exceeding 35 days in duration.
e. Protective hoarding, catch platform or fence required for or in connection with any building
works but not erected on a street or footway.
(ii) All protective hoardings, catch platforms, fences and other temporary structures erected for the
safety and convenience of persons in any public place or on any public road shall comply with
Regulation 9.
BPM_PTB_BP09 Page 4 of 7
[Ver1.5.1_Dec_2014]
4 CONSULTATION WITH RELEVANT AUTHORITIES FOR TECHNICAL CLEARANCES
(i) The applicant should consult and obtain approval and clearances required from the relevant
landowners and authorities listed in the table below to enable their requirements to be
incorporated in the plans before submission of the application.
List of Authorities to be consulted
a. Chief Engineer, Central Building Plan Unit, Pollution Control Department
b. Chief Engineer, Central Building Plan Unit, Sewerage and Drainage [Water Reclamation
(Network) Department, PUB], if proposal involves the use of existing or new sanitary
appliances and facilities
c. Chief Planner, URA (Development Control Group) if the period of the trade fair or exhibition
exceeds a total of 90 days in a year
d. Commissioner, Parks & Trees Regulatory Section, National Park Boards
e. Director, Fire Safety & Shelter Department, SCDF
f. Head URA (Car Parks Division) if public carparks are used
g. Licensing Officer, Singapore Police Force, Public Entertainment Licensing Unit
h. Manager, Land Transport Authority, Development & Building Control (Road & Transport)
i. Manager, Land Transport Authority, Development & Building Control (Rail)
j. Manager, Land Transport Authority, Development & Building Control (Vehicle Parking)
k. Commissioner, Building Control, Advertisement Licensing Department, Building Plan &
Management Group, BCA for a licence to display any advertisement or sign
BPM_PTB_BP09 Page 5 of 7
[Ver1.5.1_Dec_2014]
5 PROFESSIONAL ENGINEER ENDORSEMENT FOR SUBMISSION
(i) Submission of the drawings and PE calculations in the application are to be endorsed by the
Professional Engineer (Civil/Structural Engineer) certifying that the Plans and calculations are
submitted for the Approval as Temporary Buildings
(ii) Every sheet of the plans and each set of calculations (On the cover page and last page) are to be
endorsed and inserted with the below endorsements
______________________________________ ______________
Stamp & Signature of Professional Engineer Date
BPM_PTB_BP09 Page 6 of 7
[Ver1.5.1_Dec_2014]
ANNEX A: SUMMARY LIST FOR TEMPORARY BUILDING PERMIT SUBMISSION
The following table indicates all the temporary buildings / structures submitted for approval:-
I hereby certify that I have designed the temporary buildings(s)/building works shown in these
drawings and the relevant provisions of the Building Control (Temporary Buildings) Regulations
(Cap 29, Rg 5) have been complied with.
Signature & Name & Address of Professional Name & Address of Professional Firm: